METHOD OF REFRIGERANT COMPOSITION CONTROL IN PREMIXED REFRIGERANT CYCLE OF LIQUEFIED NATURAL GAS PRODUCTION
20200018543 ยท 2020-01-16
Assignee
Inventors
Cpc classification
F25J1/0052
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F25J1/0092
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F25J1/0022
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F25J1/0252
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F25J1/0214
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F25J1/0249
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F25J1/0254
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F25J1/0222
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
International classification
F25J1/02
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
Abstract
The invention relates to compression refrigerator control systems, viz. to refrigerant composition control in premixed refrigerant cycle of liquefied natural gas (LNG) production. The method for controlling the refrigerant composition in the pre-cooled mixed refrigerant (PMR) cycle for LNG production comprises controlling in view of the weather forecast temperatures. The method comprises measuring the concentration of each PMR component and measuring the ambient temperature. Further, it comprises calculating the required concentration of each component for each of the measured and weather forecast temperatures on the basis of the predetermined relationship between the optimum concentration of each component and ambient temperature; calculating the time period required to change appropriately each component concentration in transition to the following of the weather forecast temperatures by using the highest possible change (increase or decrease) rate of each component concentration for the said cycle; and comparing the measured and required concentration of each component in view of the calculated time periods and direction of change in the component concentrations during these periods. The invention allows a higher efficiency of the pre-cooling cycle due to maintaining the optimum PMR composition thus minimizing the cooled product temperature in LNG production.
Claims
1. A method for controlling the refrigerant composition in the pre-cooled mixed refrigerant (PMR) cycle of liquefied natural gas (LNG) production characterized in that controlling is carried out in view of the weather forecast temperatures, wherein the method comprises the steps of: measuring the concentration of each PMR component; measuring the ambient temperature; calculating the required concentration of each component for each of the measured and weather forecast temperatures on the basis of the predetermined relationship between the optimum concentration of each component and ambient temperature; calculating the time period required to change appropriately each component concentration in transition to the following of the weather forecast temperatures by using the highest possible change (increase or decrease) rate of each component concentration for the said cycle; and comparing the measured and required concentration of each component in view of the calculated time periods and direction of change in the component concentrations during these periods.
2. The method of claim 1 characterized in that the increasing concentration of each component is varied by make-up this component into the cycle, and the decreasing concentration is varied by make-up other components into the cycle.
3. The method of claim 1 characterized in that the PMR components are methane, ethane, and propane.
4. The method of claim 1 characterized in that the daily weather forecast is provided with the temperature data of each hour.
5. The method of claim 1 characterized in that the time periods, which are selected from the periods, exceed the time period between two adjacent temperature values from the weather forecast, and the measured and required concentrations of each component are compared in view of the selected time periods.
Description
[0016] The invention is explained with figures.
[0017]
[0018]
[0019] The major objective of controlling the PMR composition is minimizing the cycle temperature in view of the current ambient temperature. Thus, minimized temperature is the temperature of natural gas (NG) leaving the PMR cycle. Further, it indicates the work saved in the MR cycle of NG liquefaction that allows for the same maximum load of MR compressor to produce more product (i.e. to liquefy more NG).
[0020] It should be understood that the lighter is the PMR composition, the more effective is the PMR cycle since heat exchangers HE1 and HE2 (
[0021] Therefore, the optimum temperature of PMR components depends upon the ambient temperature. This dependence for each of the PMR components may be obtained experimentally for the particular LNG production unit.
[0022] It is essential to note that a preferable PMR cycle comprises make-up the components, i.e. to decrease the concentration of any PMR component, two others should be added. The PMR components may be added by opening the make-ups. Ethane and propane may use both gas and liquid make-ups, while methane may be added only as a gas. In the make-up process, excess liquid creating excessive level in the separator (provisionally not shown) at C3 outlet is drained (to a fractionating unit) that further promotes to lower concentration of the component, while other components existing in the gas phase in the same separator (primarily, methane) create excessive pressure and removed to MR cycle.
[0023] The ambient temperature may significantly vary, especially in autumn and spring, when the temperature drop may be up to 15 C. in a short period of time. For this reason, controlling the PMR composition only in view of the current ambient temperature with respect to the limited PMR composition change rate leads in a non-optimum PMR composition.
[0024] To achieve or at least approach to the optimum concentrations of PMR components, controlling the PMR composition according to the invention is carried out in view of the weather forecast temperatures.
[0025] The weather forecast is preferably provided as the hour temperature data in advance for 24 hours, e.g. from 5 a.m. to 5 a.m. of the next day. The weather forecast may be updated each 12 hours.
[0026] The concentration of each PMR component and ambient temperatures are measured to calculate the required concentration of each component for each of the measured and weather forecast temperatures on the basis of the predetermined relationship between the optimum concentration of each component and ambient temperature.
[0027]
[0028] Then for each of the weather forecast temperatures the required time period is calculated to change (increase or decrease) appropriately each component concentration in transition to the following weather forecast temperature, in particular, to the next hour temperature, by using the PMR cycle with the maximum possible change (increase or decrease) rate of each component. The said rates may be calculated or determined experimentally.
[0029] The time periods, which are selected from the calculated periods, exceed the period between two adjacent weather forecast temperature values, in particular, the periods exceeding 1 hour (for the hourly weather forecast).
[0030] Then the measured concentration of each component is compared to the required one and each component concentration is varied in view of the selected time periods and the direction of changing the component concentrations during these periods.
[0031] For this purpose, it is necessary to calculate the excess of the selected tune periods over the time period 1 hour) between two adjacent weather forecast temperatures, and the relevant component concentration measuring is started in advance with respect to the said excess as welt as to the direction of the component concentration change, where the comparison with the required concentration is carried by using either the lower or upper permissible limit thereof.
[0032] As shown in