Method for producing containers, comprising a delayed boxing operation
09969118 ยท 2018-05-15
Assignee
Inventors
Cpc classification
B29C49/70
PERFORMING OPERATIONS; TRANSPORTING
B29C2049/7831
PERFORMING OPERATIONS; TRANSPORTING
B29C49/541
PERFORMING OPERATIONS; TRANSPORTING
B29C2049/4892
PERFORMING OPERATIONS; TRANSPORTING
B29C49/5612
PERFORMING OPERATIONS; TRANSPORTING
B29C2049/7832
PERFORMING OPERATIONS; TRANSPORTING
B29C2949/0715
PERFORMING OPERATIONS; TRANSPORTING
B29C49/78
PERFORMING OPERATIONS; TRANSPORTING
International classification
B29C49/78
PERFORMING OPERATIONS; TRANSPORTING
Abstract
A method for producing a container (2) from a blank (3) in a mold (1) provided with a wall (4) and a mold bottom (8) that is movable relative to the wall (4) between a retracted position and a deployed position, the method including: a phase of introducing the blank (3) into the mold; a preblowing phase including the injection, into the blank (3), of a fluid pressurized to a so-called preblowing pressure, a blowing phase following the preblowing phase and including the injection, into the blank (3), of a fluid pressurized to a so-called blowing pressure greater than the preblowing pressure; a boxing phase including the displacement of the mold bottom (8) from the retracted position thereof to the deployed position thereof, initiated after the pressure in the blank (3) has reached the blowing pressure.
Claims
1. A method for producing a container (2) from a blank (3) of plastic material, within a mold (1) provided with a wall (4) that defines a cavity (5) having the shape of the container (2), and with a mold base (8) that is mobile relative to the wall between a retracted position in which the mold base (8) extends retracted relative to the cavity (5), and a deployed position in which the mold base (8) closes the cavity (5), the method comprising: a phase for introduction of the blank (3) into the mold; a pre-blow-molding phase comprising the injection into the blank (3) of a fluid under pressure at a pre-blow-molding pressure; a blow-molding phase that is after the pre-blow-molding phase and that comprises the injection into the blank (3) of a fluid under pressure at a blow-molding pressure that is greater than the pre-blow-molding pressure; and a boxing phase comprising the movement of the mold base (8) from the retracted position to the deployed position, wherein the boxing phase (3) is initiated during the blow-molding phase after the pressure in the blank (3) has reached the blow-molding pressure.
2. The method according to claim 1, further comprising: an operation for ordering the opening of a boxing solenoid valve for the movement of the mold base (8), at a time t.sub.B1 such that:
t.sub.B1+t.sub.Bt.sub.S3 where: t.sub.B is the response time of the boxing solenoid valve, and t.sub.S3 is the time from which the pressure in the blank (3) has reached the blow-molding pressure.
3. The method according to claim 2, wherein the boxing phase is conducted in such a way that the mold base (8) reaches the deployed position at a time t.sub.B3 such that:
t.sub.B3t.sub.D2 where t.sub.D2 is a time from which an at least partial depressurization phase of the blank (3) begins after the blank is placed in communication with the atmosphere.
4. The method according to claim 3, wherein the depressurization phase comprises an operation for ordering the opening of a degassing solenoid valve for putting the blank (3) in communication with the atmosphere, at a time t.sub.D1 such that:
t.sub.D1+t.sub.Dt.sub.B3 where t.sub.D is the response time of the degassing solenoid valve.
5. The method according to claim 4, wherein the depressurization phase comprises a scavenging step during which are opened simultaneously the degassing solenoid valve and a scavenging solenoid valve for the injection into the container, by a stretching rod pierced with openings, of fluid at the blow-molding pressure.
