Start-up control device and start-up control method for power plant
10386826 ยท 2019-08-20
Assignee
Inventors
- Miyuki KAWATA (Tokyo, JP)
- Yasuhiro Yoshida (Tokyo, JP)
- Takuya YOSHIDA (Tokyo, JP)
- Tatsuro Yashiki (Tokyo, JP)
- Eunkyeong KIM (Tokyo, JP)
- Kazunori Yamanaka (Yokohama, JP)
- Norihiro Iyanaga (Yokohama, JP)
- Atsushi Yamashita (Yokohama, JP)
Cpc classification
F01K13/02
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
International classification
G05B19/418
PHYSICS
F01K13/02
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
Abstract
To provide a start-up control device and a start-up control method for a power plant capable of changing the start-up completion estimated time to a desired time simply and safely while starting the power plant. The start-up control device includes an equipment state quantity acquisition unit acquiring an equipment state quantity of the power plant, a start-up schedule calculation unit calculating a current start-up schedule based on the equipment state quantity and a first thermal stress limiting value and calculating a start-up schedule changing plan based on the equipment state quantity and a second thermal stress limiting value, an equipment operation amount calculation unit calculating an equipment operation amount of the power plant based on the current start-up schedule, a screen display unit displaying respective start-up completion estimated times of the current start-up schedule and the start-up schedule changing plan, and an instruction input unit instructing the start-up schedule calculation unit to perform switching from the current start-up schedule to the start-up schedule changing plan.
Claims
1. A start-up control device for a power plant including a steam turbine, comprising: a processor; a memory storing a program which, when executed, causes the processor to: receive measurement signals from instruments arranged in the power plant and convert the measurement signals to an equipment state quantity of the power plant; calculate a running start-up schedule from a current point to a start-up completion based on the equipment state quantity and a predetermined first constraint condition and calculate a start-up schedule changing plan from the current point to the start-up completion based on the equipment state quantity and a predetermined second constraint condition; and calculate an equipment operation amount of the power plant based on the running start-up schedule; a display screen that displays start-up completion estimated times with respect to a case when the running start-up schedule is executed from the current point to the start-up completion and a case when the start-up schedule changing plan is executed from the current point to the start-up completion, respectively; and a user interface through which an operator inputs an instruction for switching from the running start-up schedule to the start-up schedule changing plan.
2. The start-up control device for the power plant according to claim 1, wherein the display screen further displays lifetime consumption rates that are degrees of low-cycle thermal fatigue accumulated in a turbine rotor provided in the steam turbine with respect to the case when the running start-up schedule is executed from the current point to the start-up completion and the case when the start-up schedule changing plan is executed from the current point to the start-up completion, respectively.
3. The start-up control device for the power plant according to claim 1, wherein the display screen further displays fuel consumption amounts to be used until the start-up completion with respect to the case when the running start-up schedule is executed from the current point to the start-up completion and the case when the start-up schedule changing plan is executed from the current point to the start-up completion, respectively.
4. The start-up control device for the power plant according to claim 1, wherein the display screen further displays the residual numbers of start-up times in a current year and excess lifetime consumption rates for the residual numbers of start-up times with respect to the case when the running start-up schedule is executed from the current point to the start-up completion and the case when the start-up schedule changing plan is executed from the current point to the start-up completion, respectively.
5. The start-up control device for the power plant according to claim 1, wherein the display screen further displays output curves of the steam turbine with respect to the case when the running start-up schedule is executed from the current point to the start-up completion and the case when the start-up schedule changing plan is executed from the current point to the start-up completion, respectively.
6. The start-up control device for the power plant according to claim 1, wherein the second constraint condition is set through an input operation on the user interface.
7. The start-up control device for the power plant according to claim 1, wherein the user interface sets a predetermined start-up completion estimated time in accordance with an input operation by the operator, and the second constraint condition is calculated based on the predetermined start-up completion estimated time.
