Abstract
An isolated overburden grouting filling method for coal gangue underground emission reduction includes determining a grouting filling key stratum according to information of a coal face; constructing a directional borehole from an underground tunnel to the inside of the grouting filling key stratum; constructing a plurality of branch holes downward in a main hole of the directional borehole; and by establishing a grouting filling system under a mine, gangue obtained from excavation gangue of the mine and gangue sorting being made into a filling slurry by means of breaking and grinding, and the filling slurry filling fractures below the key stratum through the directional borehole. The gangue generated from a mine is directly made into a filling slurry under the mine and then fills overburden mining-induced fractures, thereby achieving harmless disposal of the gangue, effectively supporting a key stratum, and controlling stratum movement and surface subsidence.
Claims
1. An isolated overburden grouting filling method for coal gangue underground emission reduction, comprising following steps: a, distinguishing, according to mining parameters and geological information on a coal mining face, key strata in an overburden; selecting, according to requirements for a surface subsidence control and a gangue filling processing volume, one of the key strata with a thicker thickness as a grouting filling key stratum, wherein a lower boundary of the grouting filling key stratum is a selected grouting filling horizon; b, selecting, from a roadway outside a terminal line of the coal mining face, a position as a drilling site; constructing an underground directional hole in a direction of the grouting filling key stratum from the drilling site, wherein a first drilling drill-hole of the underground directional hole is an inclined hole, a direction of the first drilling drill-hole is a direction of an open-cut off in the coal mining face, a trajectory of the inclined hole is spaced at a certain distance from a boundary of a water conducting fractured zone on the coal mining face; continuously drilling forwardly, after the underground directional hole enters the grouting filling key stratum, for a certain distance in a direction of the open-cut off in the coal mining face along a middle plane of the key stratum, wherein a drilling direction is parallel to an advancing direction of the coal mining face; subsequently inserting a high-strength casing, and completing a cementing of the first drilling drill-hole with a cement slurry; c, continuously drilling forwardly, along the middle plane of the grouting filling key stratum, a main hole, wherein a projection of a drilling trajectory on a horizontal plane is parallel to the advancing direction of the coal mining face, the main hole is inclined downward; stopping, when drilling the main hole to a distance of 50 m away from the open-cut off in the coal mining face, the drilling; d, constructing, starting from a drill-hole ended point of the main hole, a group of obliquely downward branch holes at regular intervals along an axis direction of the underground directional hole, wherein each group of the branch holes consists of one or more rows, and the rows are as backups for each other in each group, a drill-hole ended point of each branch hole is located below the lower boundary of the grouting filling key stratum, and above a top boundary of the fractured zone on the coal mining face; e, injecting, after completing the construction of all branch holes, a non-consolidated high-viscosity filler into the main hole and branch holes through an orifice of the underground directional hole to fill all branch holes and an interior of the main hole of the underground directional hole; f, injecting, when the coal mining face is mined at the drill-hole ended points of the branch holes in a first row of a first branch, a low-concentration gangue slurry into the maim hole through the orifice of the underground directional hole according to an attenuation of a drill-hole pressure; continuously increasing, with the coal mining face passing through the branch holes in the first row of the first group, a slurry concentration and a grouting volume according to a change of the drill-hole pressure, thereby forming a grouting filling horizon; g, spreading, with a continuous mining of the coal mining face, fractures in the grouting filling horizon forwardly; communicating, when the coal mining face approximates to the branch holes in a subsequent row, the fractures in the grouting filling horizon with the branch holes in the subsequent row to form a communication channel of main hole-branch hole-grouting filling horizon; and h, continuously grouting, with the coal mining face being continuously mined forwardly, to the fractures below the grouting filling key stratum through the main hole, wherein due to an effect of a pressure, a lower caved and a fractured zone rock mass are squeezed downwards, and the grouting filling key stratum is supported upwards, thereby increasing opening degrees of the fractures, greatly increasing the grouting volume and processing the underground gangue, effectively supporting the grouting filling key stratum, and effectively controlling the overburden and surface deformation until the mining of the coal mining face is completed.
2. The method according to claim 1, wherein in Step b, the drilling site is constructed in an uphill roadway.
3. The method according to claim 1, wherein in Step b, an angle of the inclined hole is selected within a feasible range of construction according to a distance between the drilling site and the terminal line of the coal mining face, and a minimum vertical distance between the trajectory of the inclined hole and the boundary of the water conducting fractured zone on the coal mining face ranges from 40 m to 50 m.
