Methods of computing steady-state voltage stability margins of power systems
09921602 ยท 2018-03-20
Assignee
Inventors
Cpc classification
H02J3/06
ELECTRICITY
H02J3/0012
ELECTRICITY
H02J2203/20
ELECTRICITY
Y04S20/222
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
Y04S10/30
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
Y04S10/52
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
H02J4/00
ELECTRICITY
Y02E60/00
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
Y04S40/20
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
Y02B70/3225
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
G05F5/00
PHYSICS
International classification
H02J3/06
ELECTRICITY
H02J4/00
ELECTRICITY
G05F5/00
PHYSICS
Abstract
In steady-state voltage stability analysis, as load increases toward a maximum, conventional Newton-Raphson power flow Jacobian matrix becomes increasingly ill-conditioned so power flow fails to converge before reaching maximum loading. A method to directly eliminate this singularity reformulates the power flow problem by introducing an AQ bus with specified bus angle and reactive power consumption of a load bus. For steady-state voltage stability analysis, the angle separation between the swing bus and AQ bus can be varied to control power transfer to the load, rather than specifying the load power itself. For an AQ bus, the power flow formulation is only made up of a reactive power equation, thus reducing the size of the Jacobian matrix by one. This reduced Jacobian matrix is nonsingular at the critical voltage point, eliminating a major difficulty in voltage stability analysis for power system operations.
Claims
1. A method of identifying and correcting potential voltage instability caused by a contingency in an electrical power generation and distribution system, the electrical power generation and distribution system comprising a plurality of buses, the plurality of buses comprising at least one generator bus and at least one load bus, each configuration having a maximum loadability, the method comprising the steps of: modeling a power flow problem by specifying one of the plurality of buses as an AQ bus, specifying another of the plurality of buses as a swing bus, and specifying an angular separation between the AQ bus and the swing bus; solving the power flow problem to yield a power transfer from generation to load; repeating the solving step using a new angular separation in every repetition of the solving step until a maximum power transfer from generation to load is determined; calculating a voltage stability margin by calculating the difference between the maximum power transfer and the power transfer at the current operating condition; determining whether corrective action is required by comparing the voltage stability margin to a safety margin; and taking corrective action if the determining step determines that corrective action is required, the corrective action being selected from the group of switching shunt capacitors, switching reactors, adjusting generator set points, employing Flexible AC Transmission System (FACTS) devices, employing energy storage devices, and controlling tap-changing transformers.
2. The method of claim 1 further comprising the step of repeating the modeling, solving, repeating, calculating, determining, and taking steps a plurality of times during a day of operation of the electrical power generation and distribution system.
3. The method of claim 1 wherein the power flow problem is modeled based on a snapshot of a state of the electrical power generation and distribution system.
4. The method of claim 1 wherein the modeling, solving, repeating, calculating, and determining steps are carried out by one or more programmable computers programed to carry out the modeling, solving, repeating, calculating, and determining steps.
5. The method of claim 2 wherein the plurality of times are separated by a predetermined interval.
6. The method of claim 3 wherein the snapshot is generated from data supplied by a plurality of meters associated with the plurality of buses.
7. The method of claim 1 wherein the modeling step further comprises specifying a plurality of buses as PV buses.
8. The method of claim 1 wherein the modeling step further comprises specifying a plurality of buses as PQ buses.
9. The method of claim 1 wherein the modeling step further comprises specifying a plurality of buses as PV buses and another plurality of buses as PQ buses.
10. The method of claim 3 wherein the snapshot is generated from data supplied to the one or more programmable computers by a plurality of meters associated with the plurality of buses.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1) In the drawings:
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
DESCRIPTION OF THE PREFERRED EMBODIMENTS
(13) Voltage instability has been the cause of many major blackouts [8, 5, 12]. The numbers in brackets refer to the article references listed below. In a power system operation environment, it is important to ensure that the current operating condition is voltage stable subject to all credible contingencies. Methods for calculating the stability margin for each contingency can be classified into two categories: dynamic (time-domain simulation) and steady-state (power flow methods) [6, 7]. Time-domain simulation can capture the dynamic elements of voltage instability. The invention deals with steady-state voltage stability analysis occurring over a long time span.