8. A start-up control method for a power plant including a steam turbine, the method comprising: receiving measurement signals from instruments arranged in the power plant; converting the measurement signals to an equipment state quantity of the power plant; calculating a running start-up schedule from a current point to a start-up completion based on the equipment state quantity and a predetermined first constraint condition and calculating a start-up schedule changing plan from the current point to a start-up completion based on the equipment state quantity and a predetermined second constraint condition; calculating an equipment operation amount of the power plant based on the running start-up schedule; displaying start-up completion estimated times on a display screen with respect to a case when the running start-up schedule is executed from the current point to the start-up completion and a case when the start-up schedule changing plan is executed from the current point to the start-up completion, respectively; and receiving an instruction from an operator, via a user interface, for switching from the running start-up schedule to the start-up schedule changing plan; and switching from the running start-up schedule to the start-up schedule changing plan based on the instruction from the operator.
9. The start-up control method for the power plant according to claim 8, wherein lifetime consumption rates that are degrees of low-cycle thermal fatigue accumulated in a turbine rotor provided in the steam turbine are further displayed on the display screen with respect to the case when the running start-up schedule is executed from the current point to the start-up completion and the case when the start-up schedule changing plan is executed from the current point to the start-up completion, respectively.
10. The start-up control method for the power plant according to claim 8, wherein fuel consumption amounts to be used until the start-up completion are further displayed on the display screen with respect to the case when the running start-up schedule is executed from the current point to the start-up completion and the case when the start-up schedule changing plan is executed from the current point to the start-up completion, respectively.
11. The start-up control method for the power plant according to claim 8, wherein residual numbers of start-up times in a current year and excess lifetime consumption rates for the residual numbers of start-up times are further displayed on the display screen with respect to the case when the running start-up schedule is executed from the current point to the start-up completion and the case when the start-up schedule changing plan is executed from the current point to the start-up completion, respectively.
12. The start-up control method for the power plant according to claim 8, wherein output curves of the steam turbine are further displayed on the display screen with respect to the case when the running start-up schedule is executed from the current point to the start-up completion start-up schedule and the case when the start-up schedule changing plan is executed from the current point to the start-up completion, respectively.
13. The start-up control method for the power plant according to claim 8, wherein the second constraint condition is set through an input operation on the user interface.
14. The start-up control method for the power plant according to claim 8, wherein a predetermined start-up completion estimated time is set through an input operation on the user interface, and the second constraint condition is calculated based on the predetermined start-up completion estimated time.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
DESCRIPTION OF EMBODIMENTS
(16) Hereinafter, embodiments of the present invention will be explained with reference to the drawings. The same symbols are given to the same components in respective drawings, and repeated explanation is suitably omitted.
First Embodiment
(17)
(18) In
(19) In the heat source device 201, a low-temperature medium 206 (air to be burned with a fuel in the example) is heated by heat capacity held by a heat source medium 205 (fuels such as a gas fuel, a liquid fuel and a hydrogen containing fuel in the example), which is supplied to the steam generating device 202 as a high-temperature medium 207 (combustion gas having driven the gas turbine 201 in the example).
(20) In the steam generating device 202 (an exhaust heat recovery boiler in the example), supplied water is heated by heat exchange with potential heat of the high-temperature medium 207 generated in the heat source device 201 to thereby generate a steam 208, and the steam turbine 203 is driven by the steam 208. The power generator 204 is coaxially connected to the steam turbine 203, and a rotational driving force of the steam turbine 203 is converted into electric power by the power generator 204. The generated power of the power generator 204 is outputted to, for example, a power system (not shown). A thermometer 213 is provided in the steam turbine 203, and a metal temperature of a casing in a first stage of the steam turbine 203 is measured by the thermometer 213.
(21) The heat-source medium amount adjusting device 214 (a fuel regulating valve in the example) is provided in a supply route of the heat source medium 205 connecting to the heat source device 201, regulating the heat source medium amount to be supplied to the heat source device 201. The heat-source medium amount adjusting device 214 functions as an adjusting device which adjusts a plant load of the power plant 200. Also in the supply route of the heat source medium 205, a flowmeter 211 is provided on the downstream side of the heat-source medium amount adjusting device 214, and the supply amount of the heat source medium 205 supplied to the heat source device 201 is measured by the flowmeter 211.
