BOILER FLUSHING

20220389843 ยท 2022-12-08

Assignee

Inventors

Cpc classification

International classification

Abstract

A method for flushing a heat recovery steam generator in a power plant having a gas turbine, having a compressor, a combustion chamber and a turbine with a rotor, and having a generator coupled to the gas turbine and a start-up converter to convert from an alternating current of random frequency into an alternating current of a specified frequency. The start-up converter is connected to an output of the generator at which the alternating current of random frequency is applied. Wherein, when the gas turbine is run down, the rotor is cushioned with the help of the start-up converter at a boiler flushing speed and the heat recovery steam generator is further flushed until the specifications for flushing the waste heat steam generator are complied with.

Claims

1. A method for flushing a heat recovery steam generator of a power plant with a gas turbine, comprising a compressor, a combustion chamber and a turbine with a rotor, and with a generator coupled to the gas turbine and a start-up converter for converting from an alternating current of any frequency into an alternating current of a specified frequency, wherein the start-up converter is connected to an output of the generator at which the alternating current of any frequency is applied, the method comprising: when the gas turbine is run down, supporting the rotor with the aid of the start-up converter at a boiler flushing speed and flushing the heat recovery steam generator further until specifications for flushing the heat recovery steam generator are satisfied.

2. The method as claimed in claim 1, wherein, after reaching a boiler flushing speed of the gas turbine, a gas turbine speed is repeatedly raised and lowered.

3. The method as claimed in claim 2, wherein the gas turbine speed is repeatedly raised and lowered at least until a minimum duration for a flushing process has been reached.

4. The method as claimed in claim 3, wherein the minimum duration is 5 minutes.

5. The method as claimed in claim 1, wherein the boiler flushing speed is 8% of the nominal speed.

Description

BRIEF DESCRIPTION OF THE DRAWINGS

[0018] The invention is explained in more detail by way of example on the basis of the figures, in which schematically and not to scale:

[0019] FIG. 1 shows a gas turbine connected to an electrical supply grid and

[0020] FIG. 2 shows the gas turbine speed during the running-down process according to the invention.

DETAILED DESCRIPTION OF INVENTION

[0021] FIG. 1 shows a gas turbine 1 with a compressor 2, a combustion chamber 3 and a turbine 4 with a rotor 12. In the exemplary embodiment of FIG. 1, the compressor 2 and the turbine 4 are arranged on a common shaft 5. Also arranged on the shaft 5 is a generator 6, which is connected by way of a start-up converter 7 to an energy supply grid 8.

[0022] FIG. 2 shows schematically and by way of example the gas turbine speed over time when running down a gas turbine 1 by the method according to the invention.

[0023] After switching off the combustion, the rotational speed of the gas turbine 1 is reduced, the rate of change of the speed likewise decreasing with time. Without any further outside intervention, a lower speed limit 9 relevant for flushing processes, which in FIG. 2 is depicted at 8% of the nominal speed, is passed in the downward direction at approximately 300 s and continues to fall (curve with reference numeral 10).

[0024] A further criterion for sufficient flushing is its duration at a speed above the lower speed limit 9. This duration is 5 minutes. Since, however, the beginning of flushing should not be seen as at exactly t=0 s, but a few seconds later (the figure shows a more conservative assumption), because a gas lock in the fuel supply must first be closed, the conditions (intensity and duration) for successful flushing are not satisfied at the time t=300 s.

[0025] This is where the invention comes in and supports the gas turbine 1 with the aid of the start-up converter 7 and keeps the speed above the lower speed limit 9 relevant for the flushing process. FIG. 2 shows in this respect a curve 11 for an ideal flushing process with a start-up converter 7.

[0026] The speed of the gas turbine 1 is in this case kept above the lower speed limit 9 until a minimum duration for the flushing has been reached. In FIG. 2, this minimum duration is defined by the times t1 and t2. The area under the curve 11 and between t1 and t2 represents the flushing volume.

[0027] FIG. 2 also shows that the speed of the gas turbine 1 is modulated (by the start-up converter 7). This takes place in order to avoid natural frequencies building up and damaging the installation.