Hydraulic delay toe valve system and method
10138709 ยท 2018-11-27
Assignee
Inventors
Cpc classification
E21B34/063
FIXED CONSTRUCTIONS
E21B34/108
FIXED CONSTRUCTIONS
E21B37/00
FIXED CONSTRUCTIONS
International classification
E21B34/10
FIXED CONSTRUCTIONS
E21B37/00
FIXED CONSTRUCTIONS
Abstract
An apparatus and method for providing a time delay in injection of pressured fluid into a geologic formation. In one aspect the invention is a toe valve activated by fluid pressure that opens ports after a predetermined time interval to allow fluid to pass from a well casing to a formation. The controlled time delay enables casing integrity testing before fluid is passed through the ports. This time delay also allows multiple valves to be used in the same well casing and provide a focused jetting action to better penetrate a concrete casing lining.
Claims
1. A staged time delay system for removal of debris in a wellbore casing, said staged time delay system comprising: a first tool configured to be conveyed with said wellbore casing, wherein said first tool is positionable at a first location within said wellbore casing, and wherein said first tool is configured to open a first injection point in said first tool, said first injection point collecting debris from said wellbore casing for a predetermined time as pressurized fluid at a maximum pressure rated for said wellbore casing is injected into said wellbore casing; and a second tool in fluid communication with said first tool, wherein said second tool is positionable at a second location within said wellbore casing, and is configured to open a second injection point in said second tool at the predetermined time after said first injection point is opened, said second injection point being configured to enable downhole operations after said debris is collected in said first tool leaving said second injection point free of said debris.
2. The staged time delay system of claim 1 wherein said first tool further comprises: a first mandrel portion for conveying a pressurized fluid, said first mandrel portion comprising one or more ports: a first piston slidably engaged along said first mandrel portion; a first flow restrictor controlling a rate of movement of said first piston; and a first actuating device communicating with said first piston to unseal said one or more ports to open a first injection point in said wellbore casing at said first location to allow said pressurized fluid to penetrate said wellbore casing.
3. The staged time delay system of claim 2 wherein said second tool further comprises: a second mandrel portion for conveying said pressurized fluid, said second mandrel portion comprising one or more ports; a second piston slidably engaged along said second mandrel portion; a second flow restrictor controlling a rate of movement of said second piston: and a second actuating device or said first actuating device communicating with said second piston to unseal said one or more ports to open a second injection point in said wellbore casing at said second location to allow said pressurized fluid to penetrate said wellbore casing.
4. The staged time delay system of claim 3 wherein said first tool and said second tool are each actuated by a pressure of said pressurized fluid.
5. The staged time delay system of claim 3 wherein said first mandrel portion and said second mandrel portion are part of a same mandrel.
6. The staged time delay system of claim 3 wherein said first tool has a first actuation time and said second tool has a second actuation time; said first actuation time is less said second actuation time.
7. The staged time delay system of claim 3 wherein said first tool is actuated by pressure and said second tool is actuated by a ball.
8. The staged time delay system of claim 2 wherein said second tool is selected from a group consisting of a perforating gun and a ball-actuated valve.
9. The staged time delay system of claim 1, further comprising: a third tool in fluid communication with said second tool, wherein said third tool is positionable at a third location within said wellbore casing, and wherein said third tool is configured to open a third injection point.
10. A staged injection method for removal of debris in a wellbore casing, said method comprises the steps of: installing said wellbore casing in a wellbore; injecting pressurized fluid into said wellbore casing at a maximum rated pressure of said wellbore casing; opening a first injection point in a first tool; collecting debris present in said wellbore casing at said first injection point in said first tool for a predetermined time; opening a second injection point in a second tool after expiration of said predetermined time; and performing a downhole operation through said second injection point.
11. The staged injection method of claim 10 wherein said first tool is plugged with debris during said predetermined time.
12. The staged injection method of claim 10 wherein said first tool and said second tool are controlled time delay valves, wherein each of said controlled time delay valves comprises: a mandrel portion for conveying a pressurized fluid, said mandrel portion comprising one or more ports; a piston slidably engaged along said mandrel portion; a flow restrictor controlling a rate of movement of said piston; and an actuating device communicating with said piston to unseal said one or more ports to open an injection point in said wellbore casing to allow said pressurized fluid to penetrate said wellbore casing.
13. The staged injection method of claim 12 wherein said step of opening said first injection point farther comprises: actuating said first tool and said second tool by a pressure of said pressurized fluid.
14. The staged injection method of claim 12 wherein said first tool and said second tool are actuated by one actuating device.
15. The staged injection method of claim 12 wherein said first tool has a first actuation time and said second tool has a second actuation time; said first actuation time is less said second actuation time.
16. The staged injection method of claim 12 wherein said first tool is actuated by pressure and said second tool are actuated by a ball, said method further comprising: deploying said ball into said wellbore casing after said first tool collects debris from said wellbore casing.
17. The staged injection method of claim 10 wherein said first tool is a controlled time delay tool and said second tool is a perforating gun.
18. The staged injection method of claim 17 wherein opening said first injection point further comprises: perforating through said first tool.
