DRILLING INSTALLATION: HANDLING SYSTEM, METHOD FOR INDEPENDENT OPERATIONS
20230040288 · 2023-02-09
Inventors
- Josephus Leonardus Aloysius Maria VAN DER HOORN (Schiedam, NL)
- Naxin ZHANG (Schiedam, NL)
- Mark Cornelius Marinus Franciscus Rommens (Schiedam, NL)
- Govert Hendrik Teunis ZIJDERVELD (Schiedam, NL)
Cpc classification
E02B17/021
FIXED CONSTRUCTIONS
E21B15/003
FIXED CONSTRUCTIONS
E21B19/008
FIXED CONSTRUCTIONS
International classification
E21B19/22
FIXED CONSTRUCTIONS
E21B15/00
FIXED CONSTRUCTIONS
Abstract
Drilling installation comprising a cantilever with a drilling floor for performing drilling operations; further comprising an independent operations handling system arranged for handling equipment underneath the drilling floor independent of the drilling operations on the drilling floor, wherein the independent operations handling system comprises a handling element for cooperation with the equipment to be handled, wherein the handling element is extendible underneath the cantilever.
Claims
1. A method for performing operations on a jacket or well platform that is positioned underneath a cantilever and outside of an area of a deck of a drilling installation, said cantilever being mounted on the drilling installation and comprising an independent operations handling system mounted to a bottom side of the cantilever, the method comprising using a handling element of the independent operations handling system to lift equipment from the deck of the drilling installation and transport said equipment to said jacket or well platform.
2. The method of claim 1, wherein using the handling element comprises moving the equipment from a position underneath the cantilever to a position on the deck and vice versa.
3. The method of claim 1, wherein using the handling element comprises moving the equipment outside of the cantilever.
4. The method of claim 1, wherein the independent operations handling system performs independent operations on the jacket or well platform during drilling operations of the drilling installation.
5. The method of claim 1, wherein using the handling element is performed simultaneously with drilling operations or the operations on the jacket or well platform.
6. The method of claim 1, wherein using the handling element comprises moving the handling element in an XY plane underneath the cantilever.
7. The method of claim 1, wherein using the handling element comprises vertically adjusting the handling element with respect to the cantilever.
8. The method of claim 1, wherein using the handling element comprises lowering the handling element for lowering the equipment.
9. The method of claim 1, wherein the handling element is embodied as a holding element, wherein the using of the handling element comprises holding the equipment.
10. The method of claim 9, wherein the holding element is a lifting hook.
11. The method of claim 9, wherein the holding element is a clamping device.
12. The method of claim 1, further comprising vertically adjusting the independent operations handling system between a first operational position, in which the handling element is movable underneath the cantilever, and a second operational position, in which the handling element is aside of the cantilever.
13. The method of claim 1, further comprising storing the handling element, during non-use, in a position aside of the cantilever.
14. The method of claim 13, wherein the position aside of the cantilever is outside of the cantilever.
15. The method of claim 1, wherein the equipment comprises a well intervention stack.
16. The method of claim 1, wherein the equipment comprises a blow-out preventer.
17. The method of claim 1, wherein the equipment comprises an X-mas tree.
18. A method for performing operations on a jacket or well platform that is positioned underneath a cantilever and outside of an area of a deck of a drilling installation, said cantilever being mounted on the drilling installation and comprising an independent operations handling system mounted to an outside of the cantilever, the method comprising using a handling element of the independent operations handling system to handle equipment between the deck of the drilling installation and the jacket or well platform.
19. The method of claim 18, wherein using the handling element comprises moving the equipment between the deck of the drilling installation and the jacket or well platform and vice versa.
20. The method of claim 18, wherein using the handling element comprises moving the equipment outside of the cantilever.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0044] The invention will further be elucidated on the basis of exemplary embodiments which are represented in a drawing. The exemplary embodiments are given by way of non-limitative illustration.
