COAL UNCOVERING CONSTRUCTION METHOD FOR BLASTING LARGE CROSS-SECTION GAS TUNNELS
20240035380 ยท 2024-02-01
Inventors
- Wuxian Wang (Beijing, CN)
- Su Yan (Beijing, CN)
- Liang Kuang (Chengdu, CN)
- Jinwen Yang (Beijing, CN)
- Mingli Huang (Beijing, CN)
- Yitao Feng (Beijing, CN)
- Wanqiang Zhao (Chengdu, CN)
- Liujie Jin (Beijing, CN)
- Weiming Zhang (Beijing, CN)
- Qian Dong (Beijing, CN)
- Liang Du (Beijing, CN)
Cpc classification
E21B2200/20
FIXED CONSTRUCTIONS
International classification
E21D9/00
FIXED CONSTRUCTIONS
Abstract
A coal uncovering construction method for blasting large cross-section gas tunnels includes: analyzing stress distribution characteristics in front of a tunnel boring working face, and then determining a thickness calculation model of a reserved rock wall based on a limit equilibrium theory; establishing a tunnel model, simulating a construction condition and analyzing a construction result, and determining a thickness of the reserved rock wall; and fixing a detonator through a fixed sand ring, fitting the detonator with a construction hole by adjusting an adjustable protective plate, then embedding the detonator into a blast hole, and blasting the detonator for tunnel construction. Furthermore, an extension ring is fixed between the fixed sand ring and the adjustable protective plate.
Claims
1. A coal uncovering construction method for blasting large cross-section gas tunnels, comprising the following steps: step 1, analyzing stress distribution characteristics in front of a tunnel boring working face, and then determining a thickness calculation model of a reserved rock wall based on a limit equilibrium theory; step 2, establishing a tunnel model, simulating a construction condition and analyzing a construction result, and determining a thickness of the reserved rock wall; and step 3, fixing a detonator through a fixed sand ring, fitting the detonator with a construction hole through an adjustable protective plate, then embedding the detonator into a blast hole, and blasting the detonator for tunnel construction; wherein an extension ring is fixed between the fixed sand ring and the adjustable protective plate, a bottom of the adjustable protective plate is rotatably connected with a support foot, a shape of an end of the support foot facing away from the adjustable protective plate is sharp, an inner side of the fixed sand ring is connected with a plurality of extrusion rods, the plurality of extrusion rods are distributed in an array, an end of each of the plurality of extrusion rods facing towards a center of the fixed sand ring is fixedly connected to an adhesive plate, and a side of the adhesive plate facing away from the extrusion rod is connected to a sponge mat; wherein an outer surface of each extrusion rod is provided with a plurality of arc-shaped blocks, exteriors of the plurality of arc-shaped blocks are slidably connected with a plurality of support elastic pieces, the plurality of support elastic pieces are connected with the fixed sand ring and are distributed in an array inside the fixed sand ring, and the plurality of arc-shaped blocks and the plurality of support elastic pieces are arc-shaped and each of the plurality arc-shaped blocks is matched with a corresponding one of the plurality of support elastic pieces; and wherein the extrusion rod is provided with an explosion-proof housing therein, the explosion-proof housing is provided with an energizing magnet therein, a side of the energizing magnet facing towards the adhesive plate is provided with a counterweight block, the counterweight block is provided with a follow-up magnet therein; when the energizing magnet is energized, a magnetic property of the energizing magnet is the same as that of the follow-up magnet, a side of the counterweight block facing away from the energizing magnet is provided with a knocking needle, a side of the knocking needle facing away from the energizing magnet is provided with a glass housing, the glass housing is loaded with corrosive liquid therein, a bottom end of the explosion-proof housing defines a liquid discharging hole, and the extrusion rod and the adhesive plate are respectively provided with through holes matched with the liquid discharge hole.
2. The coal uncovering construction method for blasting large cross-section gas tunnels as claimed in claim 1, wherein an exterior of the counterweight block is slidably connected with a limiting frame, the limiting frame is provided with elastic pieces therein disposed on two sides of the counterweight block, and the elastic pieces are configured to support the counterweight block.