19. The staged injection method of claim 17 Wherein opening said second injection point further comprises: pumping pressurized fluid into said wellbore casing; actuating said first tool when a pressure of said pressurized fluid exceeds a rated pressure of an actuating device in said second tool; and delaying an opening of said second injection point for a predetermined time delay.
20. The staged injection method of claim 19 wherein said predetermined time delay is within a range of 1 minute to 2 weeks.
21. The staged injection method of claim 10 wherein said downhole operation through said second injection point is a fracturing operation through a liner in said wellbore casing.
22. The staged injection method according to claim 10, further comprising: opening a third injection point in a third tool after said predetermined time; and performing said downhole operation through said third injection point.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1) For a fuller understanding of the advantages provided by the invention, reference should be made to the following detailed description together with the accompanying drawings wherein:
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
(17)
(18)
(19)
(20)
(21)
(22)
(23)
(24)
(25)
(26)
(27)
(28)
(29)
(30)
(31)
(32)
(33)
(34)
(35)
(36)
(37)
(38)
(39)
(40)
(41)
(42)
DESCRIPTION OF THE PRESENTLY PREFERRED EXEMPLARY EMBODIMENTS
(43) While this invention is susceptible of embodiment in many different forms, there is shown in the drawings and will herein be described in detailed preferred embodiment of the invention with the understanding that the present disclosure is to be considered as an exemplification of the principles of the invention and is not intended to limit the broad aspect of the invention to the embodiment illustrated.
(44) The numerous innovative teachings of the present application will be described with particular reference to the presently preferred embodiment, wherein these innovative teachings are advantageously applied to the particular problems of a establishing injection to a hydrocarbon formation system and method. However, it should be understood that this embodiment is only one example of the many advantageous uses of the innovative teachings herein. In general, statements made in the specification of the present application do not necessarily limit any of the various claimed inventions. Moreover, some statements may apply to some inventive features but not to others.
(45) The present invention is an improved toe valve apparatus and method to allow fluid to be injected through ports in an oil or gas well casing wall section (and casing cement) into a geologic formation in a time delayed manner.
(46) The apparatus, in broad aspect, provides time-delayed injection of pressurized fluid through openings in a well casing section to a geological formation comprising: a housing with openings that can communicate through ports in the walls of the apparatus housing to a formation; a movable piston or pistons capable of moving into position to provide covering and sealing the port(s) and to a position where the ports are uncovered; means for moving the piston to a final position leaving the port(s) uncovered; and means for activation the movement of the piston.
(47) The present invention represents several improvements over conventional pressure responsive devices improvements that will be appreciated by those of ordinary skills in the art of well completions. The greatest limitation of current devices is that the sleeve or power piston of the device that allows fluid to flow from the casing to a formation (through openings or ports in the apparatus wall) opens immediately after the actuation pressure is reached. This limits the test time at pressure and in many situations precludes the operator from ever reaching the desired casing test pressure. The present invention overcomes that limitation by providing a hydraulic delay to afford adequate time to test the casing at the required pressure and duration before allowing fluid communication with the well bore and geologic formation. This is accomplished by slowly releasing a trapped volume of fluid through a hydraulic metering chamber that allows a piston covering the openings to move to a position where the openings are uncovered. This feature will become even more advantageous as federal and state regulators mandate the duration or dwell time of the casing test pressure. The metering time can be increased or tailored to a specific test requirement through manipulation of the fluid type, fluid volume, by altering the flow rate of the hydraulic liquid flow restrictor and by appropriate placement and setting of pressure valves on either or both sides of the flow restrictor.
(48) A second advantage of this invention is that two or more valves can be installed (run) as part of the same casing installation. This optional configuration of running two or more valves is made possible by the delay time that allows all of the valves to start metering before any of the valves are opened. The feature and option to run two or more valves in a single casing string increases the likelihood that the first stage of the well can be fracture stimulated without any well intervention whatsoever. Other known devices do not allow more than a single valve to operate in the same well since no further actuation pressure can be applied or increased after the first valve is opened.
(49) A third significant advantage is that in the operation of the valve, the ports are opened slowly so that as the ports are opened (uncovered) the liquid is injected to the cement on the outside of the casing in a high pressure jet (resulting from the initial small opening of the ports), thus establishing better connection to the formation. As the ports are uncovered the fluid first jets as a highly effective pinpoint cutting jet and enlarges as the ports are opened to produce an effect of a guide-hole that is then enlarged.
(50) Referring to the Figures,
(51)
(52) The openings 25-27 (and a fourth port not shown) shown in
(53) In one embodiment, the piston, 5, has dual diameters (
(54) A series of outer sections 4, 6, and 8 illustrated in
(55) The rupture disc 23 or 52 is the activation device that sets the valve opening operation into play. When ready to operate (i.e., open the piston), the casing pressure is increased to a test pressure condition. This increased pressure ruptures the rupture disc 23 or 52 and fluid at casing pressure (hydrostatic, applied or any combination) enters the chamber immediately below and adjacent to the piston 5 (in
(56) In another embodiment there are added controls on the flow of fluid from the piston chamber 32 to the low pressure piston chamber 34 to more precisely regulate the speed at which the piston moves to open the ports. As illustrated in
(57) In operation an apparatus of the invention will be piped into a casing string at a location that will allow fluid injection into the formation where desired. The apparatus may be inserted into the string an either direction. An advantage of the present invention is that two or more of the valves of the invention may be used in the string. They will, as explained above, open to allow injection of fluid at multiple locations in the formation. It can also be appreciated by those skilled in the art how two or more of valves of the invention may be used and programmed at different time delays to open during different stages of well operations as desired (e.g. one or more at 5 minute delay and one or more at 20 minutes delay). For example, the apparatus may be configured so that an operator may open one or more valves (activating the sliding closure) after a five minute delay, fracture the zone at the point of the open valves, then have one or more valves and continue to fractures the zone.
