Installation method of bent cap for mutually restraining adjacent pier studs in prefabricated and assembled bridge
11708671 ยท 2023-07-25
Assignee
Inventors
- Jiaqing Wang (Anhui, CN)
- Dachuang Yao (Anhui, CN)
- Lijun Jin (Anhui, CN)
- Xinghuo Xu (Anhui, CN)
- Shisheng Fang (Anhui, CN)
- Zhenye Zhu (Anhui, CN)
- Tao Xu (Anhui, CN)
- Hao Ren (Anhui, CN)
- Jinmiao Xu (Anhui, CN)
- Biao Xing (Anhui, CN)
- Shoufeng Zhang (Anhui, CN)
Cpc classification
E01D21/00
FIXED CONSTRUCTIONS
International classification
E01D19/00
FIXED CONSTRUCTIONS
E01D19/02
FIXED CONSTRUCTIONS
Abstract
An installation method of a bent cap for mutually restraining adjacent pier studs in a prefabricated and assembled bridge is provided. A bent cap mold base is configured in a form of a bent cap, which includes fixedly arranging limiting steel rings at two ends of a rectangular frame and vertically arranging steel bar sleeves in the limiting steel rings, hoisting the cap bent mold base on top portions of adjacent two prefabricated pier studs, such that pier stud pre-embedded steel bars protruding from the top portions of the two prefabricated pier studs are correspondingly inserted into the steel bar sleeves at two ends of the bent cap mold base one by one, and limiting the adjacent two prefabricated pier studs in the bent cap mold base.
Claims
1. An installation method of a bent cap for mutually restraining adjacent pier studs in a prefabricated and assembled bridge, characterized in that: the pier studs are prefabricated pier studs, a top portion of each of the prefabricated pier studs is provided with pier stud pre-embedded steel bars, the pier stud pre-embedded steel bars are evenly distributed into a circular ring shape on the top portion of each of the prefabricated pier studs and form a pier stud pre-embedded steel bar ring with a radius r; the bent cap is a prefabricated bent cap, two ends of the prefabricated bent cap are respectively pre-embedded with bent cap pre-embedded sleeves, vertical grouting ducts are provided on a top portion of the prefabricated bent cap and are in communication with the bent cap pre-embedded sleeves, the bent cap pre-embedded sleeves on the two ends of the prefabricated bent cap are evenly distributed into a circular ring shape at each end to form a bent cap pre-embedded sleeve ring with a radius r; and the bent cap pre-embedded sleeves in the bent cap pre-embedded sleeve ring correspond to the pier stud pre-embedded steel bars in the pier stud pre-embedded steel bar ring one to one, such that the pier stud pre-embedded steel bars are able to be inserted into the bent cap pre-embedded sleeves of corresponding positions for anchorage; a bent cap mold base is configured as follows: fixedly arranging limiting steel rings at two ends of a rectangular frame, and vertically arranging steel bar sleeves in the limiting steel rings, wherein the steel bar sleeves are evenly distributed into a circular ring shape in each of the limiting steel rings and form a steel bar sleeve ring with a radius r; setting a center-to-center distance of the steel bar sleeve rings at the two ends and a center-to-center distance of the bent cap pre-embedded sleeve rings at the two ends in the prefabricated bent cap to be identical; and setting positions of the steel bar sleeves in the steel bar sleeve ring to correspond to positions of the bent cap pre-embedded sleeves in the bent cap pre-embedded sleeve ring of the corresponding end one to one; the installation method of the bent cap is performed in constructed pile top cup bearing platforms through the following steps: step 1: through hoisting, placing the prefabricated pier studs in two adjacent pile top cup bearing platforms, respectively, and preliminarily adjusting a center distance and a plane position between the two prefabricated pier studs; step 2: hoisting the cap bent mold base on the top portions of the two prefabricated pier studs, such that the pier stud pre-embedded steel bars protruding from the top portions of the two prefabricated pier studs are correspondingly inserted into the steel bar sleeves at two ends of the bent cap mold base one by one; and when the pier stud pre-embedded steel bars in the two prefabricated pier studs and the steel bar sleeves at the two ends of the bent cap mold base are not aligned due