DRILLING INSTALLATION: HANDLING SYSTEM, METHOD FOR INDEPENDENT OPERATIONS

20230040288 · 2023-02-09

    Inventors

    Cpc classification

    International classification

    Abstract

    Drilling installation comprising a cantilever with a drilling floor for performing drilling operations; further comprising an independent operations handling system arranged for handling equipment underneath the drilling floor independent of the drilling operations on the drilling floor, wherein the independent operations handling system comprises a handling element for cooperation with the equipment to be handled, wherein the handling element is extendible underneath the cantilever.

    Claims

    1. A method for performing operations on a jacket or well platform that is positioned underneath a cantilever and outside of an area of a deck of a drilling installation, said cantilever being mounted on the drilling installation and comprising an independent operations handling system mounted to a bottom side of the cantilever, the method comprising using a handling element of the independent operations handling system to lift equipment from the deck of the drilling installation and transport said equipment to said jacket or well platform.

    2. The method of claim 1, wherein using the handling element comprises moving the equipment from a position underneath the cantilever to a position on the deck and vice versa.

    3. The method of claim 1, wherein using the handling element comprises moving the equipment outside of the cantilever.

    4. The method of claim 1, wherein the independent operations handling system performs independent operations on the jacket or well platform during drilling operations of the drilling installation.

    5. The method of claim 1, wherein using the handling element is performed simultaneously with drilling operations or the operations on the jacket or well platform.

    6. The method of claim 1, wherein using the handling element comprises moving the handling element in an XY plane underneath the cantilever.

    7. The method of claim 1, wherein using the handling element comprises vertically adjusting the handling element with respect to the cantilever.

    8. The method of claim 1, wherein using the handling element comprises lowering the handling element for lowering the equipment.

    9. The method of claim 1, wherein the handling element is embodied as a holding element, wherein the using of the handling element comprises holding the equipment.

    10. The method of claim 9, wherein the holding element is a lifting hook.

    11. The method of claim 9, wherein the holding element is a clamping device.

    12. The method of claim 1, further comprising vertically adjusting the independent operations handling system between a first operational position, in which the handling element is movable underneath the cantilever, and a second operational position, in which the handling element is aside of the cantilever.

    13. The method of claim 1, further comprising storing the handling element, during non-use, in a position aside of the cantilever.

    14. The method of claim 13, wherein the position aside of the cantilever is outside of the cantilever.

    15. The method of claim 1, wherein the equipment comprises a well intervention stack.

    16. The method of claim 1, wherein the equipment comprises a blow-out preventer.

    17. The method of claim 1, wherein the equipment comprises an X-mas tree.

    18. A method for performing operations on a jacket or well platform that is positioned underneath a cantilever and outside of an area of a deck of a drilling installation, said cantilever being mounted on the drilling installation and comprising an independent operations handling system mounted to an outside of the cantilever, the method comprising using a handling element of the independent operations handling system to handle equipment between the deck of the drilling installation and the jacket or well platform.

    19. The method of claim 18, wherein using the handling element comprises moving the equipment between the deck of the drilling installation and the jacket or well platform and vice versa.

    20. The method of claim 18, wherein using the handling element comprises moving the equipment outside of the cantilever.

    Description

    BRIEF DESCRIPTION OF THE DRAWINGS

    [0044] The invention will further be elucidated on the basis of exemplary embodiments which are represented in a drawing. The exemplary embodiments are given by way of non-limitative illustration.

    [0045] In the drawing:

    [0046] FIG. 1 shows a perspective view of a general arrangement of a drilling installation with a cantilever with a handling system mounted to the cantilever;

    [0047] FIG. 2 shows an embodiment of the handling system mounted to a lateral side of the cantilever;

    [0048] FIG. 3 shows a detailed view of the handling system of FIG. 2;

    [0049] FIG. 4 shows an embodiment of the handling system positioned at an aft side of the cantilever;

    [0050] FIG. 5a shows a schematic side view of a cantilever reaching over a well platform and an embodiment of a handling system mounted to the aft side of the cantilever;

    [0051] FIG. 5b shows a top view of FIG. 5a;

    [0052] FIG. 6a shows a side view of an embodiment of a handling system mounted to a bottom side of the cantilever;

    [0053] FIG. 6b shows a bottom view of the handling system of FIG. 6a;

    [0054] FIG. 7a shows a schematic perspective view of an embodiment of a handling system underneath the cantilever;

    [0055] FIG. 7b shows a bottom view of the handling system of FIG. 7a;

    [0056] FIG. 8a shows a schematic perspective view of another embodiment of a handling system underneath the cantilever;

    [0057] FIG. 8b shows a bottom view of the handling system of FIG. 8a;

    [0058] FIG. 9 shows a perspective schematic view of another embodiment of a handling system;

    [0059] FIG. 10 shows an alternative embodiment of a handling system having a telescopic arm;

