System to Mount Ceiling Tiles in a Completely Concealed Grid System Where Individual Tile Can Be Mounted or Dismounted
20200071930 ยท 2020-03-05
Inventors
Cpc classification
E04B9/127
FIXED CONSTRUCTIONS
E04B9/225
FIXED CONSTRUCTIONS
E04B9/003
FIXED CONSTRUCTIONS
E04B9/28
FIXED CONSTRUCTIONS
International classification
E04B9/22
FIXED CONSTRUCTIONS
E04B9/28
FIXED CONSTRUCTIONS
E04B9/06
FIXED CONSTRUCTIONS
Abstract
A method, system, and tool are disclosed for installation of ceiling tiles in an improved mounting hook assembly to form a concealed grid system The system includes elements for attaching the mounting hook assembly to the tile; rotating a load bearing lever member; rotating a positioning lever member to position the load bearing member on a flange of a T grid bar; and fixing the tile below the T grid at a distance that is greater than the thickness of the tile so that when the tile is lifted up, the load bearing lever is returned to a position above the flange level of the T grid and any tile can be removed or installed in a totally concealed grid system without dislocating tiles already laid. A tool is used to engage and disengage the tiles.
Claims
1.-7. (canceled)
8. A system for the installation of ceiling tiles to form a grid system, the system comprising: a) a set of first tiles installed at a distance from an underside of a flange of a suspended grid, the distance being more than a thickness of each tile; b) a separate second tile adjacently installed next to each tile in the set of first tiles, which when the second tile is raised fully, creates a gap between an underside of the second tile and a topside of each of the set of first tiles; and c) a tool to both, i) engage a load bearing lever of a hook assembly on the second tile onto the flange of the suspended grid to mount the second tile; and ii) disengage the load bearing lever of the hook assembly on the second tile from the flange of the suspended grid to dismount the second tile, wherein the lever is configured as rotating, push pull, or snap-on type to have engagement or disengagement of the lever via the tool.
9. The system as claimed in claim 8, further comprising a decorative insert between the tiles.
10. The system as claimed in claim 8, wherein uniform thickness of the installed tile of any specified thickness can be used without kerfing.
11. The system as claimed in claim 8, further comprising brackets for inserting into corresponding kerfs in the tiles.
12. The system as claimed in claim 8, wherein the second tile can be mounted or dismounted without shifting the position of already installed set of first tiles.
13. The system as claimed in claim 8, further comprising a clamp for clamping the tiles in an upwardly lifted position during mounting and dismounting of the tiles or installing a closing tile.
14. The system as claimed in claim 8, further comprising different stud lengths to obtain multiple levels of the ceiling tiles.
15. The system as claimed in claim 8, wherein the tool is a bent rod with a handle used to mount or dismount the second tile by rotating the load bearing lever to either be perpendicular or parallel to the flange of the grid to mount or dismount the second tile.
16. A tool for installation of ceiling tiles in an improved mounting hook assembly to form a grid system, and, in particular, for installing the tiles at a distance from an underside of a flange of a suspended grid, the distance being more than a thickness of each tile; such that, with an adjacently installed tile raised fully, a gap is created between an underside of the adjacently installed raised tile and a topside of a different adjacent installed tile; wherein the tool comprises: a bent rod with a handle for insertion of the tool to both engage a load bearing lever of the hook assembly onto the flange of the suspended grid to mount the different adjacent installed tile and to disengage the load bearing lever of the hook assembly from the flange of the suspended grid to dismount the adjacent installed tile, the lever being configured as rotating, push pull, or snap-on type to have engagement or disengagement of the lever via the tool.
17. The tool as claimed in claim 16, wherein the bent rod of the tool is made up of first and second ends generally parallel to one another with an intermediate section therebetween generally perpendicular to each of the first and second ends.
Description
BRIEF DESCRIPTION OF THE ACCOMPANYING DRAWINGS
[0019]
[0020]
[0021]
[0022]
[0023]
[0024]
[0025]
[0026]
[0027]
[0028]
[0029]
[0030]
[0031]
[0032]
[0033]
[0034]
[0035]
[0036]
[0037]
DETAIL DESCRIPTION OF THE INVENTION
[0038] Throughout the specification reference will be made to individual figures. It should be appreciated that these references apply to the entire group of figures associated with that reference; such as, for example, reference to
[0039] Mounting assembly that is to be attached at the back side at prefixed locations is shown in
[0040] A plan view of the rotating lever fixed on tile before attaching to the suspension grid is shown in
[0041] It is also possible to use the tiles with kerfing to utilize same principle.
