METHOD FOR INDUCTION BEND FORMING A COMPRESSION-RESISTANT PIPE HAVING A LARGE WALL THICKNESS AND A LARGE DIAMETER
20180036780 ยท 2018-02-08
Inventors
Cpc classification
B21D7/04
PERFORMING OPERATIONS; TRANSPORTING
B21D43/006
PERFORMING OPERATIONS; TRANSPORTING
International classification
B21D7/04
PERFORMING OPERATIONS; TRANSPORTING
B21D7/16
PERFORMING OPERATIONS; TRANSPORTING
B21D43/00
PERFORMING OPERATIONS; TRANSPORTING
Abstract
The invention relates to a method for induction bend forming a compression-resistant pipe (I) having a large wall thickness and a large diameter. According to said method, in an initial phase t1, an initial tangent (3) of the pipe (I) is heat-treated by pushing the initial tangent (3) through the inductor (20) without the intervention of the bending lock (31). At the end of the initial tangent (3) the advance of the pipe is stopped at a time t2, and the inductor (20) is moved along the pipe (I) counter to the advance direction while the bending lock (31) is closed on the pipe (I). In order to induce the bending process in a phase t3, the movement speed of the inductor (20) is reduced to zero and the latter is moved to its bending position. At the same time, the advance of the pipe (I) is started. In a phase t4, a pipe bend (4) is produced at a constant process advance speed of the pipe (I). In a phase t5, the advance speed of the pipe (I) is reduced and the inductor (20) is accelerated counter to the advance direction while the bending lock (31) is opened. In a phase t6, a final tangent (5) is heated by further advancing the inductor in the opposite direction.
Claims
1. In a method for induction bend forming a pressure-resistant pipe, having a large wall thickness and a large diameter, such as a pipe used for a power plant or a liquid or gas pipeline, said method comprising the following steps: supporting the unprocessed pipe on a machine bed; feeding the pipe through an annular inductor of an electrical induction unit with a pipe feed speed v.sub.R; clamping the front pipe section in a pipe lock, which is supported on a bending arm that can pivot around a vertical axis of rotation arranged on the side of the pipe; supplying current to the induction device for heating a pipe section located within the inductor; and deflecting the bending arm through a longitudinal advance of the pipe until the pipe bend is completed; the improvement wherein, the pipe is clamped with its rear end in a holding device, which is supported moveably in the direction of a longitudinal pipe axis; in a starting phase t1, a starting tangent of the pipe is heat-treated by pushing the initial tangent through the inductor without engagement of the bending lock; the pipe feed is stopped at a time t2 at the end of the starting tangent and the inductor is moved along the pipe counter to the direction of advance, while the bending lock is closed on the pipe; a travel speed v.sub.I of the inductor is reduced to zero in order to initiate bending of the pipe in a phase t3, and is moved into its bending position and at the same time the feed of the pipe begins until the pipe feed rate v.sub.R is reached; a pipe bend is produced in a phase t4 with a constant pipe feed rate v.sub.R of the pipe; in a phase t5, the pipe feed rate v.sub.R is reduced and the inductor is accelerated counter to the feed direction, wherein the bending lock is opened; and in a phase t6, an end tangent is heated by further advance of the inductor in the opposite direction.
2. A method as in claim 1, wherein the inductor is moved into a starting position, which, viewed in the feed direction, is located before a bending position.
3. A method as in claim 2, wherein the inductor is moved into its starting position from a rearward position, viewed in the feed direction, before the beginning of phase t1.
4. A method as in claim 2, wherein the inductor is moved into its starting position during phase t1 from a rearward position, viewed in the feed direction, wherein the pipe feed rate v.sub.R is increased by the travel speed v.sub.I of the inductor.
5. A method as in claim 1, wherein the relative speed as the difference between the pipe feed rate v.sub.R and the travel speed v.sub.I of the inductor is constant in phases t1 to t6.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0009]
[0010]
[0011]
DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0012] The preferred embodiments of the present invention will now be described with reference to
[0013]
[0014] An induction device comprises an annular inductor 20, which is positioned with its center in the region of the pipe center axis 2. According to the invention, a linear adjusting device 21 is provided in order to move the inductor 20 relative to the machine bed 10.