3. The coal uncovering construction method for blasting large cross-section gas tunnels as claimed in claim 2, wherein an end of the limiting frame facing away from the energizing magnet is provided with a rubber ring, and a buffer sponge is disposed between an exterior of the glass housing and the explosion-proof housing.
4. The coal uncovering construction method for blasting large cross-section gas tunnels as claimed in claim 3, wherein a side of the liquid discharge hole facing away from the buffer sponge is slidably connected with a magnetic closing block, a plurality of telescopic rods are fixed between the magnetic closing block and the explosion-proof housing, and a side of the magnetic closing block facing towards the buffer sponge is provided with a telescopic needle.
5. The coal uncovering construction method for blasting large cross-section gas tunnels as claimed in claim 1, wherein a side of the explosion-proof housing facing away from the adhesive plate is inserted with a hollow column, the hollow column is filled with colored smoke and defines a plurality of exhaust vents, each of the plurality of exhaust vents is provided with a counterweight ball therein, an outer surface of the counterweight ball is provided with a plurality of puncture needles, a supporting elastic rod is fixed between the counterweight ball and the hollow column, two sides of the counterweight ball are provided with elastic films, and the extrusion rod defines a plurality of through holes, which are matched with the plurality of exhaust vents.
6. The coal uncovering construction method for blasting large cross-section gas tunnels as claimed in claim 5, wherein the hollow column is provided with a plurality of stirring balls therein, and each of the plurality of stirring balls is connected to the hollow column through a connecting elastic rope.
7. The coal uncovering construction method for blasting large cross-section gas tunnels as claimed in claim 1, wherein the adhesive plate is slidably connected with a pair of jacking rods therein, a side of each of the pair of jacking rods facing away from the sponge mat is provided with a powder storage bag, and a side of the powder storage bag facing away from a center of the adhesive plate is connected with a powder discharging pipe in a penetrating manner.
Description
BRIEF DESCRIPTION OF DRAWINGS
[0021] The disclosure will be further described below with reference to the attached drawings.
[0022]
[0023]
[0024]
[0025]
[0026]
[0027]
[0028]
[0029]
DESCRIPTION OF REFERENCE NUMERALS
[0030] 1-fixed sand ring; 2-extension ring; 3-adjustable protective plate; 4-support foot; 5-extrusion rod; 6-adhesive plate; 7-sponge mat; 8-arc-shaped block; 9-support elastic piece; 10-explosion-proof housing; 11-energizing magnet; 12-counterweight block; 13-follow-up magnet; 14-knocking needle; 15-elastic piece; 16-limiting frame; 17-rubber ring; 18-glass housing; 19-buffer sponge; 20-telescopic needle; 21-magnetic closing block; 22-telescopic rod; 23-hollow column; 24-counterweight ball; 25-puncture needle; 26-supporting elastic rod; 27-elastic film; 28-stirring ball; 29-connecting elastic rope; 30-jacking rod; 31-powder storage bag; 32-powder discharging pipe; 33-exhaust vent; 34-liquid discharging hole; 35-through hole; 36-through hole; 37-through hole.
DETAILED DESCRIPTION OF EMBODIMENTS
[0031] In order to enable the technical solution, technical features, objectives and effects achieved by the disclosure to be easily understood, the disclosure is further described below in conjunction with illustrated embodiments.
Embodiment 1
[0032] As shown in
[0033] Step 1, stress distribution characteristics in front of a tunnel boring working face are analyzed, and then a thickness calculation model of a reserved rock wall is determined based on a limit equilibrium theory.
[0034] Step 2, a tunnel model is established, a construction condition is simulated and a construction result is analyzed based on the tunnel model, thus a thickness of the reserved rock wall is determined according to the thickness calculation model of the reserved rock wall and the tunnel model.
[0035] Step 3, a detonator is fixed through a fixed sand ring 1, the detonator is fitted with a construction hole by adjusting an adjustable protective plate 3, then the detonator is embedded into a blast hole, and the detonator is blasted for tunnel construction. In the coal uncovering construction method for blasting large cross-section gas tunnels, the thickness calculation model of the reserved rock wall for uncovering coal in a gas outburst working area is established, and a stress state of a unit body in a limit equilibrium zone of the model is analyzed, thus a formula for calculating a critical rock wall size is derived to determine the thickness of the reserved rock wall, an effect of effectively shortening a construction period for penetrating coal measure strata can be achieved while tunnel boring safety can be ensured.