Preparation for Installation:
[0042] Tiles should be prepared with mounting hook assembly located at appropriate locations to carry the weight of tile without any sag. The locations and numbers are dependent on the strength and flexibility of ceiling tile to be mounted.
[0043] As a further simplification, one side of the tile has fixed studs to enable hooking tile onto flange of T grid on one side.
[0044] In case long support leverage is needed the levers are joined with long strips to distribute load.
[0045] Another important feature of the studs and its relative location to the edge of tile is as follows: The length of stud is as needed to have the length from bottom of stud to bottom of long lever (L.) that is more than the thickness of tile to accommodate the tool used to turn lever.
[0046] As an example, for tile of 13 mm thickness the L, can be 25 mm to allow 8 mm tool to be inserted as will be explained latter.
[0047] The suspended ceiling structure is then fixed in standard way to have exact level because the accuracy of level of grid is reflected in the level of the ceiling membranes.
[0048] The distance of the fixing of centre of stud from the edge should be more than flange width of T grid combined with length of short lever.
[0049] Tile is fixed with studs as per examples shown in
[0050] When longer support is needed on flange, the same will be as shown in
Installations:
[0051] The installations can be started as per normal practice. The grid is laid as per normal practice. Tile is fixed with special mounting system on three sides and on one side a fixed hook is attached (item 1 in
[0052] The tile is then positioned so that the levers raise above the flange and all levers are turned so that all long levers are perpendicular to flange of grid. The tile is lowered so that the long levers rest on the flanges as shown in
[0053] The levers are approachable from the top of the suspension grid for all tiles except closing tile/or tiles. The resting of tiles on grid is as in
[0054] For the closing tile it is not possible to approach the lever from plenum (Ceiling void).
[0055] The procedure to fix the closing tile and also to mount or dismount any individual tile is as shown below:
Closing Tile:Closing tile is no special tile but is one, cut to dimension of the gap and similar mounting assembly are installed. Let us consider that:
Tiles A1 to AS, also referred to as a set of first tiles, are all laid and is necessary to install closing tile (C T)
[0056] Tiles A1. AS are lifted up to the grid level. This will enable approach to the levers of mounting hook assembly
[0057] Long lever will be turned on flange to disengage the hook assembly.
[0058] To either mount (enage) or dismount (disengage) any tile in concealed grid layout as per current disclosure:
[0059] Dismounting is as follows:
Tiles A1. A3 and AS are lifted up and remain so by simple clamp to grid. MB is raised a bit to relieve load of tile. The bent tool is inserted between flange and stud of the MB tile. LB lever is pushed to a position parallel to flangewhen all rotatable levers of MB tile are turned on three sides the tile is slid off the fixed hooks that are on one side, tile is lowered and thus removed.
[0060] For mounting or engaging of M Bthe tiles A1, A3 and AS are retained in lifted position and the new tile is positioned so that the short levers face the grid and are lifted above flange.
[0061]
[0062] It should be mentioned that engineering details are given to explain and disclose the main parameters of the invention as elaborated. Alternate engineering arrangements for example:
Instead of rotary load bearing lever these can be push pull or snap on and off system.
[0063] All such variations will not alter the validity of the claims of this simple, economic and hastle free system.
[0064] It is clear that in totally concealed grid construction of ceiling tiles, the method shows a simple and novel way to mount and dismount any tile in grid and without need of specially constructed tile or gadgets such as spring hooks that alter the normally used T grid suspension.
[0065] The invention herein disclosed has following advantages:
1) It can be used to mount ceiling membrane of any thickness unlike double groove system with 20 mm thickness.
2) It can be used for the kind of ceiling membranes where edge grooving is not possible.
3) It can be used to mount and dismount any ceiling membrane which is part of completely concealed ceiling system.
4) This system can be used with intermediate decorative runner between tiles.
5) As the system uses standard suspension grid, retrofitting of the concealed grid system is possible.