(22) The main steam control valve 215 is provided in a main steam pipe connecting the steam generating device 202 to the steam turbine 203, adjusting the flow rate of steam supplied to the steam turbine 203. The main steam control valve 215 functions as an adjusting device which adjusts a plant load of the power plant 200. Also in the main steam pipe, a pressure gauge 212 is provided in a position on the downstream side (steam turbine 203 side) of the main steam control valve 215, and the pressure of mainstream steam flowing in the main stream pipe is measured by the pressure gauge 212.
(23) The start-up control device 1 includes a start-up control parameter storage unit 2, a start-up schedule calculation unit 3, a screen display unit 5, an instruction input unit 6, an equipment operation amount calculation unit 7 and an equipment state quantity acquisition unit 8.
(24) The start-up control parameter storage unit 2 stores start-up patterns, start-up control parameters and constraint conditions.
(25) The start-up schedule calculation unit 3 operates in accordance with an equipment state prediction program 4, calculating a current start-up schedule of the power plant 200 based on the start-up pattern, the start-up control parameters and the constraint condition stored in the start-up control parameter storage unit 2, and an equipment state quantity inputted from the equipment state quantity acquisition unit 8, and calculating a start-up schedule changing plan based on a constraint condition which is different from the constraint condition.
(26) The screen display unit 5 displays respective start-up completion estimated times of the current start-up schedule and the start-up schedule changing plan calculated by the start-up schedule calculation unit 3.
(27) The instruction input unit 6 outputs a switching instruction from the current start-up schedule to the start-up schedule changing plan to the start-up schedule calculation unit 3 in accordance with an input operation by an operator.
(28) The equipment operation amount calculation unit 7 calculates operation amounts of plant equipment (hereinafter referred to as equipment operation amounts) based on the current start-up schedule inputted by the start-up schedule calculation unit 3, and outputs control signals 11 corresponding to the equipment operation amounts to the plant equipment. The plant equipment in the embodiment includes the heat-source medium amount adjusting device 214 and the main steam control valve 215.
(29) The equipment state quantity acquisition unit 8 converts measurement signals 12 inputted from plant instruments into an equipment state quantity and outputs the equipment state quantity to the start-up schedule calculation unit 3. The plant instruments in the embodiment include the flow meter 211 provided in the supply route of the heat source medium 205, the pressure gauge 212 provided in the main steam pipe connecting the steam generating device 202 and the steam turbine 203 and the thermometer 213 provided in the steam turbine 203.
(30)
(31) In
(32) In a case where the thermal stress limiting value 31 is maintained as the constraint condition (in the case where the current start-up schedule is continued) after the current point, the thermal stress is suppressed to the thermal stress limiting value 31 or lower as shown by the thermal stress curve 35, and the output of the power plant 200 is assumed to reach 100% (start-up is completed) at a start-up completion estimated time 25 as shown by the output curve 22.
(33) On the other hand, in a case where the constraint condition is alleviated from the thermal stress limiting value 31 to the thermal stress limiting value 32 (in the case where the current start-up schedule is switched to the start-up schedule changing plan A) after the current point, the thermal stress is allowed until reaching the thermal stress limiting value 32 as shown by the thermal stress curve 36, and the output of the power plant 200 is assumed to reach 100% (start-up is completed) at a start-up completion estimated time 26 as shown by the output curve 23. In a case where the constraint condition is alleviated from the thermal stress limiting value 31 to the thermal stress limiting value 33 (in the case where the current start-up schedule is switched to the start-up schedule changing plan B), the thermal stress is allowed until reaching the thermal stress limiting value 33 as shown by the thermal stress curve 37, and the output of the power plant 200 is assumed to reach 100% (start-up is completed) at a start-up completion estimated time 27 as shown by the output curve 24. That is, the start-up control device 1 can move up the start-up completion estimated time by alleviating the constraint condition of the start-up schedule.
(34) The start-up schedule calculation unit 3 incorporates the equipment state quantity at the current point into the calculation of the thermal stress curves 35 to 37 from the current point to the start-up completion, the output curves 22 to 24 and the start-up completion estimated times 25 to 27 from the current point to the start-up completion, thereby improving these accuracy.
