Trenchless methods for forming curved hole channel with steel sleeve and pipeline lifting
11585467 ยท 2023-02-21
Assignee
- Infrastructure Renewal Institute of Southern China (Guangdong, CN)
- WELEAD Infrastructure Engineering Technology (Zhengzhou), Ltd. (Henan, CN)
Inventors
- Fuming Wang (Guangdong, CN)
- Hongyuan Fang (Guangdong, CN)
- Peng Zhao (Henan, CN)
- Yanhui Pan (Henan, CN)
- Bin Li (Henan, CN)
- Hang He (Henan, CN)
Cpc classification
F16L55/175
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
E03F2003/065
FIXED CONSTRUCTIONS
F16L55/18
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
E21B19/00
FIXED CONSTRUCTIONS
E03F3/06
FIXED CONSTRUCTIONS
F16L7/02
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
International classification
F16L55/175
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F16L7/02
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F16L55/18
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
E21B19/00
FIXED CONSTRUCTIONS
Abstract
Trenchless methods for forming a curved hole channel with a steel sleeve and pipeline lifting are provided, including steps of: (T1) drilling a straight hole channel, and inserting the steel sleeve into the straight hole channel; (T2) inserting a guiding pipe into the steel sleeve, and determining a bending direction of a hole channel to be formed; and (T3) inserting a flexible steel-wire pipe into the guiding pipe, and punching to form the curved hole channel. With applying the creative trenchless method for forming the curved hole channel, a specially-made grouting pipe is accurately inserted to a bottom of a subsiding pipeline section, so that a polymer material is conveniently injected to a bottom of a disease position. Though utilizing an expansion force generated by the polymer material, the subsiding pipeline section is uplifted, so as to realize trenchless repairing.
Claims
1. A trenchless method for pipeline lifting, the method comprising steps of: (S1) detecting a pipeline, and determining a position of a subsiding pipeline section; (S2) drilling a grouting hole at one side of the subsiding pipeline section, inserting a steel sleeve into the grouting hole, inserting a guiding pipe into the steel sleeve, inserting a flexible steel-wire pipe into the guiding pipe, and forming a curved hole channel by punching towards a bottom of the subsiding pipeline section with the flexible steel-wire pipe, wherein the curved hole channel surrounds the bottom of the subsiding pipeline section; (S3) pulling out the flexible steel-wire pipe; inserting a grouting pipe into the guiding pipe, and then inserting the grouting pipe to the bottom of the subsiding pipeline section; and (S4) injecting a polymer material to the bottom of the subsiding pipeline section through the grouting pipe, so as to uplift and reset the subsiding pipeline section.
2. The trenchless method for pipeline lifting, as recited in claim 1, wherein: in the step of S1, a device used for detecting the pipeline is a pipeline video robot.
3. The trenchless method for pipeline lifting, as recited in claim 1, wherein: in the step of S2, a depth of the grouting hole is from ground to a height of a central axis of an outer wall of the subsiding pipeline section.
4. The trenchless method for pipeline lifting, as recited in claim 1, wherein: the step of S4 particularly comprises steps of: (S41) injecting the polymer material to the bottom of the subsiding pipeline section through the grouting pipe by a grouting device; and (S42) filling a subsidence area with the polymer material, then expanding and solidifying the polymer material, and gradually uplifting the subsiding pipeline section.
5. The trenchless method for pipeline lifting, as recited in claim 4, wherein: in the step of S41, a grouting head is connected between the grouting device and the grouting pipe.
6. The trenchless method for pipeline lifting, as recited in claim 5, wherein: the grouting head comprises a fixing clamp, a grouting device connection pipe and a grouting connection pipe; the grouting device connection pipe is connected with the grouting device; and the grouting connection pipe is connected with the grouting pipe.
