TOP-TO-BOTTOM CONSTRUCTION SYSTEM
20200149240 ยท 2020-05-14
Inventors
Cpc classification
E02D5/48
FIXED CONSTRUCTIONS
E02D2300/0032
FIXED CONSTRUCTIONS
E02D15/08
FIXED CONSTRUCTIONS
E02D7/28
FIXED CONSTRUCTIONS
E02D5/03
FIXED CONSTRUCTIONS
E02D29/055
FIXED CONSTRUCTIONS
E02D5/34
FIXED CONSTRUCTIONS
E02D13/00
FIXED CONSTRUCTIONS
E02D2250/0023
FIXED CONSTRUCTIONS
International classification
E02D5/48
FIXED CONSTRUCTIONS
E02D13/00
FIXED CONSTRUCTIONS
E02D29/055
FIXED CONSTRUCTIONS
Abstract
Disclosed is a nesting element for use in a hollow pile. The nesting element is configured to be retained at an opening defined in a wall of the pile. The nesting element comprises a surface that is configured such that, in use, the surface substantially conforms to an internal profile at a transverse cross-section of the pile. Also disclosed are a pile system that employs one or more nesting elements in one or more respective piles, and an installation system for installing the pile system into the ground. Additionally, a method of constructing a retaining wall using the pile system and installation system is disclosed.
Claims
1-41. (canceled)
42. A nesting element for use in a hollow pile, the nesting element being configured to be retained at an opening defined in a side wall of the pile, the nesting element comprising a surface that is configured such that, in use, the surface substantially conforms to an internal profile at a transverse cross-section of the pile.
43. A nesting element as claimed in claim 42, wherein the surface extends generally orthogonally from a flange, and wherein the flange is configured to be arranged against an interior or exterior surface of the hollow pile to be retained thereat in use.
44. A nesting element as claimed in claim 43, wherein the nesting element further comprises at least one side wall that extends from the surface in a direction opposite to the flange.
45. A nesting element as claimed in claim 44, wherein the at least one side wall is configured to locate adjacent to an interior surface of the hollow pile in use.
46. A nesting element as claimed in claim 42, wherein the nesting element is configured to support one or more reinforcing bars that in-use extend vertically through the pile.
47. A nesting element as claimed in claim 46, wherein the surface is provided with one or more holes therethrough, each sized for a respective one of the one or more reinforcing bars, to support the rods at the surface, and to maintain a spacing between adjacent rods.
48. A nesting element as claimed in claim 42, wherein, when the hollow pile comprises a sheet pile having a rectangular box section extending for its length, the nesting element is correspondingly dimensioned to nest in the rectangular box section.
49. A nesting element as claimed in claim 48, wherein the surface defines an in-use upper surface of the nesting element, with the nesting element comprising two opposing side walls that each extend downwardly in use from respective opposing side edges of the upper surface, and a rear wall that extends downwardly in use from a rear edge of the upper surface.
50. A nesting element as claimed in claim 48, wherein the nesting element is open at least two sides thereof, with the two open sides being adjacent to one another; wherein a first of the two open sides is arranged to open outwardly of the sheet pile at the wall opening in use, and a second of the two open sides is arranged to open downwardly in the sheet pile in use.
51. A pile system comprising: a hollow pile that has at least one opening defined in a side wall of the pile; and a nesting element that is configured such that it is able to be retained at the at least one opening of the hollow pile, the nesting element comprising a surface that is configured such that, in use, the surface substantially conforms to an internal profile at a transverse cross-section of the pile.
52. A pile system as claimed in claim 51, wherein the hollow pile has a plurality of openings defined in and spaced out along the wall of the pile, with each opening being located to correspond to an adjacent floor level in use of the pile, and with a nesting element being provided for each opening.
53. A pile system as claimed in claim 51, the system comprising a plurality of hollow piles, wherein each of the hollow piles are configured to be connected to each other along their length whereby, when the hollow piles are connected together, they are thereby able to form a substantially self-supporting wall.
