Super Drainage System and Method for Flood Control
20190161954 ยท 2019-05-30
Inventors
Cpc classification
E02B3/02
FIXED CONSTRUCTIONS
E02B11/00
FIXED CONSTRUCTIONS
E03F1/002
FIXED CONSTRUCTIONS
E02B3/04
FIXED CONSTRUCTIONS
International classification
Abstract
A super drainage system and a method for flood control comprise an open channel, a reinforced concrete conduit (RCC) inside the open channel. The RCC has a bottom slab supported on a riverbed, a bank-side wall for retaining bank soils, and a top slab elevated above a predetermined level. The RCC supports a road below the top of river banks for traffic traveling along the river banks during normal weather conditions. The traffic is either on the top slab or on the bottom slab. During extreme weather conditions, traffic is evacuated from the super drainage system and the entire space is available for water conveyance.
Claims
1. A drainage system configured for controlling flood during extreme weathers and offering a road for traffic during normal weathers, said system comprising: a) an open channel having a first bank, a second bank and a riverbed; b) a reinforced concrete conduit (RCC), said RCC has a bottom slab supported on said riverbed, a first wall for retaining said first bank, a top slab elevated above a predetermined level and a second wall, and said RCC further comprising a number of RCC segments, each of said RCC segments having a male end and a female end; wherein said RCC supports said road below the top of said first bank, and said traffic travels on said road along said first bank during normal weathers.
2. The drainage system of claim 1, wherein said traffic is evacuated when water in said open channel reaches said predetermined level, and the entire space of said open channel and said RCC is available for water conveyance.
3. The drainage system of claim 1, wherein said RCC further comprising a wall extension that extends from one of said first wall and second wall.
4. The drainage system of claim 1, wherein said RCC further comprising a slab extension that extends from one of said top slab and bottom slab.
5. The drainage system of claim 1, wherein said road is on said top slab, said top slab is 2-8 meters below the top of said first bank.
6. The drainage system of claim 1, wherein said road is on said bottom slab inside said RCC, said bottom slab is 2-8 meters below the top of said first bank.
7. The drainage system of claim 1 further comprising rails, said rails are anchored to one of said top slab and bottom slab and form a railroad track.
8. The drainage system of claim 7 further comprising sleepers, said sleepers are embedded in said top slab.
9. The drainage system of claim 1, wherein said RCC further comprising a communication element for water communication between said open channel and said RCC, said communication element is selected from the group consisting of an opening in the walls or slabs of said RCC, a two-way gate in said second wall, and an one-way gate in said second wall.
10. The drainage system of claim 1 further comprising a buried sewage pipe, said sewage pipe is fluidly connected to said RCC.
11. The drainage system of claim 1, wherein said first bank further comprising a bench at a middle elevation between the top of said first bank and said riverbed.
12. The drainage system of claim 1, wherein said first bank further comprising an earth slope above said top slab.
13. The drainage system of claim 1, wherein said first bank further comprising a retaining wall for retaining said first bank above said top slab.
14. The drainage system of claim 1, wherein said second wall retains said second bank.
15. (canceled)
16. A method for alleviating traffic congestion in a metropolitan area comprising serving traffic on a road inside a drainage system during normal weathers, said drainage system comprising: an open channel having a first bank, a second bank and a riverbed, a reinforced concrete conduit (RCC) inside said open channel, said RCC further comprising a number of RCC segments, each having a male end and a female end; wherein said road is 2-8 m below the top of said first bank and supported by said RCC along said first bank, and said RCC has a bottom slab supported on said riverbed, a first wall retaining said first bank, a top slab elevated above a predetermined level and a second wall.
17. The method of claim 16 further comprising evacuating said traffic from said drainage system for flood control during extreme weathers.
18. The method of claim 16, wherein said road further comprising rails, said rails are anchored to one of said top slab and said bottom slab and form a railroad track.
