Method for jointing concrete column and iron beam
10378197 ยท 2019-08-13
Assignee
Inventors
Cpc classification
E04C5/0645
FIXED CONSTRUCTIONS
E04C5/08
FIXED CONSTRUCTIONS
E04H9/021
FIXED CONSTRUCTIONS
E04B1/185
FIXED CONSTRUCTIONS
E04B1/30
FIXED CONSTRUCTIONS
E04B1/98
FIXED CONSTRUCTIONS
E04B5/29
FIXED CONSTRUCTIONS
International classification
E04B1/18
FIXED CONSTRUCTIONS
E04C5/08
FIXED CONSTRUCTIONS
E04C5/06
FIXED CONSTRUCTIONS
E04B1/98
FIXED CONSTRUCTIONS
E04B1/30
FIXED CONSTRUCTIONS
Abstract
A method is provided for jointing a concrete column and an iron beam. A structure joint portion is provided between a column-beam junction and an end of the iron beam, which is mourned on a coning provided to the column. Prestressing tendons are arranged in plural rows to horizontally penetrate the column-beam junction, Tension-introduction forces are applied to the prestressing tendons to tensionally anchor an anchor plate, and thereby to integrally joint the column and the beam.
Claims
1. A method for jointing a concrete column and a iron beam in a building structure having the column and the beam, the beam being an iron beam formed of H-steel, the method comprising: forming a column-beam junction integrally to the column in advance; providing an anchor plate and an anchorage at an end of the beam, providing an end plate at an end of the beam and an anchor plate and an anchorage at a predetermined distance apart from the end of the beam, or providing an end plate, a solidified filler material with a predetermined thickness, and an anchorage at an end of the beam; providing a structure joint portion between the column-beam junction and the end of the beam; mounting the end of the beam on a cogging provided to the column; arranging prestressing tendons in plural rows to horizontally penetrate the column-beam junction; applying tension-introduction forces into the prestressing tendons to tensionally anchor the anchorage, and thereby to integrally joint the column and the beam; and providing a concrete slab with a predetermined thickness on an upper end of the beam, wherein the tension-introduction forces applied into the prestressing tendons are determined so as to fulfill the following conditions: joint separation at the structure joint portion is inhibited in a case of a moderate earthquake, which is a rare earthquake, or weaker; the joint separation is allowed to proceed in a case of a large earthquake, which is a very rare earthquake; and yielding of a lower flange of the iron beam is prevented in the case of the large earthquake, by fulfilling an expression:
P<d.sub.s/d.sub.pcT.sub.s, where P denotes a resultant force P of the tension-introduction forces, d.sub.s denotes a distance between a lower end of the beam and a top end of the slab, d.sub.pc denotes a distance between a position where the resultant force affects and the top end of the slab, T.sub.s denotes a tensile yield load of the lower flange of the iron beam and
T.sub.s=Bt.sub.y, B denotes a width of the lower flange, t denotes a plate thickness of the lower flange, and .sub.y denotes a yielding strength of the iron beam.
2. A method for jointing a concrete column and a beam in a building structure having the column and the beam, the beam being an iron beam formed of H-steel, the method comprising: forming a column-beam junction integrally to the column in advance; providing an anchor plate and an anchorage at an end of the beam, providing an end plate at an end of the beam and an anchor plate and an anchorage at a predetermined distance apart from the end of the beam, or providing an end plate, a solidified filler material with a predetermined thickness, and an anchorage at an end of the beam; providing a structure joint portion between the column-beam junction and the end of the beam; mounting the end of the beam on a cogging provided to the column; arranging prestressing tendons in plural rows to horizontally penetrate the column-beam junction; applying tension-introduction forces into the prestressing tendons to tensionally anchor the anchorage, and thereby to integrally joint the column and the beam; and providing a concrete slab with a predetermined thickness on an upper end of the beam, wherein the tension-introduction forces applied into the prestressing tendons are determined so as to fulfill the following conditions: joint separation at the structure joint portion is inhibited in a case of a moderate earthquake, which is a rare earthquake, or weaker; the joint separation is allowed to proceed in a case of a large earthquake, which is a very rare earthquake; and yielding of a lower flange of the iron beam is prevented in the case of the large earthquake, by the tension-introduction force applied into the prestressing tendon in a lower-most row being the smallest, the tension-introduction force applied into the prestressing tendon in an upper-most row being the largest, and the tension-introduction force applied into the prestressing tendons increasing at each respective prestressing tendon between the lower-most row and the upper-most row.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
DETAILED DESCRIPTION OF THE INVENTION
(10) A method for jointing a column and a beam of the present invention will be explained in detail, based on embodiments illustrated in drawings.
