BUILD ORIENTATION OPTIMISATION METHOD AND SYSTEM FOR PRODUCING AN ARTICLE BY ADDITIVE MANUFACTURING
20220339708 · 2022-10-27
Assignee
Inventors
Cpc classification
B22F10/38
PERFORMING OPERATIONS; TRANSPORTING
B22F10/28
PERFORMING OPERATIONS; TRANSPORTING
B22F10/34
PERFORMING OPERATIONS; TRANSPORTING
B33Y30/00
PERFORMING OPERATIONS; TRANSPORTING
B22F10/40
PERFORMING OPERATIONS; TRANSPORTING
B22F10/80
PERFORMING OPERATIONS; TRANSPORTING
B33Y50/00
PERFORMING OPERATIONS; TRANSPORTING
B22F12/58
PERFORMING OPERATIONS; TRANSPORTING
Y02P10/25
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
International classification
B22F10/80
PERFORMING OPERATIONS; TRANSPORTING
B22F10/37
PERFORMING OPERATIONS; TRANSPORTING
B22F12/58
PERFORMING OPERATIONS; TRANSPORTING
B33Y30/00
PERFORMING OPERATIONS; TRANSPORTING
Abstract
The present application relates to a method of producing an article by additive manufacturing including the steps of predicting regions of stress in the article, identifying an optimal build orientation for the article and dispensing a first powder and/or a second powder to form the article. The first and second powders are of the same type of powder and have been recycled to different extents and the orientation of the build is optimised so that reduced quantities of the powder which has not been recycled or which has been recycled to a lesser extent is dispensed during the build.
Claims
1. A method of producing an article by additive manufacturing comprising the steps of: predicting regions of stress in the article; identifying an optimal build orientation for the article, and dispensing a first powder and/or a second powder to form the article, wherein the first and second powders are of the same type of powder and have been recycled to different extents, and wherein the orientation of the build is optimised so that reduced quantities of the powder which has not been recycled or which has been recycled to a lesser extent is dispensed during the build.
2. A method according to claim 1, wherein the method comprises the step of performing a stress analysis on a model of the article to predict regions of stress in the article in use.
3. A method according to claim 2, wherein the method comprises the step of slicing the model to produce two-dimensional cross-sections and subjecting the two-dimensional cross-sections to the stress analysis.
4. A method according to claim 1, wherein the method comprises the step of rotating the model until an optimised build orientation for the article is obtained.
5. A method according to claim 1, wherein the orientation of the build is further optimised to minimise support structure volume.
6. A method according to claim 5, wherein the build is oriented to be substantially self-supporting.
7. A method according to claim 6, wherein the build is oriented at an angle between 45° and 90° relative to the build platform.
8. A method according to claim 1, wherein the first powder comprises non-recycled powder and the second powder comprises powder that has been recycled one or more times.
9. A method according to claim 1, wherein the first powder and the second powder comprise recycled powders.
10. A method according to claim 1, wherein mixing of the first powder and the second powder occurs once the powders have been dispensed onto a build platform.
11. A method according to claim 1, wherein mixing of the first metal powder and the second metal powder occurs prior to dispensing the metal powders onto the build platform.
12. A method according to claim 1, wherein the ratio of the first powder to the second powder is varied in dependence on predicted stress in a region of the article.
13. A method according to claim 12, wherein the ratio of the first powder to the second powder is varied in dependence on the predicted stress in that region and on either a predicted or analysed condition of the recycled metal powder.
14. A method according to claim 12, wherein the ratio of the first metal powder to the second powder in one layer is the same or different to the ratio of the first metal powder to the second metal powder in a previous layer.
15. A system comprising a processor configured to operate an additive manufacturing machine to produce an article, wherein the additive manufacturing machine comprises a first container and a second container from which powder may be selectively dispensed to form the article, wherein the first container and the second container contain the same type of powder and respectively contain powder that has been recycled to different extents and wherein the processor is configured to determine an optimised build orientation for reducing the quantity of the powder which has not been recycled or which has been recycled to a lesser extent that is dispensed to produce the article.
16. A system according to claim 15, wherein the processor is communicatively coupled to the additive manufacturing machine.
17. A system according to claim 15, wherein the processor is configured to receive or generate a model of the article.
18. A system according to claim 15, wherein the processor is configured to perform a stress analysis on the model to predict regions of stress in the article and to determine the optimised build orientation based on results of the stress analysis.
19. A system according to claim 18, wherein the stress analysis performed by the processor comprises finite element analysis.
20. A system according to claim 15, wherein the processor is configured to determine a build orientation that minimises support structure volume.
Description
DETAILED DESCRIPTION OF THE INVENTION
[0021] In order that the invention may be more clearly understood one or more embodiments thereof will now be described, by way of example only, with reference to the accompanying drawings, of which:
[0022]
[0023]
[0024]
[0025] Referring to
[0026]
[0027] As shown in
[0028]
[0029] Once an optimised build orientation has been determined which minimises the unnecessary use of powder A in regions of the article where it is not required or required to a lesser extent, the CAD model 20 is sliced electronically to obtain a series of 2D layers, which each define a planer cross section through the model 20 of the article. Numerical stress values obtained from the FEA analysis are then reviewed and analysed for each of the layers in order to identify the highest numerical stress value, i.e. the worst case scenario, for each layer. Using this information, reference data relating to the degradation behavior of titanium powder and the application requirements of the article being produced, a user or an algorithm is able to determine an appropriate mix ratio of powder A and powder B for each layer. The mix ratio for each layer is stored on the personal computer or similar device. A processor then converts the 3D model in its optimised orientation and an optimised mix ratio of powder A and powder B for a given layer into a set of instructions which can be understood by the additive manufacturing machine 10.
[0030] The personal computer (or similar device) is communicatively coupled to the AM machine 10 so that the processor can output the instructions to the AM machine 10 to produce the article in the optimised orientation as depicted in
[0031] As discussed above, the ratio of powder A to powder B may be varied in dependence on the predicted stress in a region of the article, also taking into account the degradation behavior of powder B. This means that layers of the article which do not experience high levels of stress, e.g. layers above and below region 21 (
[0032] To ensure that the layer of blended powder has a substantially uniform thickness, the wiper 16 is brought into engagement with the powder and is then moved back and forth so that powder is spread across the build platform 12 until the desired layer thickness is obtained. The wiper 16 is then retracted and held out of contact with the powder. In forming the layer of blended powder it will be appreciated that a proportion of the blended powder will be wiped from the surface of the build platform 12. This powder is collected in collection chambers located either side of the build platform 12 so that this unfused powder can be re-used.
[0033] Selected regions of powder corresponding with the desired shape of the article in its optimised build orientation are then irradiated with the laser beam 11 which causes powder in the layer to fuse and form a solid mass on cooling. Powder is then dispensed from the first container 13 and/or the second container 14 on to the build platform 12 and the above described process of forming a layer with uniform layer thickness and irradiating selected regions with a laser beam 11 is repeated until the article is formed. It will be appreciated that the ratio of powder A to powder B in each subsequent layer may be the same or different to the previous layer and that the ratio will depend on the predicted stress in that particular region of the article as determined by the FEA analysis.
[0034] The one or more embodiments are described above by way of example only. Many variations are possible without departing from the scope of protection afforded by the appended claims.