PROCESS FOR FORMING AND ASSEMBLING PIPE SECTIONS USING MECHANICAL PRESS FIT PIPE JOINTS IN A PIPELINE
20190033796 ยท 2019-01-31
Inventors
Cpc classification
F16L2201/30
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F16L58/04
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
G05B2219/31033
PHYSICS
G05B2219/35178
PHYSICS
B23P19/027
PERFORMING OPERATIONS; TRANSPORTING
F16L58/02
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F16L2201/10
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
G05B19/19
PHYSICS
F16L2201/60
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
International classification
G05B11/36
PHYSICS
G05B19/19
PHYSICS
B23P19/027
PERFORMING OPERATIONS; TRANSPORTING
G01M3/28
PHYSICS
F16L58/04
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F16L58/02
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
Abstract
Processes and systems for preparing pipe for machine processing to form pin and box ends for assembly into pipelines or to assemble pipe sections in pipelines using mechanical press-fit pipe joints in which hydraulic pressure and linear displacement parameters, respectively P and L, are fully measured and documented during both manufacturing and assembly. Installed pipelines include pipeline data monitoring systems coupled to a pipeline data management center for receiving, archiving, and analysis of the data records to aid in administration, operation and management, and troubleshooting of pipelines.
Claims
1. In a process for forming pipe section ends, or for field assembly of pipe sections in an oil and gas pipeline to be joined by mechanical press-fit joints, the process to be carried out on a swaging bench having a fixed stock at a first end configured with a clamp to secure therein a first end of a pipe section having respectively an unformed or formed end, and a movable stock slidingly supported on a second end of the bench, the movable stock coupled to a source of hydraulic pressure for sliding toward the fixed stock and configured with a clamp to secure a tooling die for forming an end of a pipe section or for securing a first formed end of a first pipe section for assembly to a corresponding second formed end of a second pipe section during field assembly of the pipeline, the improvement comprising the steps of: initializing first and second sensors including a first sensor coupled to the source of hydraulic pressure for measuring a hydraulic pressure P and a second sensor coupled between a fixed reference on the bench and the movable stock for measuring a displacement length L; configuring on a display screen operated by a processor a graph for plotting P=hydraulic pressure versus L=displacement length during real time while pipe section pin and box ends are being respectively formed or assembled; installing the tooling die in the movable stock of the swaging bench for forming the first or second end of the pipe section or for field assembly of the second end of a second pipe section to the first end of a first pipe section in the oil and gas pipeline; operating the swaging bench to form a pin end or a box end of a pipe section or to assemble a pin end of a first pipe section and a box end of a second pipe section; and measuring and displaying on the display screen the parameters P and L as the respective pin end and box end are formed or assembled to ensure the parameters P and L associated with forming or assembling the respective ends are each met within a predetermined tolerance.
2. The process of claim 1, wherein the step of initializing comprises the steps of: setting to a reference value P.sub.0 read by a pressure gauge connected to a hydraulic feed line coupled between the source of hydraulic pressure and the movable stock on the swaging bench; and setting to a zero reference L.sub.0 a displacement measuring device selected from the group consisting of a string potentiometer, a measuring tape, and a laser rangefinder.
3. The process of claim 1, wherein the step of configuring comprises the step of: displaying a graphical format containing at least a vertical axis marked in pressure units, a horizontal axis marked in displacement units, and corresponding limits for the values of P and L.
4. The process of claim 1, wherein the step of installing further comprises the step of: verifying that the swaging bench is reset to an initial condition.
5. The process of claim 1, wherein the step of operating the swaging bench comprises the steps of: increasing the hydraulic pressure P to cause the movable stock to advance toward the fixed stock; observing the changes in the values of hydraulic pressure P and displacement length L on the display; and disengaging the hydraulic pressure to halt the motion of the movable stock when the values of P and L are both within the predetermined tolerance or when either value of P or L passes outside the predetermined tolerance.
6. The process of claim 5, wherein the step of disengaging comprises the step of: activating an alarm and initiating an automatic disengagement of the hydraulic pressure when either value of P or L passes outside the predetermined tolerance.
7. The process of claim 1, after the step of measuring, further comprising the step of: verifying all parameters P and L are within specification as displayed on the display screen.
8. The process of claim 7, wherein the step of verifying comprises the step of: issuing a steady tone alarm if all parameters P and L are within specification and verifying that the process operation is complete.
