METHOD AND SYSTEM FOR COMPUTING A TRANSITION PARAMETER OF A LIQUEFIED GAS STORAGE MEDIUM
20230098469 · 2023-03-30
Assignee
Inventors
Cpc classification
F17C2205/0332
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2250/0694
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2265/031
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2250/0413
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2250/0426
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2201/0157
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2201/052
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2250/0408
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2265/066
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2270/0105
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2250/0473
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C13/028
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2250/0626
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2250/0443
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C13/02
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2250/043
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C13/026
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
Y02E60/32
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
F17C2250/0636
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2250/0452
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2223/033
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2250/0673
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2260/021
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2250/0447
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2250/032
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2250/0417
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2260/02
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2250/0439
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C13/025
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2223/0161
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2250/0491
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2221/033
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
International classification
Abstract
The present invention relates to a computer-implemented method and system for computing a transition parameter of a liquefied gas storage medium, the storage medium having at least one sealed and unrefrigerated tank, the transition parameter characterizing an evolution of a two-phase mixture contained in the sealed and unrefrigerated tank between an initial state and a final state, the two-phase mixture including a liquid phase and a vapour phase, the transition parameter may be a duration of the transition, a liquid bleeding rate or a vapour bleeding rate.
Claims
1: A computer-implemented method for computing a transition parameter of a liquefied gas storage medium, the storage medium comprising at least one sealed and unrefrigerated tank (2, 4, 5, 6, 7 or 11) equipped with a safety valve (20), the transition parameter characterizing an evolution of a two-phase mixture (13) contained in the sealed and unrefrigerated tank between an initial state (8) and a final state (9), the two-phase mixture including a liquid phase and a vapour phase, wherein said transition parameter is selected in a group consisting of a duration of the transition τ, a liquid bleeding rate {dot over (m)}.sub.l or a vapour bleeding rate {dot over (m)}.sub.v, the method comprising the steps of: determining, for the liquid phase and the vapour phase in the initial state (8), initial mass densities ρ.sub.l,i and ρ.sub.v,i, and initial internal mass energies U.sub.l,i and U.sub.v,i on the basis of an initial liquid phase temperature T.sub.l,i, an initial vapour phase temperature T.sub.v,i, an initial vapour phase pressure P.sub.i, an initial liquid phase volume V.sub.l,i and an initial liquid phase composition x.sub.l,i; determining, for the liquid phase and the vapour phase in the final state (9), final mass densities ρ.sub.l,f and ρ.sub.v,f, final internal mass energies U.sub.l,f and U.sub.v,f, and final mass enthalpies H.sub.l,f and H.sub.v,f on the basis of an equation of state and a final vapour phase pressure P.sub.f, the final pressure of the vapour phase P.sub.f being less than or equal to the setting pressure of the safety valve (20) and greater than or equal to the initial pressure of the vapour phase P.sub.i; computing the transition parameter using the following equation:
τ({dot over (Q)}+{dot over (m)}.sub.v(H.sub.v,f−Ū)+{dot over (m)}.sub.l(H.sub.l,f−Ū))=ρ.sub.l,iV.sub.l,i(Ū−U.sub.l,i)+ρ.sub.v,i(V.sub.t−V.sub.l,i)(Ū−U.sub.v,i)+ρ.sub.v,fV.sub.t(U.sub.v,f−Ū) in which {dot over (Q)} corresponds to an energy contribution by heat ingress through the walls of a tank per unit of time, V.sub.t corresponds to a total volume of the tank and with