to deviation, lifting the prefabricated pier studs again by a crane and readjusting the center distance and/or the plane position between the two prefabricated pier studs until the pier stud pre-embedded steel bars in the two prefabricated pier studs are correspondingly inserted into the vertical steel bar sleeves at the two ends of the bent cap mold base one by one, such that the adjacent two prefabricated pier studs are limited in the bent cap mold base; step 3: adjusting heights and perpendicularity of the adjacent two prefabricated pier studs to satisfy design needs, and keeping the prefabricated pier studs in a state which satisfies the design needs; step 4: performing anchorage between each of the pile top cup bearing platforms and the corresponding prefabricated pier stud to complete assembly of the prefabricated pier studs; step 5: removing the bent cap mold base, replacing the bent cap mold base with the bent cap, and inserting the pier stud pre-embedded steel bars protruding from the top portions of the prefabricated pier studs into the bent cap pre-embedded sleeves pre-embedded in the bent cap one by one; and step 6: performing grouting through the grouting ducts on the bent cap, performing anchorage between the prefabricated pier studs and the prefabricated bent cap, and completing assembly of the prefabricated bent cap.
2. The installation method of the bent cap for mutually restraining the adjacent pier studs in the prefabricated and assembled bridge according to claim 1, wherein: in step 3, arranging an auxiliary adjustment mechanism to adjust the height and perpendicularity of each prefabricated pier stud, wherein a structure of the auxiliary adjustment mechanism is that top support mechanisms are arranged between a top surface of each pile top cup bearing platform and an outer side wall of each prefabricated pier stud, the top support mechanisms are evenly distributed in at least three groups around the outer side wall of the prefabricated pier stud, each group of the top support mechanisms is able to independently adjust a top support height thereof, and adjustment of the height and/or the perpendicularity of the prefabricated pier stud is achieved through adjusting the top support height of the top support mechanisms of one group or plural groups.
3. The installation method of the bent cap for mutually restraining the adjacent pier studs in the prefabricated and assembled bridge according to claim 2, wherein a structure of each of the top support mechanisms is that a jack is provided on the top surface of each pile top cup bearing platform, a reaction frame having a horizontal support surface is provided on a corresponding position of the outer side wall of each prefabricated pier stud, and the jack is supported between the top surface of the pile top cup bearing platform and the support surface of the reaction frame.
4. The installation method of the bent cap for mutually restraining the adjacent pier studs in the prefabricated and assembled bridge according to claim 3, wherein the reaction frame is formed by a vertical universal beam and a horizontal universal beam, the vertical universal beam is attached to the outer side wall of the prefabricated pier stud and is attached to the outer side wall of the prefabricated pier stud through flange slabs separately disposed on two sides of a web of the vertical universal beam, one end of the horizontal universal beam abuts against the web of the vertical universal beam and is fixedly connected to the vertical universal beam, and a bottom surface of a lower flange slab in the horizontal universal beam is the support surface of the reaction frame.
5. The installation method of the bent cap for mutually restraining the adjacent pier studs in the prefabricated and assembled bridge according to claim 4, wherein a fixed structure of the reaction frame is that a web reserved hole is provided on the web of the vertical universal beam, pier stud reserved holes are radially and horizontally arranged in each prefabricated pier stud (2), one end of a steel rod is inserted into one of the pier stud reserved holes, and the other end of the steel rod penetrates through the web reserved hole in the vertical universal beam and is disposed on a top surface of an upper flange slab of the horizontal universal beam.