    [0060] FIG. 11 shows an alternative embodiment of a handling system mounted to the lateral side of the cantilever;

    [0061] FIG. 12 shows the handling system of FIG. 11 disconnected from the cantilever;

    [0062] FIG. 13a shows an embodiment of the handling system with a rack-and-pinion vertical displacement mechanism;

    [0063] FIG. 13b shows a detail of the embodiment of the handling element of FIG. 13a;

    [0064] FIG. 13c shows another embodiment of a handling element;

    [0065] FIG. 14 shows an embodiment of the handling system with a wireline guided through the handling system;

    [0066] FIG. 15a shows an alternative embodiment of a handling system with a vertical displacement mechanism;

    [0067] FIG. 15b shows a detail of the vertical displacement mechanism of FIG. 15a;

    [0068] FIG. 16a shows a side view of a general arrangement of the handling system holding a load underneath the cantilever when the cantilever is extended;

    [0069] FIG. 16b shows a side view of a general arrangement of the handling system of FIG. 16a with the handling system pivoted towards the drilling installation when the cantilever is extended;

    [0070] FIG. 16c shows a side view of a general arrangement of the handling system of FIG. 16a and FIG. 16b with the handling system moved vertically up and extended such that the load is above the main deck when the cantilever is extended;

    [0071] FIG. 17 shows a side view of a general arrangement of the handling system of FIG. 16a and FIG. 16b with the handling system moved vertically up during retracting of the cantilever.

    [0072] It is noted that the figures are only schematic representations of embodiments of the invention that are given by way of non-limiting example. In the figures, the same or corresponding parts are designated with the same reference numerals.

    DETAILED DESCRIPTION OF THE INVENTION

    [0073] FIG. 1 shows a schematic perspective view of a drilling installation 1. The drilling installation 1 is here embodied as a jack-up platform. Such a drilling installation 1 is typically temporarily positioned at an offshore location where an oil and/or gas field is exploited next to a well platform 18. The drilling installation 1 may be used for drilling wells when the oil and/or gas field is being explored, and may be used for maintenance or servicing of the wells and/or for well intervention during the production life of the wells.

    [0074] FIG. 1 shows a schematic perspective view of the drilling installation 1 comprising a cantilever 17. The derrick 7 is here positioned on top of the cantilever 17. The drilling floor 8 is positioned at an upper side 17a of the cantilever 17. The cantilever 17 further has lateral sides 17b, 17c, an aft side 17d, a front side 17e and a bottom side 17f.

    [0075] The moonpool 10, not visible in this figure, is provided as an opening through the cantilever 17 through which the drilling string may travel further downward towards the earth bottom. In this embodiment, the cantilever 17 is translatable with respect to the deck 5 of the drilling installation 1 in a X-direction and a Y-direction over skidding rails 37a and 37b. In alternative embodiments, the cantilever 17 may be rotatable with respect to the deck 5 or may be extendible outside of the deck 5 of the drilling installation 1 by means of translation in the X-direction only. This drilling installation 1 is a jack-up platform having three or more legs 3 that are vertically adjustable with respect to the deck 5. The legs 3 are typically adjustable between an upper position in which the legs are extending mainly above the deck 5 and between a lower position in which the legs 3 mainly extend below the deck 5. In the upper position of the legs 3, the jack-up platform 1 may be towed or may sail to an offshore location. In the lower position of the legs 3 the legs may extend into the seabottom for anchoring of the jack-up platform 1. In the embodiment of FIG. 2, the legs 3 are in the lower position and the deck 5 is above the waterline 6.

    [0076] The drilling floor 8 is the level where drilling operations, take place. It is also the level where handling and connecting of tubulars or drill strings is done. The tubulars are pipes with a standardized and/or predetermined length that are connected to each other to form a continuous drill string that can be lowered into the seabed for drilling a well. The drilling floor 8 is provided with a hole, not shown here, through which the drill string may travel downwardly into the earth bottom. Other equipment and/or installations that may be present on the deck 5 are not shown here.

    [0077] Typically, for the exploration and/or production of an oil and/or gas field, multiple wells are drilled from a single location. The wells may fan out to spread over the reservoir. Therefore, multiple well strings 11 may be present. At an upper end of a well string 11, usually a well head is provided, not shown here. The well heads may be positioned above the water level on the production platform, a so-called surface wellhead, or may be positioned on the sea bed below the water level, a so-called subsea wellhead. Servicing, maintenance and/or well intervention operations during the production life of the well, take place via the wellhead.