9. The process of claim 7, wherein the step of verifying comprises the step of: issuing a warble tone alarm if any of parameters P and L are out of specification; and identifying the anomaly of the parameter P or L that is out of specification.
10. The process of claim 7, wherein the step of measuring further comprises the steps of: disengaging and retracting the hydraulic ram; and logging the data for the P and L parameters, an identification number of the pipe section or sections formed or assembled on the swaging bench.
11. The process of claim 10, when carried out for assembling an oil and gas pipeline, further comprising the step of: logging data containing GPS (global positioning satellite) information of the location of the assembled mechanical press fit pipe joint in the oil and gas pipeline.
12. The process of claim 10, after the step of logging data, comprising the step of: releasing the pipe section formed or assembled from the swaging bench.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0016]
[0017]
[0018]
[0019]
[0020]
[0021]
[0022]
[0023]
[0024]
[0025]
[0026]
[0027]
[0028]
[0029]
[0030]
[0031]
[0032]
DETAILED DESCRIPTION OF THE INVENTION
Introduction
[0033] In an advance in the state of the art a system and associated apparatus and methods are disclosed for forming mechanical press-fit pipe joints having more uniform and consistent performance, thereby overcoming the deficiencies mentioned herein above. Data gathered, stored, and analyzed may be utilized to control both the process for forming the pipe ends prior to assembling them and the mechanical press-fit joint assembly process itself. The processes both produces superior mechanical press-fit joints and provides logging data for setting standards and enabling pipeline integrity monitoring to track pipeline conditions and performance, detect malfunctions and failures, etc. Basic data such as the pressure employed to form the pipe ends and assemble the mechanical press-fit joint, and the length of the overlap of the box (or bell) end into the pin (or cone) end being formed or joined may be accumulated and used for pipeline logging, on-going analysis, and the development of standards for mechanical press-fit pipe joints and pipeline integrity in general. Herein after the mechanical press-fit pipe joint may be called a MPF joint, referring to pipe sections joined by the apparatus and processes described herein. A MPF joint is depicted in
[0034] The accumulated data may be developed into a standard index of the fitness of an assembled mechanical press-fit joint for use in monitoring assembly, formulating industry standards, etc. Superior joints may be ensured when measurements made during preparation of the ends of the pipe sections and assembling the MPF pipe joints fall within a unique index range derived from measured assembly data and subsequent test data performed on the assembled joints. Standards for pipe of different size, weight, wall thickness, material, and grade may be developed from the accumulated assembly and test data. Monitoring of pipelines, either as routine periodic inspections or to locate pipeline integrity deviations, may be facilitated by access to stored data and the ability of a pipeline authority to utilize the tagging and logging systems disclosed herein to obtain accurate data regarding pipeline integrity. As is well understood, monitoring and inspection regimens are critical to being able to quickly locate and diagnose problems in pipelines, to discover small problems before they become large problems.
[0035] The system to be described may include a multiple input data acquisition device coupled with a programmed processor and graphical user interface, wherein the graphical user interface may be controlled by specialized software to enable the user to view the parameters of interest in real time while a press-fit pipe joint is being assembled. These functional units may be embedded in a computer or provided as separate structures, collectively called a computer. A database may be coupled to the computer or the system for accumulating data. Sensors connected to the data acquisition inputs may include components that, for example, sense the pressure P exerted to force the pipe sections together, the length L of the stroke or overlap of the pipe ends being joined, and other sensors for indicating dimensions or temperature conditions. The computer may be connected through the sensors to the hydraulic swaging (aka swedging) machines that perform the forming and assembly operations on the pipe ends. For example, the pressure measurement may be the hydraulic line pressure in lb./in.sup.2 (psi) applied by the machine for assembling the formed ends to complete an MPF joint. The length measurement may be the distance in inches that the box end of a first pipe section overlaps the pin end of the second pipe section being connected to the first section. The system may also be used during the process of forming the pipe box and pin ends on dies held by a mandrel in a suitable hydraulic swaging machine to be described. The pressure applied directly to the mandrel/die assembly by the machine, and the traverse of the die along the pipe end may also be measured and recorded by the apparatus and process to be described herein.