54. A pile system as claimed in claim 53, wherein each of the hollow piles comprises at least one male clutch and at least one corresponding female clutch, the male clutch projecting from a side wall of the hollow pile to extend longitudinally along the length of the side wall, and the female clutch being formed at a side wall of the hollow pile to extend longitudinally along the length of the side wall, the male and female clutches able to be aligned on adjacent piles whereby, when the hollow piles are connected together in-use via their clutches, they are thereby able to form a substantially smooth face along the wall.
55. A pile system as claimed in claim 54, wherein the male clutch is formed to project from an intermediate location along the side wall or is formed along a distal end of the side wall, and wherein the female clutch is respectively formed within the side wall at an intermediate location along the side wall or is formed along a distal end of the side wall.
56. A pile system as claimed in claim 55, wherein a rebate is provided within and along the length of the or each female clutch such that, in use, a sealing bead may be inserted into the rebate in use.
57. A pile system as claimed in claim 56, wherein, when the hollow piles have been connected together to form the wall, the system is configured to have a cementitious material poured into the connected piles at an open upper end of each of the hollow piles.
58. A pile system as claimed in claim 57, wherein, prior to pouring the cementitious material into the open upper end of each of the hollow piles, the system is configured to receive reinforcing vertically through each of the hollow piles.
59. A method of constructing a retaining wall, the method comprising: driving into ground a first mandrel having an elongate tubular internal profile that is correspondingly dimensioned to an external profile of a hollow pile; removing ground from within an interior of the first mandrel; driving into the ground a second mandrel that comprises an elongate channel having opposing elongate side walls that are connected to one another by a rear wall, each side wall being configured to connect with a side wall of an adjacent first mandrel to be guided thereby; removing ground from within an interior of the second mandrel; locating a hollow pile as defined in claim 10 within the first mandrel. removing the first mandrel from the ground; locating a hollow pile as defined in claim 10 within the second mandrel such that the hollow pile connects to the adjacent hollow pile that was located within the first mandrel; removing the second mandrel from the ground; and pouring a cementitious material into the hollow pile at an in-use open upper end thereof, with the cementitious material flowing down inside the pile until it reaches a surface of an in-use uppermost nesting element located at a respective wall opening.
60. A method as claimed in claim 59, wherein the retaining wall is constructed along a perimeter of a construction site and a slab of cementitious material is formed at the ground of the construction site perimeter, optionally with one or more slab support columns having first been formed into the ground, the method further comprising: excavating the ground under the slab down to a level that aligns with a line of nesting elements arranged in the hollow piles of the retaining wall at the site perimeter, the line of nesting elements being at a level that corresponds to a next floor slab; and pouring the next floor slab at the excavated ground level, the cementitious material being able to flow in through each of the pile wall and nesting element openings and into the respective hollow pile, so as to fill up the pile, either to a surface of a next lower nesting element, or to a base of the hollow pile.
61. A method as claimed in claim 60, wherein the method comprises as required, excavating ground under the next floor slab and pouring a further floor slab, with steps similar to those as set forth in claim 19 being repeated until a final base floor slab is formed at a lowermost level corresponding to a base of the retaining wall.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0071] Embodiments will now be described by way of example only, with reference to the accompanying drawings in which
[0072]
[0073]
[0074]
[0075]
[0076]
[0077]
[0078]
[0079]
[0080]
[0081]
[0082]
[0083]
[0084]
[0085]
[0086]
[0087]
[0088]
[0089]
DETAILED DESCRIPTION OF SPECIFIC EMBODIMENTS
[0090] In the following detailed description, reference is made to accompanying drawings which form a part of the detailed description. The illustrative embodiments described in the detailed description, depicted in the drawings and defined in the claims, are not intended to be limiting. Other embodiments may be utilised and other changes may be made without departing from the spirit or scope of the subject matter presented. It will be readily understood that the aspects of the present disclosure, as generally described hereafter and illustrated in the drawings can be arranged, substituted, combined, separated and designed in a wide variety of different configurations, all of which are contemplated in this disclosure.