    [0078] At a level below the drilling floor 8, here mounted to the cantilever 17, a handling system 12 is provided. The handling system 12 is arranged for performing operations independent of the drilling operations on the drilling floor 8. The handling system 12 can handle equipment underneath the drilling floor 8 for example for maintenance or well intervention operations. The handling system 12 is provided with a handling element 13. The handling element 13 can be a guide element for guiding a wireline or a slackline or a coiled tubing etc. The handling element 13 may also be embodied as a cooperation element configured for cooperation with equipment to be handled. Such equipment may be a blowout preventer or a X-mas tree or a reel etc. The handling element 13 can thus be embodied as a lifting hook or a clamping mechanism.

    [0079] As is widely known in the field of drilling, the drilling floor 8 is a hazardous area. There is being worked with heavy equipment, rotating machinery and dangerous fluids. Also, the drilling floor 8 is usually crowded with workers, drilling equipment, tubulars and/or drill string etc. Therefore, when maintenance or well intervention operations are to be performed, the drilling operations are interrupted and additional maintenance or well intervention equipment is being placed on the drilling floor. This is time consuming and may increase the risks on injuries and/or failures. By providing a handling system 12 mounted to the bottom side 17f or a lateral side 17b, 17c, or an aft side 17d of the cantilever 17, i.e. at a level below the drilling floor 8, maintenance and/or well intervention operations may be performed independent of the drilling operations. For example, the maintenance and/or well intervention operations may be performed simultaneously with the drilling operations, so the drilling operations does not need to be interrupted. Or, the maintenance and/or well intervention operations may be performed at the level below the drilling floor 8, even when there are no drilling operations, so there is no or limited interference of equipment and/or activities on the drilling floor 8. By separating these maintenance and/or well intervention operations from the drilling operations on the drilling floor, safety may be increased.

    [0080] In the embodiment of FIG. 1, the handling element 13 is holding a coiled tubing unit 27, which is equipment that may be used for well intervention operations.

    [0081] The handling element 13 of the handling system 12 is movable in a XY-plane underneath the drilling floor. Normally, such an XY-plane is approximately parallel to the bottom side 17f of the cantilever, at a level below the drilling floor 8. By providing the XY-movement, the handling system 12 can operate in the sometimes limited space that is available underneath the drilling floor 8. The handling element 13 and/or handling system 12 may be movable in the XY-plane, but the movement may be a translational and/or a rotational movement.

    [0082] The drilling installation or here, jack-up platform, 1 is positioned adjacent a jacket or well platform 18. The well platform 18 comprises multiple wellheads 19 from which well strings 11 travel downwards to the wells. For drilling, maintenance, servicing and/or well intervention operations, the cantilever 17 may extend outside of the deck 5 over the well platform 18.

    [0083] At a level below the drilling floor 8, a handling system 12 is provided with a horizontally movable handling element 13. Here, the handling system 12 is connected to a lateral side of the cantilever 17, while the horizontally movable handling element 13 is extendible underneath the cantilever 17. The handling system 12 is here embodied as a telescopic beam that is via a slewing gear 21 rotatable connectable to the cantilever 17. From the slewing gear 21 an upwardly extending connection arm 22 is provided. By providing a rotational joint, e.g. a slewing gear 21, and a horizontally extendible arm, e.g. a telescopic beam 20, a relatively large range can be obtained for the handling element 13.

    [0084] A more detailed view of an embodiment of a telescopic beam 20 is given in FIG. 10. The telescopic beam 20 has an arm 20a that is translatable inside or outside of the arm 20b. At an end of the arm 20a the handling element 13 is provided, here as a lug. On the arm 20b a slewing gear 21 is provided such that the arm 20b is rotatable around a Z-axis, a direction transverse to the XY-plane in which the telescopic beam 20 is movable. From the slewing gear 21 upwards a connection arm 22 is mounted that provides for the connection with the drilling installation 1, e.g. with a side of a cantilever 17 on the drilling installation 1.

    [0085] The handling element 13 is provided at the free end of the telescopic beam 20 and comprises in the embodiment of FIG. 1 a banana sheave 23 and a holding connection 24. Via the banana sheave 23, that can be adjustable in position itself, a wireline or coiled tubing or slackline or any other line or cabling 25 can be guided towards a well head 19 on the well platform 18. The line or cabling 25 typically is reeled onto a reel 26 that is preferably positioned on the deck 5 of the drilling installation 1. In an alternative position, the reel 26 may be positioned on a foldable texas deck 28 at a side of the platform deck 5. Various positions of the reel 26 on the deck 5 may be possible.

    [0086] The handling element 13 here comprises a holding connection 24 to hold equipment 27, such as a well intervention stack, blowout preventer, a coiled tubing unit, or X-mas tree, while moving the equipment to and/or from the well platform 18. Such equipment 27 can be positioned on the platform 1 to be picked up by the handling system 12 and to be hoisted to the well platform 18. To that end, for example a texas deck 28 or foldable deck or other access platform can be provided. Here, a texas deck 28 is provided at an aft side of the jack-up platform 1. The deck 28 can be folded towards the side when it is not needed. The equipment 27 can be lowered onto the texas deck 28 by means of a crane available on the deck 5. Various embodiments are possible for the holding connection 24, for example a lifting hook, or a clamping mechanism, or a plate connection etc.