2: A computer-implemented method for computing a transition parameter of a liquefied gas storage medium, the storage medium comprising at least one sealed and unrefrigerated tank (2, 4, 5, 6, 7 or 11) equipped with a vacuum breaker valve (21), the transition parameter characterizing an evolution of a two-phase mixture (13) contained in the sealed and unrefrigerated tank between an initial state (8) and a final state (9), the two-phase mixture including a liquid phase and a vapour phase, wherein said transition parameter is selected in a group consisting of a duration of the transition τ, a liquid bleeding rate {dot over (m)}.sub.l or a vapour bleeding rate {dot over (m)}.sub.v, the method comprising the steps of: determining, for the liquid phase and the vapour phase in the initial state (8), initial mass densities ρ.sub.l,i and ρ.sub.v,i, and initial internal mass energies U.sub.l,i and U.sub.v,i on the basis of an initial liquid phase temperature T.sub.l,i, an initial vapour phase temperature T.sub.v,i, an initial vapour phase pressure P.sub.i, an initial liquid phase volume V.sub.l,i and an initial liquid phase composition x.sub.l,i; determining, for the liquid phase and the vapour phase in the final state (9), final mass densities μ.sub.l,f and ρ.sub.v,f, final internal mass energies U.sub.l,f and U.sub.v,f, and final mass enthalpies H.sub.l,f and H.sub.v,f on the basis of an equation of state and a final vapour phase pressure P.sub.f, the final pressure of the vapour phase P.sub.f is greater than or equal to the setting pressure of the vacuum breaker valve (21) and less than or equal to the initial pressure of the vapour phase P.sub.i; computing the transition parameter using the following equation:
τ({dot over (Q)}+{dot over (m)}.sub.v(H.sub.v,f−Ū)+{dot over (m)}.sub.l(H.sub.l,f−Ū))=ρ.sub.l,iV.sub.l,i(Ū−U.sub.l,i)+ρ.sub.v,i(V.sub.t−V.sub.l,i)(Ū−U.sub.v,i)+ρ.sub.v,fV.sub.t(U.sub.v,f−Ū) in which {dot over (Q)} corresponds to an energy contribution by heat ingress through the walls of a tank per unit of time, V.sub.t corresponds to a total volume of the tank and with
3: The method according to claim 1, wherein the storage medium comprises a plurality of tanks (2, 4, 5, 6, 7 and 11) and, for the liquid phase and the vapour phase, the initial and final mass densities, the initial and final internal mass energies and the final mass enthalpies are determined for each tank, and wherein the transition parameter is computed using the following equation:
τ({dot over (Q)}.sub.j+Σ{dot over (m)}.sub.v,j(H.sub.v,f,j−Ū.sub.j)+Σ{dot over (m)}.sub.l,j(H.sub.l,f,j−Ū.sub.j))=Σρ.sub.l,i,jV.sub.l,i,j(Ū.sub.J−U.sub.l,i,j)+Σρ.sub.v,i,j(V.sub.t,j−V.sub.l,i,j)(Ū.sub.J−U.sub.v,i,j)+Σρ.sub.v,f,jV.sub.t,j(U.sub.v,f,j−Ū.sub.J) where the exponent j refers to the index of the considered tank.
4: The method according to claim 1, wherein the transition parameter is the transition duration τ, and wherein the vapour bleeding rate {dot over (m)}.sub.v and the liquid bleeding rate {dot over (m)}.sub.l are predetermined.
5: The method according to claim 1, wherein the transition parameter is the vapour bleeding rate {dot over (m)}.sub.v, and wherein the liquid bleeding rate {dot over (m)}.sub.l, and the duration of the transition are predetermined.
6: The method according to claim 1, wherein the transition parameter is the liquid bleeding rate {dot over (m)}.sub.l, and wherein the vapour bleeding rate {dot over (m)}.sub.v and the duration of the transition are predetermined.
7: The method according to claim 1, wherein the storage medium comprises at least one level sensor (14) configured to determine the volume of the liquid phase in at least one sealed and unrefrigerated tank (2, 4, 5, 6, 7 or 11), and the initial volume of the liquid phase V.sub.l,i is determined by the level sensor 14.
8: The method according to claim 1, wherein the storage medium comprises at least one temperature sensor (151 or 152) configured to measure the temperature of the vapour phase and at least one temperature sensor (153, 154 or 155) configured to measure the temperature of the liquid phase in at least one sealed and unrefrigerated tank (2, 4, 5, 6, 7 or 11), and the initial temperature of the vapour phase T.sub.v,i and the initial temperature of the liquid phase T.sub.l,i are measured by the temperature sensors (151 to 155).
9: The method according to claim 1, wherein the storage medium comprises at least one pressure sensor (16) configured to measure the pressure of the vapour phase in at least one sealed and unrefrigerated tank (2, 4, 5, 6, 7 or 11), and the initial pressure of the vapour phase P.sub.i is measured by the pressure sensor (16).
10: The method according to claim 1, wherein the storage medium comprises at least one composition sensor (17) configured to determine the composition of the liquid phase in at least one sealed and unrefrigerated tank (2, 4, 5, 6, 7 or 11), and wherein the initial composition of the liquid phase x.sub.l,i is determined by the composition sensor.
11: The method according to claim 1, wherein the storage medium comprises at least one flow rate sensor configured to measure a vapour bleeding mass flow rate (18) or a liquid bleeding mass flow rate (19) exiting a sealed and unrefrigerated tank (2, 4, 5, 6, 7 or 11), and wherein the liquid bleeding mass flow rate {dot over (m)}.sub.l or the vapour bleeding mass flow rate {dot over (m)}.sub.v is determined by the flow rate sensor (18 or 19).
