INTEGRATED PRODUCTION COMPLEX ON A GRAVITY-BASED STRUCTURE (GBS)

20240409193 ยท 2024-12-12

Assignee

Inventors

Cpc classification

International classification

Abstract

An integrated production complex includes a gravity-based structure (GBS) accommodating topside modules with process equipment. The GBS has rectangular top and base slabs, an intermediate horizontal slab, internal vertical walls, at least one compartment with a tank to store hydrocarbons and/or respective processed products, and ballast compartments. The top slab has supports, on which the topside modules are installed. The GBS has a rectangular prism central part including the top slab, and a protruding part disposed along the sides of the central part around its entire perimeter and having external vertical walls. Protruding and central parts share the base slab, with the protruding part height less than the central part. The central part has longitudinal and transverse walls forming compartments for tanks and ballast compartments. The protruding part has internal walls that are perpendicular to its external walls and form compartments, some of which are ballast compartments.

Claims

1: A production complex for hydrocarbon processing which comprises a gravity-based structure (GBS) and topside modules with process equipment located on it, the GBS has a rectangular top slab and a rectangular base slab, an intermediate horizontal slab, vertical walls, at least one compartment with a tank to store hydrocarbon and/or processed product, and at least one ballast compartment, the GBS top slab has supports, on which the topside modules are mounted, wherein the GBS has a central part and a protruding part, with the central part having form of a rectangular prism with the said top slab, and the protruding part stretching along the central part sides all around its perimeter and having external vertical walls, the GBS protruding part and central part share the said base slab, with the protruding part being lower in height than the central part, the GBS central part has longitudinal and transverse walls that form compartments, at least one of which accommodate the said tank, while some of which are ballast compartments, and the protruding part has internal walls that are perpendicular to its external walls and form compartments, some of which are ballast compartments.

2: The production complex according to claim 1, wherein some of the compartments formed by the central part longitudinal and transverse walls accommodate auxiliary equipment.

3: The production complex according to claim 1, wherein there are longitudinal and transverse walls forming additional ballast compartments between the intermediate horizontal slab and the base slab.

4: The production complex according to claim 1, wherein the supports for the topside modules are located above intersections of the central part longitudinal and transverse walls.

5: The production complex according to claim 1, wherein piping and cabling are located in the space between the top slab and lower parts of the topside modules.

Description

LIST OF DRAWINGS

[0044] FIG. 1 shows a layout of the integrated production complex on a GBS, top view.

[0045] FIG. 2a transverse section A-A for FIG. 1.

[0046] FIG. 3a longitudinal section B-B for FIG. 1.

[0047] FIG. 4a longitudinal section C-C for FIG. 1.

[0048] FIG. 5a layout of the GBS main compartments.

[0049] FIG. 6the vertical walls arrangement in section D-D for FIG. 2.

[0050] FIG. 7the vertical walls arrangement in section E-E for FIG. 2.

[0051] FIG. 8a layout of the supports of the topside modules on the GBS top slab.

[0052] FIG. 9a layout of the topside bearing structures.

EXAMPLES OF THE INVENTION IMPLEMENTATION

[0053] The integrated production complex on a gravity-based structure is a technical product of full technical readiness comprising a set of process, engineering and auxiliary equipment for production, storage and offloading of liquid hydrocarbons or ammonia, power generation, as well as a storage of auxiliary substances and materials. One example of such complex is a liquefied natural gas (LNG) plant.

[0054] Integrated GBS production complex is fabricated at a dedicated yard and towed afloat to a place of installation. The GBS is installed on a dedicated underbase foundation of a water body, which can be a sea, lake, river or reservoir. To prevent scouring of the foundation under the GBS and a bed of the water body, fixation of the bed such as gabions or other similar devices may be placed on the bed around the GBS. The GBS is installed near a dedicated quayside and is connected to a shore with racks and bridges, making it possible to lay communications to the shore without using underwater pipelines and/or extensive above-water racks, have easy access to the production complex and a possibility to swiftly evacuate personnel. The racks and bridges reaching the shore are installed after the integrated production complex is installed at the operation site. Located near the shore line, the GBS is integrated with the onshore facilities, including hydrocarbons field being the source of feedstock for the production complex. Before the GBS is installed, the quayside may be used to deliver cargoes, for example, for development of the hydrocarbons field and construction of onshore facilities.