[0036] In measuring the overlap or stroke length L of the box end, one type of sensor is called a string encoder (or string pot, draw wire, or yo-yo pot). Other types of length sensors may include optical or acoustical mechanisms. Regardless of the method used to measure and indicate the overlap length, a datum or starting point may be established, for example by positioning the box end close to the pin end (within a prescribed tolerance, such as +0 inch) and setting the overlap length measurement to zero. Various techniques for establishing such reference are well known in the art. In measuring the pressure exerted by the hydraulic machine to form the pipe ends or to assemble the pipe ends together, the pressure P is likewise set to a low set starting point such as 10 psi, which is a reference or initial condition value.
[0037] Other facilities provided in the system for the computer may include USB ports for connecting keyboards, interfaces to GPS equipment, etc.; outputs for video or other baseband signals such as HDMI outputs; data links to databases to store the data with historical records; connections for links via Ethernet or other network interface standard, and the usual connections for power, indicators, etc. The computer may be interfaced through suitable communication links with production or assembly apparatus, and may include control mechanisms for operating the production or assembly apparatus. Such mechanisms may include software, links to machine elements such as servomechanisms, switches, indicators and gauges, etc. Typical machine elements for forming the ends of the pipe include a hydraulic swaging machine. The forming die is supported in a mandrel that is held by a stationary or moving portion of the machine. An assembly machine is very similar to a swaging machine except that it forces two opposing pipe ends together under hydraulic pressure in the same manner as a swaging machine to join them together instead of forcing the end of one pipe section over a die to shape it.
[0038] Also to be disclosed herein is a new index developed to provide a readily observable and repeatable indication of the correct amount of overlap of the pin end by the box end to establish an acceptable MPF pipe joint. The purpose of such an index is to identify the instant that a correctly formed MPF joint is formed. One example is to multiply the hydraulic pressure P (lb/in.sup.2) used to press the two pipe ends together by the length of overlap L (in) of the box end over the pin end. This product has the units lb/in, which are the units of linear deflection, and may or may not be correlated with the amount of force needed to force a box or bell end of pipe onto a pin or cone end of pipe. The combination of the values of P and L that indicate a correctly formed mechanical press-fit pipe joint is also clearly evident in a graphical plot of P vs. Las shown in
[0039] The parameters P, representing the hydraulic pressure need to form the end of a piece of pipe or to assemble two formed pipe ends together, and L, representing the length, of overlap of one section over the other or the distance traveled in forming a box end to a pipe section, are based on similar parameters of importance when assembling pipe sections by other methods, such as welding or screw threads. In both traditional methods of joining pipe sections, the length of overlap L is a key parameter that is expressed by the dimensions of the box end that will overlap the pin end of the opposing section. For welded joints the length of overlap L will depend on the type of welding, the required structure of the finished joint, and other factors such as the size and material of the pipe. For threaded joints, characteristics such as the type and pitch of the threads, whether sealants are used when assembling the joint, etc., along with the other characteristics of the pipe, will govern the choice of the parameter L.
[0040] To understand why the parameters are useful in measuring the formation of mechanical press-fit pipe joints an example of a traditional method of joining pipe ends together may be helpful. Steel pipe as used in pipelines is a heavy component, so turning a section of threaded pipe onto an opposing section of pipe having mating threads may require use of a hydraulic machine to provide the necessary motive power. As the first section advances onto (or into) the second section, a certain amount of friction within the threaded area must be overcome by the hydraulic pressure to operate the machine that turns the first section against the friction developed in contact with the second section. As the joint nears completion, the end threads of one of the sections are reached, causing the hydraulic pressure to increase more rapidly. This condition indicates a joint that is close to being fully formed. In fact, the particular pressure can be a useful measure of a sufficiently threaded joint. Before that pressure is reached, the joint is likely incomplete; beyond the point where the pressure P begins to increase more rapidly is a reference pressure that if exceeded may result in stripped threads, a split pipe or other defects. The pressure indicating a proper threaded joint would be expected to lie between these two values, and will likely be closely related to the length of overlap, L. Similarly, for welded joints, the dimensions of the pipe, in particular the portions of the box and pin ends that are in contactsuch as the total surface area in contact of the joint will be related to the pressure P needed to assemble the pipe ends together and the length of overlap L.