[0045] In the drawing:
[0046]
[0047]
[0048]
[0049]
[0050]
[0051]
[0052]
[0053]
[0054]
[0055]
[0056]
[0057]
[0058]
[0059]
[0060]
[0061]
[0062]
[0063]
[0064]
[0065]
[0066]
[0067]
[0068]
[0069]
[0070]
[0071]
[0072] It is noted that the figures are only schematic representations of embodiments of the invention that are given by way of non-limiting example. In the figures, the same or corresponding parts are designated with the same reference numerals.
DETAILED DESCRIPTION OF THE INVENTION
[0073]
[0074]
[0075] The moonpool 10, not visible in this figure, is provided as an opening through the cantilever 17 through which the drilling string may travel further downward towards the earth bottom. In this embodiment, the cantilever 17 is translatable with respect to the deck 5 of the drilling installation 1 in a X-direction and a Y-direction over skidding rails 37a and 37b. In alternative embodiments, the cantilever 17 may be rotatable with respect to the deck 5 or may be extendible outside of the deck 5 of the drilling installation 1 by means of translation in the X-direction only. This drilling installation 1 is a jack-up platform having three or more legs 3 that are vertically adjustable with respect to the deck 5. The legs 3 are typically adjustable between an upper position in which the legs are extending mainly above the deck 5 and between a lower position in which the legs 3 mainly extend below the deck 5. In the upper position of the legs 3, the jack-up platform 1 may be towed or may sail to an offshore location. In the lower position of the legs 3 the legs may extend into the seabottom for anchoring of the jack-up platform 1. In the embodiment of
[0076] The drilling floor 8 is the level where drilling operations, take place. It is also the level where handling and connecting of tubulars or drill strings is done. The tubulars are pipes with a standardized and/or predetermined length that are connected to each other to form a continuous drill string that can be lowered into the seabed for drilling a well. The drilling floor 8 is provided with a hole, not shown here, through which the drill string may travel downwardly into the earth bottom. Other equipment and/or installations that may be present on the deck 5 are not shown here.
[0077] Typically, for the exploration and/or production of an oil and/or gas field, multiple wells are drilled from a single location. The wells may fan out to spread over the reservoir. Therefore, multiple well strings 11 may be present. At an upper end of a well string 11, usually a well head is provided, not shown here. The well heads may be positioned above the water level on the production platform, a so-called surface wellhead, or may be positioned on the sea bed below the water level, a so-called subsea wellhead. Servicing, maintenance and/or well intervention operations during the production life of the well, take place via the wellhead.
[0078] At a level below the drilling floor 8, here mounted to the cantilever 17, a handling system 12 is provided. The handling system 12 is arranged for performing operations independent of the drilling operations on the drilling floor 8. The handling system 12 can handle equipment underneath the drilling floor 8 for example for maintenance or well intervention operations. The handling system 12 is provided with a handling element 13. The handling element 13 can be a guide element for guiding a wireline or a slackline or a coiled tubing etc. The handling element 13 may also be embodied as a cooperation element configured for cooperation with equipment to be handled. Such equipment may be a blowout preventer or a X-mas tree or a reel etc. The handling element 13 can thus be embodied as a lifting hook or a clamping mechanism.
[0079] As is widely known in the field of drilling, the drilling floor 8 is a hazardous area. There is being worked with heavy equipment, rotating machinery and dangerous fluids. Also, the drilling floor 8 is usually crowded with workers, drilling equipment, tubulars and/or drill string etc. Therefore, when maintenance or well intervention operations are to be performed, the drilling operations are interrupted and additional maintenance or well intervention equipment is being placed on the drilling floor. This is time consuming and may increase the risks on injuries and/or failures. By providing a handling system 12 mounted to the bottom side 17f or a lateral side 17b, 17c, or an aft side 17d of the cantilever 17, i.e. at a level below the drilling floor 8, maintenance and/or well intervention operations may be performed independent of the drilling operations. For example, the maintenance and/or well intervention operations may be performed simultaneously with the drilling operations, so the drilling operations does not need to be interrupted. Or, the maintenance and/or well intervention operations may be performed at the level below the drilling floor 8, even when there are no drilling operations, so there is no or limited interference of equipment and/or activities on the drilling floor 8. By separating these maintenance and/or well intervention operations from the drilling operations on the drilling floor, safety may be increased.