6. The installation method of the bent cap for mutually restraining the adjacent pier studs in the prefabricated and assembled bridge according to claim 5, wherein the fixed structure of the reaction frame is further provided with a lower-layer fixed structure formed by a lower-layer web reserved hole, lower-layer pier stud reserved holes, and a lower-layer steel rod, wherein the lower-layer fixed structure is located at a position that does not interfere with the horizontal universal beam, one end of the lower-layer steel rod is inserted into one of the lower-layer pier stud reserved holes of the prefabricated pier stud, and the other end of the lower-layer steel rod is directly disposed in the lower-layer web reserved hole in the vertical universal beam.
7. The installation method of the bent cap for mutually restraining the adjacent pier studs in the prefabricated and assembled bridge according to claim 1, wherein: performing anchorage between each of the pile top cup bearing platforms and the corresponding prefabricated pier stud in step 4 comprises the following steps: pre-embedding a pier stud metal bellow on an outer circumferential surface of a lower section of the prefabricated pier stud, and forming a pier stud installation section having an outer circumferential surface being bellow-shaped; pre-embedding a cup metal bellow on a wall surface of a stud chamber in a cup mouth of each pile top cup bearing platform, forming a socket having a stud chamber wall surface being bellow-shaped, and pre-embedding a central steel pad (14) on a bottom surface of the stud chamber; and placing the pier stud installation section in the socket, forming an annular grouting chamber between circumferential surfaces of each other, forming a bottom plane grouting chamber on a bottom surface, and injecting a high-strength grouting material in the annular grouting chamber and the bottom plane grouting chamber to achieve the anchorage between the pile top cup bearing platform and the corresponding prefabricated pier stud.
8. The installation method of the bent cap for mutually restraining the adjacent pier studs in the prefabricated and assembled bridge according to claim 7, wherein both the pier stud metal bellow and the cup metal bellow adopt galvanized metal bellows, a thickness of the annular grouting chamber is 50 mm, and a thickness of the bottom plane grouting chamber is 20 mm.
Description
DESCRIPTION OF THE DRAWINGS
(1)
(2)
(3)
(4)
(5)
(6)
(7)
DESCRIPTION OF THE EMBODIMENTS
Description of the Embodiments
(8) With reference to
(9) With reference to
(10) Limiting steel rings 13 are fixedly arranged at two ends of a rectangular frame 12 of a steel structure, and steel bar sleeves 18 are vertically arranged in the limiting steel rings 13. The steel bar sleeves 18 are evenly distributed into a circular ring shape in each limiting steel ring 13 and form a steel bar sleeve ring with a radius r. A center-to-center distance of the steel bar sleeve rings at the two ends and a center-to-center distance of the bent cap pre-embedded sleeve rings at the two ends in the prefabricated bent cap are set to be identical. Positions of the steel bar sleeves 18 in the steel bar sleeve ring are set to correspond to positions of the bent cap pre-embedded sleeves 19 in the bent cap pre-embedded sleeve ring of the corresponding end one to one.
(11) An installation method of a bent cap for mutually restraining adjacent pier studs in a prefabricated and assembled bridge provided by this embodiment is performed in constructed pile top cup bearing platforms 1 through the following steps.
(12) In step 1, the pile top cup bearing platforms 1 are formed on pile foundations 11, the prefabricated pier studs 2 are placed in two adjacent pile top cup bearing platforms 1 through hoisting, and a center distance and a plane position between the two prefabricated pier studs 2 are preliminarily adjusted.
(13) In step 2: the cap bent mold base is hoisted on the top portions of the two prefabricated pier studs 2, such that the pier stud pre-embedded steel bars 15 protruding from the top portions of the two prefabricated pier studs are correspondingly inserted into the steel bar sleeves 18 at two ends of the bent cap mold base one by one. If the pier stud pre-embedded steel bars 15 in the two prefabricated pier studs and the steel bar sleeves 18 at the two ends of the bent cap mold base are not aligned due to deviation, the prefabricated pier studs are lifted again by a crane, the center distance and/or the plane position between the two prefabricated pier studs are readjusted until the pier stud pre-embedded steel bars 15 in the two prefabricated pier studs are correspondingly inserted into the vertical sleeves at the two ends of the bent cap mold base one by one, such that the adjacent two prefabricated pier studs 2 are limited in the bent cap mold base based on design needs.