(14) One difficulty in steady-state voltage stability analysis is that the conventional Newton-Raphson power flow fails to converge as the maximum loadability point is reached. In the unconstrained case, the Jacobian matrix J becomes singular at maximum loading, and the power flow solution will not converge when the smallest singular value of J becomes too small [6, 7].
(15) To circumvent this singularity problem, continuation power flow methods based on homotopy techniques have been developed [11, 4]. In this approach, a load-increase continuation parameter is introduced as an additional variable. As a result, the size of the Jacobian matrix is increased by one, which becomes non-singular with a suitable choice of the continuation parameter. The continuation power flow is solved in a two-step process with a predictor step and a corrector step, and requires additional manipulations and computation [1]. During the corrector step, the continuation method still needs to deal with a poorly conditioned Jacobian.
(16) The subject invention uses a new power flow method to directly eliminate the singularity issue without adding the complexity required by such homotopy methods. Elimination of the singularity allows for a well-conditioned power flow solution even at the maximum loadability point. The central idea is to reformulate the power flow with the introduction of a new type of load bus, which we call an AQ bus (A standing for angle). A conventional power flow formulation uses three types of buses: PV buses, PQ buses, and the swing bus (Table 1). For an AQ bus, the bus voltage angle and the reactive power consumption Q are specified. In this sense, a swing bus can be considered as an AV bus, because its angle is fixed and its voltage magnitude is known. In this formulation, the active power balance equation at the AQ load bus is no longer needed. Only the reactive power balance equation is kept. Furthermore, because at this bus is known, it is eliminated from the power flow solution vector consisting of bus voltage magnitudes of PQ buses and bus voltage angles of all the buses except for the swing bus. Thus the size of the resulting Jacobian matrix J.sub.R is reduced by one. This matrix is nonsingular at the maximum loadability point, and thus it avoids the singularity problem of the conventional Jacobian matrix J.
(17) The method of the invention provides means, such as a computer for running algorithms of the method, voltage angle and other meters to inputting values to be used by the algorithms, and any other suitable equipment for measuring other parameters and for issuing control or information signals used by the invention.
(18) TABLE-US-00001 TABLE 1 Power flow bus types Bus types Bus representation Fixed values PV Generator buses Active power generation and bus voltage magnitude PQ Load buses Active and reactive consumption AV Swing bus Voltage magnitude and angle AQ Load buses Voltage angle and reactive power consumption
(19) The load increase on Bus B.sub.L, when specified as an AQ bus in this new power flow method, is achieved by increasing the bus voltage angle separation .sub.s between Bus B.sub.L and the swing bus. It is expected that the load P.sub.L will increase with .sub.s until the critical voltage point, then further increases in .sub.s will result in a decrease of P.sub.L. For each value of .sub.s, the amount of P.sub.L is not known until the power flow is solved. This eliminates the active power balance equation at the load bus B.sub.L. The reactive power balance equation at B.sub.L is still maintained. For load increases involving constant-power-factor loads and at multiple buses, additional expressions are needed to develop the reduced Jacobian matrix J.sub.R. The computation of voltage stability margins using this method is no more complicated than a conventional load flow solution and the step size in increasing to reach the critical voltage point is not limited. In addition, computation-speed enhancement techniques such as decoupled power flow can still be used [3].
(20) This disclosure is organized as follows. In Section II, we use a single-load stiff-bus model to motivate the new problem formulation. Section III provides the general framework of the approach. Section IV uses two example test systems to illustrate the method. In Section V we discuss other applications, and we conclude in Section VI.
(21) II Motivation
(22) Consider the two-bus power system shown in
(23) There are two relevant power flow equations for this system, both for the load bus:
(24)
(25) Treating the load bus as a PQ bus, the Jacobian matrix obtained by taking the partial derivatives of these two equations with respect to .sub.s and V.sub.L is
(26)
(27) The Jacobian J is singular when
det J=(2V.sub.L cos .sub.sE)/X=0 (3)
which occurs at the critical voltage point.
(28) If the load bus is taken as an AQ bus, then the separation angle .sub.s can be specified without specifying P.sub.L and the active power equation is no longer needed. If Q.sub.L is fixed, then the reduced matrix J.sub.R is simply the (2,2) entry of J (2). Here the load is of constant power factor, i.e., Q.sub.L=P.sub.L tan(), allowing the reactive power equation to be rewritten as
(29)
that is,
(30)
The reduced Jacobian is the partial derivative of (5) with respect to V.sub.L
(31)
which is singular when J.sub.R=0.