[0080] In the embodiment of
[0081] The handling element 13 of the handling system 12 is movable in a XY-plane underneath the drilling floor. Normally, such an XY-plane is approximately parallel to the bottom side 17f of the cantilever, at a level below the drilling floor 8. By providing the XY-movement, the handling system 12 can operate in the sometimes limited space that is available underneath the drilling floor 8. The handling element 13 and/or handling system 12 may be movable in the XY-plane, but the movement may be a translational and/or a rotational movement.
[0082] The drilling installation or here, jack-up platform, 1 is positioned adjacent a jacket or well platform 18. The well platform 18 comprises multiple wellheads 19 from which well strings 11 travel downwards to the wells. For drilling, maintenance, servicing and/or well intervention operations, the cantilever 17 may extend outside of the deck 5 over the well platform 18.
[0083] At a level below the drilling floor 8, a handling system 12 is provided with a horizontally movable handling element 13. Here, the handling system 12 is connected to a lateral side of the cantilever 17, while the horizontally movable handling element 13 is extendible underneath the cantilever 17. The handling system 12 is here embodied as a telescopic beam that is via a slewing gear 21 rotatable connectable to the cantilever 17. From the slewing gear 21 an upwardly extending connection arm 22 is provided. By providing a rotational joint, e.g. a slewing gear 21, and a horizontally extendible arm, e.g. a telescopic beam 20, a relatively large range can be obtained for the handling element 13.
[0084] A more detailed view of an embodiment of a telescopic beam 20 is given in
[0085] The handling element 13 is provided at the free end of the telescopic beam 20 and comprises in the embodiment of
[0086] The handling element 13 here comprises a holding connection 24 to hold equipment 27, such as a well intervention stack, blowout preventer, a coiled tubing unit, or X-mas tree, while moving the equipment to and/or from the well platform 18. Such equipment 27 can be positioned on the platform 1 to be picked up by the handling system 12 and to be hoisted to the well platform 18. To that end, for example a texas deck 28 or foldable deck or other access platform can be provided. Here, a texas deck 28 is provided at an aft side of the jack-up platform 1. The deck 28 can be folded towards the side when it is not needed. The equipment 27 can be lowered onto the texas deck 28 by means of a crane available on the deck 5. Various embodiments are possible for the holding connection 24, for example a lifting hook, or a clamping mechanism, or a plate connection etc.
[0087] By providing the handling system 12, non-drilling operations such as servicing, maintenance, well intervention, work over etc. may be performed independent of the drilling operations. The drilling operations therefore do not need to be interrupted when such operations are being performed. Simultaneous operations to the drilling operations may become possible. This may provide for a more safe work environment as well as a more efficient use of the drilling installation. Eventually, the time the jack-up drilling installation 1 may be required for a specific well platform may be reduced.
[0088] The handling element 13 is horizontally movable to provide an optimal reach over the well platform and to position handling element 13 above a determined well head in order to be able to perform independent operations on that well. Advantageously, the reach of handling element 13 is larger than the moonpool area 10 to cover as much well heads on the well platform 18 as possible.
[0089] By providing a horizontally movable handling element 13 and/or handling system 12, the handling system 12 may be stored underneath the cantilever, or may be operable underneath the cantilever. Alternative embodiments such as a segmented beam, or a knuckle beam, or a drivable carriage are shown in
[0090]
[0091] Here, the handling system 12 is embodied as a segmented beam 20 having a first arm 14 and a second arm 15 that are hingedly connected to each other such that the handling element 13 at the free end 12b is movable in a horizontal plane. Here, the segmented beam 20 comprises two hingedly connected arms, but may also comprise three or more hingedly connected arms. Also, the handling system 12 may be a hybrid structure comprising of hingedly connected arms of which one arm may be embodied as a telescopic beam. The hinge joint may be provided by slewing gears or may be actuated by hydraulic cylinders.