12: The method according to claim 1, wherein the two-phase mixture (13) is a combustible mixture.
13: The method according to claim 12, wherein the combustible mixture is selected from a list consisting of liquefied natural gas, liquefied petroleum gas and liquefied hydrogen.
14: The method according to claim 12, wherein the sealed and unrefrigerated tank is a fuel reservoir for propelling a land, marine, air or space vehicle.
15: A system (10) for computing a transition parameter of a liquefied gas storage medium characterizing an evolution of a two-phase mixture (13) between an initial state (8) and a final state (9), wherein the transition parameter is selected in a group consisting of a duration of the transition τ, a liquid bleeding rate {dot over (m)}.sub.l or a vapour bleeding rate {dot over (m)}.sub.v, the system comprising: a storage medium comprising at least one sealed and unrefrigerated tank (2, 4, 5, 6, 7 or 11) containing the two-phase mixture, said two-phase mixture including a liquid phase and a vapour phase; a computation device (22) configured to implement the method according to claim 1; a human-machine interface interacting with the computation device in order to notify an operator of the computed transition parameter.
16: Land, marine, air or space vehicle comprising a fuel reservoir for propelling the vehicle and a system according to claim 15 configured to compute a transition parameter of the fuel tank.
17: A non-transitory computer readable medium comprising program instructions that, when executed by an apparatus, cause the apparatus to perform the method according to claim 1.
Description
BRIEF DESCRIPTION OF THE FIGURES
[0035] The invention will be better understood, and further aims, details, features and advantages thereof will become more clearly apparent, throughout the following description of several particular embodiments of the invention, which are provided solely by way of a non-limiting illustration, with reference to the accompanying drawings.
[0036]
[0037]
[0038]
[0039]
[0040]
DESCRIPTION OF THE EMBODIMENTS
[0041] The following embodiments are described with respect to a motorized marine vehicle, a liquefied gas propelled tanker or vessel, comprising at least one sealed and unrefrigerated tank for transporting liquefied gas or acting as a reservoir for supplying the one or more engine(s) of the vehicle with liquefied gas.
[0042] The general shape of a sealed and unrefrigerated tank can assume different types: polyhedral (for example, prismatic), cylindrical, spherical or other geometries are possible. The unrefrigerated tank can have a single or double sealing membrane. The sealing membranes are generally made of a thin stainless steel sheet or of Invar. A primary membrane is generally in direct contact with the liquefied gas at very low temperatures.
[0043]
[0044]
[0045] It is known that heat ingress through the walls of a sealed and unrefrigerated tank causes the temperature inside the tank to increase, leading to the evaporation of the liquefied gas contained therein and a corresponding increase in pressure in the gaseous ceiling.
[0046] In LNG tankers or LNG-propelled vessels, the evaporated gas (“Boil-Off Gas”, abbreviated to BOG) can be used to supply the main engines, which propel the ship, and the auxiliary engines, which generate on-board electricity. If the evaporated gas flow is greater than the consumption of the engines, the excess is directed to one or two boiler(s) or, if permitted by the regulatory conditions, is vented in order to curb the overpressure caused by the evaporation. Conversely, when the flow of evaporated gas is less than the consumption of the engines, LNG bleeding can be carried out. Forced evaporation of the bled liquefied gas (“Forcing Boil-Off Gas”, abbreviated to FBOG) then allows the difference in flow rates to be offset between natural evaporation and the consumption of the engines, which limits the depression of the gaseous ceiling contained in the tank 2, 4, 5, 6 or 7.
[0047] In order to avoid any dry losses by flaring or venting any excess gas evaporated in the event of overpressure, the operator must be able to know, in advance or in real-time, the transition parameters, namely the duration of the pressure variation τ, the vapour bleeding rate {dot over (m)}.sub.v and the liquid bleeding rate {dot over (m)}.sub.l, that characterize the thermodynamic behaviour of the LNG contained in the sealed and unrefrigerated tank 2, 4, 5, 6 or 7.
[0048]
[0049] According to a first embodiment, by knowing the temperatures, pressures, volumes and compositions of the liquefied gas and its vapour, in the initial state 8 and in the final state 9, all the physical properties of the two-phase mixture (mass densities, internal energies and enthalpies) can be determined.