[0041] One way to visualize the effect of these two variables P and L is to plot one variable vs. the other on rectangular coordinates. This will yield a curve having a positive slope as the pressure increases with increasing overlap. If the acceptable values of P and L are given a tolerance, say +/5%, for example, then an acceptance rectangle defined by the minimum and maximum permitted values of both parameters can be superimposed on the graph and its area can be calculated or delineated on the graph. The tolerance in this example is chosen to illustrate the concept. The correct tolerance may be developed from empirical data obtained during actual use. Operation of the apparatus that joins the pipe ends together until the PL curve enters the acceptance rectangle provides a readily observable indicator of a correctly assembled joint. Further, the measured values input to the computer by the sensors appear on the graphic display and also may be stored for later use. The index may be called the force-fit number, the PL product, or the press fit product for example. If the PL product is within this acceptance window on the graphical display, it is because the product of the pressure P and the length L correlates with substantial and uniform metal-to-metal contact between the box and pin ends of the pipe. This is just one example of an index and its use in facilitating the assembly of press fit mechanical joints in pipe.
[0042] The index described above may be related to other variables such as the temperature at the construction site. The accumulation of data for many installation sites, type and size of pipe, along with the values of P, L, and temperature T may suggest process variations that ensure the most reliable press fit pipe joint. The accumulated data may be recorded in tables to assist in set up of the press fit apparatus for assembling the pipe, either for constructing new pipelines or repairing old ones to return them to service. Such data can be important because temperature affects not only the malleability of the pipe material, its dimensional variations due to expansion and contraction, but also the viscosity of the hydraulic fluid used in the press fit apparatus. If sealing compounds or epoxy or other adhesive materials are use in the joint, their properties will also likely be affected by temperature variations. In general, assembly tables for MPF joints may be constructed for any variable representing a parameter involved in the press fit assembly process.
[0043] The data thus accumulated may be accessible to qualified users or subscribers, to pipeline authorities, pipe manufacturers, pipeline contractors, and the like. The data may be viewed as historical data or observed in real time. Data may be correlated with a particular manufacturer or mill that produced the pipe being installed. Access to the data may readily be provided via the Internet or other networks.
Description of the Press-Fit Apparatus
[0044] The press fit apparatus to be utilized in the system and process described herein includes two hydraulic press devices. They are similar in appearance, but are configured differently to fulfill their specific functions. Each may be thought of as a bench or frame equipped with rails along which hydraulically operated clamps or stocks are mounted. In an end preparation machine, a sliding stock may be mounted on the rails at the end of the bench connected to a source of hydraulic pressure. The sliding stock supports toolinga die held by a mandrelfor forming either of the pipe box or pin ends. On the opposite end of the rails a clamp assembly for securely hold the pipe section to be formed may be fixed to the rails along the same longitudinal axis as the die. The movable die may be forced or driven toward the stationary pipe end under hydraulic pressure supplied to the movable stock by a hydraulic pump. The hydraulic pump may be driven by an internal combustion engine, typically a diesel engine. The end preparation machine may typically be used at a site convenient for forming the box and pin ends of the pipe sections. The site may or may not be located at the site where the pipe line is being constructed.
[0045] The clamp section may have hydraulically operated hemispherical jaws joined on one side at a pivot along a radius spaced just beyond the hemispherical portions so that the jaws may be placed around the pipe to be gripped and drawn together by hydraulic pressure to clamp the pipe in position. The open ends of the jaws may be coupled together along a hydraulic cylinder to enable the jaws to be opened and closed. The hemispherical jaws may be fitted with dies to fit the particular diameter of pipe to be joined.
[0046] In a field assembly machine, which is very similar to a hydraulically operated swaging machine apparatus, the rails on the bench or frame support two opposing clamp sections that may be used to support the pipe ends to be joined. One of the clamps may be secured to the rails, while the other one may be configured to slide along the rails under the application of hydraulic pressure to cylinders secured to the sliding clamp. As in the end preparation machine, the rails ensure T least one of the clamp sections can move toward and away from the other clamp section while maintaining a fixed longitudinal relationship with each other, thus ensuring that the pipe ends to be joined are correctly aligned. The same type of pivoting jaw clamp sections may be used to secure the pipe ends for joining. In use at a pipeline site, the assembly machine may be supported by a side crane mounted on a transport vehicle. A hydraulic pump for operating the filed assembly machine may be driven by an internal combustion engine such as a diesel engine. The vehicle can thus travel along the side of the site to position the assembly machine at the location of each pair of pipe ends to be joined.
