Construction machine
10633825 ยท 2020-04-28
Assignee
Inventors
- Hidekazu MORIKI (Tokyo, JP)
- Hiroshi SAKAMOTO (Tsuchiura, JP)
- Hiroaki TANAKA (Tsuchiura, JP)
- Yasutaka Tsuruga (Tsuchiura, JP)
Cpc classification
F15B11/08
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F15B11/02
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F15B11/028
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
E02F3/43
FIXED CONSTRUCTIONS
E02F9/2029
FIXED CONSTRUCTIONS
F15B11/044
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
E02F9/2221
FIXED CONSTRUCTIONS
International classification
F15B11/044
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F15B11/028
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F15B11/17
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F15B11/08
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
Abstract
The construction machine includes: a work implement driven by a first hydraulic actuator and a second hydraulic actuator; a first directional control valve controlling a flow rate and a direction of a hydraulic fluid supplied to the first hydraulic actuator; a first speed-up directional control valve provided in a second pump line and controlling a flow rate and a direction of a hydraulic fluid supplied to the first hydraulic actuator; a second directional control valve controlling a flow rate and a direction of a hydraulic fluid supplied to the second hydraulic actuator; an excavation load sensor that detects an excavation load imposed on the work implement; and a first speed-up control section that drives the first speed-up directional control valve, and the first speed-up control section is configured to control a driving amount of the first speed-up directional control valve in response to the excavation load.
Claims
1. A construction machine comprising: a first hydraulic actuator; a second hydraulic actuator; a work implement driven by the first hydraulic actuator and the second hydraulic actuator; a first hydraulic pump; a second hydraulic pump; a first directional control valve provided in a first pump line that is a delivery hydraulic line of the first hydraulic pump and controlling a flow rate and a direction of a hydraulic fluid supplied to the first hydraulic actuator; a first speed-up directional control valve provided in a second pump line that is a delivery hydraulic line of the second hydraulic pump and controlling a flow rate and a direction of a hydraulic fluid supplied to the first hydraulic actuator; and a second directional control valve provided in the second pump line that is the delivery hydraulic line of the second hydraulic pump and controlling a flow rate and a direction of a hydraulic fluid supplied to the second hydraulic actuator, wherein the construction machine includes: an excavation load sensor that detects an excavation load imposed on the work implement; and a first speed-up control section that drives the first speed-up directional control valve, and the first speed-up control section is configured to control a driving amount of the first speed-up directional control valve in response to the excavation load detected by the excavation load sensor.
2. The construction machine according to claim 1, wherein the work implement includes a boom and an arm, the first hydraulic actuator is a boom cylinder that drives the boom, the second hydraulic actuator is an arm cylinder that drives the arm, the excavation load sensor is an arm cylinder bottom-chamber-side pressure sensor that measures a pressure of a bottom-side hydraulic chamber of the arm cylinder, and the first speed-up control section is configured to control the driving amount of the first speed-up directional control valve in response to the pressure of the bottom-side hydraulic chamber of the arm cylinder measured by the arm cylinder bottom-chamber-side pressure sensor.
3. The construction machine according to claim 1, wherein the work implement includes a boom and an arm, the first hydraulic actuator is a boom cylinder that drives the boom, the second hydraulic actuator is an arm cylinder that drives the arm, the excavation load sensor is an arm cylinder bottom-chamber-side pressure sensor that measures a pressure of a bottom-side hydraulic chamber of the arm cylinder and a boom cylinder bottom-chamber-side pressure sensor that measures a pressure of a bottom-side hydraulic chamber of the boom cylinder, and the first speed-up control section is configured to control the driving amount of the first speed-up directional control valve on the basis of a deviation between the pressure of the bottom-side hydraulic chamber of the boom cylinder measured by the boom cylinder bottom-chamber-side pressure sensor and the pressure of the bottom-side hydraulic chamber of the arm cylinder measured by the arm cylinder bottom-chamber-side pressure sensor.
