Steel cap for an electricity transmission tower
10612264 ยท 2020-04-07
Assignee
Inventors
Cpc classification
E02D27/14
FIXED CONSTRUCTIONS
E04G23/0218
FIXED CONSTRUCTIONS
Y02E10/728
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
E02D5/54
FIXED CONSTRUCTIONS
E04H12/2292
FIXED CONSTRUCTIONS
International classification
Abstract
A steel cap 7 for structurally connecting together a new foundation and an existing tower is disclosed. The new foundation includes at least one foundation element 9 positioned in the ground. The existing tower includes an existing foundation 5 and a tower structure 3 extending from and supported by the existing foundation. The steel cap comprises (a) a first element 11 for connecting the cap to the new foundation element or foundation elements and (b) a second element 13 for connecting the cap to the existing tower and thereby, in use, connecting together the new foundation and the existing tower.
Claims
1. A method of renovating an existing tower using a cap comprising a first element for connecting the cap to a plurality of new foundation piles for the existing tower, with the first element being in the form of a plate having a plurality of openings for the foundation piles, and the steel cap also comprising a second element extending from the first element for connecting the cap to the existing tower so that the cap connects together the new foundation piles and the existing tower, the method comprising: (a) driving/embedding/forming or otherwise positioning a plurality of new foundation piles in the ground in a required array around the existing tower and thereby forming a new foundation of the tower, (b) positioning the cap so that the first element extends around at least a part of the existing tower and the new foundation piles extends through the openings in the first element and the second element contacts the existing tower, (c) connecting the first element of the cap to the new foundation piles, and (d) connecting the second element of the cap to the existing tower.
2. The method defined in claim 1 wherein the plate is a flat steel plate.
3. The method defined in claim 1 wherein step (c) comprises bolting or welding the first element to the foundation piles.
4. The method defined in claim 1 wherein the existing tower has a leg having a shape and the first element includes a cut-out section in a side wall of the plate that has the same shape as a part of a transverse section of the leg of the existing tower so that the first element extends around at least a part of an outer profile of the existing tower.
5. The method defined in claim 1 wherein the second element is shaped to conform to an outer profile of the existing tower to maximize contact between the second element and the existing tower.
6. The method defined in claim 1 wherein the second element is an elongate element.
7. The method defined in claim 1 wherein the second element is a shaped plate that has a V-shape in transverse section along a length of the plate that conforms to an outer profile of the existing tower to maximize contact between the second element and the existing tower.
8. The method defined in claim 7 wherein the existing tower has a horizontal leg extending at an angle and the shaped plate extends from the first element at an angle to a plane of the first element, with the angle being selected to be the same as the angle to the horizontal of a leg of the existing tower to which the steel cap is connected.
9. The method defined in claim 1 wherein the existing tower is an existing electrical transmission tower.
10. A method of renovating an existing tower using a cap comprising a first element for connecting the cap to a new foundation pile for the existing tower, with the first element being in the form of a plate having at least one opening for the foundation pile, and the cap also comprising a second element extending from the first element for connecting the cap to the existing tower so that the cap connects together the new foundation pile and the existing tower, the method comprising: (a) driving/embedding/forming or otherwise positioning a new foundation pile in the ground in a required position in relation to the existing tower, (b) positioning the cap so that the first element extends around at least a part of the existing tower and the new foundation pile extends through the opening in the first element and the second element contacts the existing tower, (c) connecting the first element of the cap to the new foundation pile, and (d) connecting the second element of the cap to the existing tower.
Description
BRIEF DESCRIPTION OF THE DRAWING
(1) The present invention is described further by way of example only with reference to the accompanying drawings of which:
(2)
(3)
(4)
(5)
(6)
(7)
(8)
DESCRIPTION OF EMBODIMENTS
(9) The invention is concerned with providing support for an existing tower, such as an electricity transmission tower or another type of tower, and the structure of the existing tower is a secondary consideration. The existing tower may be of any type, such as a lattice tower or a monopole tower, used for any purpose. The existing tower includes a foundation and a tower structure extending from and supported by the existing foundation.