[0047] Both the end preparation and field assembly machines may preferably be coupled to a computer monitoring system (CMS or, computer) for measuring certain selected parameters involved in the MPF joint operations, including either the preparation of the pipe ends for joining or the assembly of the prepared ends in the field. The CMS, part of a process monitoring subsystem 24 (See
[0048] The system for operating the end preparation and field assembly machines also includes a data acquisition unit coupled to inputs of the CMS for receiving the parameter sensor outputs and converting those signals to digital form for processing by the computer monitoring system. The sensors may preferably be transducers for measuring the hydraulic line pressure P supplied to the hydraulic cylinders that operate the end preparation and field assembly machines, and a linear displacement transducer for measuring the length of the stroke L necessary to provide the correct amount of overlap of the box end of one section of pipe over the pin end of the adjoined section of pipe. Examples of a linear gauge transducer include a string potentiometer (or string pot or yo-yo pot), and a laser displacement meter, which are well known in the art. The operating programs that controls the CMS may be stored in non-volatile memory in the computer monitoring system.
[0049] A graphical display screen coupled to the computer is preferably used to display graphs of the parameters or data products produced by the CMS. Of principle interest is a plot of the hydraulic pressure P used to advance the movable clamp holding a pipe end toward its opposite numbereither the forming die or tooling of the end preparation machine or the clamp holding the end of the other section of pipe to be joinedand the length L of the overlap stroke produced during the formation of a mechanical press-fit joint. The pressure P is plotted versus the length L, P along the vertical axis and L along the horizontal axis. The resulting curve typically has a positive slope as the pressure increases with the increase in length of overlap. The slope and shape of the curve may contain information about the condition of the formed joint or operating conditions of the machine being monitored. This information is highly useful in gauging the quality of the joint and its longevity prospects, and is also useful in diagnosing anomalies in the pipe or the joining process. Further, as the data is stored for later analysis and the creation of a historical record, much can be learned about the pipe materials, the processes used in its manufacture and assembly, and about the integrity of the pipeline and pipeline joints in future years. The historical data in particular will be instrumental in developing better methods of joining pipe sections together in the field.
Detailed Description of the System
[0050] In the following description, reference numbers appearing in more than figure refer to the same structures.
[0051] The system 10 includes a series of major functional subsystems, beginning with facilities 12 for the receiving standard sections of raw pipe 60 (typically each 40 feet long) for undergoing the processes of preparing the ends of the sections of pipe 60 to be assembled into a pipeline using mechanical press-fit joints. The mechanical press-fit pipe joints referred to herein are forced together under pressure and require no welding or machining of screw threads of the ends of the pipe to join the sections together end-to-end at the pipeline installation site. The next subsystem comprises facilities 14 for forming the ends of the pipe to be joined together as mechanical press-fit joints. The facilities 14 may include machine apparatus powered by hydraulic pumps controlled by an operator (the hydraulic machine control 22), wherein the processes are monitored by a process monitoring computer 24 for receiving sensor data and displaying parameters of some of the preparation steps in graphical form on the display 26. The machine apparatus 14 supports the pipe end being formed in longitudinal alignment with a die as the die is forced over the pipe end under hydraulic pressure.
[0052] After the ends of the sections of pipe are formed into a box (or bell) end at one end and a pin (or cone) end at the opposite end in subsystem 14, the pipe sections are ready for assembly into the pipeline at the construction site, as represented by subsystem 16. The assembly of the pipe sections includes a machine apparatus powered by hydraulic pumps controlled by an operator (the hydraulic machine control 22), wherein the processes are monitored by a process monitoring computer 24 that displays parameters of some of the assembly steps in a graphical form on the display 26. The machine apparatus in subsystem 16, which may be a swaging machine adapted for handling pipe sections, supports the sections of pipe in longitudinal alignment as they are pressed together under hydraulic pressure.
[0053] During the formation of the pipe ends and the assembly of the pipe sections, apparatus that contains sensors and circuitry for monitoring the integrity of the assembled pipeline may be installed on the sections of pipe. The integrity monitoring circuitry applied in subsystem 18 continually measures a variety of conditions of the pipeline following its construction to provide for maintenance and safe, efficient operation of the pipeline. The data generated in subsystem 18 may preferably be forwarded to a pipeline data acquisition station 20.