(35) In the embodiment, the start-up schedule calculation unit 3 calculates the current start-up schedule based on the thermal stress limiting value 31 and the equipment state quantity at the current point as well as calculates the start-up schedule changing plans A, B based on the thermal stress limiting values 32, 33 which are different from the thermal stress limiting value 31 and the equipment state quantity at the current point.
(36) Here, as a simple method of setting the thermal stress limiting values 32, 33 of the start-up schedule changing plans A, B, it is possible to consider a method of setting values obtained by performing constant multiplication (for example, 1.1 times, 1.2 times) of the thermal stress limiting value 31 of the current start-up schedule as the thermal stress limiting values 32, 33. However, the embodiment adopts a method of setting times obtained by moving up the start-up completion estimated time 25 of the current start-up schedule by a predetermined period of time (for example, 10 minutes, 20 minutes) as the start-up completion estimated times 26, 27 of the start-up schedule changing plans A, B, and setting thermal stress peak values (max) of the start-up schedule changing plans A, B calculated based on the start-up completion estimated times 26, 27 as the thermal stress limiting values 32, 33. Accordingly, the operator can move up the start-up completion estimation time in a predetermined time unit (for example, in a unit of 10 minutes).
(37) As a method of calculating the thermal stress limiting values 32, 33, it is difficult to generate a function of calculating the thermal stress limiting values 32, 33 backward from the start-up completion estimated times 26, 27, therefore, a method of repeating calculation of the start-up schedule changing plan by incrementing the thermal stress limiting value by a small fraction from the current thermal stress limiting value 31, and by setting the thermal stress limiting values in which the start-up completion estimated times correspond to the start-up completion estimated times 26, 27 as the thermal stress limiting values 32, 33 is used.
(38)
(39) In
(40)
(41) In
(42) When it is determined as Yes (the power plant 200 is in start-up completion state) in Step 104, the start-up control device 1 stops operation (Step 110).
(43) On the other hand, when it is determined as No (the power plant 200 is not in start-up completion state) in Step 104, the equipment operation amount calculation unit 7 calculates equipment operation amounts and outputs the control signals 11 corresponding to the equipment operation amounts to the heat-source medium amount adjusting device 214 and the main steam control valve 215 (Step 105).
(44) Subsequent to Step 105, the start-up schedule calculation unit 3 calculates the start-up schedule changing plans A, B (including the start-up completion estimated times 26, 27) based on constraint conditions (thermal stress limiting values 32, 33) different from the current constraint condition (thermal stress limiting value 31) and the equipment state quantity (Step 106).
(45) Subsequent to Step 106, respective start-up completion estimated times 25 to 27 of the current start-up schedule and the start-up schedule changing plans A, B are displayed on the screen display unit 5 and a signal waiting process is executed (Step 107).
(46) While the signal waiting process (Step 107) is executed, the process proceeds to Step 105 (route a) at regular intervals which are previously set in consideration of the output timing of the control signals of the plant equipment (the heat-source medium amount adjusting device 214 and the main steam control valve 215), and processes after Step S105 are executed as described above.
(47) Also while the signal waiting process (Step 107) is executed, the process proceeds to Step 102 (route b) at regular intervals which are previously set in consideration of the measurement timing of the plant instruments 211 to 213, and processes after Step S102 are executed as described above.
(48) When an input operation is performed on the instruction input unit 6 while the signal waiting process (Step 107) is executed, the process proceeds to Step 108 (route c), in which a switching instruction to the start-up schedule changing plan A or B is received (Step 108) and the constraint condition (the thermal stress limiting value 31) stored in the start-up control parameter storage unit 2 is updated by the constraint condition (thermal stress limiting values 32 or 33) corresponding to the stand-up schedule changing plan A or B to be switched (Step 109). Subsequent to Step S109, processes after Step 103 are executed as described above.
(49) When the start-up control device 1 according to the embodiment is used, the stand-up schedule changing plans A, B are calculated based on the thermal stress limiting values 32, 33 which are set in accordance with desired start-up completion estimated times 26, 27 and the equipment state quantity at the current point, therefore, the start-up completion estimated time 25 can be changed to the desired start-up completion estimated time 26 or 27 simply and safely during the start-up of the power plant 200. Accordingly, the operator can flexibly deal with changes in power demand and the like during the start-up of the power plant 200.