[0015] A bending arm 30 is pivotally supported at a vertical bending axis 32, wherein the distance of the bending axis 32 perpendicular to the pipe center axis 2 can be adjusted in order to set the desired bending radius. A bending lock 31 for gripping and clamping the pipe 1 is arranged on the bending arm 30.
[0016] Relatively close to the inductor 20 and the heat inflow zone is a cooling device 40, with which the surface temperature is cooled down, for example using water, as soon as the corresponding length section has emerged from the forming zone.
[0017] Sensors for capturing the path and speed of the pipe 1 as well as of the inductor ring 20 are provided for carrying out the method according to the invention, as well as control modules in a control unit with which the paths and speed, as well as the connection and disconnection of the inductor unit, are brought into the correlations provided according to the invention.
[0018]
[0019] At the starting time shown in
[0020] The induction device 20 and the cooling device are switched on and the axial advance of the pipe 1 takes place in a first phase (see
[0021] In order to begin the bending process, the bending lock 31 on the bending arm 30 must grip the pipe 1 and clamp it so that the forces, which lead to the bending, can be introduced. However, the approach of the bending lock 31 and the application of the clamping forces require a certain period of time. A relative movement between the bending lock 31 and the pipe 1 must be avoided during the approach. The bending arm 30 with its bending lock 31 cannot be moved parallel to the advance of the pipe 1 because the structural effort for such a longitudinal movement of the support for the bending arm 30 would be much too high and because the distance of the bending lock 31 from the heating zone on the inductor ring 20 would change.
[0022] Therefore, according to the invention, the relative movement between the pipe 1 and the bending lock 31 is to be neutralized in a short phase t2 (see
[0023] When the pipe 1 is at a standstill, the bending lock 31 can be moved in, as shown in
[0024] If a pipe bend is to be produced, the initial point of the bend, which is present at the end of phase t3, can lie arbitrarily on the longitudinal axis 2 of pipe 1. On the other hand, the above-described operations at t1, t2, and t3 must be started with a precisely calculated approach so that a certain axial pipe position for the beginning of the bending process is reached when bending begins.
[0025] During the phase t4, the known induction bending process is carried out with a constant pipe feed rate v.sub.R and a stationary inductor 20, as shown in
[0026] In order to subject a rear tangent 5 on the pipe 1 to the same heat treatment as the remaining length sections of pipe 1 after the completion of the pipe bend 4, the pipe 1 and the inductor 20 move in opposite directions to the above-described starting process.
[0027] Shortly before reaching the intended bend length, the pipe feed is gradually slowed down in phase t5 at the speed v.sub.R and at the same time, the opposing movement of the inductor 20 starts at such a travel speed v.sub.I that the relative movement between the pipe 1 and inductor 20 remains constant. As a result, the residence time of each length section of the pipe 1 also remains constant in the migrating heat-affected zone. When the pipe 1 is at a standstill, the bending lock 31 can be opened. As a result, pipe 1 is now completely unobstructed by the bending arm 30.
[0028] To treat only a short end-side tangent 5 on the pipe 1, the inductor 20 can be moved simply into its end position facing the machine bed 10 in phase t6 with a constant travel speed v.sub.I, see
[0029] In order to obtain a longer tangent 5, in particular a tangent 5 followed directly by a further pipe bend, the method can be continued, as can be seen from the further flow chart according to
[0030] There has thus been shown and described a novel method for induction bend forming a pressure-resistant pipe having a large wall thickness and a large diameter, which fulfills all the objects and advantages sought therefor. Many changes, modifications, variations and other uses and applications of the subject invention will, however, become apparent to those skilled in the art after considering this specification and the accompanying drawings which disclose the preferred embodiments thereof. All such changes, modifications, variations and other uses and applications which do not depart from the spirit and scope of the invention are deemed to be covered by the invention, which is to be limited only by the claims which follow.