[0036] As shown in
[0037] As shown in
[0038] As shown in
[0039] As shown in
[0040] As shown in
[0041] As shown in
[0042] As shown in
[0043] As shown in
Embodiment 2
[0044] As shown in
[0045] A working principle of the method is as follows: establishing the reserved rock wall model for uncovering coal in the gas outburst working area, and analyzing the stress state of the unit body in the limit equilibrium zone of the model, thereby to derive the formula for calculating the critical rock wall size to determine the thickness of the reserved rock wall, so that the thickness of the reserved rock wall is accurately determined, and the effect of effectively shortening the construction period for penetrating the coal measure strata while ensuring the tunnel boring safety.
[0046] When the thickness of the reserved rock wall is determined and the detonator is used for blasting, the worker needs to put the detonator into the fixed sand ring 1 first, and then push the plurality of extrusion rods 5 to drive the corresponding plurality of adhesive plates 6 to move until the plurality of adhesive plates 6 fit with the outer surface of the detonator, and then the detonator is fixed. At this time, the detonator is embedded into the blast hole excavated in advance, and the angle of the support foot 4 is adjusted to support the adjustable protective plate 3, thereby to support the detonator to ensure that the detonator does not deviate after being embedded, effectively ensuring the construction quality.
[0047] During the installation of the plurality of extrusion rods 5, the plurality of arc-shaped blocks 8 are driven to slide by pushing the plurality of extrusion rods 5. During the sliding process, the plurality of arc-shaped blocks 8 come into contact with the plurality of support elastic pieces 9, thereby pushing the plurality of support elastic pieces 9 to bend and deform until the plurality of arc-shaped blocks 8 completely slides over the plurality of support elastic pieces 9. When the plurality of arc-shaped blocks 8 slides over all of the plurality of support elastic pieces 9, the plurality of support elastic pieces 9 will reset, and then the plurality of arc-shaped blocks 8 are limited and the plurality of arc-shaped blocks 8 are prevented from resetting. Therefore, in this way, the plurality of arc-shaped blocks 8 can be effectively limited, thereby limiting the plurality of extrusion rods 5 and the corresponding adhesive plates 6, preventing the situation where the detonator slides out from the inner side of the fixed sand ring 1 after the detonator installation.
[0048] Under normal circumstances, the detonator can explode, causing the rock and soil to blast. However, some detonators may fail to explode due to internal faults, which can be called misfired detonators. Once the misfired detonators appear, caution should be taken and the safety of the worker should be the first priority. Some misfired detonators cannot be used again and need to be safely removed and destructed. At this time, the worker can remotely activate the switch signal of the energizing magnet 11 to enable it to operate, and then a repulsive force is applied to the follow-up magnet 13. At this time, the counterweight block 12 will push the knocking needle 14 to move under the repulsive force until the knocking needle 14 collides with the glass housing 18. When the knocking needle 14 collides with the glass housing 18, the glass housing 18 breaks down and the corrosion liquid stored inside leaks. The leaked corrosion liquid will drip onto the outer surface of the detonator through the liquid discharging hole 34, the through hole 35 of the extrusion rod 5, and the through hole 36 of the adhesive plate 6, and the through hole 35 of the extrusion rod 5 and the through hole 36 of the adhesive plate 6 are matched with the liquid discharge hole 34. Therefore, the detonator is corroded until the internal gunpowder is soaked, causing the inside gunpowder to completely fail. It should be noted that the entire corrosion process requires different time depending on the concentration of the corrosion liquid. The worker can only go to recycle and process the detonator within half an hour after the completion of the corrosion operation, so that the misfired detonators can be automatically destructed to protect the worker's safety.