Second Embodiment
(50) Next, a second embodiment of the present invention will be explained.
(51) The embodiment differs from the first embodiment in a point that lifetime consumption rates of a turbine rotor (not shown) provided in the steam turbine 203 (see
(52)
(53) In
(54) A method of calculating the lifetime consumption rate will be explained below.
(55)
(56) In
(57) When the start-up control device 1 according to the embodiment is used, the same advantages as those of the first embodiment can be obtained and the operator can determine whether the switching from the current start-up schedule to the start-up schedule changing plan A or B is executed or not by comparing and considering respective lifetime consumption rates of the current start-up schedule and the start-up schedule changing plans A, B.
Third Embodiment
(58) Next, a third embodiment of the present invention will be explained.
(59) The embodiment differs from the first embodiment in a point that the degree of influence on an annual operation plan of the power plant 200 is displayed on the screen display unit 5 (see
(60) First, the annual operation plan of the power plant 200 will be explained.
(61) In general, the start-up schedule of the power plant 200 is classified into either one of start-up modes such as a hot mode, a warm mode and a cold mode according to the stop time of the steam turbine 203 or the temperature inside the turbine rotor. The annual operation plan sets the lifetime consumption rate and the annual number of start-up times with respect to each start-up mode.
(62) Next, a method of formulating the annual operation plan will be explained.
(63) The starting time is increased in the order of the hot mode, the warm mode and the cold mode when comparing in the same thermal stress limiting value. Therefore, the thermal stress limiting value is set to be lower (set a planned value of the lifetime consumption rate to be smaller) in the hot mode in which a margin with respect to a required starting time is large, the thermal stress limiting value is set to be higher (set a planned value of the lifetime consumption rate to be larger) in the cold mode in which the margin with respect to the required starting time is small, and the annual number of start-up times in each start-up mode is adjusted, thereby formulating an effective annual operation plan in consideration of the balance between operating costs and the lifetime of the turbine rotor.
(64) Specifically, the standard lifetime consumption rates in respective start-up modes (hereinafter referred to as lifetime consumption rate planned values) are represented as Ahot, Awarm and Acold, and the planned numbers of start-up times in a current year in respective start-up modes (hereinafter referred to as annual number of start-up times planned values) are represented by Bhot, Bwarm and Bcold. The annual number of start-up times planned values in respective start-up modes Bhot, Bwarm and Bcold are determined such that a product-sum value of the lifetime consumption rate planned values and the annual number of start-up times planned values AhotBhot+AwarmBwarm+AcoldBcold corresponds to the lifetime consumption rate allowed in the current year. The formulation of the annual operation plan as above has generally been performed.
(65) The present invention assumes that the starting time is shortened by increasing the lifetime consumption rates to be larger than the lifetime consumption rate planned values Ahot, Awarm and Acold, therefore, the operator can review the lifetime consumption rate planned values Ahot, Awarm and Acold in respective start-up modes by displaying respective lifetime consumption rates of the current start-up schedule and the start-up schedule changing plans A, B as in the start-up schedule selection screen 5a (see
(66) However, in the start-up schedule selection screen (see
(67)
(68) In
(69) Hereinafter, a method of calculating the residual number of start-up times and the excess lifetime consumption rate will be explained by citing a case where the current start-up schedule belongs to the warm mode.
(70) The start-up control parameter storage unit 2 previously stores the lifetime consumption rate planned values Ahot, Awarm and Acold in respective start-up modes and the annual number of start-up times planned values Bhot, Bwarm and Bcold in respective modes. Here, assume that the lifetime consumption rate planned value Awarm in the warm section is 0.024%, the annual number of start-up times planned value Bwarm in the warm mode is 16 times, and the start-up schedule in the warm mode in the past has been executed once with a lifetime consumption rate 0.025%. In this case, the current residual number of start-up times is calculated as 16 times1 time=15 times, and the lifetime consumption rate planned value Awarm in the warm mode is 0.024%, therefore, the excess lifetime consumption rate in the past start-up schedule is calculated as 0.025%-0.024%=0.001% pt. Here, the lifetime consumption rate of the current start-up schedule corresponds to the lifetime consumption rate planned value Awarm (0.024%) in the warm mode if any change is not made, therefore, the excess lifetime consumption rate in the current start-up schedule is calculated as 0.024%Awarm(=0.024%)=0.000% pt. When the excess lifetime consumption rate in the past 0.001% pt is added to the above, the current excess lifetime consumption rate will be 0.001% pt. As a result, 15 which is the residual number of start-up times in the current start-up schedule, and 0.001 which is the excess lifetime consumption rate with respect to 15 times as residual number of start-up times are displayed on the start-up schedule selection screen 5a.
