A METHOD OF INSTALLING A PILE BY MEANS OF A PILE GUIDE
20180106007 ยท 2018-04-19
Assignee
Inventors
Cpc classification
E02D7/14
FIXED CONSTRUCTIONS
E02D5/285
FIXED CONSTRUCTIONS
E02D27/52
FIXED CONSTRUCTIONS
International classification
Abstract
In a method of installing a pile in the sea bottom by means of a pile guide which has a frame and at least an upper and a lower pair of cooperating guide members, wherein the upper pair and the lower pair are located at a distance from each other in vertical direction. Each pair of guide members comprises a passive guide member and an active guide member. The passive guide members are moved to respective fixed initial guiding positions with respect to the frame and the active guide members are moved to the pile until the passive and the active guide members engage the pile, after which the pile is hold between the upper pair of guide members and between the lower pair of guide members during driving the pile into the sea bottom, during which the actual forces between the pile and the respective guide members are determined.
Claims
1. A method of installing a pile in the sea bottom by means of a pile guide having a frame and at least an upper and a lower pair of cooperating guide members, wherein the upper pair and the lower pair are located at a distance from each other in a vertical direction, wherein each pair of guide members comprises a passive guide member and an active guide member, the method comprising: moving each of the passive guide members and the active guide members towards the pile (P) after placing the pile between each of the pairs of guide members, wherein the passive guide members are moved to respective fixed initial guiding positions with respect to the frame and the active guide members are moved to the pile until the passive and the active guide members engage the pile; holding the pile between the upper pair of guide members and between the lower pair of guide members during driving the pile into the sea bottom, during which the actual forces between the pile and the respective guide members are determined.
2. The method according to claim 1, wherein during pile driving the active guide member of at least one pair of guide members is initially moved in a direction away from the pile if the actual forces at both the passive and active guide member of that pair increase without moving the passive guide member, but wherein the passive guide member of that pair is moved in a direction away from the pile if the actual force at the passive guide member remains above a certain level without increase of the actual force at the active member.
3. The method according to claim 1, wherein during pile driving at least two guide members are locked in their actual positions if an actual force at one of the guide members of the upper pair and an opposite actual force at one of the guide members of the lower pair both increase whereas the actual forces at the remaining guide members do not increase, wherein at least the guide members are locked where the respective actual forces increase.
4. The method according to claim 1, wherein during pile driving the method comprises: if the actual force at the active guide member of one of the pairs of guide members decreases, then the active guide member of that pair of guide members is moved in the direction of the pile, and if the actual force at the passive guide member of one of the pairs of guide members decreases, then the active guide member of that pair of guide members is moved in the direction of the pile, but if the actual force at the passive guide member of that pair of guide members remains below a predetermined level upon moving the active guide member of that pair of guide members in the direction of the pile, then the passive guide member of that pair of guide members is moved in the direction of the pile.
5. The method according to claim 1, wherein the guide members are operated hydraulically.
6. The method according to claim 1, wherein locations where resultant forces of the guide members engage the pile lie in a common plane.
7. The method according to claim 1, wherein the passive guide members of both pairs of guide members are located at the same side of the centerline of the pile.
8. The method according to claim 1, wherein the pair of upper guide members form a first pair of upper guide members, wherein a second, similar pair of upper guide members are located in a plane perpendicular to the common plane, and wherein the pair of lower guide members form a first pair of lower guide members, wherein a second, similar pair of lower guide members are located in a plane perpendicular to the common plane.
9. The method according to claim 1, wherein after placing the pile between each of the pairs of guide members, first the passive guide members are moved to respective fixed initial guiding positions with respect to the frame and subsequently the active guide members are moved to the pile until the passive and the active guide members engage the pile.
10. A pile guide for guiding a pile during submerged pile driving, comprising a frame including a passage configured to receive a pile, at least two guide members configured to guide the pile, which guide members are moveable with respect to the frame between respective guiding positions and respective releasing positions, wherein in the guiding positions the guide members project into the passage and face each other, and wherein in the releasing positions the guide members are located at a larger distance from each other than in the respective guiding positions, wherein at least one of the guide members is a passive guide member having a fixed guiding position.
11. The pile guide according to claim 10, wherein the other guide member is an active guide member having a flexible guiding position.
