Method and brick configuration for sports field construction
10676876 ยท 2020-06-09
Assignee
Inventors
Cpc classification
E01C13/06
FIXED CONSTRUCTIONS
E01C13/02
FIXED CONSTRUCTIONS
International classification
E01C13/02
FIXED CONSTRUCTIONS
Abstract
A method and clay brick configuration for use in sports field construction having a generally rectangular paver like configuration with spaced parallel flat upper and lower surface portions with angular inclined spaced parallel side surfaces. Oppositely disposed substantially vertical end surfaces define the brick's overall length. The clay brick provides for interlocking surface to surface engagement during field construction and compaction in vertical and horizontal brick surface adjacent engagement placement.
Claims
1. The method of constructing an athletic field foundation using pre-formed clay bricks comprises, a. forming a clay bricks having flat spaced parallel upper and lower surfaces, spaced parallel transversely angular inclined sidewalls and opposing vertical end walls at right angular relation to said bricks upper and lower surfaces, b. installing a sub-surface layer of clay bricks arranged in abutting relationship to one another, c. installing a surface layer of loose clay compactable material over the sub-surface layer of clay bricks aligned in angular abutting relationship to one another, d. compacting the surface layer of loose clay compactable material and the sub-surface layer of the clay bricks, e. interlocking the sub-surface layer of clay bricks by force vector angular surface to angular surface engagement under loose clay compactable compression for translateral displacement, f. forming a co-mingled continuous monolithic layer of clay bricks by said force vector compaction.
2. The method of claim 1 wherein the clay brick arrangements in abutting relationship step comprises, placing said clay bricks in angular inclined sidewall abutment relationship.
3. The method of claim 1 wherein the clay brick arrangement abutting relationship step further comprises, placing said bricks in upper longitudinal, vertical and horizontal abutting relationship on said athletic field.
4. The method of claim 1 wherein forming clay bricks having flat spaced parallel upper and lower surfaces, spaced parallel transversely angular parallel sidewalls and opposing vertical end walls comprises, compaction extrusion of a clay blend of natural occurring materials through a spaced parallel angular extrusion dye plates.
5. The method of claim 1 wherein the interlocking sub-surface layers of clay bricks by force angular vector surface to surface engagement step comprises, applying vertical directional force to said abutting layers of clay brick by linear compaction application against said brick's upright surfaces.
6. The method of claim 1 wherein forming a co-mingled contiguous monolithic layer of clay bricks from force vector compaction further comprises, tangential force transfer directly between the angular vertical off axis abutting brick surfaces along a force transfer surface there between.
7. The method claim of claim 1 wherein said angular inclined sidewalls of said bricks are in a range of one degrees to 15 degrees off true vertical.
Description
DESCRIPTION OF THE DRAWINGS
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
DETAILED DESCRIPTION OF THE INVENTION
(9) Referring now to
(10) As such, the clay brick 10 is of a solid monolithic configuration formed, in this example, from compressed and collated naturally occurring clay and blended materials available for specialized sports filed construction, well known within the industry.
(11) The bricks 10 of the invention are formed, as noted, of a clay blend which is passed through a specialized extrusion dye 17, as seen best in
(12) Referring now to
(13) In this example, a top compaction layer 23 of a loose clay mixture material from which the bricks 10 are formed is shown overlying the multiple clay bricks 10 top surfaces 11. The top compaction layer 23 is illustrated prior to compaction at 23A and during at 23B. It will be seen that during the applied vertical force F, compression of the surface forming method step will coalesce the interengaged sidewalls 13 and 14 as described interlocking them to one another in a stable integral uniform clay layer assuring a stable construction surface critical to sports field formation features, as noted.
(14) Referring now to
(15) It will be evident, therefore, that due to the parallel angular inclination of the respective side surfaces 14 achieved by on side placement that a force vector FV transfer is achieved under vertical compaction induced by force arrow 24 and indicated by linear compaction application representation 25.
(16) The method step formation of a compacted playing surface PS is achieved by a compaction top layer 26A over the exposed horizontally aligned brick side surface 13 indicated a pre-compaction at 26 and during compaction at 26B.
(17) It will be evident that the side surface placement of the bricks 10 will achieve a thicker base as compared to the hereinbefore described side to side abutting relationships in
(18) Referring now to
(19) It will thus be seen that a new and novel sports field brick configuration and method step application has been illustrated and described and it will be apparent to those skilled in the art that various changes and modifications may be made thereto without departing from the spirit of the invention. Therefore,