4. The construction machine according to claim 3, wherein the first speed-up control section is configured to exercise control such that an opening area of the first speed-up directional control valve is made smaller as the deviation between the pressure of the bottom-side hydraulic chamber of the boom cylinder and the pressure of the bottom-side hydraulic chamber of the arm cylinder is smaller, and such that the opening area of the first speed-up directional control valve is made larger as the pressure of the bottom-side hydraulic chamber of the arm cylinder is higher.
5. The construction machine according to claim 1, further comprising a target surface distance acquisition section that measures or computes a target surface distance that is a distance between a target surface subjected to work conducted by the work implement and the work implement, wherein the first speed-up control section is configured to exercise control such that the driving amount of the first speed-up directional control valve is corrected in response to the target surface distance.
6. The construction machine according to claim 1, wherein the first directional control valve and the first speed-up directional control valve are driven by a pilot hydraulic fluid generated by a pilot hydraulic fluid source, the first directional control valve and the first speed-up directional control valve each include a meter-out opening that communicates a discharge-side hydraulic chamber of the first hydraulic actuator with a hydraulic tank, and a value of the pilot pressure at which the meter-out opening of the first speed-up directional control valve starts to open is set lower than a value of the pilot pressure at which the meter-out opening of the first directional control valve starts to open.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
MODES FOR CARRYING OUT THE INVENTION
(13) Embodiments of a construction machine according to the present invention will be described hereinafter with reference to the drawings.
First Embodiment
(14)
(15) The work implement 15 is attached to a front portion of the upper swing structure 10 in such a manner as to be able to be elevated. The upper swing structure 10 is provided with an operation room. Operation devices such as a travel right operation lever device 1a, a travel left operation lever device 1b, and a right operation lever device 1c and a left operation lever device 1d for instructing behavior of the work implement 15 and a swing motion are disposed in the operation room.
(16) The work implement 15 has a multijoint structure having a boom 11, an arm 12, and a bucket 8. The boom 11 rotates vertically with respect to the upper swing structure 10 by extension/contraction of a boom cylinder 5, the arm 12 rotates vertically and longitudinally with respect to the boom 11 by extension/contraction of an arm cylinder 6, and the bucket 8 rotates vertically and longitudinally with respect to the arm 12 by extension/contraction of a bucket cylinder 7.
(17) Furthermore, the work implement 15 includes, for calculating a position of the work implement 15, an angle sensor 13a that is provided near a coupling portion between the upper swing structure 10 and the boom 11 and that detects an angle of the boom 11, an angle sensor 13b that is provided near a coupling portion between the boom 11 and the arm 12 and that detects an angle of the arm 12, and an angle sensor 13c that is provided near the arm 12 and the bucket 8 and that detects an angle of the bucket 8. Angle signals detected by these angle sensors 13a to 13c are inputted to a main controller 100 to be described later.
(18) A control valve 20 controls a flow (a flow rate and a direction) of a hydraulic fluid supplied from the hydraulic pump device 2 to each of hydraulic actuators including the boom cylinder 5, the arm cylinder 6, the bucket cylinder 7, and the left and right travel hydraulic motors 3b and 3a described above.
(19)
(20) In
(21) The hydraulic pump device 2 includes a first hydraulic pump 21 and a second hydraulic pump 22. The first hydraulic pump 21 and the second hydraulic pump 22 are driven by the engine 14, and deliver hydraulic fluids to a first pump line L1 and a second pump line L2, respectively. While the first hydraulic pump 21 and the second hydraulic pump 22 will be described as fixed displacement hydraulic pumps in the present embodiment, the present invention is not limited to this and the hydraulic pump device 2 may be configured with variable displacement hydraulic pumps.
(22) The control valve 20 is configured with a dual pump line system composed by the first pump line L1 and the second pump line L2. A boom directional control valve 23 that serves as a first directional control valve is connected to the first pump line L1, and the hydraulic fluid delivered by the first hydraulic pump 21 is supplied to the boom cylinder 5. Likewise, a boom speed-up directional control valve 24 that serves as a first speed-up directional control valve and an arm directional control valve 25 that serves as a second directional control valve are connected to the second pump line L2, and the hydraulic fluid delivered by the second hydraulic pump 22 is supplied to the boom cylinder 5 and the arm cylinder 6. It is noted that the boom speed-up directional control valve 24 and the arm directional control valve 25 are configured to be able to divert the hydraulic fluid by a parallel circuit L2a.