(58) In general the apparatus will be constructed of steel having properties similar to the well casing.
(59) A prototype apparatus had the general dimensions of about 60 inches in length, with a nominal outside diameter of 6.5 inches and an inside diameter of 3.75 inches. Other dimensions as appropriate for the well and operation in which the apparatus is intended to be used are intended to be included in the invention and may easily be determined by those of ordinary skill in the art.
(60)
(61) In the foregoing specification, the invention has been described with reference to specific embodiments thereof. It will, however, be evident that various modifications and changes can be made thereto without departing from the broader spirit and scope of the invention as set forth in the appended claims. The specification is, accordingly, to be regarded in an illustrative rather than a restrictive sense. Therefore, the scope of the invention should be limited only by the appended claims.
Preferred Exemplary Controlled Time Delay Apparatus with Stacked Delay Restrictor (0900-0940)
(62) The present invention is generally illustrated in more detail in
(63) According to yet another preferred exemplary embodiment, the delay elements may be designed as a cartridge that may be slide in and out of the restrictor. The cartridge may have a form factor that is compatible with the restrictor. According to a preferred exemplary embodiment, the cartridge may be positioned and customized to achieve a desired time delay.
Preferred Exemplary ID/OD Controlled Time Delay Ratio
(64) Table 1.0 illustrates an exemplary ratio of inner diameter (ID) to outer diameter (OD) in an exemplary controlled time delay apparatus. According to a preferred exemplary embodiment the ratio of ID/OD ranges from 0.4 to 0.99. According to a preferred exemplary embodiment, a full bore version wherein the inner diameter of the apparatus is almost equal to the inner diameter of the wellbore casing enables substantially more fluid flow during production. Table 2.0 illustrate the inner casing ID and outer casing ID corresponding to the Name column of Table 1.0. For example, a name of 4 refers to a casing OD of 4.5 in table 2.0.
(65) TABLE-US-00001 TABLE 1.0 Outer Inner Diameter Diameter Name (in) (in) 4 5.65 3.34 5 5.65 3.34 5 6.88 3.75 4 Full Bore x x 5 Full Bore 7.38 4.6
(66) TABLE-US-00002 TABLE 2.0 Casing Casing Casing OD Weight ID (in) (lb/ft) (in) 4.5 13.50 3.03 4.5 11.60 3.11 5.5 23.00 3.78 5.5 20.00 3.90 5.5 17.00 4.03
(67) According to a preferred exemplary embodiment, an inner tool diameter and an inner casing diameter ratio ranges from 0.4 to 1.1.
Preferred Exemplary Section of a Controlled Toe Valve Apparatus Illustrating Port Closed Time. Actuation Time Period and Port Open Time Interval (1000-1030)
(68) Port Closed Time (1010):
(69) As generally illustrated in
(70) Port Actuation Time Period (1020):
(71) As generally illustrated in
(72) Port Open Time Interval (1030):
(73) As generally illustrated in
Preferred Exemplary Chart of a Pressure Casing Test with a Controlled Time Delay Toe Valve Apparatus (1100-1190)
(74)
(75) According to a preferred exemplary embodiment, the port opening time interval may range from 1 second to 1 hour. According to a more preferred exemplary embodiment the port opening time interval may range from 0.5 second to 20 minutes. According to another preferred exemplary embodiment, the port opening time interval is almost 0 seconds.
(76) Similar to the chart in
Preferred Exemplary Reverse Acting Rupture Disk (1200-1220)
(77) As generally illustrated in
Preferred Exemplary Controlled Time Delay Apparatus with Mandrel Ports and Housing Opening Shapes (1300-1500)
(78)
(79)
(80) A constant width slot or variable width slot such as a tear drop may also be used as an opening in the housing or a port in the mandrel. Any shape that is constant width as the piston travels may be used as an opening in the housing or a port in the mandrel. Similarly, a shape such as a tear drop that may become wider or narrower as the piston moves past the openings and the ports may be used as an opening in the housing or a port in the mandrel. The flow area of the inner mandrel may be designed for limited entry applications so that flow is diverted to multiple injection points at high enough flow rate.