7. The trenchless method for pipeline lifting, as recited in claim 1, further comprising steps of: (S5) after completing resettlement of the subsiding pipeline section, reinforcing and stabilizing surrounding soil of the subsiding pipeline section; after completing reinforcing, successively taking out the grouting pipe, the guiding pipe and the steel sleeve from the grouting hole; and grouting for sealing the grouting hole.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENT
(9) In order to make objects, technical solutions and effects of the present invention clearer, the present invention is further illustrated in detail with the accompanying drawings and the preferred embodiments as follows. It should be understood that the described preferred embodiments herein are only for explaining the present invention, not for limiting the present invention.
First Preferred Embodiment
(10) Referring to
(11) (T1) drilling a straight hole channel, and inserting the steel sleeve 3 into the straight hole channel;
(12) (T2) inserting a guiding pipe 4 into the steel sleeve 3, and determining a bending direction of a hole channel to be formed; and
(13) (T3) inserting a flexible steel-wire pipe 5 into the guiding pipe 4, and punching to form the curved hole channel.
(14) In the first preferred embodiment, the guiding pipe is a rubber pipe with a curved tail end.
(15) Particularly, the guiding pipe 4 plays a guiding function for punching, so as to conveniently punch to a specified position, namely a bottom of a subsiding pipeline section 1; therefore, the tail end of the guiding pipe 4 must be curved and has a definite orientation. Moreover, the steel sleeve 3 is straight, and thus the guiding pipe 4 is preferred to be made of rubber.
(16) The flexible steel-wire pipe 5 has a three-layer structure, comprising an inner layer, a middle layer, and an outer layer, wherein: the inner layer and the outer layer are made of Poly Vinyl Chloride (PVC) soft plastic; and the middle layer is steel wires.
(17) Particularly, the flexible steel-wire pipe 5 is mainly for punching and required to have certain hardness. Therefore, in the first preferred embodiment, the flexible steel-wire pipe 5 has the three-layer structure, comprising the inner layer, the middle layer, and the outer layer, wherein: the inner layer and the outer layer are made of PVC soft plastic; and the middle layer is the steel wires. The middle layer of steel wires is for better punching and fixing.
(18) Punching means controlling the flexible steel-wire pipe 5 to drill through an external machine with applying the guiding pipe as direction control, so that the curved hole channel is formed. The above method is able to form the curved hole channel inside the medium in a trenchless way and is convenient to use.
Second Preferred Embodiment
(19) Referring to
(20) (S1) detecting a pipeline, and determining a position of a subsiding pipeline section 1;
(21) (S2) selecting a position of a grouting hole 2 at ground of a side of the subsiding pipeline section 1, and extending a hole channel of the grouting hole 2 to a bottom of the subsiding pipeline section 1 with a trenchless method for forming a curved hole channel with a steel sleeve;
(22) (S3) pulling out a flexible steel-wire pipe 5; inserting a grouting pipe 6 into a guiding pipe 4, and then inserting the grouting pipe to the bottom of the subsiding pipeline section 1; and
(23) (S4) injecting a polymer material to the bottom of the subsiding pipeline section 1 through the grouting pipe 6, so as to uplift and reset the subsiding pipeline section 1.
(24) Particularly, a specific position of the subsiding pipeline section 1 is firstly detected; after determining the position of the subsiding pipeline section 1, the grouting hole 2 is drilled at one side of the subsiding pipeline section 1; in order to avoid collapse of the grouting hole 2, after successfully drilling the grouting hole, the steel sleeve 3 is inserted into the grouting hole 2, wherein a diameter of the steel sleeve is preferred to be consistent with that of the grouting hole 2; then, the guiding pipe 4 is inserted into the steel sleeve 3; next, the flexible steel-wire pipe 5 is inserted into the guiding pipe 4 for punching conveniently; through punching towards the bottom of the subsiding pipeline section 1 with the flexible steel-wire pipe 5, the curved hole channel is formed, which surrounds the bottom of the subsiding pipeline section 1 for grouting conveniently; after finishing punching, the flexible steel-wire pipe 5 is pulled out, and the grouting pipe 6 is inserted; the grouting pipe 6 is flexible and able to be inserted to the bottom of the subsiding pipeline section 1 with a radian of the grouting hole 2; finally, the polymer material is injected to the bottom of the subsiding pipeline section 1, so as to uplift the subsiding pipeline section 1 and complete the resettlement.