(23) The first pump line L1 and the second pump line L2 are individually provided with relief valves 26 and 27, respectively. When a pressure of each of the pump lines reaches a preset relief pressure, the relief valve 26 or 27 opens to relieve the hydraulic fluid to a tank.
(24) The boom directional control valve 23 is driven to move by a pilot hydraulic fluid supplied to a pressure receiving section via solenoid proportional valves 23a and 23b. Likewise, the boom speed-up directional control valve 24 moves by supplying a pilot hydraulic fluid to a pressure receiving section of the boom speed-up directional control valve 24 via solenoid proportional valves 24a and 23b (note that the solenoid proportional valve 23b is also used for moving the boom directional control valve 23), and the arm directional control valve 25 moves by supplying a pilot hydraulic fluid to a pressure receiving section of the arm directional control valve 25 via solenoid proportional valves 25a and 25b.
(25) These solenoid proportional valves 23a, 23b, 24a, 25a, and 25b each output a secondary pilot hydraulic fluid, which is obtained by reducing a pressure of the pilot hydraulic fluid supplied from a pilot hydraulic fluid source 29 as an original pressure at a pressure in response to a command current from the main controller 100, to the directional control valves 23 to 25.
(26) The right operation lever device 1c outputs, as a boom operation signal, a voltage signal in response to an operation amount and an operation direction of an operation lever to the main controller 100. Likewise, the left operation lever device 1d outputs, as an arm operation signal, a voltage signal in response to an operation amount and an operation direction of an operation lever to the main controller 100.
(27) The boom cylinder 5 is provided with a boom cylinder bottom-chamber-side pressure sensor 5b that detects a pressure of a bottom-side hydraulic chamber, and the arm cylinder 6 is provided with an arm cylinder bottom-chamber-side pressure sensor 6b that detects a pressure of a bottom-side hydraulic chamber and that serve as an excavation load sensor as in claims. The boom cylinder bottom-chamber-side pressure sensor 5b and the arm cylinder bottom-chamber-side pressure sensor 6b each output a detected pressure signal to the main controller 100.
(28) A mode setting switch 32 is disposed within the operation room, and enables an operator to select whether to enable or disable semiautomatic control in work conducted by the construction machine. That is, either True: the semiautomatic control enabled or False: the semiautomatic control disabled can be selected.
(29) The main controller 100 inputs a semiautomatic control enable flag transmitted from the mode setting switch 32, target surface information transmitted from the information controller 200, the boom angle signal and the arm angle signal transmitted from the angle sensors 13a and 13b, respectively, and the boom bottom pressure signal and the arm bottom pressure signal transmitted from the boom cylinder bottom-chamber-side pressure sensor 5b and the arm cylinder bottom-chamber-side pressure sensor 6b, respectively. The main controller 100 outputs command signals to the solenoid proportional valves 23a, 23b, 24a, 25a, and 25b for driving them respectively in response to these input signals. It is noted that computing performed by the information controller 200 is of no direct relevance to the present invention; thus, a description thereof will be omitted.
(30) Next, the main controller 100 that configures the first embodiment of the construction machine according to the present invention will be described with reference to the drawings.
(31) As shown in
(32) The target pilot pressure computing section 110 input the boom operation amount signal from the right operation lever device 1c and the arm operation amount signal from the left operation lever device 1d. The target pilot pressure computing section 110 computes a boom raising target pilot pressure, a boom lowering target pilot pressure, an arm crowding target pilot pressure, and an arm dumping target pilot pressure in response to the input signals, and outputs the computed pressures to the main spool control section 140. It is noted that the boom raising target pilot pressure is set higher as a boom operation amount is larger in a boom raising direction, and that the boom lowering target pilot pressure is set higher as the boom operation amount is larger in a boom lowering direction. Likewise, the arm crowding target pilot pressure is set higher as an arm operation amount is larger in an arm crowding direction, and that the arm dumping target pilot pressure is set higher as the arm operation amount is larger in an arm dumping direction.