[0091] The method of construction as described herein can be deployed in a so-called top-to-bottom construction methodology. The method can make use of a sheet pile such as those used for retaining walls, but modified for the top-to-bottom construction methodology. More particularly, the disclosure relates to the formation of a retaining wall structure at the perimeter of a construction site such as an underground basement, car park, cellar, etc. and upon which e.g. a multi-story construction may be erected.
[0092] Also described herein is a nesting element in the form of a stopper element, one or more of which can be used to modify each sheet pile, to make the sheet pile suitable for a stage-wise pouring thereinto of a cementitious material such as concrete. The stopper elements can enable floor slabs of the underground construction to key into each modified sheet pile as part of the top-to-bottom construction methodology. Also disclosed are components of a pile driving system which enable each modified sheet pile to be driven into the ground to form the retaining wall. The top-to-bottom construction methodology described herein can reduce time and construction costs, as well as simplifying existing underground construction techniques.
[0093] Referring firstly to
[0094] The opening (230) is defined in a side wall (240) of the sheet pile (200) to open into an elongate box section (201) of the sheet pile that extends generally centrally through the pile and provides a main structural spine thereof. In the embodiment of
[0095] The stopper element (100) can allow the sheet pile (200) to be employed in a top-to-bottom construction methodology. In this regard, the upper surface (102) of the stopper element (100) can stop the flow of a pour of concrete down through the box section (201), which has a number of benefits in the top-to-bottom methodology, as will also be described hereafter.
[0096] The upper surface (102) of the stopper element (100) is also configured such that, when the stopper element is located at the opening (230), surface (102) substantially conforms to an internal profile at a transverse cross-section of the box section (201). This substantial conformity does not exclude the upper surface (102) being spaced from an internal surface (210) of the sheet pile (200), but it does require the surface (102) to be sufficiently close to surface (210) so as not to allow concrete (150) that is poured into an open upper end of the box section (201) to pass through to a lower section of the pile.
[0097] As will be described in greater detail hereafter, this concrete-stop feature enables the sheet pile to be tied to a floor slab as the top-to-bottom construction method proceeds. This in turn means that construction is able to continue above and below the pile level presently under construction, i.e. once the concrete (150) has cured at a given level. This may be advantageous in improving the efficiency of the construction, potentially reducing construction times and associated costs.
[0098] Furthermore, for a small span floor area, the stopper element (100) can enables each sheet pile to key to and thus support a floor slab (
[0099] In the embodiment depicted, the stopper element (100) takes the form of a rectangular prism that is readily fabricated (e.g. welded from plate, moulded from tough plastic, etc.). The stopper element (100) comprises at least one, and in this case two side walls (20) that each extend downwardly in use from respective opposing side edges (21, 22) of the surface (102). The stopper element (100) additionally comprises a rear wall (25) that extends downwardly in use from a rear edge (23) of the surface (102). In use, each of the side walls (20) and rear wall (25) may closely face or abut a corresponding surface of the box section (201) of the sheet pile (200), to better support the stopper element (100) within the box section. The side walls (20) and rear wall (25) increase the structural rigidity of the stopper element (100) such that it is better able to support concrete (150) that impinges and weighs upon the surface (102) when poured into the box section (201) of the sheet pile (200) from above.
[0100] The stopper element (100) comprises a flange in the form of a peripheral retention lip (30) that surrounds a front face of the stopper element (100), with the lip (30) being connected to each of the surface (102) and side walls (20) and extending generally orthogonally therefrom. The lip (30) is configured to be arranged against an exterior surface of the sheet pile (200) and retains the stopper element (100) at the opening (230). The lip (30) helps to support the stopper element (100), such that the weight of concrete (150) on the surface is resisted and generally borne by the lip (30). The lip (30) may be affixed to the exterior surface of the sheet pile (e.g. bolted, screwed, adhered, etc.). Whilst the flange is shown in the form of a peripheral lip, it may simply comprise one or more tabs, etc. that can enable the stopper element (100) to be retained (e.g. affixed) at the opening (230).