    [0087] By providing the handling system 12, non-drilling operations such as servicing, maintenance, well intervention, work over etc. may be performed independent of the drilling operations. The drilling operations therefore do not need to be interrupted when such operations are being performed. Simultaneous operations to the drilling operations may become possible. This may provide for a more safe work environment as well as a more efficient use of the drilling installation. Eventually, the time the jack-up drilling installation 1 may be required for a specific well platform may be reduced.

    [0088] The handling element 13 is horizontally movable to provide an optimal reach over the well platform and to position handling element 13 above a determined well head in order to be able to perform independent operations on that well. Advantageously, the reach of handling element 13 is larger than the moonpool area 10 to cover as much well heads on the well platform 18 as possible.

    [0089] By providing a horizontally movable handling element 13 and/or handling system 12, the handling system 12 may be stored underneath the cantilever, or may be operable underneath the cantilever. Alternative embodiments such as a segmented beam, or a knuckle beam, or a drivable carriage are shown in FIG. 3, 5, 6, 7 or 8.

    [0090] FIG. 2 shows a more detailed perspective view of the handling system 12 mounted to a lateral side of the cantilever 17, for example a starboard side or a port side, or an aft side. An advantage of mounting the handling system to the port or starboard side of the cantilever 17 may be that, when retracting the cantilever, the handling system 12 can come above the deck 5. There, the handling system 12 may disconnected from the cantilever 17 for storage on deck 5 or for maintenance.

    [0091] Here, the handling system 12 is embodied as a segmented beam 20 having a first arm 14 and a second arm 15 that are hingedly connected to each other such that the handling element 13 at the free end 12b is movable in a horizontal plane. Here, the segmented beam 20 comprises two hingedly connected arms, but may also comprise three or more hingedly connected arms. Also, the handling system 12 may be a hybrid structure comprising of hingedly connected arms of which one arm may be embodied as a telescopic beam. The hinge joint may be provided by slewing gears or may be actuated by hydraulic cylinders.

    [0092] In the embodiment of FIG. 2, the holding connection 24 of the handling element 13 is connected to a well intervention stack 27 that is positioned on the texas deck 28 for being hoisted to the platform 18. For positioning the equipment 27 onto the platform 18, it is advantageous that the handling system 12 is adjustable in the Z-direction and/or that lifting capacity is available on the handling system 12. The arms 14, 15 may be movable in the XY-plane to position the handling element 12 holding e.g. the well intervention stack or guiding e.g. the wireline to a position in accordance with the determined well, e.g. the well head of the well to be serviced or on which well intervention operations are to be performed. This position can be a position above the determined well head. Then, to lower the well intervention stack towards the well head, it is advantageous that the handling system 12 is adjustable in the Z-direction. By then adjusting the vertical position of the handling system 12, for example by means of hydraulic cylinders, the well intervention stack, or similar equipment, can be lowered and placed onto the well platform 18. Two hydraulic cylinders 29 are connected to the connection arm 22 to adjust the height of the connection arm 22 with respect to the cantilever 17. As such, the vertical position of the handling system 12 may be adjusted in a range provided by the strokes of the hydraulic cylinders 29. To guide the vertical movement of the connection arm 22, two brackets 30, here sliding bushes 30, are provided. In an embodiment, the lifting capacity may be provided by the hydraulic cylinders 29 as well. In another embodiment, a hoisting cable running over sheaves on or through the handling system 12 may be provided. The sliding bushes 30 may also provide for relative easy disconnection of the connection arm 22 and the handling system 12 with the cantilever 17. As such, the handling system 12 can be disconnected from the cantilever 17 and stored on the deck 5, for example during sailing and/or towing of the jack-up platform 1, or for maintenance purposes on the handling system 12.

    [0093] For example, the well intervention stack 27 may be connected to the lifting hook 24 of the handling element 13 and may then, by movement of the handling element 13 in the horizontal XY-plane be positioned above the determined wellhead 19 of the well jacket 18. Then, the hydraulic cylinders 29 may be operated to lower the connection arm 22 and thus the handling system 12 with the connected equipment 27 towards the well jacket 18.

    [0094] FIG. 3 shows the handling system 12 in a storage position at a lateral side of the cantilever 17. The handling system 12 is here too embodied as a segmented beam having a first beam 14 with the handling element 13 at its end and a second beam 15 connectable to the cantilever 17 via the slewing bearing 21 and the connection arm 22. The beams 14 and 15 are hingedly connected to each other via a slewing gear, but other hinge joints may be provided as well. Alternatively, the rotational movement between the two beams may be activated by hydraulic cylinders. The two cylinders 29 that are connected to the connection arm 22 may provide for vertical adjustment of the handling system 12 over the stroke of the cylinders. Alternatively and/or additionally, lifting capacity may be provided by the cylinders 29 and/or by a hoisting system 31 comprising a hoisting cable 32 running from winch 33a over sheaves 33b on the handling system 12. In this embodiment, the banana sheave 23 for guiding wires and/or cabling from a reel on the deck 5 to the well platform is adjustable by means of displacement mechanism 34, here cylinders 34.