19. (canceled)
20. A method for establishing a drainage system configured for controlling flood during extreme weathers and offering a road for traffic during normal weathers, said method comprising: a) inserting a male end of a reinforced concrete conduit (RCC) segment into a female end of an adjacent RCC segment repeatedly and forming a RCC with a number of RCC segments inside an open channel, said RCC has a bottom slab supported on a riverbed of said open channel, a first wall retaining a first bank of said open channel, a top slab elevated above a predetermined level and a second wall; wherein said RCC supports said road below the top of said first bank, said traffic travels on said road along said first bank during normal weathers.
21. The method of claim 20, wherein said RCC segments are pre-casted.
22. The method of claim 20 further comprising anchoring rails to said top slab for forming a railroad track.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0021] The super drainage system, method and advantages of the present invention will be better understood by referring to the drawings, in which:
[0022]
[0023]
[0024]
[0025]
[0026]
[0027]
[0028]
[0029]
[0030]
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENT
[0031] Various terms are defined below. As used herein and in the claims, the term super drainage system means a drainage system that can handle massive amount of water without overflowing its banks during extreme weather conditions as well as offer a road and serve traffic during low water levels in normal weather conditions. The term reinforced concrete conduit is abbreviated to RCC. It means a box-shaped conduit having two walls and two slabs. It has a quadrilateral cross-section including trapezoid, rectangle or square. RCCs are made of concrete that is reinforced by steel wires or fibers. A RCC can be formed with a number of RCC segments. Each RCC segment has a preferred length of 1-5 m. The term reinforced concrete conduit and extension is abbreviated to RCCE. It means a reinforced concrete conduit with either wall extensions, slab extensions or both. An extension can be in alignment with a wall or slab, or at a certain angle from a wall or slab. The term traffic means the movement of vehicles or persons along a road that is not submerged in water. The traffic includes trains, automobiles, buses, bikers, pedestrians, etc. The trains include passenger trains (e.g., light rails, high-speed trains, and commuter trains) and freight trains that run on rails.
[0032] As used herein and in the claims, the term a predetermined level means a water level that is predetermined by a designer, operator or owner. When water in the drainage system reaches this predetermined level, evacuate all traffic from the system. This level is in general around the middle elevation of banks or lower, leaving sufficient space above for traffic during normal weather conditions. The term normal weathers means normal precipitations. During these events, the water remains below the predetermined level. It normally accounts for the majority time of a year (e.g., 350 days). The term extreme weathers means a heavy rain that lasts for more than several hours, or rains last for days, or excessive water from melting snow due to unexpected warm temperatures. They cause water in the drainage system to rise above the predetermined level. It is an event with low probability of occurrence (e.g., a few times per year or less). The term entire space means all cavities confined by two banks, including any enclosed channel and open channel in the super drainage system as well as the space below the top of an extended bank across a flood plain when exists. The term sleepers means crossties, beams with a rectangular cross-section being laid underneath rails. They tie two rails in place and form a railroad track. They transfer loads from rails to the two walls of RCC.
[0033]
[0034]
[0035] As a variation, a second bank (on the right) is retained by a second RCC 24 at low elevations and blocks 25 at high elevations. Side openings 26 in a water side wall are at a lower elevation for equalizing the water level 14 in the open channel 13 and in enclosed channel 29. Top openings 27 in the top slab allow air to enter or exit the enclosed channel 29 freely when the water level 14 varies. Fences 28 prevent people from falling into the water. At the riverbed 12, erosion control measures such as rip-rap or concrete matrix can be implemented. During extreme weather conditions, the storm water will flow through both the enclosed channels and open channel 13. In comparison with a natural channel in
[0036] Alternatively, the second bank can be the same as the first bank 19. Alternatively, an open channel can have a first bank 19 and an earth bank 11 shown in
[0037]
[0038] In this embodiment, both the upward and downward wall extensions retain banks along with the first walls. This creates more space for water conveyance. Along the first bank, traffic travels on the top slab of the first RCCE 31. Along the second bank, traffic travels on the bottom slab 20 of the second RCCE 33 inside the enclosed channel. In either case, RCCEs support a road for traffic and the road is preferably 2-8 meters below the top of the banks. This figure shows a monolithic RCCE that is preferably pre-casted. Alternatively, the downward wall extension 34 is casted separated from reinforced concrete conduit (RCC). The downward wall extension 34 is installed first and RCC is then laid on top of the wall extension along with an interlock mechanism (e.g., pins and holes, not shown) between these two.