[0054] Other components of the system include a hydraulic machine control 22 coupled to each of the formation 14 and assembly 16 machine apparatus. In typical embodiments these may be manually-operated controls and appropriate sensors 23 (as will be described) for measuring selected control parameters. A process monitoring computer 24 may be coupled to the machine control subsystem 22, 23 for receiving the sensor data and developing responses thereto. A display 26 connected to the process monitoring computer 24 provides visual, graphical representation of the control parameters. A process program for controlling operations of the process monitoring computer 24 including the graphical display of the hydraulic pressure P and the stroke length L may be stored in the non-volatile program memory. The process monitoring computer 24 may further include a communication interface for coupling to a network 36. The pipeline data acquisition subsystem 20 also preferably includes a communications interface coupled to the network 36. The network 36 enables data communication of the subsystems 20 and 24 with a data management center computer 40 (aka DMC 40) for archiving and processing the data regarding the preparation, assembly, and monitoring of the pipe sections and the completed pipeline. A database 42 and display 44 are provided to facilitate the archiving and processing functions of the subsystem 40.
[0055] The DMC 40 computer may be a system of computers, servers, etc. as needed to perform the functions assigned to it in gathering, analyzing, and otherwise processing the data sent to the DMC 40. These and other functions may be provided by appropriate software developed for the purposes of managing these functions. A suite of applications software 38 may include at least one operating program for processing data measurements regarding pipeline operating parameters and conditions originating from the data acquisition system such as the hydraulic pressure P and the stroke length L data acquired during the end-preparation and field assembly operations. The data management center computer 40 may further be utilized in a data management system responsive to data obtained during monitoring of pipeline data by apparatus coupled to installed pipelines. Data communicated to the data management center computer 40 may be processed by components of the suite of applications software 38 accessible from the data management center computer 40. The suite of applications software 38 includes the necessary storage facilities, which may be directly coupled to the data management center computer 40 or accessible via a network to remote storage facilities, as is well understood in the art. The data obtained by such apparatus (to be described with
[0056]
[0057] The hydraulic machine 22 is typically powered by a hydraulic power unit 30 such as a diesel powered pump (not shown) equipped with a manifold, fluid lines and valves to control the flow of fluid under pressure to actuators on the machines. The hydraulic machines may be operated by an operator using a manual control unit 32 while observing the display 26 that graphically displays the operating parameters while forming or assembling a mechanical pipe joint. One feature incorporated into the system of
[0058]
[0059] Continuing with
[0060] Hydraulic pressure for operation of the end prep machine may be supplied from a diesel powered hydraulic power unit 30 through line 39, under the control of the manual control 32. Line 39 may be multiple lines depending on the structure of the hydraulic cylinder(s) used to power the sliding stock 80. Line 39 connects to the output of a junction block 100 that is supplied hydraulic fluid under high pressure from the hydraulic power unit 30 through a valve 102 controlled by the control 32. The amount of pressuree.g., Ib./in.sup.2 (Psi) is sensed by transducer 104, which is coupled to an input to the data acquisition section of the process monitoring computer 24 via a line 108. This transducer provides the sensor signal corresponding to the hydraulic pressure P to be described herein below. The junction block 100 includes the dump valve 34 that is controlled via a line 106 from the process monitoring computer 24 when it is necessary to interrupt the flow of hydraulic fluid to the hydraulic cylinders that control the advance of the sliding stock, for example when the pressure P exceeds a safe value. The dump valve 34 may also be manually operated by an operator (mechanism not shown for clarity, but is well known in the art).