[0101] When the pile is not in a sheet form, and has a different cross-sectional profile (e.g. tubular, triangular, square, hexagonal, etc.), the stopper element (100) can be reshaped accordingly, such as by assuming the shape as depicted in the embodiment of the stopper element (100) shown in
[0102] Regarding the stopper element (100) as shown in
[0103] As shown in
[0104] A pair of male clutches (220b) are formed to project from an intermediate location along a different side wall (240) to that of the female clutches. It is understood that a single side wall could have any number of either male or female clutches, or alternatively could have both male and female clutches, as suitable, to resist the tensile or torsional force loading on the clutches in use. The sheet pile (200) has an opening (230) that is defined in a side wall (240) of the pile (200) at which the stopper element shown in
[0105] The stopper element (100) can be configured to support one or more optional reinforcing bars/rods (110) that extend vertically in use through the box section (201) of the sheet pile (200). For example, the surface (102) can be provided with one or more holes (40) therethrough, each sized for a respective one of the reinforcing bars/rods (110). The stopper element (100) supports the reinforcing bars/rods (110) at the surface (102), and maintains a spacing between adjacent reinforcing bars/rods as concrete (150) flows into the sheet pile. Where the sheet pile (200) has multiple stopper elements (100) spaced out along its length, these work together to evenly support the reinforcing bars/rods (110) through the box section (201), maintaining a spacing between adjacent reinforcing bars/rods along the length of the sheet pile (200).
[0106] Typically, a plurality of sheet piles (200) with associated stopper elements (100) are pre-assembled (e.g. prior to being brought to a construction site). Each sheet pile may (
[0107] Each king pile (300) takes the form of a cylindrical (e.g. tube) pile. In use, each sheet pile (200) has a king pile (300) arranged and connected along either side thereof, such as depicted in
[0108] Typically, each sheet pile (200) has a plurality of openings (230) defined in and spaced out along the side wall (240) of the pile (200). For example, for a 12 metre length side wall (i.e. a length that can be permissibly transported on a truck), three intermediate openings (230) can be provided at 3 meter intervals along its length.
[0109] Each opening (230) is located to correspond to an adjacent floor level in use of the pile (200). For example, as shown in
[0110] Each of the sheet piles (200) and king piles (300) are configured along respective sides thereof to be connected to each other along their length, such as depicted by
[0111] In this regard, as depicted in
[0112] Once the sheet (200) and king (300) piles have been connected together, and optionally reinforced, to form the wall, concrete (150) is poured into the piles at an open upper end of each of each pile such as that depicted in
[0113] In an alternative embodiment, as shown in
[0114] In some embodiments, the sheet piles and stopper elements can be manufactured from plastics or composite materials. In other embodiments, the sheet piles and stopper elements can be manufactured from steel.
[0115] To drive the sheet piles (200) into the ground a pile driving installation system is employed.
[0116] As depicted in
[0117] The mandrel (500) further comprises two spaced elongate pin members (510) that each extend from the mandrel head (550) to locate and extend between a respective one of the sets of sheet pile flanges (220). In this way, the mandrel (500) better engages with the sheet pile (200) during pile driving. After pile driving, the pin members (510) can be slidingly withdrawn from the sheet pile (200). Each pin member (510) is configured to extend beyond the sheet pile (200) lower end in use as shown. Each pin member (510) further comprises a pointed end (520) to facilitate its insertion into the ground.