12. The pile guide according to claim 10, wherein at least one of the passive guide member and the active guide member is moveable between its guiding position and releasing position by a hydraulic cylinder.
13. The pile guide according to claim 11, wherein the passive guide member is movable by a hydraulic cylinder and pushed to a fixed end position in its guiding position.
14. The pile guide according to claim 11, wherein the active guide member is movable by a hydraulic cylinder and its guiding position is controlled by control of actual hydraulic pressure in the corresponding hydraulic cylinder.
15. The pile guide according to claim 13, wherein the hydraulic cylinder for moving the passive guide member operates at a higher pressure than a second hydraulic cylinder for moving the active guide member.
16. The pile guide according to claim 10, wherein the other guide member is also a passive guide member having a fixed guiding position.
17. The pile guide according to claim 16, wherein the passive guide members are moveable between their respective guiding positions and their respective releasing positions by respective hydraulic cylinders, wherein the passive guide members are pushed to their fixed end positions in their respective guiding positions.
18. The pile guide according to claim 10, wherein both guide members are located opposite to each other in their guiding positions, forming a cooperating pair of guide members.
19. The pile guide according to claim 18, wherein said pair of guide members form a first pair of guide members and wherein a second, similar pair of guide members are located in a plane perpendicular to a plane extending in longitudinal direction of the passage and in which said first pair of cooperating guide members are located.
20. The pile guide according to claim 18, wherein said pair of guide members form a first pair of guide members and wherein a third, similar pair of guide members are located at a distance from the first pair of guide members in longitudinal direction of said passage.
21. The pile guide according to claim 10, wherein at least one of the guide members comprises a roller to engage the pile.
22. The pile guide according to claim 10, wherein the frame comprises a cylindrical guide sleeve which envelopes the passage.
23. The pile guide according to one of the claim 10, wherein at least one of the guide members is movable by a hydraulic cylinder which is connected to an accumulator for relieving the guide member above a predetermined hydraulic pressure.
24. (canceled)
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0034] The invention will hereafter be elucidated with reference to schematic drawings showing an embodiment of the invention by way of example.
[0035]
[0036]
DETAILED DESCRIPTION
[0037]
[0038] The embodiment of the pile guide 1 as shown in
[0039] Each of the guide members 4, 7 is moveable with respect to the pile P and the guide sleeve 2 between a guiding position and a releasing position. Each guide member 4, 7 can be moved by means of a hydraulic cylinder (two of which are schematically illustrated in
[0040] The guide members 4, 7 of the embodiment as shown in
[0041] The active guide member 4b, 7b has a flexible guiding position (represented by spacing between dashed lines 8b). This means that its position is adjustable by controlling the hydraulic cylinder 10. For example, if a pile P has a slightly different diameter the passive guide member 4a, 7a of a pair of guide members will still be at its fixed guiding position whereas the guiding position of the active guide member 4b, 7b will be adapted to the actual different diameter such that the pile P is not deformed by a too high local pressure or such that no gap will arise between the rollers 5 of the opposite guide members 4, 7 and the pile P. The presence of the passive guide member 4a, 7a provides a fast preparation for pile-driving since it can be moved to its initial fixed guiding position without a complicated hydraulic control. The guiding position of the active guide member 4b, 7b is controlled by actual hydraulic pressure in the corresponding hydraulic cylinder 8b. In practice, the hydraulic cylinder 9 for moving the passive guide member 4a, 7a can be operated at a higher pressure than the hydraulic cylinder 10 for moving the active guide member 4b, 7b.
[0042] Both hydraulic cylinders are connected to respective accumulators (not shown) for relieving the guide members 4, 7 above a predetermined pressure. The accumulators prevent over pressure or overload of the pile guide 1 and the pile P in case of guiding a pile P which has a deviating diameter due to fabrication inaccuracy. For example, if the pile shape and diameter varies along its length, during pile-driving these variations must pass the rollers 5. When a larger diameter section of pile P, for example a weld bead, ovality or the like, passes, the rollers 5 must be moved outwardly with respect to each other. This is allowed by the accumulators. Basically, the majority of such a movement will be done by the accumulator cooperating with the active guide member 4b, 7b, but in case of an increase in pile diameter at the passive guide member 4a, 7a the accumulator cooperating with the passive guide member 4a, 7a may operate. It is noted that the accumulators can safeguard the guide members 4, 7 including the rollers 5 as well as the pile P. Since the contact stresses between the pile P and the rollers 5 are high, in practice the number of the rollers 5 and their diameter will be selected such that the risk of damage is minimized. The accumulators may be omitted in case of fast response times of the hydraulic cylinders. Nevertheless, in practice accumulators may still be applied from point of view of safety.