[0061]
[0062] The remaining structures of
Description of the Mechanical Press-Fit Processes
[0063]
[0064] The pre-prep steps of
[0065] Following the cleaning operations, the application of corrosion inhibitors may be preferred. Corrosion inhibitors of two types may be used; one is solvent based, the other is mineral oil based. Each may be selected to suit a particular set of conditions of the pipe segment and subsequent process steps, environmental conditions, etc. For example, while the solvent-based corrosion inhibitors do not require an extra step to remove them prior to coating or other operations, the oil-based corrosion inhibitors generally require a light spray coating of a cleaning fluid just prior to the end-forming processes in the swedging machine operations as described below using the machines depicted in
[0066] Proceeding with
[0067] Considering further the flow chart of
[0068] Setting the datum for P and L may be accomplished as follows. Once the pipe section 60 is secured within the pipe clamp 90 the free end of the gauge string 114 is extended from the string pot 110 (mounted on the fixed pipe clamp in this example) and attached to the post 116 mounted on the sliding stock 80 that holds the box 600 or pin 610 die in the mandrel 82. The sliding stock 80 is advanced along the rails 84 until the die 600 or 610 is within a predetermined distance of the pipe end. This distance, which may vary from zero to inch, for example, enables the string pot to be set to read zero inches at L=L.sub.0. From this datum point, the length L being known as the objective will be reached when L=L.sub.f as shown in
[0069] It will be recalled that the traditional method of indicating the distance the box end should overlap the pin end was to inscribeusually by handa mark on the pin end using chalk or other readily visible marker. Then, when the box end is forced over the pin end, the force is applied until the end of the box end reaches the mark on the pin end. Clearly this operation depends on skilled eye-hand coordination of the operator of the machine applying the force to the box end, as well as other operating conditions of the equipment, etc. It is inherently an unreliable method of joining pipe ends together, partly because of uncertain repeatability. Further, in the traditional method, no record of the distancethe amount of overlap of the box end over the adjoining pin endwas created, nor was the value of the length standardized or any process used to verify its accuracy or ensure its repeatability for the particular pipe segment undergoing the process. This lack of verification or repeatability information impairs the ability to determine the causes of mechanical pipe joint failures because there is no data to retrace the history of particular pipe joints. Without sufficient data about how pipe joints are prepared and assembled there is no reliable way to make the claim that a pipeline has been properly assembled and will withstand the operational, environmental, and geological conditions that it will experience during the life of the pipeline.
[0070] In the present invention, the distance from the end of the pin end to the mark is defined as the value of L.sub.f described in the foregoing. Thus, in operation, at the datum L=L.sub.0 the hydraulic pressure may preferably set to its initial value, for example, P=P.sub.0=10 psi as an example. The values of P and L having been set to their initial values, the hydraulic pressure may be increased gradually to cause the die 600, 610 installed in the mandrel 82 to advance toward the end of the pipe to be formed. Since the OD of the pin end is intentionally slightly larger than the ID of the box end, an interference contact is established and considerable frictional resistance is encountered. This resistance opposes the increase in hydraulic pressure such that the rise in pressure P is plotted in curve 400 (See
[0071] Returning to
[0072] The marking step 222 may be accomplished by a variety of methods. The preferred method for the illustrated example is to etch, inscribe, or stamp into the metal surface a numeric code or serial number, including certain specific data, as expressed in alpha-numeric form or encoded as a bar code, which may preferably be a two-dimensional bar code. One exemplary type of two-dimensional data matrix bar code, applied by a dot peening process, is available from Mecco Partners, LLC, Cranberry Township, Pa. 16066. Such codes can be read by industrial bar code readers such as are available from Cognex Corporation, Natick, Mass. 01760. The encoded data may include the location of the manufacturing plant, the date and time the pipe end was formed, the type end (box or pin), Mil specification data, etc. This data may be combined with the P and L data obtained during the end preparation forming process in a data record established for each section of pipe. The data record may further be supplemented by assembly data at the pipeline site, where the parameters P and L are again measured and stored in the data record as will be described herein.
[0073] Decision step 224, following step 222 is provided to determine whether the pipe section 60 must be coated or undergo the installation of a monitoring bus conduit or whether it is to be transferred to storage or prepared for transport in step 226. If the pipe section is to be coated, such as for corrosion protection, another decision point is entered at step 240 on
[0074] Before continuing with the process depicted in
[0075] In pipe lines that will not have a monitoring bus installed on the external surface of the pipe, only the internal surface of the pipe will normally be coated. If a monitoring bus into be installed, the pipe segments will receive an external coating as part of the process of installing the monitoring bus. In other instances, both internal and external coating is required. Thus,
[0076] In step 248, the monitoring bus may be attached to the external surface of the pipe section by means well known in the art, and disposed such that the connectors at each end of a monitoring bus segment are accessible to be joined together across the press-fit pipe joint after assembly of the pipe sections end-to-end to form the pipeline. Following installation of the monitoring bus, the section of pipe passes through the external coating process to the applicable specification in step 250. If the external coating passes inspection in step 252, the pipe section, complete with the monitoring bus and the external coating, is transferred to step 254 for transport or storage to await the assembly of the pipe section into a pipeline.