[0118] The drive installation system further comprises an attachment in the form of a wedge (530) for location at an in-use open lower end of the sheet pile (200) as depicted in
[0119] The drive installation system further comprises a detachable cover plate (560) for each stopper element (100), when the latter is located in the sheet pile (200) side wall opening (230). The cover plate (560) is releasably secured to the stopper element (100) at the side wall opening (230) (i.e. for subsequent removal during a construction phasei.e. to allow for the inflow of concrete into the sheet pile). The cover plate (560) is also configured to prevent ground matter (earth) from entering the hollow pile during driving of the sheet pile into the ground.
[0120] In an alternative embodiment of the pile driving installation system, box section mandrels can be used instead of driving the individual sheet piles. This alternative installation system comprises a first box section mandrel (600) as shown in
[0121] A second mandrel (610), as illustrated in
[0122] In some embodiments, it may be advantageous to drive the first mandrel (600) and multiple second mandrels (610) prior to drilling, and then to drill out each thereafter. In some embodiments, there may be a need only to use two second mandrels (610), i.e. that are reused repetitively to create the entire retaining wall.
[0123] The second mandrel can generally take the form of elongate channel having opposing elongate side walls (640) that are connected to one another by a rear wall (630). Each side wall (640) has a female clutch (622) proximal the distal ends of the side wall (64), the female clutch (622) being configured to engage a corresponding and respective male clutch (620) of an adjacent mandrel. The corresponding and respective male clutch (620) may project from one of either; the opposing sides walls (640A or 640B) of an adjacent first mandrel (600), the opposing side walls (640) of an adjacent second mandrel (610A) or the same side wall of an adjacent second mandrel (610C). As can be seen in
[0124] Regardless of the specific configuration, the connection of male and female clutches between mandrels enables the guided driving of a subsequent second mandrel (either after a first or a second mandrel) into the ground.
[0125] The pile driving installation system, where box section mandrels are used, can be advantageous in that the clutches of the sheet piles are not exposed to contamination with dirt nor are they subjected to shear and other damaging impact forces during the driving process.
[0126] In some embodiments, as seen in
[0127]
[0128] In each case, a first mandrel (600) is driven into the ground, and a second mandrel (610) is driven adjacent to the first mandrel (600). The first (600) and second (610) mandrels are aligned to connect along their clutches, and the second mandrel (610) is thus guided into the correct alignment alongside the first mandrel (600) during driving. Further, additional second mandrels (610) can then be driven into the ground alongside either the first (600), second (610), etc mandrels as required. The ground within an interior of the first mandrel (600) and second mandrel (61) is then removed (such as by drilling, etc.). A sheet pile (200) can then be located within the hollow first mandrel (600). Once the first mandrel (600) is removed from the ground, a second sheet pile (200) can then be located within the hollow second mandrel (610) that sits adjacent the sheet pile (200) by sliding the second sheet pile along the clutches (i.e. as shown in
[0129]
[0130] The method then comprises pouring concrete (150) into each pile (200, 300) at the in-use open upper end thereof. Each may be reinforced as set forth above. The concrete flows down inside each sheet pile until it reaches a surface (102) of the uppermost stopper element (100) located at a respective wall opening (230) such as depicted in
[0131] As also depicted in
[0132] As depicted in
[0133] The top-to-bottom construction methodology to be implemented will be described hereafter with further reference to
[0134] As depicted in
[0135] As depicted in
[0136] As depicted in
[0137] In an alternative mode of the top-to-bottom method, each floor slab (410, 420, 430, 450) may be formed in sequence, moving down floor-by-floor from the ground level floor slab (400). Thus, each level is excavated is sequence.
[0138] Variations and modifications may be made to the parts previously described without departing from the spirit or ambit of the disclosure.
[0139] In the claims which follow and in the preceding description, except where the context requires otherwise due to express language or necessary implication, the word comprise or variations such as comprises or comprising is used in an inclusive sense, i.e. to specify the presence of the stated features but not to preclude the presence or addition of further features in various embodiments.