    [0095] FIG. 4 shows the handling system 13 connected to the aft side 17d of the cantilever 17. The lifting capacity for lifting the equipment 27 is in this embodiment as well provided by a hoisting cable 32 running from winch 33a over sheaves 33b. Here, the handling element 13, the lifting connection 24 and/or the banana sheave 23, is horizontally extendible together with the first beam 14 and the second beam 15 of the handling system 12 when the handling system 12 is operated to bring the equipment to the determined position. Once at the determined position, the equipment 27, here together with the lifting connection 24 is lowered to the well platform 18 by means of the hoisting system 31. By using the hoisting system 31, not the whole handling system 12 is vertically adjustable, but only the handling element 13. Typically, the positioning in the XY-plane may be done first, then the height in vertical direction may be adjusted when required. To enable independent operations, such as well intervention operations, a guide element 23 for guiding the wireline 25 from the reel 26 may be sufficient. Then, positioning of the handling element 13, and thus of the handling system 12, in the horizontal XY-plane, may allow for providing a relatively large reach over the well platform 18.

    [0096] FIGS. 5a and 5b give an alternative embodiment of a handling system 12 at the aft side 17d. Here, the handling system 12 comprises a first beam 14 and a second beam 15 hingedly connected to each other by which the hinge joint is actuated with a hydraulic cylinder 38.

    [0097] FIGS. 6a and 6b and FIGS. 7a and 7b show alternative embodiments of a handling system 12 mounted to the bottom side 17f the cantilever 17. The handling system 12 is provided as a carriage 39, that is movable over a ring-shaped rail 35. The rail 35 is arranged around the moonpool 10 so that operations through the moonpool 10 do not have to be interrupted. The carriage 39 is movable over the rail, and as such movable in a XY plane below the cantilever 17. In the embodiment of FIGS. 6a and 6b, carriage 39 is provided with an extension arm 40, e.g radially movable with respect to the carriage 39, extending the reach of the handling system 12 Further, a hoisting system 31 with sheaves 33 can be provided mounted onto the carriage for hoisting equipment. The handling element 12 may be provided at an end of the extension arm 40, as in FIG. 6a, or may be provided on the carriage 39. Alternative to a ring-shaped rail an XY-skidding system 36 may be provided configured around the moonpool 10, as embodied in FIGS. 8a and 8b. The handling element 13 can thus be positioned at determined positions reachable by the XY-skidding system.

    [0098] FIG. 9 shows an alternative embodiment of the handling system 13, mounted to the aft end of the cantilever 17. The handling system 13 is here a segmented beam 20 having a first arm 14 and a second arm 15 hingedly connected to each other and actuatable with respect to each other by means of cylinders. The first arm 14 is here embodied as a bend beam which may allow for a relatively larger reach than with a straight first arm. The handling system 12 is via a slewing gear 21 and a connection arm 22 connected to the cantilever 17.

    [0099] FIG. 11 shows an alternative embodiment of a handling system 12 mounted to a lateral side 17b of the cantilever 17. The handling system 12 here comprises an upwardly extending connection arm 22. At a lower end of the connection arm 22, a horizontally extendible arm 20 is connected to the connection arm 22. The horizontally extendible 20 is here connected via a slewing gear 21 to the connection arm 22, providing for 360 degrees of reach of the arm 20. The horizontally extendible arm 20 is here embodied as segmented beam 20 having a fore arm or first arm 14 and a base arm or second arm 15. At a free end 12b of the arm 20 is the handling element 13 provided. The handling system 12 further comprises a support structure 43 to which the connection arm 22 is mounted. The support structure 43 is mounted to the lateral side 17b of the cantilever. The support structure 43 comprises brackets 30 for guiding the connection arm 22. Adjacent the connection arm, and along the base arm 15 and fore arm 14, a stairway 45a and a walking bridge 45b is provided to allow workmen to access the handling system 12.

    [0100] Here, the handling system 12 is mounted at a fixed position to the cantilever, i.e. the support structure 43 is fixedly connected to the cantilever 17. Alternatively, the support structure 43 can be horizontally extendible with respect to the cantilever 17, e.g. the support structure may be translatable over rails or tracks mounted to the cantilever. As such, the horizontal reach of the arm 20 may be extended and/or the handling system 12 may be additionally used to handle equipment to/from the main deck and well bay jacket.