[0077] Returning to step 240 of
[0078] The coating materials used in the processes illustrated in
[0079]
[0080] The dual sequences (a) and (b) are depicted in
[0081] Following Step 316, the process follows the same steps whether forming the pipe ends or assembling box-to-pin end to form a mechanical press-fit pipe joint. Thus, upon loading and securing the pipe section in the end prep bench in step 316, the flow advances to step 318 where the operator enters data about the pipe section in defined areas of the graphical display (see
[0082] In step 324, the operator engages the hydraulic ram, typically by moving a lever or operating a switch on the control panel 32 (See
[0083] Steps 340-344 are an interim or alternative sequence to cover as alternative embodiments the manual or automatic operation of the swaging machines 70, 130 in response to the activation of an alarm condition. If manual operation is preferred, the flow proceeds to step 342 to enable the operator to control the shift of the machine to a neutral condition to disengage the hydraulic ram of the swaging machine 70 or 130. If automatic operation is preferred, the CMS 24 (aka the process monitoring computer 24) shifts the machine to neutral to disengage the hydraulic ram and stop the machine.
[0084] When the hydraulic ram is disengaged and retracted in step 350, the process monitoring computer 24 logs the data of the parameters P.sub.f and L.sub.f along with the ID number, GPS coordinates, tag number, etc. before proceeding the step 352 to undergo the inspection of the completed pipe end or pipe joint. Upon verification in step 352 the flow advances to step 354. If the process is forming a pipe end (box or pin) the pipe section may be released in step 356 and proceed to step 360. If the process is forming a pipe joint during field assembly, the field assembly machine (
[0085] Upon completion of the pipeline assembly, the pipeline is preferably tested in step 360 to confirm its functional utility and integrity. The testing may at a minimum comprise the steps of performing electrical and data signal tests of the pipeline data monitoring system; performing a pressure test of the installed pipeline for leaks and flow volume; and attaching ultrasound test apparatus to the pipeline for acoustic testing for leaks and flow turbulence. While such tests are well-known in the industry and not always carried out in practice, they are essential to the operation of a pipeline constructed according to the principles described herein, to ensure an adequate data record for each joint of the pipeline.
[0086] If the respective process operations are to continue, per step 362, the data log is updated and the pipe end tagthe permanent label discussed previouslyis imprinted in step 364 before the process returns to step 304 in
[0087]
[0088]
[0089]
[0090] Also depicted in
[0091]
[0092]
[0093]
[0094]
[0095]
CONCLUSION
[0096] Disclosed herein are systems and methods concerning construction of pipelines in at least four aspects including (1) the preparation of sections of pipe to be joined by mechanical, press-fit joints; (2) the assembly of such sections of pipe; wherein the processes involved are monitored by a computer programmed to measure and display to an operator in real time parameters that indicate the quality of the pipe ends being formed and the mechanical press-fit joints when being assembled. The data is accumulated and sent to a data management center for archival and analysis purposes to provide source material for the development of standards for the construction, maintenance, and security of installed pipelines. (3) The sections of pipe formed and assembled by the system and methods of the present invention include the components of a pipeline integrity system that measures and monitors conditions of the installed pipeline such as stresses due to geological and climatological variations, as well as internal pressures and temperature associated with the use of the pipeline to transport fluid commodities over long distances. (4) This data accumulated is likewise sent to the data management center to be stored and made available for analysis and maintenance. The data management center can monitor all data received and determine when an emergency occurs that arise from leaks or stresses experienced by the pipeline.
[0097] While the inventions have been shown in exemplary forms, they are not thus limited but are susceptible to various changes and modifications without departing from the spirit thereof. For example, the data processing systems, apparatus, and methods described herein are adaptable to data monitoring and processing of other types of pipeline structures. The data sensing and monitoring, apparatus and methods are likewise adaptable with little modification to other types of pipeline structures. Various parameters of pipe characteristics may be monitored using the same concepts disclosed in the foregoing descriptions. The processes for preparing the metal surfaces disclosed herein may be modified as to technique and materials used without departing from the concepts applied in preparing pipe materials for undergoing the forming operations depicted and described herein. Further, the hydraulic machines used in forming the mechanical press-fit pipe ends can be used to form any pipe end and for other methods of joining pipe sections together. Sections to be welded may have their ends belled to fit over an internal sleeve, as in a pipe joint to be welded, for example.