[0043] Under operating conditions, before pile-driving, the eight guide members 4, 7 are retracted towards the wall of the guide sleeve 2 and a pile P is lowered by means of a hoist crane and inserted into the passage 3 of the guide sleeve 2 just above the sea bottom. The passive guide members 4a, 7a are moved to their fixed guiding positions and the pile P is clamped between the passive guide members 4a, 7a and the active guide members 4b, 7b by operating and controlling the cylinders for moving the active guide members 4b, 7b. The pile P is then lowered into the sea bottom and pile-driving is started. After installing the pile P the guide members 4, 7 are retracted and the pile guide 1 is lifted from the pile P.
[0044]
[0045] In the method the actual forces between the pile P and the respective guide members 4, 7 are measured. The actual forces provide feedback to a control system and on the basis of these signals the hydraulically controlled guide members 4, 7 can be moved to and from the pile P. The method responds to several situations.
[0046] For example, if the actual force at the passive guide member 4a as well as at the active guide member 4b of the cooperating upper pair of guide members 4 exceed respective predetermined threshold levels, the active guide member 4b is moved in a direction away from the pile P in order to compensate for a portion of the pile P with increased diameter which passes the pair of upper guide members 4. Basically, the position of the passive guide member 4a with respect to the guide sleeve 2 remains unchanged. However, if the actual force at the passive guide member 4a of the upper pair 4 remains high in spite of moving the active guide member 4b in a direction away from the pile P and the actual force at the active member 4b does not increase, the passive guide member 4a is moved in a direction away from the pile P. Hence, in practice the method first attempts to compensate for a diameter increase by controlling the position of the active guide member 4b only, but also controls the position of the passive guide member 4a if required. A similar method of control occurs at the lower pair of guide members 7.
[0047] If, for example, during pile driving the actual force at the passive guide member 4a of the upper pair of guide members 4 as well as the actual force at the active guide member 7b of the lower pair of guide members 7 increase whereas the actual force at the active guide member 4b of the upper pair of guide members 4 as well as the actual force at the passive guide member 7a of the lower pair of guide members 7 do not increase, all of the guide members 4, 7 remain in their actual position. When the opposite actual forces at diagonally located upper and lower guide members, in this example 4a and 7b, both increase, the pile P is typically leaning. A similar response of the guide members 4, 7 may be performed if the pile leans in a different direction.
[0048] If, for example, during pile driving the actual force at the active guide member 4b of the upper pair of guide members 4 decreases, then the active guide member 4b of the upper pair of guide members 4 is moved in the direction of the pile P. If the actual force at the passive guide member 4a of the upper pair of guide members 4 decreases, then the active guide member 4b of the upper pair of guide members 4 is moved in the direction of the pile P, but if the actual force at the passive guide member 4a of the upper pair of guide members 4 remains below a predetermined level upon moving the active guide member 4b of the upper pair of guide members 4 in the direction of the pile P, then the passive guide member 4a of the upper pair of guide members 4 is moved in the direction of the pile P. This situation typically occurs in case of decreasing diameter of the pile P. A similar method of control occurs at the lower pair of guide members 7.
[0049] From the foregoing, it will be clear that the invention provides a method for installing a pile in the sea bottom in a fast and accurate manner, whereas resistance between the pile and the guide members is minimized during pile driving.
[0050] The invention is not limited to the embodiments shown in the drawings and described hereinbefore, which may be varied in different manners within the scope of the claims and their technical equivalents. For example, it is conceivable that the guide members are moveable by alternative drive means. Furthermore, the passive guide member and the active guide member of a pair of guide members may be out of line in their guiding positions but still facing each other. Moreover, the guide rollers may be replaced by slide pads or the like.