(32) For the 2-bus system in
(33)
(34) The values of the determinants of J and J.sub.R are shown in
(35)
(36) III Theoretical Framework and Computation Algorrithms
(37) In this section, we consider the general framework of a power flow formulation including an AQ bus, and extend the method for steady-state voltage stability analysis allowing for load and generation increases on multiple buses and for constant power factor loads.
(38) Consider a power system with N.sub.G generator buses and N.sub.L load buses, such that the total number of buses is N=N.sub.G+N.sub.L. Let Bus 1 be the swing bus, Buses 2 to N.sub.G be the generator PV buses, and Buses N.sub.G+1 to N be the load PQ buses.
(39) The power flow problem consists of solving the active and reactive power injection balance equations
P.sub.i=P.sub.if.sub.Pi(, V)=0, i=2, . . . , N (7)
Q.sub.i=Q.sub.if.sub.Qi(, V)=0, i=N.sub.G+1, . . . , N (8)
where P.sub.i and Q.sub.i are the scheduled active and reactive power injections at Bus i. Vectors V and contain the bus voltage magnitudes and angles, and and are the computed active and reactive power injections, respectively. P is the vector of active power mismatches at Buses 2 to N, and Q is the vector of reactive power mismatches at Buses N.sub.G+1 to N.
(40) The power flow problem is commonly solved by the Newton-Raphson method, using the iteration
(41)
where the Jacobian matrix J is a square matrix of dimension (2NN.sub.G1) containing the partial derivatives of the active and reactive power flow equations with respect to the bus angles and the voltage magnitudes V, where
(42)
and V are the corrections and V, respectively.
(43) A. Power Flow Formulation Including an AQ Bus
(44) Suppose Bus N is an AQ bus with .sub.N=.sub.N and Q.sub.N specified, then the Newton-Raphson iteration reduces to
(45)
where
J.sub.R11=J.sub.11(1 . . . N2; 1 . . . N2)|.sub..sub.
J.sub.R12=J.sub.12(1 . . . N2; 1 . . . NN.sub.G)|.sub..sub.
J.sub.R21=J.sub.21(1 . . . NN.sub.G; 1 . . . N2)|.sub..sub.
J.sub.R22=J.sub.22|.sub..sub.
The number of bus angle variables is reduced by one, such that
.sub.R=[.sub.2 . . . .sub.N1].sup.T. (18)
(46) The AQ bus active power flow equation is eliminated, such that P.sub.R is the vector of active power mismatches at Buses 2 to (N1). The load P.sub.N on Bus N is no longer specified, but it can be computed using f.sub.Pi(, V).
(47) This reduced power flow formulation would not yield directly a specific P.sub.N on Bus N. However, this is not a hindrance in voltage stability analysis. Instead of increasing P.sub.N on Bus N and not knowing whether the non-convergent result is actually the maximum loadability point, a user can keep increasing the angular separation between Bus N and the swing bus until the maximum power transfer point is reached. The reduced Jacobian J.sub.R would not be singular at that point and the maximum loadability point can be readily computed.
(48) B. Voltage Stability Analysis for Constant-Power-Factor Loads
(49) In voltage stability analysis, it is common to specify constant-power-factor loads. In this section, we will extend the iteration (13) to a more general case by considering constant-power-factor load increases at multiple load buses to be supplied by generators at multiple locations.