Embodiment 1
(11) Now referring to
(12) Although not shown, the PC columns 1 are constructed as one span for one layer, or for one story, and arranged apart from one other with predetermined distances. Lower ends of the prestressing tendons 2 are connected with the foundation of the building structure. The prestressing tendon 2 includes prestressing steel rods 2a, each of which is tensionally anchored by fastening with anchorage 10, including a bearing plate and a nut, at an upper part of the PC column 1 for each span. The PC columns 1 are connected at upper parts of the spans in order, and stably kept in an erect state.
(13) In the connection of the PC columns 1, a column of a second span is erected on a column of a first span. The prestressing steel rod 2a is disposed in the column of the first span, and is tensionally anchored at an upper part of the first span by the anchorage 10. Its upper end is connected by a coupler 11 to a lower end of a prestressing steel rod 2a for the second span. It is tensionally anchored in a erect state at an upper part of the second span column by an anchorage 10, in the same manner as the first span. Subsequently, the same processes are repeated up to the uppermost story, to assemble the PC columns 1. After the prestressing steel rod 2a is tensionally anchored, a grout is filled between the prestressing steel rod 2a and the sheath 3a to achieve a bond type with rustproofing.
(14) At an end of the iron beam 4, an anchor plate 12 is provided and integrally jointed by welding, for example. In order to more rigidly joint and integrate the anchor plate 12 with the iron beam 4, it is preferable to provide and connect a reinforcing member 13 between the anchor plate 12 and the iron beam 4 by welding. The iron beam 4 is installed on the upper part of the assembled PC column 1 for each layer.
(15) The end of the iron beam 4 is mounted via a buffer material 14 on the cogging 5 of the PC column 1 erected as described above. A predetermined gap is provided for a structure joint portion 15 between it and the column-beam junction A. The prestressing tendons 2, such as prestressing steel rods 2b, are inserted and set through the horizontal sheaths 3b. The structure joint portion 15 is filled with joint mortar, for example. After the joint mortar is solidified, the prestressing steel rods 2b is tensionally anchored by fastening with the anchorage 10 including a bearing plate and a nut in the same manner as described above. The PC column 1 and the iron beam 4 are integrated with sandwiching the structure joint portion 15 between the anchor plate 12 and the column-beam junction A. It is preferable to provide a slipping material 16 between the buffer material 14 and the cogging 5. After the prestressing steel rods 2b are tensionally anchored, a grout is filled between the prestressing steel rod 2b and the sheath 3b to achieve a bond type with rustproofing.
(16) Thereafter, a top reinforcing bar 17 is linked to reinforcement fittings 9 provided in advance at a slab position. A concrete slab 7 is formed on the upper end of the iron beam 4 with a predetermined thickness. It is formed by placing a cast-in-place concrete, and integrated with the iron beam 4 and the PC column 1 by stud bolts 8 and the top reinforcing bar 17.
Embodiment 2
(17) Next referring to
(18) In this embodiment, an end plate 18 is integrally provided at an end of the iron beam 4 by welding. An anchor plate 12 is provided inwards apart from the end of the iron beam 4 with a predetermined distance. A reinforcing member 13 is disposed between the anchor plate 12 and the end plate 18. The reinforcing member 13 is integrally installed among the end plate 18, the anchor plate 12 and the iron beam 4 by welding. The other components are substantively the same as those in the first embodiment.
(19) In this manner, the plates 12, 18 are doubly provided at the end of the iron beam 4. This structure significantly improves flexural rigidity of the iron beam end in comparison with the single-plate, or anchor plate, structure disclosed in the first embodiment. Also, this ensure smooth transmission of bending stress from the beam to the column. It is preferable in cases of long spans and/or heavy loading capacity. In the second embodiment, the structure joint portions 15 on both sides are sandwiched between the column-beam junction A and the respective end plates 18 of the iron beams 4. The end of the prestressing steel rod 2b is tensionally anchored between the anchor plates 12 on both sides. This achieves integration of the PC column 1 and the iron beam 4. The end of the iron beam 4 is reinforced by the end plate 18, the anchor plate 12 and the reinforcing member 13. Also, a little extra length of the prestressing steel rod 2b increases allowance for elongation, and thereby enlarges extent of unfolding, that is, buffering capacity, of the structure joint portion 15. This enables prevention of damaging the end of the iron beam 4, and the whole building having a very tough structure.
Embodiment 3
(20) Referring now to
(21) In this embodiment, an appropriate filler material 19, such as concrete or mortar, for example, is filled between the doubled plates 12, 18 according to the second embodiment. This further improves the flexural rigidity of the iron beam end. Also, this ensures smooth transmission of the bending stress from the iron beam 4 to the PC column 1. Thereby, high toughness is exerted in cases of long spans and/or buildings with heavy loading capacities. The other components are substantively the same as those of the second embodiment.