Preferred Exemplary Flowchart of a Controlled Time Delay Apparatus (1600)
(81) As generally seen in the flow chart of
Preferred Exemplary Flowchart of a Controlled Time Delay Apparatus (1610)
(82) As generally seen in the flow chart of
Preferred Exemplary Dual Actuating Controlled Time Delay Apparatus (1700-1900)
(83) As generally illustrated in
(84) Prior art systems do not provide for two or more toe valves in a single system due to the fact that the first connection to the formation releases all the pressure in the well casing, therefore making a potential second toe valve ineffective. This is caused by the tolerance in actuation pressure inherent in the actuation devices. According to a preferred exemplary embodiment, the time delays of individual toe valves are controlled independently so that multiple connection points to the formation are created. The effect of multiple connection points to the formation may result in increased connection efficiency and increased flow area to the formation. According to a preferred exemplary embodiment, the flow area may be increased by 50% to more than 1000%. According to a preferred exemplary embodiment, the time delays of the individual toe valves are the same. According to another preferred exemplary embodiment, the time delays of the individual toe valves are not equal. According to yet another preferred exemplary embodiment, a ratio of the first actuation time period and the second actuation time period ranges from 0.01 to 100. According to a further preferred exemplary embodiment, a ratio of the first port open time interval and the second port open time interval ranges from 0.01 to 100. According to yet another preferred exemplary embodiment, one valve provides a fail-safe mechanism for connection to the formation. The difference in rated pressures of the first actuating device (1713) and the second actuating device (1703) may be within 500 PSI. This is particularly important as the rated pressure of actuating devices such as rupture disks are rated within +500 PSI. In order to account for the differences in rated pressure, two delay tools with a rated pressure difference of +500 PSI may be used to minimize the uncertainty in the actuation pressure. In the event that one valve fails to open or function the other valve may act as a replacement or fail-safe to provide connection to the formation.
Preferred Exemplary Flowchart of a Controlled Time Delay with a Dual Actuating Toe Valve (2000)
(85) As generally seen in the flow chart of
Preferred Exemplary Single Actuating Controlled Dual Time Delay Apparatus (2100-2200)
(86) As generally illustrated in
Preferred Exemplary Flowchart of a Controlled Time Delay with a Single Actuating Toe Valve (2300)
(87) As generally seen in the flow chart of
Preferred Exemplary Flowchart of Perforating and Fracturing Through a Controlled Time Delay Toe Valve (2400)
(88) As generally seen in the flow chart of
Preferred Exemplary Apparatus Ball Seat in a Controlled Time Delay Injection Valve (2500-2600)
(89) The wiper plug designs used in today's horizontal well bores were initially developed for use in vertical well bores. The horizontal well bores present a more challenging trajectory for the equipment due to the extended casing length and concentrated friction on only one side of the wiper plug. As a consequence, the elastomeric fins of a wiper plug can become worn on one side and render incapable of sealing properly in the dimensions of the conventional shoe joint. This causes a phenomena called wet shoe. The downfalls of having a wet shoe in a cemented wellbore casing include possible leak paths, lack of isolation, and no pressure integrity of the casing. Therefore, when a pressure casing integrity test fails, the cause of the failure is either a wet shoe or leak in the casing. According to a preferred exemplary embodiment, time delay injection valve or a toe valve with a ball seat enables detection of wet shoe when a ball or a restriction plug element dropped into the wellbore casing seats in the ball seat and seals the toe end to remediate the wet shoe. On the other hand, if the ball seated in the time delay injection valve still causes a casing integrity test to fail, then the cause of the failure is not the wet shoe which further indicates that the cause of failure is related to the casing integrity. In some instances, the casing integrity failure may be due to weaker joints or a hole in the casing. According to a preferred exemplary embodiment, the time delay injection valve is a hydraulic controlled time delay valve. For example the time delay injection valve may be a hydraulic controlled time delay valve as illustrated in
(90)
(91) According to another preferred exemplary embodiment, the restriction plug element is non-degradable in wellbore fluids. According to a preferred exemplary embodiment, the restriction plug element has a shape that may be selected from a group comprising a sphere, dart, oval, or cylinder.
Preferred Exemplary Flowchart of Wet Shoe Detection with a Controlled Time Delay Toe Valve (2700)
(92) As generally seen in the flow chart of
Preferred Exemplary System of Debris Removal in a Wellbore Casing (2800)
(93) In a fracture treatment application, the well can contain residual cement or other debris which can block or restrict the function of perforations or casing conveyed completion valves. This blockage may occur during initial injection at low rates to pump down a tool string, or when the pumping rate increases during a fracture stimulation treatment, or after some time at the increased pumping rate.
(94) In a cemented liner application, it is common practice to over displace the cement by 20-40% of cement volume to achieve a good liner lap (good cement job across the liner top for pressure integrity). When the running tool is disconnected from the liner hanger system, the over displaced cement then falls back into the liner top, which leaves behind cement stringers, and other debris. These stringers, and debris then gravitate to the heel of the well, and later will be pumped from the heel to the toe when opening the toe valves. These stringers and debris have been known to plug or lock up toe valves.
(95) According to a preferred exemplary embodiment, two or more injections points may be used in a staggered fashion in order to collect debris before creating an obstruction free connection to the formation. This is particularly important for a liner hanger job wherein a liner hangs of the inside surface of the casing. If the casing is not substantially clean, the liner may not hang on to the inside surface.
Preferred Exemplary Flowchart of Debris Removal with a Controlled Dual Injection Apparatus (2900)
(96) As generally seen in the flow chart of
Preferred Exemplary Flowchart of Debris Removal with a Controlled Dual Time Delay Apparatus (3000)
(97) As generally seen in the flow chart of
Preferred Exemplary Flowchart of Debris Removal with a Controlled Time Delay Apparatus and a Perforating Gun (3100)
(98) As generally seen in the flow chart of
Preferred Exemplary Flowchart of Debris Removal with a Controlled Dual Injection Apparatus (3200)
(99) As generally seen in the flow chart of
(100) According to a preferred exemplary embodiment, the first tool is plugged with debris during the predetermined time.