(33) The work implement position acquisition section 120 inputs the boom angle signal and the arm angle signal from the angle sensors 13a and 13b, computes a tip end position of the bucket 8 in response to the input signals by using preset geometric information on the boom 11 and the arm 12, and outputs the computed tip end position, as a work implement position signal, to the target surface distance acquisition section 130. It is noted that the work implement position is computed as, for example, one point on a coordinate system fixed to the construction machine. However, the work implement position is not limited to this but may be computed as a plurality of point groups taking into account the shape of the work implement 15. Alternatively, the work implement position acquisition section 120 may perform computing similar to that performed by the locus controller for the construction machine described in Patent Document 1.
(34) The target surface distance acquisition section 130 inputs the target surface information transmitted from the information controller 200 and the work implement position signal from the work implement position acquisition section 120, computes a distance between the work implement 15 and a construction target surface (hereinafter, referred to as target surface distance), and outputs the target surface distance to the main spool control section 140 and the boom speed-up control section 150. It is noted that the target surface information is given as, for example, two points on a two-dimensional plane coordinate system fixed to the construction machine. However, the target surface information is not limited to this but may be given as three points that configure a plane on a global three-dimensional coordinate system. In the latter case, however, it is required to perform coordinate transformation from the three-dimensional coordinate system into a coordinate system same as that on which the work implement position is defined. Furthermore, when computing the work implement position as the point groups, the target surface distance acquisition section 130 may compute the target surface distance using a point closest to the target surface information. Alternatively, the target surface distance acquisition section 130 may perform computing similar to that performed by the locus controller for the construction machine described in Patent Document 1 to compute a shortest distance h.
(35) The main spool control section 140 inputs the semiautomatic control enable flag transmitted from the mode setting switch 32, the boom raising target pilot pressure, the boom lowering target pilot pressure, the arm crowding target pilot pressure, and the arm dumping target pilot pressure from the target pilot pressure computing section 110, and a target surface distance signal from the target surface distance acquisition section 130. When the semiautomatic control enable flag is True, the main spool control section 140 performs computing to correct the target pilot pressures in response to the target surface distance, computes a boom raising solenoid valve drive signal, a boom lowering solenoid valve drive signal, an arm crowding solenoid valve drive signal, and an arm dumping solenoid valve drive signal, and outputs these signals as drive signals for driving the solenoid proportional valves 23a, 23b, 25a, and 25b corresponding to the drive signals. Details of the computing performed by the main spool control section 140 will be described later.
(36) The boom speed-up control section 150 inputs the semiautomatic control enable flag transmitted from the mode setting switch 32, a boom raising control pilot pressure from the main spool control section 140, the target surface distance signal from the target surface distance acquisition section 130, the boom cylinder bottom-side hydraulic chamber pressure signal (hereinafter, also referred to as boom bottom pressure signal) and the arm cylinder bottom-side hydraulic chamber pressure signal (hereinafter, also referred to as arm bottom pressure signal) transmitted from the pressure sensors 5b and 6b, respectively. The boom speed-up control section 150 performs computing to correct the boom raising target pilot pressure, computes a boom raising speed-up solenoid valve drive signal, and outputs the drive signal as a drive signal for driving the solenoid proportional valve 24a. Details of the computing performed by the boom speed-up control section 150 will be described later.
(37) An example of the computing performed by the main spool control section 140 will be described with reference to
(38) The boom raising corrected pilot pressure table 141 inputs the target surface distance signal, computes a boom raising corrected pilot pressure using a preset table, and outputs the boom raising corrected pilot pressure to the maximum value selector 142. The maximum value selector 142 inputs the boom raising target pilot pressure and the boom raising corrected pilot pressure, selects a maximum value between the boom raising target pilot pressure and the boom raising corrected pilot pressure, and outputs the maximum value to a second input terminal of the selector 145a. The boom raising corrected pilot pressure table 141 is set such that the boom raising corrected pilot pressure becomes higher as the target surface distance becomes larger in a negative direction, that is, as the work implement 15 gets deeper into the target surface. It is thereby possible to perform a boom raising motion in response to the target surface distance and prevent the work implement 15 from getting into the target surface.