(22) When the filler material 19 is filled between the end plate 18 and the anchor plate 12 provided at the end of the iron beam 4, a side board 20 may be provided between the doubled plates 12, 18 to enclose them except an upper surface. Required reinforcing bars 21 may be arranged among the enclosed doubled plates. Parts of the reinforcing bars 21 may be exposed to an upper position, where the slab 7 will be formed, and may be bound with the top reinforcing bar 17. The concrete may be placed along with that for slab 7.
(23) In this manner, the filler material 19 is filled between the doubled plates 12, 18. This significantly reduces stress applied to the anchor plate 12, and makes it possible to relatively decrease thicknesses of the end plate 18 and the anchor plate 12. Also, this relieves stress applied to these plates and the welded portion, and thereby makes it possible to prevent breakage of the welded portion and the like.
Embodiment 4
(24) Now referring to
(25) A method for jointing a column and a beam according to the fourth embodiment is a simplified and improved version of the third embodiment. An end plate 18 is provided at an end of an iron beam 4, but an anchor plate is omitted for simplification. The other structures are the same as those of the third embodiment. Detailed explanation is omitted for avoiding redundancy by assigning the same signs. In other words, plural horizontal sheaths 3b are disposed in a block of solidified filler material 19. The respective prestressing tendons 2b are inserted through them. The end of the prestressing tendon 2b is tensionally anchored by fastening the anchorage 10 outside a surface of the block of the filler material 19.
(26) In this manner, the configuration is different from that of the third embodiment, but there is no substantive difference in joint strengths between the column and the beam. Especially, forming the block of the filler material 19 adjacent to the end plate 18 requires only to form an enclosing box shape with wood boards, and to dispose plural horizontal sheaths 3b. This produces good workability, and reduces cost since no anchor plate is used. It is tensionally anchored by fastening with the anchorage 10 on a surface. For example, the prestressing steel rod 2b is inserted and set through it.
(27) The preferable examples having basic configurations of the present invention are illustrated above. However, arrangement of reinforcing bars or the like is not shown in parts, such as the column and the slab, having no association with the basic configurations of the present invention.
(28) It is preferable that the column is constructed by binding precast concrete columns with prestress. This is called precast and prestressed concrete. However, no limitation is intended. It may be constructed with cast-in-place prestressed concrete. Also, it may be constructed with precast reinforced concrete or cast-in-place reinforced concrete. In other words, any concrete column is possible, so long as it is formed to have a column-beam junction A with a cogging 5, before an iron beam is installed.
(29) The columns illustrated in the examples are middle columns having four column-beam junctions A at all sides. No other columns in a building structure are illustrated, such as outer peripheral columns, which are columns having column-beam junctions A at three sides, or corner columns, which are columns having column-beam junctions A at two sides. However, they can be formed in the similar manner. In other words, they are different from the illustrated ones in the examples in that an iron beam exists on one side of the column and there is no configuration for anchoring ends of prestressing tendons on the opposite side surface. The ends of the prestressing tendon can be anchored with appropriate anchorage 10 or the like. The other components can be the same as those of the examples.
(30) Next referring to
(31) In order to ease understanding, parts are omitted and not illustrated, having no association with the basic configuration, such as top reinforcing bars, stud bolts, or the like. The iron beam 4 is H-steel. The H-steel has a width B, a plate thickness t of the flange, a height H, and a yielding strength . A cast-in-place concrete slab 7 is provided on the upper end of the iron beam 4 to be integrated with the iron beam 4 and thereby to be a composite beam. The slab has a thickness a, and a distance d.sub.s from the lower end of the iron beam 4 to the top end of the slab.
(32) The doubled-plate 12, 18 structure is formed at the end of the iron beam 4. The filler material 19, such as concrete, is filled between the doubled plates. Prestressing tendons penetrate the column-beam junction A to joint the iron beams 4 of both sides, and are arranged in four rows. Each of the rows includes two prestressing steel rods 2a. The tension-introduction forces P.sub.1, P.sub.2, P.sub.3, and P.sub.4 is applied to the prestressing steel rods 2a for respective rows. The resultant force of them is denoted by P, where P= P.sub.i, i=1 to 4.
(33) In the section of the end of the beam, a distance between a position where the resultant force of the prestressing tendons affects and the top end of the slab is denoted by d.sub.pc.
(34) Generally, bending moments affecting the beam ends located at left and right sides of the column in a case of earthquake have opposite directions and the same magnitudes. In FIGS., the bending moments caused by force of the earthquake are illustrated by signs M() at the left side and M(+) at the right side. A distribution diagram beside them shows sectional stress intensity of the beam ends caused by the bending moments.
(35) As shown in
(36) This is the reason why the problem to be solved by the present invention is prevention of yielding of the iron beam at the right side. For this purpose, a joint-separation control condition is defined to control joint separation.