    [0101] In this embodiment, the connection arm 22 is vertically movable with respect to the support structure 43 and to allow for sliding movement of the connection arm, or pedestal, within the brackets, the brackets 30 can be embodied as sliding bushes 30. To provide for the vertical displacement of the connection arm 22 and horizontal arm 20, a rack-and-pinion displacement mechanism 44 can be provided, as shown in FIG. 13a.

    [0102] FIG. 12 shows the connection arm 22 and the horizontal arm 20 disconnected from the support structure 43. Here, this is provided by opening the brackets 30. In the closed position of the brackets 30, the connection arm 22 is received and can be guided in the brackets 30. In the open position of the brackets 30, the connection arm 22 can be removed from the support structure. By providing the removable connection arm 22 and/or horizontal arm 20, this may facilitate maintenance and/or storage of the handling system during non-use of the handling system, e.g. to improve combined load characteristics of the cantilever or clearance to topside structures. The handling system 12 may then be stored e.g. on a temporary frame 46 on the deck 5.

    [0103] FIG. 13a shows the rack-and-pinion displacement mechanism 44, comprising a rack 44a and pinions 44b. The rack 44a is here part of the support structure 43, whereas the pinions 44b are provided on the connection arm 22. The rack 44a may for example extend over approximately the height of the cantilever 17. By providing the rack-and-pinion displacement mechanism 44 the vertical displacement reach of the handling element 13 may become larger giving the handling system 12 more possibilities for handling equipment and performing operations. In this embodiment, the support structure 43 with brackets 30 receive the connection arm 22 and the connection arm 22 is adjustable with respect to the support structure 43.

    [0104] In the embodiment of FIG. 13a, the handling element 13 here comprises a first handling part 13a for holding a wireline 48 and a second handling part 13b for holding a wireline stack. This is shown in more detail in FIG. 13b. In FIG. 13b, for reasons of simplicity, only the support structure 43 with the brackets 30 and the connection arm 22 is shown. The first and second arms 14, 15 of the segmented arm 20 are only schematically shown. The wireline 48 is guided through the connection arm 22, which is shown in more detail in FIG. 14. Then, the wireline 48 is guided along or through the arms 15, 14 of the horizontally extendible arm 20. Thereto, sheaves or rollers 58a, 58b, 58c are provided. The first handling part 13a of the handling element 13 is here embodied as a sheave for guiding the wireline 48. The second handling part 13b of the handling element 13 is here embodied as a hoist element for holding second equipment, such as a wireline stack. The hoist element can be a hook, or a ring, or a specific structure to connect the wireline stack to the hoisting line or lines. It is also possible to provide for a hook or a ring or another specific connection per hoisting line. As such, the handling element is dedicated for a determined operation, here a wireline operation. Also shown in FIGS. 13a and 13b is that the handling system 12 is provided with a further handling element 13ii, here a hoist block. So, multiple handling elements 13 may be provided, wherein each handling element may be dedicated for a determined operation. Alternatively, the handling elements or parts thereof may be exchangeable depending on the operation to be performed.

    [0105] A wireline stack or wireline rig-up consists of a tool string composed of for example a stuffing box on top, a lubricator and a blow out preventer. For wireline operations, the lower end of the wireline rig-up is connected to the well head or X-mas tree, wireline is guided into the rig-up from the guiding sheave 13a and runs through the rig-up into the drill pipe. Here, the rig-up second handling part 13b is provided with a dual hoist line/cable 57 running on a dual drum 47. The two hoist cables 57 can be connected to an outer edge of a top side of the rig-up and can be lifted and lowered by the dual drum 47. The first handling part, sheave 13a, guiding the wireline 48, is positioned between these cables 58, and as such, the wireline can be guided relatively easy to the center of an entrance of the wireline rig-up. Thus, the wireline rig-up can be held under approximately constant tension during wireline operations, which is advantageous, as such a wireline rig-up typically collapses under its own weight, so by tensioning it with a hoist line provided on the handling system, additional hoisting activity and use of additional equipment can be obviated. Also, the wireline rig-up can be pulled up and held closely to the first handling part guiding the wireline, which saves space compared to normal wireline operations.

    [0106] The dual drum winch 47 is here provided near a knuckle of the knuckle beam. The further handling element 13ii, is here embodied as a hoisting block, suitable for loads such as a container, X-mas tree or well intervention stack, with a hoisting line 58 running on a winch or drum 59.

    [0107] As shown in FIG. 13c, the handling element 13 is here configured for specific well intervention operations like coiled tubing. Such a handling element 13 comprises a guiding arch and/or a mechanism for holding a well intervention stack or coiled tubing unit 27. The handling element 13 here is provided with clamping elements that clamp around a holding block of the coiled tubing unit 27. The handling system can be arranged with at least one handling element and can be arranged with handling elements suitable for different operations, e.g. a handling element suitable for wireline operations as well as a handling element suitable for coiled tubing.