(39) The selector 145a inputs the boom raising target pilot pressure signal through a first input terminal thereof, an output signal from the maximum value selector 142 described above through the second input terminal, and a semiautomatic control enable flag signal through a switched input terminal thereof. The selector 145a selects and outputs the boom raising target pilot pressure signal when the semiautomatic control enable flag signal is False, and selects and outputs the maximum value between the boom raising target pilot pressure signal and the boom raising corrected pilot pressure signal when the semiautomatic control enable flag signal is True. An output signal from the selector 145a is outputted, as a boom raising control pilot pressure signal, to the solenoid valve drive signal table 146a and the boom speed-up control section 150.
(40) The solenoid valve drive signal table 146a computes and outputs the solenoid valve drive signal in response to the input boom raising control pilot pressure signal by using a preset table to drive the solenoid proportional valve 23a. Likewise, the solenoid valve drive signal table 146b computes and outputs the solenoid valve drive signal in response to the input boom raising/lowering target pilot pressure signal by using a preset table to drive the solenoid proportional valve 23b.
(41) The arm crowding corrected pilot pressure gain table 143 inputs the target surface distance signal, computes an arm crowding corrected pilot pressure gain in response to the target surface distance by using a preset table, and outputs the arm crowding corrected pilot pressure gain to the multiplier 144. The multiplier 144 inputs the arm crowding target pilot pressure and the arm crowding corrected pilot pressure gain, multiplies the input arm crowding target pilot pressure by the input arm crowding corrected pilot pressure gain, and outputs a multiplication result to a second input terminal of the selector 145c. The arm crowding corrected pilot pressure gain table 143 is set such that the arm crowding corrected pilot pressure becomes lower as the target surface distance becomes larger in the negative direction, that is, as the work implement 15 gets deeper into the target surface. It is thereby possible to reduce an arm crowding speed in response to the target surface distance and prevent the work implement 15 from getting into the target surface.
(42) The selector 145c inputs the arm crowding target pilot pressure signal through a first input terminal thereof, an output signal from the multiplier 144 described above through the second input terminal, and the semiautomatic control enable flag signal through a switched input terminal thereof. The selector 145c selects and outputs the arm crowding target pilot pressure signal when the semiautomatic control enable flag signal is False, and selects and outputs an arm crowding corrected pilot pressure signal obtained by multiplying the arm crowding target pilot pressure signal by the arm crowding corrected pilot pressure gain when the semiautomatic control enable flag signal is True. An output signal from the selector 145c is outputted, as the arm crowding control pilot pressure signal, to the solenoid valve drive signal table 146c.
(43) The solenoid valve drive signal table 146c computes and outputs the solenoid valve drive signal in response to the input arm crowding control pilot pressure signal by using a preset table to drive the solenoid proportional valve 25a. Likewise, the solenoid valve drive signal table 146d computes and outputs the solenoid valve drive signal in response to the input arm dumping target pilot pressure signal by using a preset table to drive the solenoid proportional valve 25b.
(44) It is noted that the boom raising target pilot pressure and the arm crowding target pilot pressure may be corrected by vector direction correction described in Patent Document 1.
(45) Next, an example of the computing performed by the boom speed-up control section 150 will be described with reference to
(46) The subtracter 151 inputs the boom bottom pressure signal and the arm bottom pressure signal, computes a pressure deviation by subtracting the arm bottom pressure signal from the boom bottom pressure signal, and outputs the pressure deviation to the pilot pressure upper limit value table 152. It is noted that the pressure deviation getting smaller indicates an increase of an arm bottom pressure relative to a boom bottom pressure, which in turn indicates an increase of an excavation load imposed on the work implement 15. The pilot pressure upper limit value table 152 computes a pilot pressure upper limit value in response to the input pressure deviation by using a preset table, and outputs the pilot pressure upper limit value to the maximum value selector 155.