[0055] Construction of GBS production complexes will solve challenges caused by the extended and costly works to get prepared for the construction and to build a piled plant, as well as by the fact that it would not be possible to use such plant on a floating structure to develop fields in water areas with ice conditions.

[0056] One of options of the proposed integrated GBS production complex could be a power generation unit utilizing thermal energy from natural gas combustion. Such complexes can receive liquefied natural gas (LNG) from specialized tankersgas carriers, store it, regasify and convert it to power.

[0057] The main elements of a production line are the gravity-based structure (GBS) and the topsidemodularized process equipment (FIG. 1-4).

[0058] The GBS is a solid reinforced-concrete structure serving as a storage for raw materials produced and processed, as well as for auxiliary substances and materials. The GBS is a base for the topside of the production complex and is designed to be installed on the bottom of a water body under its own weight. Central part 1 of the GBS is shaped as a rectangular prism and has top slab 2.

[0059] On the sides of central part 1 along the whole perimeter, GBS protruding part 3 with vertical outer walls is located. GBS central part 1 and protruding part 3 have common bottom slab 4, and the height of protruding part 3 is lower than the height of GBS central part 1.

[0060] GBS central part 1 is separated into compartments with vertical longitudinal and transversal walls 5 (FIG. 5-7). Some compartments, e.g. compartments 6, are used to store the produced and processed feedstock, while other compartments, e.g. compartments 7, are used to store ballast water. GBS protruding part 3 is separated with vertical walls 5 perpendicular to its outer walls into compartments. Compartments 8 located along the longer sides of the GBS are also included in the ballast system.

[0061] GBS top slab 2 has reinforced concrete supports 9 on which topside modules 10 are installed.

[0062] The GBS can stay afloat during water transportation to the site of installation of the integrated production complex and can withstand ice impact in ice conditions. Changing the GBS condition from floating to stationary at the site of installation on foundation 11 is ensured by flooding ballast compartments 7, 8 with water.

[0063] The GBS outer dimensions may vary depending on the production complex purpose, e.g. for an LNG plant the GBS dimensions (including the protruding part 3) may be as follows: length 324 m, width 154 m, height 30.2 m. In this case the length of the GBS central part 1 is 300 m, the width is 108 m, the height is 30.2 m. The protruding part 3 on the sides of the GBS has the width of 22 m, on the short-end walls of the GBS12 m. The height of protruding part 3 is 13.75 m.

[0064] The main space-planning solutions of the GBS structures are defined by technological parameters, as well as internal and external loads affecting the GBS structure, taking into account their maximum possible negative combination.

[0065] The GBS central part 1 is rectangular prism-shaped and includes the main bearing structures, i.e. the vertical longitudinal and transversal walls 5 and horizontal slabs: top slab 2, base slab 4, and intermediate support slab 13 under main tanks 12 for the storage of hydrocarbons and/or respective processed products. The bearing structures ensure the required spatial stiffness of the cage of the GBS, including during transportation of the integrated production complex and it being afloat until it is installed. Reinforced-concrete walls also provide partition the GBS into compartments in accordance with their functional purpose. Some of transverse walls 5 may have a rectangular opening in their central part instead of being solid. In this case they essentially serve the purpose of stiffening ribs.

[0066] Reinforced-concrete walls also serve as bearing structures that transfer the load from the topside to support slab 13 and foundation 11, that is why topside supports 9 are located above the intersections of vertical longitudinal and transversal walls 5 of the GBS.

[0067] Top slab 2 of the GBS has slopes from the central longitudinal line to the edges for drainage of atmospheric precipitation and process spills. The structure of top slab 2 is designed to withstand explosion loads in case of emergency situations. In case cryogenic liquids are involved in the technological process, in order to protect top slab 2 from spillage of cryogenic media, steel with enhanced cold resistance characteristics is used as reinforcement.

[0068] Horizontal support slab 13 is provided between top and base slabs 2 and 4 to distribute the loads from liquid hydrocarbons and/or respective processed products storage tank 12. Longitudinal and transverse walls 14 under said slab 13 transfer the load to base slab 4 and ensure the spatial stiffness of the structure.

[0069] Reinforced concrete based on modified normal density concrete with tensioned reinforcement is the main material of GBS central part 1.