(101) According to another preferred exemplary embodiment, the second tool and the third tool are controlled time delay valves.
(102) According to a yet another preferred exemplary embodiment, the second tool and the third tool are actuated by a pressure of the pressurized fluid.
(103) According to a further preferred exemplary embodiment, the first tool and the second tool are actuated by a first actuating device and the third tool actuated by a second actuating device.
(104) According to a more preferred exemplary embodiment, the first tool and second tool are actuated by pressure and the third tool is actuated by a ball. The ball is deployed into the wellbore casing after the first tool collects debris from the wellbore casing.
(105) According to a more preferred exemplary embodiment, the system may further comprises a fourth controlled time delay tool which is configured to be collects debris through a fourth injection point along with the first injection point.
Preferred Exemplary Sliding Sleeve Apparatus Manufactured from a One Piece Mandrel
(106) As generally illustrated in
(107) According to a preferred exemplary embodiment, a sliding sleeve valve for use in a wellbore casing comprises a mandrel with a first threaded end and a second threaded end. The sliding sleeve valve may be conveyed with said wellbore casing. The sliding sleeve valve may be installed on a toe end of said wellbore casing. The mandrel may be a tubular annular single piece member. The mandrel may be made from materials selected from a group comprising of steel, cast iron, ceramics or, composites. The one piece integral piece enables the mandrel to carry the full torsional load 10,000 ft-lbs to 30,000 ft-lbs of a wellbore casing when the first threaded end and the second threaded end are threaded to ends of the wellbore casing. The first threaded end and the second threaded end may be designed to carry the wellbore casing (60) specification. According to a further preferred exemplary embodiment the first threaded end and the threaded end are configured with threads that are configured to conform to the wellbore casing torque specification.
(108) According to a further preferred exemplary embodiment the sliding sleeve valve is assembled with components from one end only. For example, the rupture disk (23), the piston (5), the first outer housing (6), the high pressure chamber (32), the restriction assembly (44), the second outer housing (4) and the end cap (43) are all slid/glided or installed from the first threaded end (41) towards the direction of the second threaded end (51). According to another preferred exemplary embodiment a plurality of components are installed longitudinally from either end of the mandrel.
(109) According to a preferred exemplary embodiment a plurality of components are installed on an outer surface of the mandrel. For example, the rupture disk (23), the piston (5), the first outer housing (6), the high pressure chamber (32), the restriction assembly (44), the second outer housing (4) and the end cap (43) are all slid/glided or installed on the outer surface of the mandrel (29). According to another preferred exemplary embodiment the plurality of components are installed on an inner surface of the mandrel. According to yet another preferred exemplary embodiment the plurality of components are installed on an inner surface of the mandrel and an outer surface of the mandrel.
(110) According to a preferred exemplary embodiment said sliding sleeve valve is a controlled hydraulic time delay valve. According to a further preferred exemplary embodiment the controlled hydraulic time delay valve comprises dual time delay valves which are each actuated by dual actuating devices. According to a further preferred exemplary embodiment the controlled hydraulic time delay valve comprises dual time delay valves which are both actuated by a single actuating device.
Preferred Exemplary Flowchart of Assembling a Sliding Sleeve Valve with a One Piece Mandrel (3400)
(111) As generally seen in the flow chart of
System Summary
(112) The present invention system anticipates a wide variety of variations in the basic theme of time delay valves, but can be generalized a controlled time delay apparatus integrated into a well casing for injection of pressurized fluid into a subterranean formation, the apparatus comprising: a housing with openings, a piston, a delay restrictor, an actuating device and a high pressure chamber with a hydraulic fluid; the delay restrictor is configured to be in pressure communication with the high pressure chamber; a rate of travel of the piston is restrained by a passage of the hydraulic fluid from the high pressure chamber into a low pressure chamber through the delay restrictor;
(113) wherein
(114) upon actuation by the actuating device, the piston travels for an actuation time period, after elapse of the actuation time period, the piston travel allows opening of the openings so that the pressurized fluid flows through the openings for a port opening time interval.
(115) This general system summary may be augmented by the various elements described herein to produce a wide variety of invention embodiments consistent with this overall design description.
Method Summary
(116) The present invention method anticipates a wide variety of variations in the basic theme of implementation, but can be generalized as a controlled time delay method wherein the method is performed on a controlled time delay apparatus integrated into a well casing for injection of pressurized fluid into a subterranean formation, the apparatus comprising: a housing with openings, a piston, a delay restrictor, an actuating device and a high pressure chamber with a hydraulic fluid; the delay restrictor is configured to be in pressure communication with the high pressure chamber; a rate of travel of the piston is restrained by a passage of the hydraulic fluid from the high pressure chamber into a low pressure chamber through the delay restrictor;
(117) wherein
(118) upon actuation by the actuating device, the piston travels for an actuation time period, after elapse of the actuation time period, the piston travel allows opening of the openings so that the pressurized fluid flows through the openings for a port opening time interval;
(119) wherein the method comprises the steps of: (1) installing a wellbore casing in a wellbore along with the apparatus; (2) injecting the pressurized fluid into the wellbore casing; (3) actuating the actuating device when the maximum pressure exceeds a rated pressure of the actuating device; (4) allowing the piston to travel for the actuation time period; and (5) enabling the piston to travel to open the openings for the port opening time interval so that the pressurized fluid flows into the subterranean formation.