[0050] In the initial state 8, for the liquid phase and the vapour phase, the computed data 82, namely the mass density ρ.sub.l,i and ρ.sub.v,i, and the internal mass energies U.sub.l,i and U.sub.v,i, are determined on the basis of the input data 81, that is the liquid phase temperature T.sub.l,i, the vapour phase temperature T.sub.v,i, the vapour phase pressure P.sub.i, the liquid phase volume V.sub.l,i and the liquid phase composition x.sub.l,i. The temperatures, the pressure and the volume can be measured by sensors or specified by the operator. The composition of the liquefied gas x.sub.l,i sets the composition of its vapour x.sub.v,i. In particular, if the liquefied gas is LNG, its composition x.sub.l,i is specified in the quality certificate and the bill of lading issued at the time of loading into the sealed and unrefrigerated tank 2, 4, 5, 6 or 7, or is measured using a composition sensor, or is even pre-computed using an “ageing” model of the LNG.
[0051] In the final state 9, the operator specifies the input data 91, that is the pressure of the vapour phase P.sub.f. The two-phase mixture is assumed to be in thermodynamic equilibrium and the liquefied gas is assumed to be at its bubble point. According to these assumptions, the pressure of the vapour phase P.sub.f sets both the temperature of the liquefied gas T.sub.l,f and the temperature of its vapour T.sub.v,f inside the tank, which are equal. The composition of the liquefied gas x.sub.l,f and the composition of its vapour x.sub.v,i are determined on the basis of an equation of state. In a preferred embodiment, this equation of state is the three-parameter cubic equation of state derived from the Redlich-Kwong-Peng-Robinson equation developed by Martin Cismondi and Jorgen Mollerup (in “Development and application of a three-parameter RK-PR equation of state”, Fluid Phase Equilibria, 232, 2005, pages 74-89). For the liquid and the vapour phase, the computed data 92, namely the mass densities ρ.sub.l,f and ρ.sub.v,f, the internal mass energies U.sub.l,f and U.sub.v,f, and the mass enthalpies H.sub.l,f and H.sub.v,f, are determined on the basis of the input data 91 specified by the operator.
[0052] As the two-phase mixture changes between the initial state 8 and the final state 9, the liquid bleeding rate {dot over (m)}.sub.l, the vapour bleeding rate {dot over (m)}.sub.v, and the contributed power by virtue of heat ingress through the walls of a tank {dot over (Q)} are assumed to be constant. The liquid and vapour bleeding rates can be measured by flow rate sensors or specified by the operator. The power {dot over (Q)} is determined on the basis of the Boil-Off Rate (BOR) of the tank, usually provided by the manufacturer. This parameter characterizes the thermal resistance of the tank insulation to any heat ingress. In a preferred embodiment, the BOR is corrected by taking into account the filling level of the tank.
[0053] Solving the system of conservation of mass and energy equations between the initial state 8 and the final state 9 allows the value of the desired transition parameter to be computed directly.
[0054] According to one embodiment, at set vapour {dot over (m)}.sub.v and liquid {dot over (m)}.sub.l bleeding rates, the operator specifies a final pressure P.sub.f above the initial pressure P.sub.i in order to compute a pressure build-up time T inside a sealed and unrefrigerated tank 2, 4, 5, 6 or 7. For example, when an LNG tanker or an LNG-propelled vessel is moored in a port area where the regulations stipulate shutting down the main and auxiliary engines (with the vessel then being supplied with onshore electricity), and prohibit flaring or venting of the evaporated LNG, the operator needs to know the time during which the vessel will be able to remain at the quayside while maintaining a pressure level that is acceptable for the operability of the tank.
[0055] According to an alternative embodiment, at set vapour {dot over (m)}.sub.v and liquid {dot over (m)}.sub.l bleeding rates, the operator specifies a final pressure P.sub.f below the initial pressure P.sub.i in order to compute a pressure drop time τ inside a sealed and unrefrigerated tank 2, 4, 5, 6 or 7. For example, when the engines of an LNG tanker or LNG-propelled vessel consume more than the flow of naturally evaporated gas, the operator needs to know how much time is available before liquid bleeding needs to be carried out in order to supply the engines and maintain the pressure at a level that is acceptable for the operability of the tank.
[0056] According to another embodiment, at a set transition duration τ and liquid bleeding rate {dot over (m)}.sub.l, the operator specifies the final pressure P.sub.f in order to compute the vapour bleeding rate {dot over (m)}.sub.v in a sealed and unrefrigerated tank 2, 4, 5, 6 or 7. For example, when the stopover time of an LNG tanker or LNG-propelled vessel is predetermined, the operator may need to know the vapour bleeding rate that should be applied in order to supply the auxiliary engines, which generate on-board electricity, while keeping the pressure at an acceptable value for the operability of the tank.
[0057]
[0058] According to one embodiment, the level sensor 14 for determining the volume of liquefied gas in the tank can be an electrical capacitance sensor, a float, a radar or a laser. In a preferred embodiment, the temperature sensors 151 to 155 can also fulfil this function.