6. The method according to claim 4, wherein the depressurization phase is preceded by an operation for closing a blow-molding solenoid valve, at a time t.sub.s4, and by an operation for opening a scavenging solenoid valve, at a time t.sub.BA1, such that:
t.sub.S3<t.sub.BA2<t.sub.S5<t.sub.D2 where:
t.sub.BA2=t.sub.BA1+t.sub.BA
t.sub.S5=t.sub.S4+t.sub.S
t.sub.B2=t.sub.D1+t.sub.D t.sub.BA is the response time of the scavenging solenoid valve, and t.sub.S is the response time of the blow-molding solenoid valve.
7. The method according to claim 5, wherein the depressurization phase further comprises a degassing step during which the degassing solenoid valve remains open while the scavenging solenoid valve is closed.
8. The method according to claim 7, wherein the boxing phase ends with the retraction of the mold base (8) from a high position to a low position, which is initiated at the end of the degassing step.
9. The method according to claim 8, wherein the retraction of the mold base (8) is initiated at either of a same time or after the degassing step is initiated.
10. The method according to claim 6, wherein the depressurization phase further comprises a degassing step during which the degassing solenoid valve remains open while the scavenging solenoid valve is closed.
11. The method according to claim 10, wherein the boxing phase ends with the retraction of the mold base (8) from a high position to a low position, which is initiated at the end of the degassing step.
12. The method according to claim 11, wherein the retraction of the mold base (8) is initiated at either of a same time or after the degassing step is initiated.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1) Other objects and advantages of the invention will emerge in light of the description given hereafter with reference to the accompanying drawings in which:
(2)
(3)
(4)
(5)
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
(6) Depicted in
(7) This mold 1 comprises a wall 4 that defines an inner cavity 5 distributed around a main axis 6 of the mold that, when the containers to be formed are rotationally symmetric, forms an axis of symmetry of the mold 1.
(8) The cavity 5 partially defines a shape for a lateral wall or body of the container 2. The wall 4 exhibits, in a lower part, an opening 7 that defines a passage for a mold base 8 that is mounted mobile relative to the wall 4 between a low position, shown in
(9) The blank 3, and then the container 2 formed from it, rest on an upper face 10 of the mold 1 by means of a collar 11 of the blank 3 (or of the container 2), which delimits a neck 12 of the blank 3 (or of the container 2), held outside of the mold 1.
(10) Under the collar 11, the blank 3 (then the container 2) has a body 13, which extends overall in the axial direction, and a base 14, which is first of all semi-spherical (
(11) To produce the container 2 from a blank 3, the procedure is as follows.
(12) The mold 1 being in its configuration shown in
(13) There is then introduced into the blank 3, through the neck 12, a stretching rod 15 that is mobile in the axial direction; as soon as the rod 15 reaches the base 14 of the blank 3, the pre-blow molding is initiated by injecting into the blank 3 a fluid (particularly air) at a pressure P1 for pre-blow molding (less than 15 bar, and, for example, on the order of 5 to 7 bar). According to a preferred embodiment, the rod 15 is hollow and pierced with holes that open into the cavity 5.
(14) The stretching speed and air flow are such that the rod 15 remains in contact with the base 14 of the blank 3 throughout the pre-blow molding.
(15) When the rod 15 reaches the mold base 8 by pressing the base 14 of the container there that is being formed (
(16) The pre-blow-molding pressure P1 is not sufficient to press the material thoroughly against the wall 4 of the mold 1, and it is necessary to inject into the container 2 being formed a blow-molding pressure P2 that is greater than the pre-blow-molding pressure P1 (in practice, the blow-molding pressure P2 is equal to or greater than 15 bar, and, for example, on the order of 20 to 30 bar).
(17) Then, a sudden rise of pressure is produced in the blank 3, until this pressure is equal to the blow-molding pressure P2. After a predetermined period of maintaining the blow-molding pressure P2 in the container 2 thus formed, it is depressurized in two steps.
(18) A first step consists in maintaining the injection into the container 2 of fluid at the blow-molding pressure P2 by means of the scavenging solenoid valve (the blow-molding solenoid valve being closed), while the container is put in communication with the atmosphere (i.e., open air).