    [0108] Advantageously, a wireline 48 is guided through the handling system 12, as shown in FIG. 14. The wireline reel 49 is here mounted on the lateral side 17b of the cantilever 17. The wireline 48 is guided through the connection arm 22 and is then guided along the horizontal arm 20 until it reaches the handling element 13 to be guided into a drill pipe through the wireline rig-up and well head. By routing the wireline internally in and along the handling system 12, forces on the wireline can be reduced and the wireline can be more protected from external influences, which may improve the lifetime of the wireline.

    [0109] FIG. 15a shows another embodiment of a rack-and-pinion displacement mechanism 44. In the embodiment of FIG. 12, the vertical displacement is although relatively large, nevertheless limited by the position of the fixed brackets 30. Here, in the embodiment of FIG. 15a, the brackets 30 are connected to the connection arm 22 and the brackets 30 are provided with the pinions that are displaceable over a rack of the support structure 43. The brackets 30, as part of the support structure 43, now form a carriage 50 in which the connection arm 22 is received for supporting the connection arm 22. By displacing the carriage 50 along the rack, the connection arm 22 and the horizontal arm 20 also move along. Thus, the vertical displacement reach of the handling system 12 may be increased. Even, now equipment such as container can be lifted and taken on board of the drilling installation 1 e.g. during retracting of the cantilever. Also in this embodiment, the brackets 30 can be adjusted to the open position to allow the connection arm 22 to be removable from the support structure 43 for storage and/or maintenance purposes. Alternatively, only the horizontal arm may be disconnected, at the slewing gear, from the connection arm. By disconnecting the connection arm and/or horizontal arm, the combined load characteristics of the cantilever may be improved in some situations. Also, in certain situations, the clearance to the deck may be improved. The connection arm or pedestal 22 is top-mounted to the side of the cantilever 17, and the boom or horizontal arm 20 can slew 360° around the lower end of the pedestal. A top view of the support structure 43 with brackets 30 and connection arm 22 is shown in FIG. 15b. The pinions 44b are connected to the brackets 30 and are movable with respect to the rack 44a. The rack 44a is on the fixedly mounted part of the support structure 43, whereas the brackets 30 form the movable part of the support structure 43 receiving the connection arm 22. The fixedly mounted part of the support structure 43 comprises at least a U-shaped guide 60, wherein the rack 44a is provided on one leg of the U-shape. Between the legs of the U-shaped guide rollers 61 and 62 are provided to center the carriage 50 with the pinions 44b onto the racks 44a during displacement and to transfer loads to/from the support structure 43. The pinions 44a can be driven by any suitable driving source, e.g. electrical motor, hydraulic drive etc.

    [0110] Instead of a rack-and-pinion displacement mechanism, a winch for hoisting the connection arm vertically along the support structure 43 may be provided, or the already mentioned hydraulic cylinders.

    [0111] The guide 60 can have various embodiment, such as T-shaped with three rail enclosing wheels per set or U-shaped rail with two wheels enclosed by the rails, as in FIG. 15b. The front side wall of each U-shaped vertical guide is provided with a rack to interact with one of the pinions. Alternatively and in case of a T-shaped rail, a central rack can be attached to the support structure 43 to interact with at least one pinion which is mounted to the brackets 30 or carriage 50 or the connection arm 22.

    [0112] FIG. 16a shows a sequence for handling of material from below the cantilever 17 to the main deck 5. In FIG. 16a, drilling operations are being performed from the drilling floor and the handling system 12 is performing, simultaneous to the drilling operations, the handling of a load 63 underneath the cantilever 17. The horizontally movable arm 20, for example, a segmented beam 20, is pivoted in a horizontal XY-plane until the load 63 is directed towards the drilling installation 1 as shown in FIG. 16b, preferably the arm 20 is aside the cantilever 17. Then, shown in FIG. 16c, the handling system 12 is moved vertically upwards, until the load 63 receives sufficient clearance with the main deck 5. Here, the connection arm 22 is moved vertically up with respect to the support structure 43 and the brackets 30. Further, the arm 20 can extend until the load 63 reaches above the main deck 5 as shown in FIG. 16c. Horizontal arm 20 can be moved and stretched out such that the arm 20 reaches over the main deck 5. A container or other equipment 63 can placed on deck 5 by lowering arm 20, via the vertical displacement mechanism 34, or by using the hoist of the handling element 13. This operational sequence can be performed independent of the operations on the drilling floor, and the operations on the drilling floor do not need to be interrupted for handling material or equipment between the jacket and the main deck 5. By using the handling system 12 for this equipment handling, main deck crane activity can be reduced.

    [0113] FIG. 17 gives an alternative to the step of FIG. 16c. Here, the cantilever 17 is being retracted to a position substantially above the main deck 5. During retraction, the arm 20 of the handling system 12 is aside the cantilever 17 and is being moved vertically upward until the load 63 has sufficient free space above the deck 5 and obstacles. As such, the handling system 12 can be used to take additional equipment during retraction of the cantilever, by which, again, main deck crane activity may be reduced.