[0092] In the embodiment of
[0093] For example, the well intervention stack 27 may be connected to the lifting hook 24 of the handling element 13 and may then, by movement of the handling element 13 in the horizontal XY-plane be positioned above the determined wellhead 19 of the well jacket 18. Then, the hydraulic cylinders 29 may be operated to lower the connection arm 22 and thus the handling system 12 with the connected equipment 27 towards the well jacket 18.
[0094]
[0095]
[0096]
[0097]
[0098]
[0099]
[0100] Here, the handling system 12 is mounted at a fixed position to the cantilever, i.e. the support structure 43 is fixedly connected to the cantilever 17. Alternatively, the support structure 43 can be horizontally extendible with respect to the cantilever 17, e.g. the support structure may be translatable over rails or tracks mounted to the cantilever. As such, the horizontal reach of the arm 20 may be extended and/or the handling system 12 may be additionally used to handle equipment to/from the main deck and well bay jacket.
[0101] In this embodiment, the connection arm 22 is vertically movable with respect to the support structure 43 and to allow for sliding movement of the connection arm, or pedestal, within the brackets, the brackets 30 can be embodied as sliding bushes 30. To provide for the vertical displacement of the connection arm 22 and horizontal arm 20, a rack-and-pinion displacement mechanism 44 can be provided, as shown in
[0102]
[0103]
[0104] In the embodiment of
[0105] A wireline stack or wireline rig-up consists of a tool string composed of for example a stuffing box on top, a lubricator and a blow out preventer. For wireline operations, the lower end of the wireline rig-up is connected to the well head or X-mas tree, wireline is guided into the rig-up from the guiding sheave 13a and runs through the rig-up into the drill pipe. Here, the rig-up second handling part 13b is provided with a dual hoist line/cable 57 running on a dual drum 47. The two hoist cables 57 can be connected to an outer edge of a top side of the rig-up and can be lifted and lowered by the dual drum 47. The first handling part, sheave 13a, guiding the wireline 48, is positioned between these cables 58, and as such, the wireline can be guided relatively easy to the center of an entrance of the wireline rig-up. Thus, the wireline rig-up can be held under approximately constant tension during wireline operations, which is advantageous, as such a wireline rig-up typically collapses under its own weight, so by tensioning it with a hoist line provided on the handling system, additional hoisting activity and use of additional equipment can be obviated. Also, the wireline rig-up can be pulled up and held closely to the first handling part guiding the wireline, which saves space compared to normal wireline operations.
[0106] The dual drum winch 47 is here provided near a knuckle of the knuckle beam. The further handling element 13ii, is here embodied as a hoisting block, suitable for loads such as a container, X-mas tree or well intervention stack, with a hoisting line 58 running on a winch or drum 59.
[0107] As shown in
[0108] Advantageously, a wireline 48 is guided through the handling system 12, as shown in
[0109]
[0110] Instead of a rack-and-pinion displacement mechanism, a winch for hoisting the connection arm vertically along the support structure 43 may be provided, or the already mentioned hydraulic cylinders.
[0111] The guide 60 can have various embodiment, such as T-shaped with three rail enclosing wheels per set or U-shaped rail with two wheels enclosed by the rails, as in
[0112]
[0113]
[0114] Alternatives are possible to extend the vertical displacement of the handling system 12. For example, the rack on which the pedestal or connection arm can be displaced can be extended to above or below. In another example the boom or arm segment(s) can be pivotable in a vertical plane, e.g. while positioned alongside the cantilever. Thereto, horizontal hinge(s) and suitable actuators can be provided. In another example, the boom fore arm may be equipped with an additional arm segment which is pivotable in the vertical plane around a horizontal hinge and then can be tilted up by any type of suitable actuator.
[0115] For the purpose of clarity and a concise description, features are described herein as part of the same or separate embodiments, however, it will be appreciated that the scope of the invention may include embodiments having combinations of all or some of the features described. It may be understood that the embodiments shown have the same or similar components, apart from where they are described as being different.
