YIELDABLE CONSTRUCTION METHOD FOR EARLY RELEASING SURROUNDING ROCK DEFORMATION ON WEAK COUNTER-INCLINED SLOPE
20180010316 · 2018-01-11
Inventors
- Weijiang CHU (HANGZHOU, CN)
- Chunsheng ZHANG (Hangzhou, CN)
- Jing HOU (Hangzhou, CN)
- Jiayao WU (Hangzhou, CN)
- Yong ZHOU (Hangzhou, CN)
Cpc classification
Y02A10/23
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
F42D3/04
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
International classification
Abstract
The present invention provides a yieldable construction method for early releasing surrounding rock deformation on a weak toppling slope, thereby reducing surrounding rock toppling deformation risk in and after an excavation process and ensuring overall slope stability and safety of a supporting structure. A technical solution of the present invention is as follows: loosing a rock mass through controlled blasting; inducing toppling deformation of the slope by injecting water and softening a blasting relaxation part of the rock mass; determining timing of water injection by monitoring slope surface displacement characteristics of the slope; and performing a normal excavation process of the toppling deformation slope after injecting is completed. The present invention is applicable to design and construction of high slope engineering of a special kind of rocks, i.e., a toppling deformation slope composed of weak rock masses.
Claims
1. A yieldable construction method for early releasing surrounding rock deformation on a weak counter-inclined slope, wherein the method comprises: loosing a rock mass through controlled blasting; inducing toppling deformation of the slope by injecting water and softening a blasting relaxation part of the rock mass; determining timing of water injection by monitoring slope surface displacement characteristics of the slope; and performing a normal excavation process of a toppling deformation slope after the injecting is completed.
2. The yieldable construction method for early releasing surrounding rock deformation on the weak counter-inclined slope of claim 1, wherein the method comprises steps below: a. excavating a plurality of construction adits inside a slope excavation contour line (1), drilling blast holes (4) in the construction adits, and completing blasting charge; b. arranging a plurality of surface displacement monitoring points (5) on a slope surface, and monitoring slope surface (2) displacement deformation characteristics; c. detonating the blast holes (4); d. drilling water injection holes (6) through the construction adits after the slope surface (2) displacement deformation characteristics monitored at the surface displacement monitoring points (5) tend to be convergent; e. injecting high-pressure water into surrounding rock relaxation parts produced by detonation via the water injection holes (6) until a slope surface surrounding rock deformation increment caused in the water injection process is less than 5% compared with accumulative deformation, and stopping injecting water; f. injecting a cement grout into slope foot through the water injection holes (6); and g. performing a normal excavation process of the toppling deformation slope.
3. The yieldable construction method for early releasing surrounding rock deformation on the weak counter-inclined slope of claim 2, wherein in the step e, the water is injected into the water injection holes (6) through a cyclic water injection method; and in each water injection cycle process, water injection pressure is maintained to inject the water for a certain period of time, and after the slope surface displacement deformation characteristics monitored at the surface displacement monitoring points (5) tend to be stable after water injection is stopped, the next water injection cycle is started.
4. The yieldable construction method for early releasing surrounding rock deformation on the weak counter-inclined slope of claim 3, wherein in a first water injection cycle, the water injection pressure is controlled as 2 MPa, the injection pressure of 2 MPa is maintained for more than 5 hours, then the water injection pressure is reduced to 0.5 MPa, and the water injection pressure of 0.5 MPa is maintained for 2 days; in a second water injection cycle, the water injection pressure is controlled as 0.5 MPa, and the water injection pressure of 0.5 MPa is maintained for 3 days; and in an (n+2)th water injection cycle, the water injection pressure is controlled as 0.5 MPa, and the water injection pressure of 0.5 MPa is maintained for 3 days, wherein n is a positive integer.
5. The yieldable construction method for early releasing surrounding rock deformation on the weak counter-inclined slope according to claim 2, wherein in the step f, a grouting pressure of the cement grout is controlled as 0.2-0.3 MPa, and when a single-hole grouting rate is less than 0.5 L/min, grouting is stopped.
6. The yieldable construction method for early releasing surrounding rock deformation on the weak counter-inclined slope according to claim 2, wherein totally three construction adits exist at different elevations in an excavation slope, including a first adit (31), a second adit (32) and a third adit (33) in sequence from top to bottom; vertical elevation H1 of the first adit (31) away from a slope opening line is equal to ⅓H, vertical elevation H2 of the second adit (32) away from the slope opening line is equal to ⅔H, and the third adit (33) is located at a slope toe excavation position; a vertical distance of each of the construction adits away from the slope surface (2) is 0.2H-0.3H, and a vertical distance of each of the construction adits away from the excavation contour line (1) is greater than or equal to 20 m and less than or equal to 40 m, wherein H is a height of a slope excavation area.
7. The yieldable construction method for early releasing surrounding rock deformation on the weak counter-inclined slope of claim 6, wherein the blast holes (4) are drilled in the slope surface (2) side via the construction adits, and a drilling elevation angle is 25-40 degrees, wherein the blast holes (4) are drilled towards the slope surface (2) side through a downdip angle of 20-40 degrees via the third construction adit (33); the length of the bottom of the drilled elevated blast hole (4) away from the slope surface (2) is 5-8 m, and the length direction of the drilled declined blast holes (4) covers the slope toe excavation position.
8. The yieldable construction method for early releasing surrounding rock deformation on the weak counter-inclined slope of claim 7, wherein the water injection holes (6) are formed parallel to the blast holes (4).
9. The yieldable construction method for early releasing surrounding rock deformation on the weak counter-inclined slope of claim 6, wherein totally four rows of surface displacement monitoring points (5) are arranged, wherein the arrangement elevation of the first row of surface displacement monitoring points (5) is positioned at the slope opening line, the second row of and the third row of surface displacement monitoring points (5) are arranged in the middle of the slope in equal ratios according to the elevation, and the arrangement elevation of the fourth row of surface displacement monitoring points (5) is arranged at a position of 3-5 m away from an upper side of the excavated slope toe.
10. The yieldable construction method for early releasing surrounding rock deformation on the weak counter-inclined slope of claim 6, wherein the blast holes (4) in the first adit (31) and the second adit (32) are detonated during blasting, and after the slope surface tends to be stable, the blast holes (4) in the third adit (33) are detonated.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0030]
[0031]
[0032]
DETAILED DESCRIPTION OF THE INVENTION
[0033] The present embodiment has the main characteristic that a slope deformation sensitive part is subjected to controlled blasting, and high-pressure water is injected to induce toppling deformation of the slope so as to reduce surrounding rock toppling deformation risk in and after an excavation process, thereby ensuring overall slope stability and safety of a supporting structure. The present embodiment includes the following steps: [0034] a. as shown in
[0035] As shown in