4. The method according to claim 1, wherein in Step b, the drilling is stopped after continuously drilling forwardly for a distance of 30 m in the direction of the open-cut off in the coal mining face, for inserting a high-strength casing.
5. The method according to claim 1, wherein in Step c, the main hole is inclined downward by 3 to 5.
6. The method according to claim 1, wherein in Step d, each row of branch holes consists of 3 to 5 branch holes arranged in a fan-shape manner, and/or the drill-hole ended points of the branch holes are located 20 m to 50 m below the lower boundary of the grouting filling key stratum, and 30 m to 50 m above the top boundary of the water conducting fractured zone on the coal mining face.
7. The method according to claim 1, wherein in Step e, gelatin or yellow mud is adopted as the non-consolidating high-viscosity filler, and/or all branch holes and the interior of the main hole of the underground directional hole are filled to play a role of temporarily closing the branch holes, with no solidification to block the branch holes, and a stable pressure is maintained at the orifice.
8. The method according to claim 1, wherein in Step g, since a grouting pressure at the connection point between a subsequent branch hole and the main hole is higher than a pressure at a bottom of the branch hole, the gangue slurry in the main hole is promoted to flow into the branch hole to squeeze fillers in the branch hole into the fractures in the grouting filling horizon, and enable the branch hole to be a grouting filling channel, thereby starting the grouting filling of the branch hole.
9. The method according to claim 1, wherein a construction of the underground directional hole is completed before mining in the coal mining face, and one or more underground directional holes are arranged according to a width of the coal mining face, a diffusion radius of the slurry, and a requirement for the filling volume.
10. The method according to claim 1, wherein the grouting filling system is built underground without occupying land resources on a ground, the gangue comes from an underground roadway excavation and a selected gangue, is stored and buffered in the filling system, and is crushed and milled to make gangue powder, the gangue powder is mixed with water to make gangue slurry for filling, or is directly mixed with water in a process of crushing and grinding to make the gangue slurry.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0028]
[0029]
[0030]
[0031]
[0032] In the figures: 1. Coal mining face; 2. Grouting filling key stratum; 3. Terminal line of coal mining face; 4. Roadway; 5. Underground directional hole; 6. first drilling drill-hole; 7. Open-off cut in coal mining face; 8. Water Conducting Fractured zone on coal mining face; 9. Advancing direction of coal mining face; 10. Branch hole; 11. Branch hole in first row of first group; 12. Main hole; 13. Grouting filling stratum horizon.
DETAILED DESCRIPTION OF THE EMBODIMENTS
[0033] The present disclosure will be further described with reference to the accompanying drawings.
[0034] As illustrated in
[0035] In Step a, key strata in an overburden are distinguished according to mining parameters and geological information on a coal mining face 1. One of the key strata with a thicker thickness is selected as a grouting filling key stratum 2 according to requirements for a surface subsidence control and a gangue filling processing volume, and a lower boundary of the grouting filling key stratum 2 is a selected grouting filling horizon.
[0036] In Step b, a position is selected as a drilling site from a roadway 4 (such as uphill roadway and the like) outside a terminal line 3 of the coal mining face. An underground directional hole 5 is constructed in a direction of the grouting filling key stratum 2 from the drilling site. A first drilling drill-hole 6 of the underground directional hole 5 is an inclined hole, a direction of the first drilling drill-hole 6 is a direction of an open-cut off 7 in the coal mining face. An angle of the inclined hole is selected within a feasible range of construction according to a distance between the drilling site and the terminal line 3 of the coal mining face, and a minimum vertical distance between the trajectory of the inclined hole and the boundary of the water conducting fractured zone 8 on the coal mining face ranges from 40 m to 50 m. After the underground directional hole 5 enters the grouting filling key stratum 2, the underground directional hole 5 is continuously drilled forwardly in a direction of the open-cut off 6 in the coal mining face along a middle plane of the key stratum, the drilling is stopped after drilling forwardly for a distance of 30 m, the drilling direction is parallel to the advancing direction 9 of the coal mining face, a high-strength casing is inserted and the cementing of the first drilling drill-hole 6 is completed with the cement slurry.