(47) The pilot pressure upper limit value table 152 is set such that the pilot pressure upper limit value becomes lower as the pressure deviation between the boom bottom pressure signal and the arm bottom pressure signal becomes smaller, that is, the excavation load imposed on the work implement 15 becomes heavier. Thus, when the excavation load increases, it is detected that the arm bottom pressure increases and the deviation between the arm bottom pressure and the boom bottom pressure becomes smaller, and a boom raising speed-up pilot pressure delivered by the solenoid proportional valve 24a is suppressed to limit a meter-in opening of the boom speed-up directional control valve 24. As a result, diversion of the hydraulic fluid from the second hydraulic pump 22 to the boom cylinder 5 is suppressed and a speed balance is kept between the arm cylinder 6 and the boom cylinder 5; thus, it is possible to attain predetermined finishing precision.
(48) The second pilot pressure upper limit value table 153 computes a second pilot pressure upper limit value in response to the input arm bottom pressure signal by using a preset table, and outputs the second pilot pressure upper limit value to the maximum value selector 155. The second pilot pressure upper limit value table 153 is set such that the second pilot pressure upper limit value becomes higher as the arm bottom pressure signal becomes higher. It is noted that the arm bottom pressure indicated by a dotted line A in
(49) The third pilot pressure upper limit value table 154 inputs the target surface distance signal, computes a third pilot pressure upper limit value using a preset table, and outputs the third pilot pressure upper limit value to the maximum value selector 155. The third pilot pressure upper limit value table 154 is set such that the second pilot pressure upper limit value becomes higher as the target surface distance becomes larger. This setting makes it possible to ensure the diversion of the hydraulic fluid from the second hydraulic pump 22 to the boom cylinder 5 and avoid the relief-caused loss when the work implement 15 is at a distant position from the target surface.
(50) The maximum value selector 155 inputs the pilot pressure upper limit value, the second pilot pressure upper limit value, and the third pilot pressure upper limit value, corrects the pilot pressure upper limit value by selecting a maximum value among the pilot pressure upper limit value, the second pilot pressure upper limit value, and the third pilot pressure upper limit value, and outputs the corrected pilot pressure upper limit value to the minimum value selector 156.
(51) The minimum value selector 156 inputs the boom raising control pilot pressure generated by operator's lever operation and the pilot pressure upper limit value from the maximum value selector 155, corrects the boom raising control pilot pressure by selecting a minimum value between the boom raising control pilot pressure and the pilot pressure upper limit value, and outputs the corrected boom raising control pilot pressure to a second input terminal of the selector 157.
(52) The selector 157 inputs the boom raising control pilot pressure signal through a first input terminal thereof, an output signal from the minimum value selector 156 described above through the second input terminal, and the semiautomatic control enable flag signal through a switched input terminal thereof. The selector 157 selects and outputs the boom raising control pilot pressure signal when the semiautomatic control enable flag signal is False, and selects and outputs a value obtained by correcting the boom raising control pilot pressure in response to the boom bottom pressure, the arm bottom pressure, and the target surface distance when the semiautomatic control enable flag signal is True. An output signal from the selector 157 is outputted to the solenoid valve drive signal table 158.
(53) The solenoid valve drive signal table 158 computes and outputs the boom raising speed-up solenoid valve drive signal in response to the boom raising control pilot pressure by using a preset table to drive the solenoid proportional valve 24a.
(54) Next, a computing flow of the boom speed-up control section 150 will be described with reference to
(55) The boom speed-up control section 150 in the main controller 100 determines whether the semiautomatic control is enabled or disabled (Step S101). Specifically, the boom speed-up control section 150 determines whether the semiautomatic control enable flag signal is True or False. When the semiautomatic control enable flag signal is True, the flow goes to (Step S102); otherwise, the flow goes to RETURN.