(71) Subsequently, the residual number of start-up times and the excess lifetime consumption rate of the start-up schedule changing plan A are calculated. Here, when the lifetime consumption rate of the start-up schedule changing plan A is 0.045%, the excess lifetime consumption rate of the start-up schedule changing plan A is calculated as 0.045%Awarm(=0.024%)=0.021% pt. When 0.001% pt as the excess lifetime consumption rate in the past is added to the above, the excess lifetime consumption rate with respect to 15 times as the residual number of start-up times in the case of being switched to the start-up schedule changing plan A will be 0.022% pt. As a result, 15 which is the residual number of start-up times in the start-up schedule changing plan A, and 0.022 which is the excess lifetime consumption rate with respect to 1.5 times as residual number of start-up times are displayed on the start-up schedule selection screen 5a.
(72) Subsequently, the residual number of start-up times and the excess lifetime consumption rate of the start-up schedule changing plan B are calculated. Here, when the lifetime consumption rate of the start-up schedule changing plan B is 0.049%, the excess lifetime consumption rate of the start-up schedule changing plan B is calculated as 0.049%Awarm(=0.024%)=0.025% pt. When 0.001% pt as the excess lifetime consumption rate in the past is added to the above, the excess lifetime consumption rate with respect to 15 times as the residual number of start-up times in the case of being switched to the start-up schedule changing plan B is calculated as 0.026% pt. In the case where the excess lifetime consumption rate (0.026% pt) exceeds the lifetime consumption rate planned value Awarm (=0.024%) per one start-up as in the above case, one time is subtracted from the residual number of start-up times (15 times) and the lifetime consumption rate planned value Awarm (=0.024%) per one start-up is subtracted from the excess lifetime consumption rate (0.026% pt), thereby correcting the values respectively. As a result, 14 which is the residual number of start-up times after being switched to the start-up schedule changing plan B, and 0.002 which is the excess lifetime consumption rate with respect to 14 times as residual number of start-up times are displayed on the start-up schedule selection screen 5a. Accordingly, the operator can correctly grasp the residual number of start-up times and the excess lifetime consumption rate with respect to the residual number of start-up times even when the excess lifetime consumption rate exceeds the lifetime consumption rate planned value per one start-up.
(73) When the start-up control device 1 according to the embodiment is used, the same advantages as those of the first embodiment can be obtained and the operator can determine whether the switching from the current start-up schedule to the start-up schedule changing plan A or B is executed or not by comparing and considering the degree of influence on respective annual operation plans of the current start-up schedule and the start-up schedule changing plans A, B (the residual number of start-up times and the excess lifetime consumption rate with respect to the residual number of start-up times).
Fourth Embodiment
(74) Next, a fourth embodiment of the present invention will be explained.
(75) The embodiment differs from the first embodiment in a point that fuel consumption amounts to be used until the start-up completion are displayed on the screen display unit 5 (see
(76)
(77) In
(78) When the start-up control device 1 according to the embodiment is used, the same advantages as those of the first embodiment can be obtained and the operator can determine whether the switching from the current start-up schedule to the start-up schedule changing plan A or B is executed or not by comparing and considering respective fuel consumption amounts to be used until the start-up completion in the current start-up schedule and the start-up schedule changing plans A, B.
Fifth Embodiment
(79) Next, a fifth embodiment of the present invention will be explained.