(19) This step, known as scavenging, makes it possible to have the fluid circulate in the container 2 to set the material with it, while keeping it in contact with the wall 4 so as to heat-set it. The pressure in the container 2 undergoes a first rapid drop until stabilizing at an intermediate value P3 between the pre-blow-molding pressure P1 and the blow-molding pressure P2.
(20) A second step, known as degassing, consists in stopping the injection by the scavenging solenoid valve, while maintaining the communication of the container 2 with the atmosphere. The pressure in the container 2 then undergoes a second rapid drop until reaching atmospheric pressure.
(21) An operation of raising the mold base 8, known as boxing, is initiated during the blow-molding operation, so as to impart to the material of the base 14 a slight over-stretching that is conducive to the orientation of the molecules (and therefore to the rigidity) and to the taking of shape on the upper surface 9 of the mold base 8.
(22)
(23) The curves are synchronized on the time axis that is common to them, the vertical dotted lines making it possible to make a matching of the curves at certain selected times.
(24) The opening command of the pre-blow-molding solenoid valve is given at a time t.sub.P1 known as pre-blow-molding peak start. Since the pre-blow-molding solenoid valve is assigned a response time t.sub.P, the pressure P prevailing in the container 2 undergoes a rise from a time t.sub.P2 known as pre-blow-molding real start such that:
t.sub.P2=t.sub.P1+t.sub.P.
(25) Likewise, the opening command of the blow-molding solenoid valve is given at a time t.sub.S1 known as blow-molding peak start. Since the blow-molding solenoid valve is assigned a response time t.sub.S, the pressure P prevailing in the container 2 undergoes an inflection (abrupt rise) at a time t.sub.S2 known as blow-molding real start such that:
t.sub.S2=t.sub.S1+t.sub.S.
(26) The pressure P in the blank rises rapidly, from the time t.sub.S2 (where the pressure P is about equal to the value of the pre-blow-molding pressure P1), until reaching the value of the blow-molding pressure P2, which corresponds to the maximum value of the pressure prevailing in the container during the entire period of the forming. The time where the pressure P reaches the value of the blow-molding pressure P2, i.e., the time from which the value of the pressure P stops rising, is denoted t.sub.S3.
(27) The opening command of the boxing solenoid valve ordering the movement of the mold base 8 is given at a time t.sub.B1 known as boxing peak start. Since the boxing solenoid valve is assigned a response time t.sub.B, the movement of the mold base 8 from its low position starts at a time t.sub.B2 known as boxing real start such that:
t.sub.B2=t.sub.B1+t.sub.B.
(28) As we have already indicated, and as can be seen in
t.sub.B2t.sub.S3.
(29) Although it is conceivable, it is not necessarily satisfactory to order the boxing peak start t.sub.B2 after the time t.sub.S3 where the pressure P in the blank 3 reaches its maximum.
(30) It is actually preferable, in order to make a fine adjustment, to take into account the response time t.sub.B of the boxing solenoid valve, which is a fact that cannot be adjusted but is known and fixed (apart from the derivative of this response time t.sub.B, which can be compensated for).
(31) Thus, taking into account what precedes, in order to initiate the boxing after the time t.sub.S3, it is enough to adjust the boxing peak start t.sub.B1 so that:
t.sub.B1+t.sub.Bt.sub.S3.
(32) The beginning time of the depressurization phase of the blank 3, during which it is put in communication with the atmosphere, is denoted t.sub.D2. This time t.sub.D2 launches a scavenging step, during which the placing in open air and the injection of blow-molding fluid under pressure via the scavenging solenoid valve ensures circulation of fluid in the container 2, conducive to its cooling and to its taking of shape both on its body 13 and on its base 14. Earlier, as shown in
(33) The time at which the closing of the blow-molding solenoid valve is ordered is denoted t.sub.S4, and the time at which the blow-molding solenoid valve is actually closed after its closing order is denoted t.sub.S5:
t.sub.S5=t.sub.S4+t.sub.S.