[0070] GBS protruding part 3 is located along the perimeter of GBS central part 1, forming a single structure with it. Long sides of protruding part 3 mostly house ballast compartments 8 (FIG. 5), while the short-end sides mostly house auxiliary and engineering compartments 15. GBS protruding part 3 serves the following main purposes: [0071] achieving the required target GBS buoyancy parameters; [0072] housing ballast compartments 8 mostly intended for the GBS balancing, ensuring the GBS being afloat with an even keel, without roll and trim; [0073] forming a natural protective barrier in case of design emergency collision/ship impact; protruding part 3 will absorb and dissipate most of the collision's energy, preventing damage to the main part of the GBS cage ensuring the integrity and preservation of main tanks 12 and bearing structures of the topside foundation; [0074] housing auxiliary process and marine equipment ensuring LNG tankers mooring and offloading of liquid hydrocarbons.

[0075] Storage tanks for liquid hydrocarbons and/or respective processed products are accommodated in the GBS compartments and intended for storage of products of the integrated production complex. Depending on its intended use, the production complex may also have storage tanks for feedstock, semi-processed products, and consumables. GBS central part 1 has a number of tanks 12 (FIG. 5) that may have different design depending on the properties of substances to be stored. For storage of LNG and cryogenic liquids under pressure close to athmospheric, membrane tanks are used. In this case, tank 12 consisting of a steel membrane made of stainless steel or invar (FeNi alloy) separated from concrete structure by a thermal insulation layer is installed inside concrete compartment 6. The thermal insulation layer is located directly on top slab 2, intermediate slab 13 and GBS walls, transferring the loads from tank 12 and its liquid content to the above-mentioned boundary structures. The GBS slabs and walls thus serve as support structures for membrane tanks, with which they are integrated into a single structural unit. To prevent any leaks, the bottom and the side surfaces of membrane tanks 12 have a secondary barrier being an additional membrane installed inside the thermal insulation layer.

[0076] In case of an LNG plant, liquefied gas is stored in two 115,000-cbm tanks 12, each installed in a 1354024 m individual compartment 6.

[0077] Compartments 6 with tanks 12 are surrounded by dry compartments 16 enabling inspections of external surfaces of the tanks boundary structures.

[0078] For storage of condensate and other liquid hydrocarbons that do not require low temperatures, GBS concrete compartments 17 may be used, with their boundary structures serving as a protective barrier. Some of compartments 7 can be used both for ballast water and for storage of condensate and other liquid hydrocarbons that do not require low temperatures. In case of an LNG plant, there is 75,000-cbm 1353030 m compartment 7 for stable condensate storage and one of compartments 17 for substandart condensate storage with a capacity of 5,000 cbm and 30830 m in size.

[0079] Wet storage involving an underlying water layer may be used for hydrocarbons that are less dense than water. In this case, the bottom layer of the stored product around 1 m in thickness is considered a commingling area ensuring guaranteed separation of water and the stored product during loading operations. Compartment 7 is also slightly pressurized (from the atmospheric pressure level) using a nitrogen blanket in the upper part of the compartment 7 to air-proof compartment 7 and prevent any flammable and explosive gas mixtures with hydrocarbon vapors from forming.

[0080] The height of the underlying water layer in compartment 7 may be fixed or variable. In case of the former, the height of the underlying water layer is fixed, e.g. at two meters, irrespective of the quantity of condensate or other liquid hydrocarbons stored in the compartment. The change of the condensate volume in compartment 7 is compensated by the change of the volume of the nitrogen blanket. In the latter case, the height of the underlying water layer changes for compartment 7 to be permanently filled with liquid. As compartment 7 is filled with condensate or other liquid hydrocarbons, part of water is removed from it with active ballast system. When the level of hydrocarbons stored decreases, additional water is fed to compartment 7.

[0081] Compartments 6 for storage of large volumes of hydrocarbons are located in GBS central part 1. Smaller compartments as tanks (for example, for diesel fuel, hot oil or glycol water) could also be located in protruding part 3 of GBS.

[0082] To store small volumes, self-supported tanks are also used in GBS compartments (in central part 1 or in protruding part 3). In case of LNG plant, self-supported tanks are used for waste water, demineralized water, fresh water, wash water, absorber, butane and propane.