(80) The embodiment differs from the first embodiment in a point that respective output curves and the thermal stress curves of the current start-up schedule and the start-up schedule changing plans A, B are displayed on the screen display unit 5 (see
(81)
(82) In
(83) When the start-up control device 1 according to the embodiment is used, the same advantages as those of the first embodiment can be obtained and the operator can determine whether the switching from the current start-up schedule to the start-up schedule changing plan A or B is executed or not by comparing and considering respective output curves 22 to 24 and the thermal stress curves 35 to 37 in the current start-up schedule and the start-up schedule changing plans A, B.
Sixth Embodiment
(84) Next, a sixth embodiment according to the present invention will be explained.
(85) The embodiment differs from the first embodiment in a point that the constraint condition of the start-up schedule changing plan is designated by the operator, which is not set by the start-up schedule calculation unit 3 based on a predetermined calculation formula.
(86)
(87) In
(88)
(89) In
(90) On a thermal stress limiting value input field 58, the thermal stress limiting value of the start-up schedule changing plan inputted through the operation on the instruction input unit 6 is displayed. On a start-up completion estimated time display field 59, the start-up completion estimated time of the start-up schedule changing plan is to be displayed, however, nothing is displayed before the start-up schedule changing plan is calculated. When the calculation button 56 is clicked or tapped after the thermal stress limiting value is inputted in the thermal stress limiting value input field 58, the start-up schedule changing plan is calculated, and the start-up completion estimated time of the start-up schedule changing plan is displayed on the start-up completion estimated time display field 59 as shown in
(91) Here, when a time lag occurs until the determination button 57 is operated from the operation on the calculation button 56, the equipment state quantity varies during the time lag, which may cause a significant error in the start-up completion estimated time.
(92) Accordingly, the determination button 57 can be configured so as to be operated only during a predetermined period of time (for example, for five minutes) from the completion of calculation of the start-up schedule changing plan (after the transition from Step 103 to Step 107 in
(93) When the start-up control device 1 according to the embodiment is used, not only the same advantages as those of the first embodiment can be obtained but also the start-up schedule changing plan is calculated based on the constraint condition designated by the operator and the operator can determine whether the switching from the current start-up schedule to the start-up schedule changing plan A or B is executed or not by comparing and considering respective start-up completion estimated times in the current start-up schedule and the start-up schedule changing plan.
Seventh Embodiment
(94) Next, a seventh embodiment of the present invention will be explained.
(95) The embodiment corresponds to an embodiment in which the constraint condition of the start-up schedule changing plan is replaced with the start-up completion estimated time of the start-up schedule changing plan as the item designated by the operator in the sixth embodiment.
(96) Hereinafter, explanation will be made by focusing on a point different from the sixth embodiment.
(97)
(98) In
(99)
(100) In
(101) On a start-up completion estimated time input field 60, the start-up completion estimated time inputted through the operation on the instruction input unit 6 is displayed. On a lifetime consumption rate display field 61, the lifetime consumption rate of the start-up schedule changing plan is to be displayed, however, nothing is displayed before the start-up schedule changing plan is calculated. When the calculation button 56 is clicked or tapped after the start-up completion estimated time is inputted in the start-up completion estimated time input field 60, the start-up schedule changing plan is calculated, and the lifetime consumption rate of the start-up schedule changing plan is displayed on the lifetime consumption rate display field 61 as shown in
(102) When the start-up control device 1 according to the embodiment is used, not only the same advantages as those of the first embodiment can be obtained but also the start-up schedule changing plan is calculated based on the start-up completion estimated time designated by the operator and the operator can determine whether the switching from the current start-up schedule to the start-up schedule changing plan is executed or not by comparing and considering respective lifetime consumption rates of the current start-up schedule and the start-up schedule changing plan.
(103) The present invention is not limited to the above embodiments but includes various modification examples. For example, the above embodiments have been explained in detail for explaining the present invention to be easily understood, and the present invention is not limited to the embodiments having all the components explained above. It is possible to replace part of components of a certain embodiment with components of another embodiment, or it is possible to add a component of another embodiment to components of a certain embodiment.
(104) The above embodiments are suitable for start-up control of a combined cycle power plant, however, the present invention is not limited to this and can be applied to a nuclear power plant, a co-generation plant using fossil fuels and industrial plants requiring time for starting a boiler and so on.