[0039]
[0040] The enclosed channel 29 is sealed along its perimeter in this case. With both ends open, the RCC conveys water from its starting point upstream to its end point downstream (not shown), similar to a typical buried RCC in prior art. It can be used for conveying fast-moving water under pressure with means such as pumps. In another word, conveyance capacity can also be increased by speeding up flow inside an enclosed channel (i.e., RCC) if deepening or widening an open channel is restricted. Alternatively, four rails (i.e., two tracks) can be installed on the top slab of RCCE 41. Any previously installed rails can be used to transport materials during construction. Alternatively, the two rail tracks are installed inside the enclosed channel 29, separated by the partition wall 42. Alternatively, the partition wall 42 is replaced by columns at an interval of 1-3 meters.
[0041] As a variation, the second bank is retained by a bottom RCCE 47 and a top RCC 48. Pins can be used for locking the water-side wall of the top RCC 48 and the bank-side wall of the bottom RCCE 47 together. A sewage pipe 35 is fluidly connected with the bottom RCCE 47. The top RCC 48 can support surface traffic on its top slab and a subway on its bottom slab. Two-way gates 49 are installed in the water-side wall of the bottom RCCE 47 for flow control.
[0042]
[0043] During normal weathers, people (not shown) walk on a road 55 supported by the RCCE 51 and commuter trains 59 run near the retaining wall 56. Optionally, the flood plain 53 can also be used for leisure activities. When an extreme weather condition is predicted and the water rises to a predetermined level, evacuate trains 59 and people from the super drainage system, and make the entire space available for water conveyance. In this case, the flood plain 53 is similar to a wide bench 17 in
[0044] As shown in
[0045] As shown in
[0046] Sleepers 67 are embedded in the top slab of the RCC 61. Four rails 68 are anchored to the sleepers 67. Alternatively, two rails (i.e., one track) are installed on the top slab of the RCC 61, which results in a minimum width of an open channel (e.g., 5 meters). Two rails are anchored to the bottom slab of the RCC 61 as a slab track. Alternatively, motorists, bikers or people use the top slab of the RCC 61 as a road. In this figure, water reaches a maximum water level 69 during extreme weather conditions.
[0047] As shown in
[0048]
[0049]
[0050] Buried reinforced concrete box culverts are widely for drainage. Commonly used seals at joints include elastomer tubes/stripes, rubber gasket rings, etc. They are readily available from the market and not shown here for simplicity. It is preferred that the RCCs or RCCEs are pre-casted in segments, each having a length of 2-3 meters with a male end and a female end. A RCC is formed by inserting the male end of a RCC segment into the female end of an adjacent RCC segment and extends along a bank of an open channel continuously.
[0051]
[0052] Alternatively, metal pins can be used for locking a top slab onto both walls of the U through pre-made holes. Alternatively, dowels can be pre-embedded in a top slab and inserted into pre-made holes on the top of U. It is preferably that the top slab 71 and sleepers 72 are pre-casted as one piece. Alternatively, sleepers are pre-casted separately and anchored to a top slab during construction. These sleepers transfer traffic loads onto a first wall 62 and a second wall 63 as denoted in
[0053] A method for establishing a drainage system that is configured for controlling flood during extreme precipitations and offering a road for traffic during normal weather conditions includes inserting a male end of a RCC segment into a female end of an adjacent RCC segment repeatedly and forming a reinforced concrete conduit (RCC) in an open channel. The RCC has a bottom slab supported on a riverbed, a bank-side wall retaining bank soils, and a top slab elevated above a predetermined level. The RCC supports the road that serves traffic traveling along a bank during normal weather conditions.
[0054] A method for alleviating traffic congestion in a metropolitan area comprises serving traffic on a road inside the drainage system during normal weather conditions. The road is 2-8 meters below the bank top on the top slab or bottom slab of the RCC. Passenger trains are preferred as they are environmentally friendly. During extreme weather conditions, traffic is evacuated from the system. Both the enclosed channel inside the RCC and the open channel are available for conveyance of massive water.