(14) In step 3, heights and perpendicularity of the adjacent two prefabricated pier studs 2 are adjusted to satisfy the design needs, and the prefabricated pier studs 2 are kept in a state which satisfies the design needs.
(15) In step 4, anchorage is performed between each of the pile top cup bearing platforms 1 and the corresponding prefabricated pier stud 2 to complete assembly of the prefabricated pier studs 2.
(16) In step 5, the bent cap mold base is removed, the bent cap mold base is replaced with the bent cap, steel backing plates 16 are placed between the top portions of the pier studs and the bent cap, and the pier stud pre-embedded steel bars 15 protruding from the top portions of the prefabricated pier studs are inserted into the bent cap pre-embedded sleeves 19 pre-embedded in the bent cap one by one.
(17) In step 6, grouting is performed through the grouting ducts 17 on the bent cap, anchorage is performed between the prefabricated pier studs 2 and the prefabricated bent cap 22, and assembly of the prefabricated bent cap 22 is thus completed.
(18) In specific implementation, step 3 further includes the following step. An auxiliary adjustment mechanism is arranged to adjust the height and perpendicularity of each prefabricated pier stud 2.
(19) A structure of the auxiliary adjustment mechanism shown in
(20) A structure of each of the top support mechanisms is that a jack 8 is provided on the top surface of each pile top cup bearing platform 1. A reaction frame 3 having a horizontal support surface is provided on a corresponding position of the outer side wall of the prefabricated pier stud 2, and the jack 8 is supported between the top surface of the pile top cup bearing platform 1 and the support surface of the reaction frame 3.
(21) As shown in
(22) A fixed structure of the arranged reaction frame 3 is that: a web reserved hole 7 is provided on the web of the vertical universal beam 6. As shown in
(23) In specific implementation, in order to provide structural stability, the fixed structure of the reaction frame 3 is further provided with a lower-layer fixed structure formed by: a lower-layer web reserved hole 7a, lower-layer pier stud reserved holes 20a, and a lower-layer steel rod 4a. The lower-layer fixed structure is located at a position that does not interfere with the horizontal universal beam 5. One end of the lower-layer steel rod 4a is inserted into one of the lower-layer pier stud reserved holes 20a of the prefabricated pier stud, and the other end of the lower-layer steel rod 4a is directly disposed in the lower-layer web reserved hole 7a in the vertical universal beam 6.
(24) In addition, a center of the jack 8 should be as close as possible to the prefabricated pier stud 2 when operating conditions are met, so as to reduce concrete damage when the steel rod is inserted into a mouth portion. A circular pad 10 with a larger area than that of a bottom portion of the jack 8 may be placed on the bottom portion of the jack 8, so that a force may be evenly received.
(25) In this embodiment, the step of performing anchorage between each of the pile top cup bearing platforms 1 and the corresponding prefabricated pier stud 2 in step 4 further includes the following steps.
(26) As shown in
(27) The installation method of the bent cap for mutually restraining the adjacent pier studs in the prefabricated and assembled bridge provided by the disclosure is verified in the assembly construction of the assembly-type pier studs and bent caps of the reconstruction and expansion project of the Tai'an to Zaozhuang (Lu-Sujie) section of the Jingtai Expressway. The success rate of one-time assembly construction of pier studs and bent caps reaches 100%, and the construction efficiency is significantly improved. Construction difficulty of difficult construction matching and low accuracy found in assembly construction of prefabricated circular pier studs and prefabricated bent caps is effectively prevented, and a good application prospect is provided in the same type of assembly construction.