Reinforcing of tower base in existing guyed Towers
20230228115 ยท 2023-07-20
Inventors
Cpc classification
International classification
Abstract
A method of reinforcing the tower base in existing guyed towers. A guyed tower is a tower supported by a base and guy cables. The tower's foundations are Base and Deadman anchors. The base is an isolated spread footing which is pier and pad or pile foundation. This method of reinforcing is a new mechanism to transfer part of the download on base to an alternative mat foundation.
The reason of using this mechanism is that the soil underneath the tower base is getting high stresses above its limit. The soil is getting overstressed due to some reasons that it happens frequently.
The standard procedure is before building any tower, the Geotechnical engineer does test boreholes at the proposed location of the tower foundations (Base Deadman Anchors). The geotechnical engineer provides the soil report with soil parameters at each borehole. The structural engineer designs the guyed tower and get the download on the tower base to design the spread footing (or pile). The download is the result of the dead load (tower own weight, mounts, antennas, microwave dishes, cables & equipment) and live load (wind & ice). The structural engineer designs the base to transfer the download from the tower to the soil safely based on the information that was given by the geotechnical engineer. In the future, if no change in loading, then the base will function well as designed, however the client always changes the dead load (antennas, microwave dishes, cables & equipment) and this is due to the fast-growing telecom technologies and the country needs. So, in most cases the base requires reinforcing.
The nonstandard procedure is to design the tower base, based on normal dry soil. Normal dry soil is a soil with average soil parameters values, this could happen due to short notice given by the client to the geotechnical engineer and the geo couldn't make it before designing the base. In this case the structural engineer designs the base with some assumed soil parameters and increasing the download to cover the absence of soil report (multiply download by factor more than 1.0, usually 1.20). Later after receiving the soil report, sometimes the soil parameters are weaker than the parameters that was used by the structural engineer. Here, the engineer must find the stresses on soil underneath the tower base and compare it with the soil report, if it was above the soil limit then reinforcing the base is required.
Something else which is the ice thickness, and this is defined by the ANSI-TIA-222. Telecommunications Industry Associations reviews the ice records and publish new list of the past 50 years of ice thickness. Also, they provide some changes on ice calculation formula vs height, this all increases the download, then increases the stresses on soil. If the stresses on soil are less than the capacity of soil, then it is safe but if not then reinforcing is required.
By-law, clients (tower owners) are required to provide structural analysis for the tower and foundations for any loading change. Most of cases the foundation is getting overstressed, and it requires reinforcing. The new mechanism is taking part of the load that is overstressing the soil underneath the base and transfer it to a new mat foundation.
Claims
1-11- (canceled)
12-A method of reinforcing the tower base in existing guyed towers, it could be used for any kind of tower base, being spread footing or pile foundation, it is using the existing splice pad connections between first and second section of the guyed tower to install the new reinforcing assembly.
13-This method of reinforcing is a new mechanism to transfer part of the download on existing base to an alternative mat foundation, it is for any guyed tower that it is built from sections, connected to each other through splice pads (Flanges)and bolts.
14-The new mechanism consists of (4) assemblies (I, II, III & IV). First assembly (I) is a rigid frame, this frame is built around the tower and located under the top splice pad of first section. This frame is connected to the splice pads, using the same bolts with different grip. The frame is built from built-up beams and weldments, all are welded together. Second assembly (II) are lattice legs. Third assembly (III) includes mat foundation and base plates. The new mat foundation is built around the existing base at the ground surface, reinforced with rebar top & bottom each way. The base plates are two plates, one is sliding on the other. The bottom plate is fixed into the mat foundation using concrete anchors. The top plate is movable, sliding on bottom plate using grease in between plates. Fourth assembly (IV) includes a steel wire cable, a turnbuckle, wire rope thimbles & hinges. This assembly is going around all the movable base plates in assembly (III). Torquing the turnbuckle will move the movable plate towards the tower, which is connected to the lattice leg. This will result, moving part of the download from the existing base to the new mechanism.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0004]
[0005]
[0006]
[0007]
[0008]
[0009]
[0010]
[0011]
[0012]
[0013]
[0014]
DETAILED DESCRIPTION
[0015] The guyed tower (
[0016] The tower base will be one of two types, isolated spread footing (
[0017] The new mechanism is consisted of (4) assemblies.
[0018] Assembly (I) (
[0019] Assembly (II) (
[0020] Assembly (III) (
[0021] Assembly (IV) (
[0022] After all set, apply the required torque to produce tension in the steel wire cable, this tension will produce forces in lattice leg to carry the extra load on the base. This mechanism is to move some of the extra loading to the new mat foundation.
[0023] The structural system that is illustrating this mechanism is shown in (
DEFINITIONS
[0024] B Tower Base.
[0025] D Tower Deadman Anchors.
[0026] H Section height.
[0027] T Tension force due to unit force at the top.
[0028] 1.1 Concrete pad in spread footing.
[0029] 1.2 Concrete pier or pile foundation.
[0030] 1.3 Pivot on top of tower base.
[0031] 1.4 Bottom base plate of first tower sections.
[0032] 1.5 1.sup.st section in the tower.
[0033] 1.6 Top splice plate of 1S.sup.t tower section.
[0034] 1.7 2.sup.nd section in the tower.
[0035] I.1 Weldment.
[0036] 1.2 Beam.
[0037] II Lattice legs.
[0038] III.1 Mat foundation.
[0039] 111.2 Fixed base plate.
[0040] 111.3 Movable base plate.
[0041] IV.1 Steel wire cable
[0042] IV.2 Wire rope thimble.
[0043] IV.3 Turnbuckle.