(56) The boom speed-up control section 150 computes the pilot pressure upper limit value, the second pilot pressure upper limit value, and the third pilot pressure upper limit value (Steps S102, S103, and S104). Specifically, the pilot pressure upper limit value table 152, the second pilot pressure upper limit value table 153, and the third pilot pressure upper limit value table 154 execute the computing.
(57) The boom speed-up control section 150 determines whether the pilot pressure upper limit value exceeds the second pilot pressure upper limit value or not (Step S105). When the pilot pressure upper limit value exceeds the second pilot pressure upper limit value, the flow goes to (Step S107); otherwise, the flow goes to (Step S106).
(58) When the pilot pressure upper limit value does not exceed the second pilot pressure upper limit value in (Step S105), the boom speed-up control section 150 sets the pilot pressure upper limit value to the second pilot pressure upper limit value (Step S106). The flow then goes to (Step S107).
(59) The boom speed-up control section 150 determines whether the pilot pressure upper limit value exceeds the third pilot pressure upper limit value (Step S107). When the pilot pressure upper limit value exceeds the third pilot pressure upper limit value, the flow goes to (Step S109); otherwise, the flow goes to (Step S108).
(60) When the pilot pressure upper limit value does not exceed the third pilot pressure upper limit value in (Step S107), the boom speed-up control section 150 sets the pilot pressure upper limit value to the third pilot pressure upper limit value (Step S108). The flow then goes to (Step S109).
(61) The boom speed-up control section 150 determines whether the boom raising control pilot pressure is lower than the pilot pressure upper limit value (Step S109). When the boom raising control pilot pressure is lower than the pilot pressure upper limit value, the flow goes to RETURN and the boom raising speed-up solenoid valve 24a is controlled in response to the boom raising control pilot pressure. In this case, controlling a driving amount of the boom speed-up directional control valve 24 depending on the excavation load or the like, which is characteristic of the present invention, is not executed. When the boom raising control pilot pressure is not lower than the pilot pressure upper limit value, the flow goes to (Step S110).
(62) When the boom raising control pilot pressure is not lower than the pilot pressure upper limit value in (Step S109), the boom speed-up control section 150 sets the boom raising control pilot pressure to the pilot pressure upper limit value (Step S110). Specifically, the boom raising speed-up solenoid valve 24a is controlled in response to the pilot pressure upper limit value. As a result, the controlling the driving amount of the boom speed-up directional control valve 24 depending on the excavation load or the like is executed; thus, it is possible to suppress the diversion and prevent the deviation from the target locus while avoiding the relief-caused loss even when the excavation load increases.
(63) Next, behavior of the first embodiment of the construction machine according to the present invention will be described with reference to the drawings.
(64)
(65) In
(66) In
(67) When the arm bottom pressure becomes higher than the boom bottom pressure at time T1, the diversion amount of the hydraulic fluid passing through the boom speed-up directional control valve 24 increases; thus, the boom cylinder speed increases and the arm cylinder speed decreases as shown in (b). As a result, the target surface distance increases. In other words, a problem occurs that the work implement 15 moves away from the construction target surface.
(68) Next, the behavior in the present embodiment will be described with reference to
(69) This is because the control exercised by the boom speed-up control section 150 limits the pilot pressure acting on the boom speed-up directional control valve 24 in response to the arm bottom pressure. As a result, the target surface distance is kept around 0 as shown in (a).
(70) According to the first embodiment of the construction machine of the present invention described above, the second directional control valve and the first speed-up directional control valve are configured to be able to divert the hydraulic fluid and the driving amount of the first speed-up directional control valve is controlled in response to the excavation load. Therefore, even when the excavation load increases, it is possible to suppress the diversion and prevent the deviation from the target locus while avoiding the relief-caused loss. As a consequence, it is possible to ensure predetermined finishing precision.
Second Embodiment
(71) A second embodiment of the construction machine according to the present invention will be described hereinafter with reference to the drawings.
(72) While a configuration of a hydraulic drive system in the second embodiment of the construction machine according to the present invention is generally the same as that in the first embodiment, the second embodiment differs from the first embodiment in that opening area characteristics for the pilot pressures are changed from ordinary characteristics according to the conventional technique.