(37) The joint-separation control condition is to satisfy the expression:
P<d.sub.s/d.sub.pcT.sub.s,
where
d.sub.s=H+a,
(38) T.sub.s=Bt.sub.y, which denotes the tensile yield load of the flange at the tensile side of the iron beam,
(39) P= P.sub.1, where i=1, . . . , n (illustrated is a case of n=4), and
(40) d.sub.pc denotes the distance from the position where the resultant force of the prestressing tendons affects on the section of the beam end, to the top end of the slab.
(41) Next referring to the scheme shown in
(42) Assume that no joint separation occurs as shown in
(43) In comparison, the jointing method of the present invention controls structure joint separation in a case of a large earthquake, as shown in
(44) It should be noted that a little unfolding of the joint separation is actually enough to exert the effect. The illustration shows only a scheme.
(45) The prestressing tendons 2 penetrating the column-beam junction to joint the column and the beam may be tensionally anchored in an unbonded form. The prestressing tendons 2 tensionally anchored in an unbonded form is easy to extend in a case of a large earthquake. This is more effective because the joint separation is more easy in cooperation with the existence of the slipping material 16.
(46) The unbonded type can be formed, for example, by using prestressing steel rods plated or coated with epoxy resin, and by filling no grout between the prestressing steel rods and sheaths. Also, usual prestressing steel strands for unbonded type covered with polyethylene can be used. In this case, no filling of grout is needed.
(47) The tension-introduction forces applied to the prestressing tendons may be different according to rows. For example, the resultant force of the prestressing tendons 2 is the same as that in a case that the tension-introduction forces are the same. The tension-introduction force applied to the nearest prestressing tendon to the tensile side is the smallest. It becomes large as it comes near the compressive side. This facilitates the joint separation. Since the resultant force of all of the prestressing tendons is not changed, the designed prestressing force can be introduced as usual.
(48) Therefore, it is preferable in the present invention that tension-introduction force applied to the prestressing tendons 2 nearest to the lower end of the iron beam 4 is 30% or less of yield load of the prestressing tendons 2, tension-introduction force applied to the prestressing tendons 2 nearest to the slab side is 60% of yield load of the prestressing tendons 2, and tension-introduction force applied to the middle prestressing tendons 2 is from 40% to 50% of yield load of the prestressing tendons 2.
(49) The above described embodiments are not intended to limit components or object of the present invention. Various changes can be performed without deviation from the object of the present invention.
(50) A method for jointing a concrete column and a iron beam according to the present invention is used in a building structure having a column and a beam. A column-beam junction A is integrally formed to the column in advance. An anchor plate 12 and an anchorage 10 is provided at an end of the beam, an end plate 18 is provided at an end of the beam and an anchor plate 12 and an anchorage 10 are provided apart from the end of the beam with a predetermined distance, or an end plate 18, a solidified filler material 19 with a predetermined thickness, and an anchorage 10 are provided at an end of the beam. A structure joint portion 15 is provided between the column-beam junction A and the end of the iron beam 4, which is mounted on a cogging 5 provided to the column. Prestressing tendons 2 are arranged in a plurality of rows to horizontally penetrate the column-beam junction A. Tension-introduction forces are applied into the prestressing tendons 2 to tensionally anchor the anchorage 10, and thereby to integrally joint the column and the beam. A concrete slab 7 with a predetermined thickness is provided on the upper end of the iron beam 4. In the method for jointing the column and the beam, a joint-separation control condition is set and fulfilled, so as to inhibit joint separation at the structure joint portion 15 in a case of a moderate earthquake, which is a rare earthquake, or weaker, and to allow the joint separation in order to prevent yielding the iron beam 4 in a case of a large earthquake, which is a very rare earthquake. At the structure joint portion of the end of the beam, joint separation does not happen in the case of a moderate earthquake, which is a rare earthquake, or weaker. The column and the beam remain in a rigid joint condition. Both of the column and the beam are within an elastic range, and exert aseismatic performance. In the case of a large earthquake, which is a very rare earthquake, the joint is separated in an elastic state. The beam member is rotationally deformed to reduce stress shared by the iron beam. This enables the prevention of yielding of the beam to keep it in a damage-free state. After the earthquake, an elastic restoration force of the prestressing tendon causes the separated joint to fold. The whole structure including the column, the beam and the like is restored to the original position. No residual deformation remains. The disclosed invention can be widely applied or utilized to these types of buildings.
REFERENCE SIGNS LIST
(51) 1: PC column; 2: prestressing tendon; 2a, 2b: prestressing steel rod; 3a, 3b: sheath; 4: iron beam; 5: cogging; 7: concrete slab; 8: stud bolt; 9: reinforcement fitting; 10: anchorage; 11: coupler; 12: anchor plate; 13: reinforcing member; 14: buffer material; 15: structure joint portion; 16: slipping material; 17: top reinforcing bar; 18: end plate; 19: filler material; 20: side board; 21: reinforcing bar; and, A: column-beam junction.