[0116] For example, it may be understood that the handling system as described above may have various embodiments as well as combinations of elements of these embodiments. Also, it may be understood that the handling system may be positioned at a lateral side or at an aft side or at a bottom side of the cantilever, irrespective of the embodiment of the handling system.
[0117] Other aspects of the embodiments are a drilling installation comprising a derrick and a drilling floor for performing drilling operations, wherein the drilling floor is on a cantilever extendible outside of the drilling installation and the derrick is positioned over the drilling floor; further comprising an independent operations handling system arranged for handling equipment underneath the cantilever independent of the drilling operations on the drilling floor; wherein the independent operations handling system comprises a handling element for cooperation with the equipment to be handled; wherein the handling element is movable in a XY-plane underneath the cantilever.
[0118] In another aspect, the handling system comprises a horizontally extendible arm with the handling element at a free end of the arm.
[0119] In a further aspect, the handling element is configured for guiding equipment such as a wireline and/or coiled tubing, for example as a banana sheave.
[0120] As another aspect, the handling element is configured for holding equipment, such as a well intervention stack, a blow-out-preventer and/or a X-mas-tree, for example as a lifting hook or a clamping mechanism.
[0121] In another embodiment, the handling system and/or the handling element further is arranged for movement in the Z-direction.
[0122] In a further embodiment, the handling system further is provided with hoisting means.
[0123] In another embodiment, the handling system is mounted to a bottom side and/or a lateral side of the cantilever.
[0124] In a further embodiment, the drilling installation comprises a reel on the deck of the drilling installation facing the handling system, wherein the reel is arranged for comprising equipment such as a wireline or coiled tubing to be handled by the handling system or further comprises an equipment station at a side of the drilling installation facing the handling system, for example configured as a foldable texas deck.
[0125] In another example, the handling system is removable connected to the cantilever for storage on the drilling installation during non-use of the handling system.
[0126] Another aspect is the cantilever for mounting on a drilling installation, wherein the cantilever is provided with a handling system at a lower end thereof for handling equipment independent of drilling operations, wherein the handling system comprises a handling element that is arranged for movement in a XY-plane underneath the cantilever.
[0127] Another aspect is the handling system configured for mounting to a cantilever for handling equipment underneath the cantilever, comprising a handling element for cooperation with the equipment, wherein the handling element is arranged for movement in a XY-plane.
[0128] In another embodiment, the handling system comprises a segmented beam extending in the XY-plane, wherein the handling element is arranged on a free end of the segmented beam.
[0129] In a further embodiment, an end of the segmented beam opposite of the free end is connectable to the cantilever.
[0130] In yet a further embodiment, the connectable end is adjustable with respect to the cantilever in a Z-direction transverse to the XY-plane.
[0131] In a yet another embodiment, the handling system is disconnectedly mountable to the cantilever.
[0132] A further aspect is a method for performing operations on wells independent of drilling operations on a drilling installation with a cantilever extendible outside of the drilling installation, comprising providing a handling system for handling equipment to perform the independent operations, wherein the handling system comprises a handling element for cooperation with the equipment, moving the handling element in an XY-plane underneath the cantilever to a position in accordance with a determined well head and/or further moving the handling system and/or the handling element in a Z-direction downwards for lowering equipment, such as a well intervention stack or a blowout preventer to the determined well head.
[0133] In the claims, any reference signs placed between parentheses shall not be construed as limiting the claim. The word ‘comprising’ does not exclude the presence of other features or steps than those listed in a claim. Furthermore, the words ‘a’ and ‘an’ shall not be construed as limited to ‘only one’, but instead are used to mean ‘at least one’, and do not exclude a plurality. The mere fact that certain measures are recited in mutually different claims does not indicate that a combination of these measures cannot be used to an advantage.
[0134] Many variants will be apparent to the person skilled in the art. All variants are understood to be comprised within the scope of the invention defined in the following claims.