(25) Referring to
(26) Particularly, the main resettlement target of the second preferred embodiment is the small-diameter pipeline which generally represents the pipeline with a nominal diameter smaller than 800 mm. People cannot enter the small-diameter pipeline to check whether a subsidence disease exists. Therefore, the pipeline video robot 7 is required to enter the pipeline and determine the position of the subsiding pipeline section 1.
(27) Referring to
(28) Particularly, when drilling the grouting hole 2, a tail end of the grouting hole 2 is appropriate to reach the height of the central axis of the outer wall of the subsiding pipeline section 1. For subsequent punching, the depth of the grouting hole 2 is extended to the bottom of the subsiding pipeline section 1. If too deep or too shallow, an achieved effect is not good enough. An optimal position of punching is that the depth reaches a position of the central axis.
(29) Referring to
(30) Particularly, the grouting pipe 6 is for injecting the polymer material to the bottom of the subsiding pipeline section 1. However, a part of the grouting hole 2 is curved. Therefore, only the flexible pipe having certain flexibility can be used. In the second preferred embodiment, the grouting pipe 6 is the PVC vulcanized rubber flexible pipe.
(31) Furthermore, according to the second preferred embodiment, the step of S4 particularly comprises steps of:
(32) (S41) injecting the polymer material to the bottom of the subsiding pipeline section 1 through the grouting pipe 6 by a grouting device 8; and
(33) (S42) filling a subsidence area with the polymer material, then expanding and solidifying, and gradually uplifting the subsiding pipeline section 1 by an expansion force thereof.
(34) In the above step of S41, a grouting head is connected between the grouting device 8 and the grouting pipe 6.
(35) Particularly, a detailed process of uplifting the subsiding pipeline section 1 is described above. The grouting device 8 is used to inject the polymer material to the bottom of the subsiding pipeline section 1. At this time, good sealing between the grouting device 8 and the grouting pipe 6 is required. Therefore, the grouting head is used for connection. The grouting head is mainly for sealing the connection between the grouting device 8 and the grouting pipe 6.
(36) Furthermore, the grouting head comprises a fixing clamp 9, a grouting device connection pipe 10 and a grouting connection pipe 11, wherein: the grouting device connection pipe 10 is connected with the grouting device 8; and the grouting connection pipe 11 is connected with the grouting pipe 6.
(37) Particularly, the fixing clamp 9 is for better fixing the grouting device connection pipe 10 and the grouting connection pipe 11, so as to realize a fixing function during grouting.
(38) Furthermore, according to the second preferred embodiment, the trenchless method for pipeline lifting further comprises steps of:
(39) (S5) after completing resettlement of the subsiding pipeline section 1, reinforcing and stabilizing surrounding soil of the subsiding pipeline section 1; after completing reinforcing, successively taking out the grouting pipe 6, the guiding pipe 4 and the steel sleeve 3 from the grouting hole 2; and grouting for sealing the grouting hole 2.
(40) Particularly, after resetting the subsiding pipeline section 1, in order not to affect the original position, corresponding treatment works should be made; that is to say, the grouting pipe 6, the guiding pipe 4 and the steel sleeve 3 are taken out from the grouting hole 2, and then the grouting hole 2 is sealed through grouting, wherein grouting herein means pouring the cement grout into the grouting hole 2, so as to seal the grouting hole 2.
(41) It should be noted that: although the present invention mainly aims at solving the resettlement technology for the small-diameter drainage pipeline, but also applicable to the resettlement for the large-diameter drainage pipeline.
(42) It should be understood that: for one of ordinary skill in the art, equivalent replacements or modifications can be made based on the technical solutions of the present invention and the inventive concepts thereof, which should be all encompassed in the protection scope of the claims of the present invention.