(50) Let Buses N.sub.P to N be load buses with constant power factor cos , that is, Q.sub.I=P.sub.I tan .sub.I for I=N.sub.P, . . . , N. The active power load increases at these load buses are scaled with respect to Bus N, that is,
P.sub.lP.sub.l.sup.0=.sub.l(P.sub.NP.sub.N.sup.0), l=N.sub.p, . . . , N1. (19)
(51) The load increase is balanced by increases in outputs of generators on Buses 1 to q, with the active power at these generators scaled according to the swing bus
P.sub.kP.sub.k.sup.0=.sub.k(P.sub.1P.sub.1.sup.0), k=2, . . . , q. (20)
(52) In a solved power flow solution, the active power injections at Buses 1 and N are computed as the power flow leaving the buses on the lines interconnecting them to the other buses. Thus in an AQ-bus formulation, we account for the groups of increasing load and generation by modifying the power flow injection equations such that
f.sub.Pk(V,)=.sub.kf.sub.P1(V,), k=2, . . . , q (21)
f.sub.Pl(V,)=.sub.lf.sub.PN(V,), l=N.sub.p, . . . , N1 (22)
f.sub.Ql(V,)=.sub.lf.sub.PN(V,)tan .sub.l, l=N.sub.p, . . . , N1. (23)
(53) The other injection equations remain unchanged.
(54) In obtaining a new reduced Jacobian matrix to solve this new power flow problem, we need two row vectors of partial derivatives of f.sub.P1 and f.sub.PN
(55)
where J.sub.i is the ith row of the Jacobian. Note that J.sub.N is row N1 of J without the entry due to .sub.N, and J.sub.1 is not contained in J because Bus 1 is the swing bus.
(56) Thus the reduced Jacobian J.sub.R in (13) for the fixed reactive power injection problem is modified to form a new reduced Jacobian vector J.sub.R, such that
where N.sub.JR=2NN.sub.G2 is the dimension of J.sub.R. The other rows of J.sub.R remain unchanged.
(57) In this more general formulation of the AQ-bus power flow, the Newton-Raphson iteration becomes
(58)
where the power mismatch (21)-(23) is based on the previous iteration. In voltage stability margin calculations, the injection solution at a lower angle separation condition can be used to initiate the solution process.
(59) C. Algorithms for Computing Voltage Stability Margins
(60) Because vector J.sub.R in (28) would not be singular at the maximum loadability point, fast and well-conditioned voltage stability margin calculation methods can be formulated. Here we present two algorithms for steady-state voltage stability analysis as basic applications of the AQ-bus method.
(61) Algorithm 1: Using AQ-Bus Power Flow with Vector J.sub.R to Compute Voltage Stability Margins
(62) 1. From the current operating point (base case) with a power transfer of P.sub.0, specify the load and generation increment schedule, and the load composition (such as constant power factors).
(63) 2. Use a conventional power flow program with increasing loads until the Newton-Raphson algorithm no longer converges.
(64) 3. Starting from the last converged solution in Step 2, apply the AQ-bus power flow method (19)-(28) to continue the power flow solution by increasing the angle separation (.sub.1.sub.N) between the AQ bus and the swing bus until the maximum power transfer P.sub.0max is reached. Typically, the bus with the largest load increase will be selected to be the AQ bus. The base-case voltage stability margin is P.sub.0m=P.sub.0maxP.sub.0.
(65) 4. Specify a set of N.sub.c contingencies to be analyzed.
(66) 5. For contingency i, repeat Steps 2 and 3 for the post-contingency system to compute the maximum power transfer P.sub.0max and the voltage stability margin P.sub.im=P.sub.imaxP.sub.0.
(67) 6. Repeat Step 5 for all contingencies i=1, 2, . . . , N.sub.C.
(68) 7. The contingency-based voltage stability margin, measured as additional power delivered to the load until the maximum loadability point, is given by
(69)
(70) Note that for any of the contingencies in Step 5, if the AQ-bus algorithm for P.sub.0 fails to converge, that is, P.sub.0 is not a feasible solution, then the AQ-bus algorithm can be used to reduce P.sub.0 until a converged power flow solution is obtained. The new power flow solution would then be a voltage secure operating condition.
(71) Also note in Steps 3 and 5 of Algorithm 1, all the capability of the conventional power flow can be used. For example, taps can be adjusted to maintain voltages, and generators exceeding their reactive power capability can be changed to PQ buses from PV buses. Both capabilities are important for finding the proper voltage stability limit.
(72) The advantage of using a conventional power flow algorithm in Step 2 of Algorithm 1 is that it will allow a user to select the AQ bus for Step 3. There are several ways to select the AQ bus: (1) use the bus with the largest load increase (as stated in Step 3 of Algorithm 1), (2) use the bus with the largest rate of decrease of the bus voltage magnitude, or (3) use the bus angle with the largest component in the singular vector of the smallest singular value of J from the last converged solution. Frequently all three will yield the same bus.