    [0114] Alternatives are possible to extend the vertical displacement of the handling system 12. For example, the rack on which the pedestal or connection arm can be displaced can be extended to above or below. In another example the boom or arm segment(s) can be pivotable in a vertical plane, e.g. while positioned alongside the cantilever. Thereto, horizontal hinge(s) and suitable actuators can be provided. In another example, the boom fore arm may be equipped with an additional arm segment which is pivotable in the vertical plane around a horizontal hinge and then can be tilted up by any type of suitable actuator.

    [0115] For the purpose of clarity and a concise description, features are described herein as part of the same or separate embodiments, however, it will be appreciated that the scope of the invention may include embodiments having combinations of all or some of the features described. It may be understood that the embodiments shown have the same or similar components, apart from where they are described as being different.

    [0116] For example, it may be understood that the handling system as described above may have various embodiments as well as combinations of elements of these embodiments. Also, it may be understood that the handling system may be positioned at a lateral side or at an aft side or at a bottom side of the cantilever, irrespective of the embodiment of the handling system.

    [0117] Other aspects of the embodiments are a drilling installation comprising a derrick and a drilling floor for performing drilling operations, wherein the drilling floor is on a cantilever extendible outside of the drilling installation and the derrick is positioned over the drilling floor; further comprising an independent operations handling system arranged for handling equipment underneath the cantilever independent of the drilling operations on the drilling floor; wherein the independent operations handling system comprises a handling element for cooperation with the equipment to be handled; wherein the handling element is movable in a XY-plane underneath the cantilever.

    [0118] In another aspect, the handling system comprises a horizontally extendible arm with the handling element at a free end of the arm.

    [0119] In a further aspect, the handling element is configured for guiding equipment such as a wireline and/or coiled tubing, for example as a banana sheave.

    [0120] As another aspect, the handling element is configured for holding equipment, such as a well intervention stack, a blow-out-preventer and/or a X-mas-tree, for example as a lifting hook or a clamping mechanism.

    [0121] In another embodiment, the handling system and/or the handling element further is arranged for movement in the Z-direction.

    [0122] In a further embodiment, the handling system further is provided with hoisting means.

    [0123] In another embodiment, the handling system is mounted to a bottom side and/or a lateral side of the cantilever.

    [0124] In a further embodiment, the drilling installation comprises a reel on the deck of the drilling installation facing the handling system, wherein the reel is arranged for comprising equipment such as a wireline or coiled tubing to be handled by the handling system or further comprises an equipment station at a side of the drilling installation facing the handling system, for example configured as a foldable texas deck.

    [0125] In another example, the handling system is removable connected to the cantilever for storage on the drilling installation during non-use of the handling system.

    [0126] Another aspect is the cantilever for mounting on a drilling installation, wherein the cantilever is provided with a handling system at a lower end thereof for handling equipment independent of drilling operations, wherein the handling system comprises a handling element that is arranged for movement in a XY-plane underneath the cantilever.

    [0127] Another aspect is the handling system configured for mounting to a cantilever for handling equipment underneath the cantilever, comprising a handling element for cooperation with the equipment, wherein the handling element is arranged for movement in a XY-plane.

    [0128] In another embodiment, the handling system comprises a segmented beam extending in the XY-plane, wherein the handling element is arranged on a free end of the segmented beam.

    [0129] In a further embodiment, an end of the segmented beam opposite of the free end is connectable to the cantilever.

    [0130] In yet a further embodiment, the connectable end is adjustable with respect to the cantilever in a Z-direction transverse to the XY-plane.

    [0131] In a yet another embodiment, the handling system is disconnectedly mountable to the cantilever.

    [0132] A further aspect is a method for performing operations on wells independent of drilling operations on a drilling installation with a cantilever extendible outside of the drilling installation, comprising providing a handling system for handling equipment to perform the independent operations, wherein the handling system comprises a handling element for cooperation with the equipment, moving the handling element in an XY-plane underneath the cantilever to a position in accordance with a determined well head and/or further moving the handling system and/or the handling element in a Z-direction downwards for lowering equipment, such as a well intervention stack or a blowout preventer to the determined well head.

    [0133] In the claims, any reference signs placed between parentheses shall not be construed as limiting the claim. The word ‘comprising’ does not exclude the presence of other features or steps than those listed in a claim. Furthermore, the words ‘a’ and ‘an’ shall not be construed as limited to ‘only one’, but instead are used to mean ‘at least one’, and do not exclude a plurality. The mere fact that certain measures are recited in mutually different claims does not indicate that a combination of these measures cannot be used to an advantage.

    [0134] Many variants will be apparent to the person skilled in the art. All variants are understood to be comprised within the scope of the invention defined in the following claims.