(120) This general method summary may be augmented by the various elements described herein to produce a wide variety of invention embodiments consistent with this overall design description.
Casing Integrity Test Method Summary
(121) The present invention method anticipates a wide variety of variations in the basic theme of implementation, but can be generalized as a casing integrity test method wherein the method is performed with a controlled time delay apparatus the time delay apparatus comprising: a housing with openings, a piston, a restrictor, an actuating device and a high pressure chamber with a hydraulic fluid; the restrictor is configured to be in pressure communication with the high pressure chamber; a rate of travel of the piston is restrained by a passage of the hydraulic fluid from the high pressure chamber into a low pressure chamber through the restrictor;
(122) wherein upon actuation by the actuating device, the piston travels for an actuation time period, after elapse of the actuation time period, the piston travel allows opening of the openings so that the pressurized fluid flows through the openings for a port opening time interval;
(123) wherein the method comprises the steps of: (1) installing a wellbore casing in a wellbore along with the apparatus; (2) injecting the fluid to about 80% of a maximum casing pressure; (3) testing for casing integrity; (4) increasing pressure of the pressurized fluid so that the pressure exceeds a rated pressure of the actuating device; (5) increasing pressure of the pressurized fluid to about 100% of the maximum casing pressure allowing the piston to travel for the actuation time period; (6) testing casing integrity for the actuation time period; and (7) enabling the piston to travel to open the openings for the port opening time interval so that the pressurized fluid flows into the subterranean formation.
(124) This general method summary may be augmented by the various elements described herein to produce a wide variety of invention embodiments consistent with this overall design description.
System/Method Variations
(125) The present invention anticipates a wide variety of variations in the basic theme of oil and gas extraction. The examples presented previously do not represent the entire scope of possible usages. They are meant to cite a few of the almost limitless possibilities.
(126) This basic system and method may be augmented with a variety of ancillary embodiments, including but not limited to:
(127) An embodiment wherein the delay restrictor is a cartridge comprising a plurality of delay elements connected as a series chain.
(128) An embodiment wherein the delay restrictor is a cartridge comprising a plurality of delay elements connected in a combination of series chain and a parallel chain.
(129) An embodiment wherein the hydraulic fluid has a viscosity ranging from 3 to 10000 centistokes.
(130) An embodiment wherein the hydraulic fluid further has plugging agents that are configured to further retard the rate of travel of the piston.
(131) An embodiment wherein the hydraulic fluid is configured to change phase from a solid to a liquid.
(132) An embodiment wherein the actuation time period ranges from greater than 60 minutes to less than 2 weeks.
(133) An embodiment wherein the actuation time period is almost 0 seconds so that the openings open instantaneously.
(134) An embodiment wherein the actuation time period ranges from 0.5 seconds to 60 minutes.
(135) An embodiment wherein the actuation time period is ranges from 2 minutes to 3 minutes.
(136) An embodiment wherein the port opening time interval ranges from 0.5 seconds to 20 minutes.
(137) An embodiment wherein the port opening time interval is almost 0 seconds.
(138) An embodiment wherein the apparatus is associated with an inner diameter and an outer diameter; the ratio of inner diameter to outer diameter ranges from 0.4 to 0.9.
(139) An embodiment wherein the apparatus is associated with an inner tool diameter and the well bore casing is associated with an inner casing diameter ratio; the ratio of inner tool diameter to outer casing diameter ranges from 0.4 to 1.1.
(140) An embodiment wherein the actuating device has a rating pressure that is substantially equal to a pressure of the wellbore casing.
(141) An embodiment wherein the actuating device is a reverse acting rupture disk.
(142) An embodiment wherein the actuating device is a rupture disk.
(143) An embodiment wherein the mandrel further comprises ports; the ports are configured to align to the openings in the housing during the port opening time interval.
(144) An embodiment wherein a shape of the openings in the housing is selected from a group consisting of: a circle, an oval, a triangle, and a rectangle.
(145) An embodiment wherein a shape of the ports in the mandrel is selected from a group consisting of: a circle, an oval, a triangle or a rectangle.
(146) An embodiment wherein a jet of the pressurized fluid is produced when the pressurized fluid injects into the subterranean formation as the ports in the mandrel travel slowly across the openings in the housing.
(147) An embodiment wherein a shape of the jet is determined by a shape of the ports and a shape of the openings.
(148) One skilled in the art will recognize that other embodiments are possible based on combinations of elements taught within the above invention description.