(73) It is also possible to solve for voltage stability margins without updating J.sub.R (13). This method can be useful when one wants to avoid changing or reprogramming the Jacobian matrix entries, but it has slower convergence. The load increase condition (19), the generator increase condition (20), and the load power factor condition Q.sub.I=P.sub.I tan .sub.I are now enforced as fixed values after each power flow iteration has converged.
(74) To be more specific, start from the nominal power flow solution with the load on Bus N at P.sub.0. The angular separation of Bus N and the swing bus is increased without changing any injections. The power flow is solved, and the resulting load at Bus N and the generation at the swing bus are computed. This new value P.sub.N is used to compute the load increase on the other load buses (19), to be balanced by the generations according to (20). These new load and generation values are used to solve for another AQ-bus power flow. The process is repeated until the load and generation proportions are within tolerance. This procedure is summarized is the following algorithm.
(75) Algorithm 2: Using Unmodified J.sub.R to Compute Voltage Stability Margins
(76) 1. From the current operating point (base case) with a power transfer of P.sub.0, determine the load and generation increment schedule, and the load composition (such as constant power factor).
(77) 2. Use a conventional power flow program with increasing loads until the Newton-Raphson algorithm no longer converges.
(78) 3. Starting from the last converged solution in Step 2, apply the AQ-bus power flow algorithm (13) by increasing the angle separation between the AQ bus and the swing bus, to obtain a converged value of load at Bus N as P.sub.N.
(79) 4. Update the loads and generations at the other buses according to (19) and (20), respectively, and repeat the power flow solution, until (19) and (20) are satisfied.
(80) 5. Increase the angular separation between Bus and the swing bus and repeat Steps 3 and 4 until the load power at Bus N reaches the maximum value.
(81) 6. Apply Steps 4 to 7 of Algorithm 1 using Steps 2 to 5 of this algorithm to find the contingency-based voltage stability margin.
(82) It is expected that Algorithm 2 would be slower than Algorithm 1. However, in Algorithm 2, minimal additional code for the Jacobian is needed.
(83) IV Illustrative Examples
(84) In this section the AQ-bus power flow approach is applied to solve for the voltage stability margin of a 2-area, 4-machine system, and a 48-machine system.
(85) A. Two-area System
(86) We first use the Klein-Rogers-Kundur 2-area, 4-machine system [2] shown in
(87) Using Algorithm 1, the conventional power flow solution is shown as the dash-dash line of the larger PV curve in
(88) We also plot the load active power at Bus 14 versus the angle separation .sub.1.sub.14 with the black curves in
(89) 1) Singular Value Analysis
(90) At the maximum loadability point, the largest singular value of J is 423 and the two smallest singular values are 3.59 and 0.02. At the same operating point, the largest and smallest singular values of the vector J.sub.R matrix are 423 and 2.49, respectively. Thus vector J.sub.R does not exhibit any singularity or convergence problems.
(91) At the point where the conventional power flow fails to converge, the smallest singular value of the Jacobian is 0.05 and its singular vector is given in Table 2. Note that the element of the singular vector with the largest magnitude corresponds to .sub.14, the bus angle of the chosen AQ bus.
(92) TABLE-US-00002 TABLE 2 Singular vector corresponding to the smallest singular value of the conventional power flow Jacobian Singular vector component Corresponding variable 0.025 .sub.2 0.064 .sub.3 0.075 .sub.4 0.005 .sub.10 0.329 .sub.11 0.358 .sub.12 0.416 .sub.13 0.450 .sub.14 0.031 .sub.20 0.228 .sub.101 0.332 .sub.110 0.366 .sub.120 0.085 V.sub.3 0.086 V.sub.4 0.021 V.sub.10 0.117 V.sub.13 0.125 V.sub.14 0.048 V.sub.20 0.172 V.sub.101 0.024 V.sub.110 0.062 V.sub.120
(93) 2) Including Var Limits on a Generator
(94) Because the AQ-bus power flow incorporates all the functionalities of a conventional power flow, we can readily demonstrate the effect of a var limit on a generator. Suppose we impose a maximum reactive power generation of 3 pu for Generator 2, that is, if the reactive power generation of Generator 2 exceeds 3 pu, it will be changed into a PQ bus with Q=3 pu. The resulting PV and P curves for the same load increase conditions are shown as the smaller solid line curves in
(95) Also of interest is the amount of reactive power provided by the four generators.
