Longwall mine construction method N00
10494924 ยท 2019-12-03
Assignee
Inventors
Cpc classification
E21F1/006
FIXED CONSTRUCTIONS
E21D23/0034
FIXED CONSTRUCTIONS
E21D23/0463
FIXED CONSTRUCTIONS
E21F1/00
FIXED CONSTRUCTIONS
E21C41/16
FIXED CONSTRUCTIONS
International classification
E21F1/00
FIXED CONSTRUCTIONS
Abstract
A longwall N00 mining method includes performing a no-entry excavation and non-pillar mining in N working faces of a new district, and the whole district is provided with an air-return dip, a haulage dip and a track dip, wherein the air-return dip and the track dip are located on one end of the district, and the haulage dip is connected to the other end of the district, and connected to the air-return dip. This method can not only ensure ventilation of the whole coal cutting are, but also when mining is performed in each working face in the district, entries can be automatically formed due to top-cutting pressure release by using a part of a gob area, and thereby it is not required to separately excavate any gateroad entry during mining coal nor need to retain any coal pillar, so as to save resources and improve efficiency.
Claims
1. A longwall N00 mining method, wherein in that, a mining is performed in N working faces of a new district, and the whole district is provided with an air-return dip, a haulage dip and a track dip, wherein the air-return dip and the track dip are located on one end of the district, and the haulage dip is connected to the other end of the district, and connected to the air-return dip; wherein, a mining process in each of the working faces comprises: mining from the haulage dip to the air-return dip and the track dip; forming a gob area; and cutting top of the roof of the gob area for releasing pressure and retaining an entry during mining, wherein a position of a retained entry is a portion close to a next working face, and the retained entry is used as an upper gateroad of the working face.
2. The longwall N00 mining method according to claim 1, wherein, the haulage dip is changed during mining with one end being always connected to a shaft head, and the other end being always connected to the air-return dip.
3. The longwall N00 mining method according to claim 2, wherein, directional roof cutting is used during the cutting top of the roof of the gob area for releasing pressure and retaining an entry.
4. The longwall N00 mining method according to claim 3, wherein, anchor rods and anchor cables are used for roof support during the cutting top of the roof of the gob area for releasing pressure and retaining an entry.
5. The longwall N00 mining method according to claim 3, wherein, a hydraulic prop support is used near to the entry during the cutting top of the roof of the gob area for releasing pressure and retaining an entry.
6. The longwall N00 mining method according to claim 5, wherein t, a wood plate is arranged on the hydraulic prop.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1) The following detailed description of the present disclosure is taken in conjunction with the accompanying drawings.
(2)
(3)
DETAILED DESCRIPTION
(4) Typical embodiments embodying features and advantages of the present disclosure will be set forth in the following description. It is appreciated that the present disclosure may have various modifications in various embodiments, all without departing from scope of the invention, and the description and drawings are regarded to be illustrative in nature and not limit the present disclosure.
(5) A longwall N00 mining method is a novel coal mining method with ventilation of the whole district can be ensured without excavating the upper gateroad and the lower gateroad when mining is conducted in the working face longwall, nor need to retain any coal pillar. Hereinafter, the structure of one embodiment will be explained in details. The term district as used herein refers to a mining block section that has an independent production system and is divided along a strike within a phase or a mining level. A nearly horizontal coal seam can be also referred as a panel. An inclined longwall strip mining district can also be referred as a strip district.
(6) The longwall N00 mining method according to the present disclosure in a specific application as shown in
(7) In the embodiment, the district 2 includes a plurality of working faces 20. On the first mining face 20, one section of the haulage dip 28 is used as an upper gateroad 21 of the first mining face 20. During mining, an entry is retained on a position closed to a next working face 20 to form a lower gateroad 22. In addition, a passage 27 is provided on a mining face 23. In the embodiment, the upper gateroad 21, the passage 27, the lower gateroad 22 and an original haulage dip 28 are connected in turn, that is, the passages of the ventilation system are always connected with each other.
(8) In the embodiment, when mining is performed in a general working face 20, the retained entry on the side of the previous working face is used as the upper gateroad, and the passage 27 of the mining face 23 is used as a ventilation passage, and the self-retained entry is used as a lower gateroad 22, so that a complete ventilation system is still formed.
(9) It is not necessary to excavate the upper gateroad and the lower gateroad in any working face 20 before mining work throughout the above process, only need to continuously retain entry. Accordingly, the work efficiency can be improved and resource consumption can be reduced.
(10) In addition, in the embodiment, retaining entry can be implemented while the top is cut to release pressure. A plurality of cutting drill holes on the same line are constructed on the roof of the working face, after construction of the cutting drill holes by using a cutting drilling machine, the cutting drill holes can be fractured directionally by using a blasting or expanding device to form cracks on the roof. After the coal seam is re-mined, the roof of the pressure release area at the gob is automatically cut off along the crack to form entry ribs of the lower gateroad. Due to crushing expansion of the rock, a stable support of the geological structure of the pressure release area at the gob can be finally achieved. After pressure release by cutting the top, the roof cannot bring any pressure force against the gob area, thereby no coal pillar is retained for support, which can greatly improve the coal mining rate, reduce cost and effectively use energy, so that the market prospect is very good. Also, the passage 27 and the lower gateroad 22 can be supported by arranging supports used for coal mining, to ensure that the two passages cannot collapse as the dynamic changes of the mining work and allow the ventilation passages unobstructed. And, optionally, the lower gateroad 22 may be provided with a lateral support structure to maintain and shape the lateral ribs of the lower gateroad 22.
(11) In the embodiment, each working face 20 during mining includes:
(12) mining in a direction from one end away from the air-return dip 25 and the track dip 26 (i.e., one end close to the haulage dip 28) toward the air-return dip 25 and the track dip 26;
(13) forming a gob area;
(14) cutting top for releasing pressure and retaining an entry during mining, wherein the retained entry position is a side close to the next working face 20.
(15) In this embodiment, the air-return dip 25 and the track dip 26 are unchanged throughout the mining process in order to fix the passages. The haulage dip 28 can be gradually changed along the retained entry during mining in order to adapt for variation of the passages. And the haulage dip 28, after the district 2 is mined out, forms a passage that is substantially parallel to the air-return dip 25 and the track dip 26.
(16) A mining direction of the coal mining system as described in the description refers to overall advancing direction, the coal mining machine in the coal mining system may perform mining towards the left or the right along a front wall in the passage 27, in order to propel to the advancing direction (the direction as indicated by a solid arrow in
(17) In the embodiment, for top-cutting pressure release and gob-side entry retaining, directional roof cutting and directional blasting are required, and the roof of the entry can be supported by the anchor rods and the anchor cables, and hydraulic props and wood plates are used for comprehensive support, so as to ensure safety. A retained entry is formed after mining coal without being separately excavated, which can save time and reduce waste of resources such as coal, to ensure effective use of the resources.
(18) Advantageous effects of the present disclosure are presented as follows: as compared with the prior art, the present disclosure can not only ensure ventilation of the whole coal cutting are, but also when mining is performed in each working face in the district, entrys can be automatically formed due to top-cutting pressure release by using a part of a gob area, and thereby it is not required to separately excavate any gateroad entry during mining coal nor need to retain any coal pillar, so as to save resources and improve efficiency.
(19) The technical solution of the present disclosure has already described through some exemplary embodiments. It is apparent that those skilled in the art can make modifications and variations to the invention without departing from the scope of the invention. The invention is intended to cover the modifications and variations provided that they fall in the scope of protection defined by the following claims or their equivalents.