[0037] In Step c, after the cementing of the first drilling drill-hole 6 is completed, the main hole 12 is continuously drilled forwardly along the middle plane of the grouting filling key stratum. A projection of a drilling trajectory on a horizontal plane is parallel to the advancing direction 9 of the coal mining face. The main hole 12 is inclined downward by 3 to 5, and the drilling is stopped when the main hole is drilled to a distance of 50 m away from the open-cut off 7 in the coal mining face.
[0038] In Step d, starting from a drill-hole ended point of the main hole 12, a group of obliquely downward branch holes 12 are constructed at regular intervals along an axis direction of the underground directional hole 5. Each group of branch holes 10 consists of one or more rows, each row consists of 3 to 5 branch holes arranged in a fan-shape manner. The rows are as backups for each other in each group, the drill-hole ended point of each branch hole 10 is located 20 m to 50 m below the lower boundary of the grouting filling key stratum 2, and 30 m to 50 m above the top boundary of the water conducting fractured zone 8 on the coal mining face.
[0039] In Step e, after the construction of all branch holes 10 is completed, the non-consolidated high-viscosity filler (such as gelatin, yellow mud, polymer) is injected into the main hole 12 and the branch holes 10 through an orifice of the underground directional hole 5, which fills all the branch holes 10 and the interior of the main hole of the underground directional hole and plays a role of temporarily closing the branch holes, with no solidification to block the branch holes 10, and then a stable pressure is maintained at the orifice.
[0040] The construction of the underground directional hole 5 is completed before mining in the coal mining face 1. One or more directional holes 5 are arranged according to parameters such as the width of the coal mining face 1, the diffusion radius of the slurry, and the demand for the filling volume.
[0041] In Step f, after the coal mining face 1 starts mining, when the coal mining face is mined at the drill-hole ended point of the branch hole 11 in the first row of the first group, the low-concentration gangue slurry is injected into the maim hole 12 through the orifice of the underground directional hole 5 according to an attenuation of the drill-hole pressure. With the coal mining face passing through the branch holes 11 in the first row of the first group, a slurry concentration and a grouting volume are continuously increased according to a change of the drill-hole pressure, thereby forming the grouting filling horizon 13. During the grouting filling process of the branch hole 11 in the first row of the first group, since the fractures in the grouting filling horizon 13 have not developed to the subsequent branch holes, the fillers in the subsequent branch holes still do not leak, thus blocking the gangue slurry from flowing into the subsequent branch holes, and avoiding the blockage of the subsequent branch holes caused by the sedimentation of the gangue particles.
[0042] The grouting filling system is built underground without occupying land resources on a ground. The gangue comes from an underground roadway excavation and a selected gangue. The gangue is stored and buffered in the filling system, and is crushed and milled to make gangue powder. The gangue powder is mixed with water to make gangue slurry for filling, or is directly mixed with water in a process of crushing and grinding to make the gangue slurry.
[0043] In Step g, with the continuous mining of the coal mining face 1, the fractures in the grouting filling horizon 13 are spread forwardly. When the coal mining face 1 approaches the branch holes in a subsequent row, the fractures in the grouting filling horizon 13 are communicated with the branch holes in the subsequent row to form a communication channel of main hole 12-branch hole 10-grouting filling horizon 13. At this time, since a grouting pressure at the connection point between the subsequent branch hole and the main hole 12 is higher than a pressure at a bottom of the branch hole 10, the gangue slurry in the main hole 12 is promoted to flow into the branch hole 10 to squeeze fillers in the branch hole 10 into the fractures in the grouting filling horizon 13, and enable the branch hole 10 to be a grouting filling channel, thereby starting the grouting filling of the branch hole.
[0044] In Step h, with the coal mining face being continuously mined forwardly, a grouting is continuously implemented to fill the fractures below the grouting filling key stratum 2 through the main hole 12. Due to an effect of the pressure, a lower caved and a fractured zone rock mass are squeezed downwards, and the grouting filling key stratum 2 is supported upwards, thereby increasing opening degrees of the fractures, greatly increasing the grouting volume and processing the underground gangue, effectively supporting the grouting filling key stratum 2, and effectively controlling the overburden and the surface deformation until the mining of the coal mining face 1 is completed.