(96) 3) Solution Using Algorithm 2
(97) We applied Algorithm 2 to the two-area system and obtained the same results as with Algorithm 1. Note that with Algorithm 2, J.sub.R is not modified to include the load and generator increase schedules. Thus Algorithm 2 is similar to a dishonest Newton method and needs more iterations than Algorithm 1.
(98) B. NPCC 48-Machine System
(99) In this section we extend the AQ-bus power flow to a 48-machine NPCC (Northeast Power Coordinating Council) system [9] using Algorithm 1. A portion of the system map is given in
(100) TABLE-US-00003 TABLE 3 Generator schedule for 48-machine system Generator Bus # Bus Type .sub.k 50 AV (swing) 30 PV 0.10 36 PV 0.80
(101) TABLE-US-00004 TABLE 4 Load schedule for 48-machine system Load Bus # Bus Type .sub.l 16 AQ 4 PQ 0.50 15 PQ 0.25
(102) We use the AQ-bus method to compute the PV curve for the base case, which is shown in
(103) To demonstrate the computation of the voltage stability margin for contingency analysis, a set of line outage contingencies (A-E) is selected, as listed in Table 5. The location of these lines are labeled in
(104) Note that Line 73-74 is in New York. Hence its outage results in a PV curve not much different from the base case PV curve. Lines 3-2 and 3-18 are near the buses with load increases, and thus the PV curves resulting from their outage show less stability margins. Lines 8-73 and 2-37 are interface lines between New York and New England. Their outages have significant impact on the voltage stability margin because part of the load increase in New England is supplied by a New York generator. From Table 5, the contingency-based voltage stability margin is 944 MW for the load on Bus 16.
(105) TABLE-US-00005 TABLE 5 Contingency list for 48-machine system Line Pre-contingency Voltage Stability Contingency Outage Power Flow Margin A 73-74 72 MW 1,346 MW B 8-73 97 MW 944 MW C 2-37 53 MW 1,221 MW D 3-2 295 MW 1,005 MW E 3-18 50 MW 1,231 MW
(106) V Other Applications
(107) The novel AQ-bus power flow method can be used in a practical application as a method of identifying and correcting potential voltage instability caused by a contingency in an electrical power generation and distribution system, the electrical power generation and distribution system comprising a plurality of buses, the plurality of buses comprising at least one generator bus and at least one load bus, each bus having a maximum loadability. In such an application, the method may comprise the steps of: modeling a power flow problem by specifying one of the plurality of buses as an AQ bus, specifying another of the plurality of buses as a swing bus, and specifying an angular separation between the AQ bus and the swing bus; solving the power flow problem to yield a power transfer from generation to load; repeating the solving step using a new increased angular separation in every repetition of the solving step until a maximum power transfer from generation to load is determined; calculating a voltage stability margin by calculating the difference between the maximum power transfer and the power transfer at the current operating condition; determining whether corrective action is required by comparing the voltage stability margin to a safety margin; taking corrective action if the determining step determines that corrective action is required, such as switching shunt capacitors or reactors, adjusting generator set points, employing Flexible AC Transmission System (FACTS) or energy storage devices, or controlling tap-changing transformers, for example, during operation of the system.
(108) The modeling step may include specifying other buses in the system as PV buses or PQ buses, in addition to the AQ bus and swing bus.
(109) The foregoing method may be repeated a plurality of times during a day of operation of the electrical power generation and distribution system. The method may be repeated after a predetermined interval, such as every five minutes, or every thirty seconds, for example, during operation of the system.
(110) The steps of modeling, solving, repeating, calculating, and determining could be carried out by one or more programmable computers programmed to carry out those steps, as one of skill in the art would understand. The power flow problem can be modeled based on a snapshot of a state of the electrical power generation and distribution system. The snapshot may be generated from data supplied to the one or more programmable computers by a plurality of meters associated with the plurality of buses. Optionally, fewer than all of the buses may be associated with meters.