[0049] After the detonator explodes normally, the fixed sand ring 1 will be decomposed by the impact force of the explosion, and the extrusion rods 5 also break down under the action of the explosion. At this time, the explosion-proof housing 10 can protect its internal structure from the damage caused by the impact force of the explosion. At this time, the elastic pieces 15 can support and limit the counterweight block 12 to prevent the counterweight block 12 from colliding with the glass housing 18 during the detonator explosion process. It should be noted that the repulsive force generated after the activation of the energizing magnet 11 should be sufficient to drive the counterweight block 12 to push the elastic pieces 15 to deform, thus achieving the effect of cyclic use. Furthermore, the design of the rubber ring 17 and the buffer sponge 19 can protect and limit the glass housing 18 during the rolling process of the explosion-proof housing 10 after detonator explosion, preventing the glass housing 18 from breaking down or coming into contact with the knocking needle 14.
[0050] After the counterweight block 12 drives the knocking needle 14 to break down the glass housing 18, it will sink to the bottom of the glass housing 18. During this process, the magnetic force of the follow-up magnet 13 can act on the magnetic closing block 21, which drives the magnetic closing block 21 to compress the telescopic rods 22 and push the telescopic needle 20 to move. It should be noted that the telescopic needle 20 is telescopic, so that at the same time, the telescopic needle 20 can also extend out and come into contact with the glass housing 18 under the action of the magnetic force, and then the glass housing 18 is punctured to break down, further ensuring the normal flow of the corrosive liquid during the misfired detonators destruction, and improving the stability of the misfired detonators destruction. It should be noted that under normal conditions, the magnetic closing block 21 fully compresses the telescopic rods 22, and the telescopic needle 20 cannot come into contact with the glass housing 18.
[0051] After the normal explosion of the detonator, the structural components inside the explosion-proof housing 10 are mostly intact and reusable due to the protection of the explosion-proof housing 10. During the explosion of the detonator, the impact force generated can cause the counterweight balls 24 to drive the corresponding supporting elastic rods 26 to shake back and forth. During the shaking process of the counterweight balls 24, each of the counterweight balls 24 can drive the corresponding plurality of puncture needles 25 to pierce the elastic films 27 disposed on the two sides of the counterweight ball 24. After the elastic films 27 are pierced, the colored smoke stored inside the hollow column 23 escapes, and then the position of the explosion-proof housing 10 can be positioned to facilitate the recycling and utilization after the explosion, reducing the search time for the worker. After the detonator explodes, the plurality of stirring balls 28 inside the hollow column 23 can pull the connecting elastic ropes 29 corresponding to the plurality of stirring balls 28 to bounce back and forth under the action of inertia force, thereby stirring the colored smoke inside the hollow column 23 and preventing the precipitation of colored particles containing in the smoke from causing difficulties for the worker to find.
[0052] During the installation of the detonator, the plurality of adhesive plates 6 can drive the corresponding plurality of sponge mats 7 to gradually fit with the outer surface of the detonator. During this process, the jacking rods 30 can slide under the action of the outer surface of the detonator, pushing and squeezing to spray the dry powder inside the powder storage bags 31. The sprayed dry powder can drip onto the outer surface of the detonator, keeping its surface dry and preventing the damp environment in the rock and soil from affecting the detonation of the detonator.
[0053] The foregoing terms of front, back, left, right, upper, and lower all refer to
[0054] In the description of the disclosure, it should be understood that the orientation or positional relationship indicated by the terms center, longitudinal, transverse, front, rear, left, right, vertical, horizontal, top, bottom, outer, etc. is based on the orientation or positional relationship shown in the attached drawings, rather than indicating or implying that the indicated device or element must have a particular orientation, and is constructed and operated in a particular orientation, and therefore cannot be understood as a limitation to the scope of the protection of the disclosure.
[0055] The basic principles, main technical features, and advantages of the disclosure are shown and described above. It should be understood by those skilled in the related art that the disclosure is not limited by the foregoing embodiments, and the foregoing embodiments and the specification of the disclosure are merely used to illustrate the principles of the disclosure, and various changes and improvements may be made in the disclosure without departing from the spirit and scope of the disclosure, and these changes and improvements fall within the scope of the protection of the disclosure. The scope of the protection of the disclosure is defined by the written content of the disclosure and their equivalents.