[0059] According to one embodiment, the temperature sensors 151-155 are temperature probes, in general there are four or five probes, distributed over the entire height of the tank at known altitudes. In a preferred embodiment, the probes are installed such that at least one probe 153, 154 or 155 is immersed in the liquefied gas, and at least one probe 151 or 152 is located at the level of the vapour phase. Measuring the level of the liquefied gas in the tank allows the submerged probes and the probes located in the vapour phase to be identified based on the known altitude of each probe. When several probes are immersed in the liquefied gas, the temperature measurements are averaged in order to determine the initial temperature of the liquid phase T.sub.l,i. Similarly, when several probes are located in the vapour phase, the temperature measurements are averaged in order to determine the initial temperature of the vapour phase T.sub.v,i.
[0060] According to one embodiment, the pressure sensor 16 is a manometer measuring the manometric pressure of the gaseous phase in the tank. The manometric pressure is then corrected by taking into account the atmospheric pressure in order to determine the initial pressure of the gaseous ceilng P.sub.i.
[0061] According to one embodiment, the composition sensor 17 is a gaseous phase chromatograph analyzing samples of re-evaporated liquefied gas in order to determine the initial composition of the liquid phase x.sub.l,i.
[0062] According to one embodiment, the flow rate sensors for measuring vapour bleeding 18 are flow meters installed at the inlet of the boilers and engines supplied with gas. The flow rate sensor for measuring the flow rate of liquefied gas bleeding 19 is a flow meter located at the pump outlet. In a preferred embodiment, the flow meters are Coriolis effect mass flow meters.
[0063] In one embodiment, the tank comprises a safety valve 20 that opens automatically at its setting pressure. In the case of a tank containing LNG, the setting pressure is generally set to 700 mbarg or to 2 barg. For example, when the main engines of an LNG tanker or LNG-propelled vessel are shutdown, the consumption of the auxiliary engines is insufficient to compensate for the flow of evaporated gas, and the regulatory conditions prohibit the excess gas from being flared or vented, the operator needs to know the pressure build-up time T of the gaseous ceiling to the pressure for automatically opening the valve. In this case, the operator specifies a final vapour phase pressure P.sub.f that is less than or equal to the setting pressure of the safety valve 20 but is greater than or equal to the initial vapour phase pressure P.sub.i.
[0064] According to one embodiment, the tank comprises a vacuum breaker valve 21 that automatically opens at its setting pressure. In the case of a tank containing LNG, the setting pressure of the vacuum breaker valve is generally set to 20 mbarg or to 50 mbarg. For example, when the engines of an LNG tanker or an LNG-propelled vessel consume more than the flow rate of naturally evaporated gas, the operator needs to know the time of the pressure drop r from the gaseous ceiling to the pressure for automatically opening the vacuum breaker valve. In this case, the operator specifies a final vapour phase pressure P.sub.f that is greater than or equal to the setting pressure of the vacuum breaker valve 21 but is less than or equal to the initial vapour phase pressure P.sub.i.
[0065]
[0066] According to one embodiment, the operator specifies the final pressure P.sub.f and the input data specific to the two-phase mixture 13 are physical quantities measured by one or more level 14, temperature 151 to 155, pressure 16, composition 17 and flow rate 18 and 19 sensor(s). The measured physical quantities are conveyed to the operator via a human-machine interface interacting with the computation device 22.
[0067] As an alternative embodiment, the operator specifies the final pressure P.sub.f and all or some of the input data specific to the two-phase mixture 13, which are known (for example, the initial composition of the liquid phase x.sub.l,i at the time of loading the liquefied gas indicated in the quality certificate and the bill of lading) or have been precomputed (for example, the initial composition of the liquid phase x.sub.l,i determined from an ageing model of the liquefied gas).
[0068] Some of the elements that are shown, in particular the computation device 22, can be produced in various forms, in a unitary or distributed manner, by means of hardware and/or software components. Hardware components that can be used are specific ASICs, FPGAs or microprocessors. Software components can be written in various programming languages, for example, C, C++, Java or VHDL. This list is not exhaustive.
[0069] Although the invention has been described in relation to several particular embodiments, it is clear that it is by no means limited thereto and that it includes all the technical equivalents of the described means, as well as the combinations thereof if these fall within the scope of the invention.
[0070] The use of the verbs “comprise” or “include” and their conjugated forms does not exclude the presence of elements or steps other than those described in a claim.
[0071] In the claims, any reference sign between brackets must not be interpreted as being a limitation of the claim.