(111) In this disclosure, Algorithm 1 and Algorithm 2 use the conventional power flow method up to the point at which it no longer converges, after which point, the novel AQ-bus power flow method is used. It should be understood that in its practical application the AQ-bus power flow method can be used by itself, and the conventional power flow method is not necessarily used at all.
(112) In addition to its application in the operation of existing power systems, the novel AQ-bus power flow method can be used for identifying and correcting potential voltage instability problems while planning and designing power grid systems or future expansions of existing power grid systems.
(113) VI Conclusions
(114) In this disclosure, we have developed a general-purpose power flow method that directly eliminates the matrix singularity issues that arise in PV curve calculations by introducing a new AQ-bus type. The elimination of the singularity using the AQ-bus method was motivated using a classical two-bus system, and a framework was developed to include multiple load buses and multiple generators in the computation of PV curves. We present two algorithms for practical implementation of the method and demonstrated both algorithms on a small two-area system. Finally, we extend the method to a 48-machine system to show its scalability and applicability to steady-state voltage stability margin calculation and contingency analysis.
(115) This method provides many advantages in the computation of steady-state voltage stability margins because it does not have numerical issues at the maximum power transfer point. Thus, power system operators can calculate the stability margins using this method far more reliably and quickly than a conventional power flow method.
(116) The references identified by numbers in brackets above are:
(117) [1] H.-D. Chiang, A. Flueck, K. Shah, and N. Balu, CPFLOW: a practical tool for tracing power system steady-state stationary behavior due to load and generation variations, IEEE Transactions on Power Systems, vol. 10, no. 2, pp. 623-634, 1995.
(118) [2] M. Klein, G. J. Rogers, and P. Kundur, A fundamental study of inter-area oscillations in power systems, IEEE Transactions on Power Systems, vol. 6, pp. 914-921, August 1991.
(119) [3] B. Stott, Review of load-flow calculation methods, Proceedings of the IEEE, vol. 62, no. 7, pp. 916-929, 1974.
(120) [4] V. Ajjarapu, Computational Techniques for Voltage Stability Assessment and Control. New York: Springer Science+Business Media, 2006.
(121) [5] F. Bourgin, G. Testud, B. Heilbronn, and J. Verseille, Present Practices and Trends on the French Power System to Prevent Voltage Collapse, IEEE Transactions on Power Systems, vol. 8, no. 3, pp. 778-788, 1993.
(122) [6] C. Taylor, Power System Voltage Stability. 1 em plus 0.5 em minus 0.4 em New York: McGraw-Hill, 1994.
(123) [7] T. Van Cutsem and C. Vournas, Voltage Stability of Electric Power Systems. New York: Springer Science+Business Media, 1998.
(124) [8] A. Kurita and T. Sakurai, The power system failure on Jul. 23, 1987 in Tokyo, in Proc. of the 27th Conf. on Decision and Control, 1988.
(125) [9] J. H. Chow, R. Galarza, P. Accari, and W. Price, Inertial and slow coherency aggregation algorithms for power system dynamic model reduction, IEEE Trans. on Power Systems, vol. 10, no. 2, pp. 680-685, 1995.
(126) [10] Y. Guo, B. Zhang, W. Wu, Q. Guo, and H. Sun, Solvability and Solutions for Bus-Type Extended Load Flow, Electrical Power and Energy Systems, vol. 51, pp. 89-97, 2013.
(127) [11] K. Iba, H. Suzuki, M. Egawa, and T. Watanabe, Calculation of critical loading condition with nose curve using homotopy continuation method, IEEE Transactions on Power Systems, vol. 6, no. 2, pp. 584-593, 1991.
(128) [12] G. Andersson, P. Donalek, R. Farmer, N. Hatziargyriou, I. Kamwa, P. Kundur, N. Martins, J. Paserba, P. Pourbeik, J. Sanchez-Gasca, R. Schulz, A. Stankovic, C. Taylor, and V. Vittal, Causes of the 2003 major grid blackouts in North America and Europe, and recommended means to improve system dynamic performance, IEEE Transactions on Power Apparatus and Systems, vol. 20, no. 4, pp. 1922-1928, November 2005.
(129) While specific embodiments of the invention have been shown and described in detail to illustrate the application of the principles of the invention, it will be understood that the invention may be embodied otherwise without departing from such principles.