(10) The vertical cross-section of
(11) (a) one leg 3 of an existing tower,
(12) (b) two foundation elements in the form of new piles 9 that have been driven into the ground (but could be otherwise embedded in the ground) and form a part of a new, i.e. an additional foundation for the existing tower leg 3, and
(13) (c) a steel cap generally identified by the numeral 7 structurally interconnecting the piles 9 of the new foundation and the existing tower leg 3 so that the new foundation structurally supports the existing tower leg 3.
(14) It is noted that the leg 3 may be an element that forms part of the tower structure or part of the tower foundation.
(15) The existing tower shown in
(16) As mentioned above, the new foundation for the existing tower leg 3 includes two new piles 9 as shown in
(17) Whilst not shown in the vertical cross-section of
(18) The new piles 9 may be of any suitable construction. For example, each pile 9 may be composite micro-pile comprising a steel casing filled with grout and a high-strength central piece of threaded reinforcing steel. In use, the cased section is installed in a drilled hole in the ground and provides lateral resistance and the reinforcing bar and grout are positioned and injected respectively in the space defined by the casing and provide axial resistance.
(19) The number and type and arrangement of the new piles 9 or other new foundation elements may be as required given the geology of a site of the existing tower and the structural properties required to support the existing tower leg 3 and the accessibility of the site. One key consideration is to locate the new piles 9 of the new foundation so that the process of drilling and installing the piles 9 or other process for embedding/forming the piles in the ground does not interfere with the structure and therefore the viability of the existing tower.
(20) The steel cap 7 shown in
(21) The steel cap 7 also comprises a second element in the form of a length of a shaped steel plate 13 for connecting the steel cap 7 to the existing tower leg 3. The shaped steel plate 13 is V-shaped in transverse section to conform to the V-shaped outer profile of the steel post 21 of the existing tower leg 3 to maximum contact of the shaped steel plate 13 and the steel post 21.
(22) The steel plate 11 is formed to extend 180 around the perimeter of the existing tower leg 3. Specifically, as can be seen in
(23) There may be situations where a single steel cap 7 is sufficient. There may also be situations where more than one steel cap 7 is required.
(24) The steel plate 11 may be any suitable thickness and steel grade and has an inner edge 23 that has the above-described V-shaped notch 25. The angled steel plate 13 is located in the notch 25 and welded to the steel plate 11.
(25) The shaped steel plate 13 extends at an angle (see
(26) With the above arrangement, in use, when the steel plate 11 is positioned horizontally adjacent the existing tower leg 3 with the shaped steel plate 13 against the steel post 21 of the existing tower leg 3, there is maximum contact of the shaped steel plate 13 and the steel post 21 of the existing tower leg 3 along the length of the shaped steel plate 13.
(27) In use, typically,
(28) (a) the new piles 9 are driven/embedded/formed or otherwise positioned in the ground in a required array around an existing tower leg 3 to form the new foundation for the leg 3,
(29) (b) the steel cap 7 is positioned on an upper surface of the new piles 11 with upper threaded ends of the new piles extending through the openings 15 in the steel plate 11 of the steel cap 7 and nuts threaded onto the threaded ends thereby connecting the steel plate 11 to the new piles 11, with the shaped steel plate 13 contacting the outer surface of the exiting tower leg 3, and
(30) (c) the shaped steel plate 13 is connected to the existing tower leg 3 by fasteners 21, in the form of nuts and bolt pairs, thereby completing the new foundation and the consequential additional structural support for the existing tower leg 3 and, by extension, the tower.
(31) The threaded ends of the new piles 9 and the nuts mentioned in paragraph (b) above form fastening assemblies that are generally identified by the numeral 29 in
(32) It can be appreciated that the steel cap 7 is an efficient and effective option for interconnecting the new foundation (specifically the piles 9) and the existing tower leg 3 and providing required additional structural support for the existing tower leg 3 and, by extension, the tower.
(33) In the embodiment of the steel cap 7 shown in
(34) The embodiment of the steel cap 7 shown in
(35) The embodiment of the steel cap 7 shown in
(36) The embodiment of the renovated tower shown in
(37) When present, as is often the case, the bracing members 31 may have an impact on the shape of the steel plate 11 of the steel cap 7. This is a design issue that is illustrated by the embodiment shown in
(38) The embodiment of the renovated tower shown in
(39) Many modifications may be made to the embodiments of the present invention described above without departing from the spirit and scope of the invention.
(40) By way of example, in the embodiment of the steel cap 7 shown in