Controlled Dual Time Delay System Summary
(149) The present invention system anticipates a wide variety of variations in the basic theme of time delay valves, but can be generalized a controlled dual time delay system for injection of pressurized fluid through a wellbore casing at a plurality of locations into a subterranean formation, the system comprising: a first delay tool integrated into the wellbore casing at a first location; the first tool comprises a first housing with first openings, a first piston, and a first actuating device; a second delay tool integrated into the wellbore casing at a second location; the second tool comprises a second housing with second openings, a second piston, and a second actuating device; wherein upon actuation by the first actuating device, the first piston travels for a first actuation time period, after elapse of the first actuation time period, the first piston travel allows opening of the first openings so that the pressurized fluid flows through the first openings for a first port opening time interval; and upon actuation by the second actuating device, the second piston travels for a second actuation time period, after elapse of the second actuation time period, the second piston travel allows opening of the second openings so that the pressurized fluid flows through the second openings for a second port opening time interval.
Controlled Dual Time Delay Method Summary
(150) The present invention method anticipates a wide variety of variations in the basic theme of implementation, but can be generalized as a controlled dual time delay method for controlled injection of pressurized fluid into a subterranean formation at a plurality of locations, the method operating in conjunction with a controlled dual time delay system, the controlled dual time delay system comprising: a first delay tool integrated into the wellbore casing at a first location; the first delay tool comprises a first housing with first openings, a first piston, and a first actuating device; a second delay tool integrated into the wellbore casing at a second location; the second delay tool comprises a second housing with second openings, a second piston, and a second actuating device; wherein the controlled dual time delay method comprises the steps of: (1) installing a wellbore casing in a wellbore along with the dual time delay system; (2) injecting the pressurized fluid at about maximum pressure; (3) activating the first actuating device when the maximum pressure exceeds a rated pressure of the first actuating device and activating the second actuating device when the maximum pressure exceeds a rated pressure of the second actuating device; (4) allowing the first piston to travel for a first actuation time period and allowing the second piston to travel for a second actuation time period; (5) enabling the first piston to travel to open the first openings for a first port opening time interval and enabling the second piston to travel to open said second openings for a second port opening time interval, so that the pressurized fluid flows into the subterranean formation.
(151) This general method summary may be augmented by the various elements described herein to produce a wide variety of invention embodiments consistent with this overall design description.
Single-Actuating Controlled Time Delay System Summary
(152) The present invention system anticipates a wide variety of variations in the basic theme of time delay valves, but can be generalized a single-actuating controlled time delay system integrated into a wellbore casing for injecting pressurized fluid through the wellbore casing into a subterranean formation, the dual toe valve comprising: a housing with first openings and second openings, a first piston, a second piston, and an actuating device; wherein upon actuation by the actuating device, the first piston travels for a first actuation time period, after elapse of the first actuation time period, the first piston travel allows opening of the first openings so that the pressurized fluid flows through the first openings for a first port opening time interval; upon actuation by the actuating device, the second piston travels for a second actuation time period, after elapse of the second actuation time period, the second piston travel allows opening of the second openings so that the pressurized fluid flows through the second openings for a second port opening time interval; and upon actuation by the actuating device, the first piston and the second piston travel in opposite directions.
Single-Actuating Controlled Time Delay Method Summary
(153) The present invention method anticipates a wide variety of variations in the basic theme of implementation, but can be generalized as a single-actuating controlled time delay method for controlled injection of pressurized fluid into a subterranean formation at a plurality of locations, the method operating in conjunction with a controlled single-actuating time delay toe valve integrated into a wellbore casing for injecting pressurized fluid through the wellbore casing into a subterranean formation, the single-actuating time delay toe valve comprising: a housing with first openings and second openings, a first piston, a second piston, and an actuating device; wherein the single-actuating time delay method comprises the steps of: (1) installing a wellbore casing in a wellbore along with the single actuating dual toe valve; (2) injecting the pressurized fluid at about maximum pressure; (3) activating the actuating device when the maximum pressure exceeds a rated pressure of the actuating device; (4) allowing the first piston to travel for a first actuation time period and allowing the second piston to travel for a second actuation time period; (5) enabling the first piston to travel to open the first openings for a first port opening time interval and enabling the second piston to travel to open the second openings for a second port opening time interval, so that the pressurized fluid flows into the subterranean formation.
(154) This general method summary may be augmented by the various elements described herein to produce a wide variety of invention embodiments consistent with this overall design description.
Wet Shoe Detection System Summary
(155) The present invention system anticipates a wide variety of variations in the basic theme of time delay valves, but can be generalized an apparatus integrated into a well casing, a time delay injection valve with a seating surface built into the valve; the seating surface is configured to seat a restriction plug element; whereby, when a leak is detected in the well casing during a casing integrity test, a restriction plug element is dropped to seat in the conforming seating surface to determine if the leak is due to the wet shoe.
Wet Shoe Detection Method Summary
(156) The present invention method anticipates a wide variety of variations in the basic theme of implementation, but can be generalized as a method for detecting a wet shoe in a wellbore casing, the method operating in conjunction with an apparatus integrated into a toe end of the well casing, the apparatus a time delay injection valve with a seating surface built into the valve; the seating surface is configured to seat a restriction plug element; whereby, when a leak is detected in the well casing during a casing integrity test, a restriction plug element is dropped to seat in the conforming seating surface to determine if the leak is due to the wet shoe; wherein said method comprises the steps of: (1) installing a wellbore casing in a wellbore along with the apparatus; (2) performing a casing integrity test at maximum pressure; (3) checking if the casing integrity test passes, if so, proceeding to step (9); (4) deploying the restriction plug element into the wellbore casing; (5) seating the restriction plug element in the conforming seating surface of the apparatus; (6) performing a casing integrity test at maximum pressure; (7) checking if the casing integrity test passes, if so, proceeding to step (9); (8) fixing the source of the leak; and (9) performing perforation and fracturing operations.