(73) In
(74) In the conventional technique, as shown in
(75) In the present embodiment, by contrast, the boom directional control valve 23 is set such that the meter-in opening area starts to increase earlier than the meter-out opening area for the boom raising pilot pressure as shown in (a) of
(76) Setting the opening area characteristics in this way makes it possible to adjust the meter-out opening areas for the boom only by the boom speed-up directional control valve 24 in a region in which the pilot pressure is low, that is, in a region in which the boom speed is low.
(77) For example, in the present embodiment, comparing a case in which the boom raising pilot pressure is applied as Pi1 indicated by a broken line shown in (a) of
(78) Owing to this, in the present embodiment, when the boom raising speed-up pilot pressure is limited in a case, for example, in which the excavation load increases, the meter-out opening area of the boom speed-up directional control valve 24 can be reduced simultaneously with closing of the meter-in opening thereof; thus, it is possible to increase a boom rod pressure. This can prevent a reduction of the load pressure of the boom cylinder 5 in an extension direction thereof due to the excavation reaction force and, therefore, keep the speed balance between the arm cylinder 6 and the boom cylinder 5. As a consequence, it is possible to attain predetermined finishing precision.
(79) Next, behavior of the second embodiment of the construction machine according to the present invention will be described with reference to the drawings.
(80) In
(81) In
(82) When the arm bottom pressure becomes closer to the boom bottom pressure from time T1 to time T1, the pilot pressure acting on the boom speed-up directional control valve 24 is limited as described above. As a result, the meter-in opening area of the boom speed-up directional control valve 24 decreases as shown in (c); thus, the diversion amount of the hydraulic fluid passing through the boom speed-up directional control valve 24 does not increase, and the balance is kept between the boom cylinder speed and the arm cylinder speed as shown in (b). At this time, the meter-out opening area of the boom speed-up directional control valve 24 also decreases as shown in (d). However, the meter-out opening area of the boom directional control valve 23 is relatively large and the total meter-out opening area, therefore, becomes relatively large; thus, an increment of the boom rod pressure shown in (e) is small.
(83) At time T2, at which the boom bottom pressure further decreases by the excavation reaction force and reaches approximately 0 as shown in (e), the boom cylinder 5 starts to extend at a speed equal to or higher than a flow rate of the supplied hydraulic fluid. As a result, the target surface distance shown in (a) increases. In other words, a problem occurs that the work implement 15 moves away from the construction target surface.
(84) Next, the behavior in the present embodiment will be described with reference to
(85) At time T2, the boom bottom pressure further decreases by the excavation reaction force and reaches approximately 0. However, the boom rod pressure is relatively high as shown in (e); thus, it is possible to prevent the boom cylinder 5 from extending at the speed equal to or higher than the flow rate of the supplied hydraulic fluid as shown in (b). As a result, the target surface distance is kept around 0 as shown in (a).
(86) The second embodiment of the construction machine according to the present invention described above can attain similar effects to those of the first embodiment.
(87) It is noted that the present invention is not limited to the embodiments described above but encompasses various modifications. For example, the present invention has been described while the boom cylinder 5 and the arm cylinder 6 are taken as an example in the above embodiments; however, the present invention is not limited to this.
(88) Furthermore, the above embodiments have been described in detail for facilitating understanding the present invention, and the present invention is not always limited to the construction machine having all the configurations described above.
REFERENCE SIGNS LIST
(89) 5: Boom cylinder (first hydraulic actuator) 6: Arm cylinder (second hydraulic actuator) 5b: Boom cylinder bottom-chamber-side pressure sensor 6b: Arm cylinder bottom-chamber-side pressure sensor (excavation load sensor) 15: Work implement 21: First hydraulic pump 22: Second hydraulic pump 23: Boom directional control valve (first directional control valve) 24: Boom speed-up directional control valve (first speed-up directional control valve) 25: Arm directional control valve (second directional control valve) 32: Mode setting switch 100: Main controller 130: Target surface distance acquisition section 150: Boom speed-up control section 200: Information controller L1: First pump line L2: Second pump line