(34) Moreover, the time at which the opening of the degassing solenoid valve is ordered for the placing in communication of the container with the atmosphere is denoted t.sub.D1. Since the degassing solenoid valve is assigned a response time t.sub.D, the degassing solenoid valve is ordered so that the time, denoted t.sub.D2, at which the depressurization in the container begins, is later than the time t.sub.S5:
t.sub.D2>t.sub.S5.
(35) When the scavenging is implemented, the scavenging solenoid valve order (assigned with a response time t.sub.BA) is implemented at a time t.sub.BA1 such that the opening of the scavenging solenoid valve is effective at a time t.sub.BA2 (where t.sub.BA2=t.sub.BA1+t.sub.BA) that is definitely later than the time t.sub.S3, but earlier than the time t.sub.S5, so as to maintain the pressure in the container before the depressurization is initiated:
t.sub.S3<t.sub.BA2
t.sub.BA2<t.sub.S5
(36) So that:
t.sub.S3<t.sub.BA2<t.sub.S5<t.sub.D2
(37) Once the depressurization has begun, the pressure in the container 2 drops rapidly until stabilizing at the intermediate value P3. The time from which the pressure P in the container 2 reaches the intermediate pressure P3 (known as scavenging pressure and depending on the value of the blow-molding pressure P2 and on the flow rates of the blow-molding and degassing solenoid valves) is denoted t.sub.D3.
(38) The closing of the scavenging solenoid valve is ordered at a time denoted t.sub.BA3. Taking into account the response time t.sub.BA of the scavenging solenoid valve, the fluid at the blow-molding pressure P2 ceases to be injected into the container 2 at a time denoted t.sub.BA4 such that:
t.sub.BA3+t.sub.BA=t.sub.BA4
(39) From this time t.sub.BA4, the degassing step starts during which the pressure P in the container 2 undergoes a new drop, reaching the atmospheric pressure and becoming stable at it.
(40) Moreover, the time where the mold base reaches its deployed position (i.e., its end of travel) is denoted t.sub.B3. According to a preferred embodiment, shown in
t.sub.B3t.sub.D2
(41) In other words, the boxing phase is completed at the latest at the end of the blow-molding phase (i.e., before the beginning of the degassing step at the time t.sub.D2). Taking into account the response time t.sub.D of the degassing solenoid valve, the time t.sub.D1 at which the opening of the degassing solenoid valve is ordered is selected such that:
t.sub.D2=t.sub.D1+t.sub.Dt.sub.B3.
(42) The boxing phase ends by the retraction of the mold base 8 from its high position to its low position. This retraction is ordered at a time denoted t.sub.B4 and initiated effectively from a time denoted t.sub.B5 such that:
t.sub.B4+t.sub.B=t.sub.B5
(43) This retraction is preferably initiated at the earliest at the end of the scavenging step, and optionally during the degassing. In other words, if the time from which the pressure in the container is equal to the atmospheric pressure is denoted t.sub.BA5:
t.sub.B5t.sub.BA5
(44) The pressure P in the container 2 having reached it maximum value (i.e., the blow-molding pressure P2) before the boxing is initiated, the forces being exerted on the mold base 8 in the container 2 and being opposed to the rise of the base 8 during the boxing do not increase during the boxing. Therefore, it is not necessary to increase the forces being exerted on the mold base 8 to continue its movement.
(45) Furthermore, since the abrupt increase phase of the pressure in the container has already been completed, the material of the blank 2 has essentially reached the mold base 8 (on the upper surface 9 of which it is kept centered by the rod 15), and the uncertainties of form linked to possible shifts of the material during the boxing phase are limited. The effect of this is a greater consistency in the quality of the containers produced.
(46) When the boxing is performed so as to ensure that the mold base 8 reaches its high position before the end of blow molding, the speed of movement of the mold base 8 is approximately constant during the entire boxing. This linearity is rendered by the movement curve of the mold base in
(47) The method that has just been described is not suited to all molds; it is suited, in particular, to a mold (such as the one shown in the accompanying drawings) in which the problems of the pinching of material between the wall of the mold and the mold base in low position or those problems due to a slight boxing travel relative to the needs that said form necessitates do not occur.