(157) This general method summary may be augmented by the various elements described herein to produce a wide variety of invention embodiments consistent with this overall design description.
Fracturing Method Summary
(158) The present invention method anticipates a wide variety of variations in the basic theme of implementation, but can be generalized as a fracturing method for pumping fracturing fluid into a subterranean formation through a controlled time delay apparatus, the controlled time delay apparatus comprising: a housing with openings, a piston, a restrictor, an actuating device and a high pressure chamber with a hydraulic fluid; the stacked delay restrictor is configured to be in pressure communication with the high pressure chamber; a rate of travel of the piston is restrained by a passage of the hydraulic fluid from the high pressure chamber into a low pressure chamber through the stacked delay restrictor; wherein the fracturing method comprises the steps of: (1) installing a wellbore casing in a wellbore along with the time delay apparatus; (2) pumping up wellbore pressure to a maximum pressure; (3) activating the actuating device when the maximum pressure exceeds a rated pressure of the actuating device; (4) performing a casing integrity test for an actuation time period at the maximum pressure; (5) enabling the piston to travel to open the openings so that a connection is established to the subterranean formation; and (6) pumping fracturing fluid through the time delay apparatus.
(159) This general method summary may be augmented by the various elements described herein to produce a wide variety of invention embodiments consistent with this overall design description.
Staged Time Delay System Summary
(160) The present invention system anticipates a wide variety of variations in the basic theme of time delay valves, but can be generalized a staged time delay system for removal of debris in a wellbore casing, the staged time delay system comprising a first tool and a second tool; the first tool is conveyed with the wellbore casing;
(161) wherein when pressurized fluid is injected into the wellbore casing at a maximum pressure, a first injection point in the first tool is opened; the first injection point collects debris from the wellbore casing for a predetermined time; and a second injection point in the second tool is opened after the predetermined time; the second injection point is configured to enable downhole operations after the debris is collected in the first tool leaving the second injection point free of the debris.
Staged Injection Method Summary
(162) The present invention method anticipates a wide variety of variations in the basic theme of implementation, but can be generalized as a staged injection method for removal of debris in a wellbore casing, the method operating in conjunction with a staged time delay system, the staged time delay system comprising a first tool and a second tool; wherein the staged injection method comprises the steps of: (1) installing a wellbore casing in a wellbore; (2) injecting pressurized fluid into the wellbore casing at a maximum pressure; (3) opening a first injection point in the first tool; (4) collecting debris present in the wellbore casing at first injection point in the first tool for a predetermined time; (5) opening a second injection point in the second tool; and (6) performing a downhole operation through the second injection point.
(163) This general method summary may be augmented by the various elements described herein to produce a wide variety of invention embodiments consistent with this overall design description.
Sliding Sleeve Valve System Summary
(164) The present invention system anticipates a wide variety of variations in the basic theme of time delay valves, but can be generalized a sliding sleeve valve for use in a wellbore casing comprising a mandrel with a first threaded end and a second threaded end; the mandrel manufactured from one integral piece such that the mandrel carries a torque rating of the wellbore casing when the mandrel is threaded to ends of the wellbore casing.
Sliding Sleeve Valve Method Summary
(165) The present invention method anticipates a wide variety of variations in the basic theme of implementation, but can be generalized as a method of manufacturing a sliding sleeve valve for use in a wellbore casing; the sliding sleeve valve comprising a mandrel with a first threaded end and a second threaded end; the mandrel manufactured from one integral piece such that the mandrel carries a torque rating of the wellbore casing when mandrel is threaded to the wellbore casing; wherein the method comprises the steps of: (1) installing a pressure actuating disk onto the mandrel; (2) installing a piston onto the mandrel to cover a plurality of openings in the mandrel from the first threaded end towards the second threaded end and hydraulically locking in place; (3) sliding a first outer housing over the piston from the first threaded end and stopping on a first shoulder; (4) installing a high pressure chamber with the fluid from the first threaded end and stopping adjacent to the piston; (5) installing a restriction assembly from the first end and stopping adjacent to the high pressure chamber; (6) sliding a second outer housing over the mandrel adjacent to the restriction assembly; (7) installing an end cap in the mandrel and creating a low pressure chamber adjacent to the restriction assembly; and (8) threading the wellbore casing to the sliding sleeve valve with the mandrel.
(166) This general method summary may be augmented by the various elements described herein to produce a wide variety of invention embodiments consistent with this overall design description.
CONCLUSION
(167) An apparatus and method for providing a time delay in injection of pressured fluid into a geologic formation has been disclosed. In one aspect the invention is a toe valve activated by fluid pressure that opens ports after a predetermined time interval to allow fluid to pass from a well casing to a formation. The controlled time delay enables casing integrity testing before fluid is passed through the ports. This time delay also allows multiple valves to be used in the same well casing and provide a focused jetting action to better penetrate a concrete casing lining.