[0083] Auxiliary and engineering compartments 16 in GBS central part 1 are located to the sides of main hydrocarbon storage compartments 6 and in the center between them. Said compartments 16 are intended for process needs, placement of equipment, tanks of process fluids, as well as access and evacuation routes for personnel. With dry compartments 16 along the perimeter of main compartments 6 for hydrocarbons storage, external surfaces of the boundary walls of tanks 12 for hydrocarbons storage can be inspected.

[0084] Auxiliary and engineering compartments 15 are located in protruding part 3 of the GBS. Said compartments 15 are intended for process needs, placement of equipment and tanks of process fluids.

[0085] The engineering equipment includes: power supply system, including substations; heating, ventilation and air conditioning (HVAC) systems; a ballast water heating and recirculation system; water supply and disposal systems; firewater pumps and pipelines; foam fire-fighting system skids; an electrochemical protection system; telecommunication and alarm systems and video surveillance system. Most of the engineering equipment is located on top slab 2 and/or on modules 10, while the restin engineering compartments 15. Auxiliary compartments 15 could be left empty, with ladders and manholes for accessing the interior.

[0086] Supports 9 of the topside modules on GBS top slab 2 ensure that support reactions are transferred on the main load-bearing structures of the GBS from topside modules 10. Structurally, the supports are reinforced-concrete pylons with heads for embedded components. At GBS supports 9 and topside modules 10 connection points, special sealings 18 are used (FIG. 9) to ensure free rotation and movement in predetermined directions to compensate thermal expansion of topside modules 10.

[0087] Location of supports 9 on the layout (FIG. 8) is defined basing on crossing of GBS load-bearing walls 5 to ensure distribution of loads from topside modules 10.

[0088] The height of supports 9 is selected so as to provide enough space 19 between GBS top slab 2 and a lower part of topside modules 10 to place piping and cable communications between the topside and equipment in the GBS compartments and for people and machinery to be able to move on GBS top slab 2.

[0089] The GBS ballast system includes internal ballast compartments 7, internal ballast compartments 20 under support slab 13, formed by vertical walls 14, as well as external ballast compartments 8 located in GBS central part 1 and in GBS protruding part 3. The ballast recirculation and heating system is provided to prevent freezing of water in the ballast compartments.

[0090] The water in the ballast compartments is heated using waste heat from exhaust gas of gas turbines installed on topside modules 10.

[0091] The ballast system performs two main functions: [0092] ballasting, i.e. changing the weight of the GBS, ensuring the required GBS draft when afloat and the structure stability once the GBS is installed on the underbase foundation; [0093] GBS balancing, i.e. bringing the GBS on an even keel, without roll and trim when afloat, through compensation with ballast water for the structure centre of gravity deviation from its geometric center.

[0094] The topside on which process equipment is located is composed of modules 10. The number of modules 10 is decided upon during the production complex engineering phase. Location of the modules on the GBS is assumed taking into account their weight to make sure the centre of gravity of the production complex being close to the geometric center of the GBS so as to reduce the volume of ballast water required to balance out the structure when afloat.

[0095] Topside modules 10 are three-dimensional steel frames with bracings, which accommodate process equipment, electrical equipment, automation systems, etc.

[0096] Vertical columns 21, vertical ties 22 and floor beams 23 are the main elements of the frames with bracings of module 10 (FIG. 9). At a fundamental level, topside modules 10 are not different from topside modules used in the oil & gas sector in terms of their design and layout.

[0097] The equipment configuration depends on the purpose of the integrated production complex. For example, at an LNG plant, modules 10 include raw gas treatment units, equipment for gas liquefaction and LNG offloading to tankers-gas carriers, as well as auxiliary equipment and utility lines.

[0098] For ease of equipment maintenance and personnel access, each module 10 has several decks. Main tier 24 of each module 10 is at the same height to enable combining evacuation routs and load handling routs across the topside, thus reducing the load on GBS top slab 2. Other tiers of the topside modules 10 vary in height depending on their function and equipment.

[0099] Liquid hydrocarbon offloading jetty 25 is structurally integrated with the GBS and the topside. Fenders and an offloading platform with loading arms as well as other marine and process equipment enabling liquid hydrocarbon offloading are installed on the protruding part 3 on the seaward side of the GBS. Mooring equipment for tanker berthing is installed on the topside seaward side.

[0100] Jetty 25 can also be used to discharge liquid hydrocarbons from a tanker. If the production complex on a gravity-based structure is a power generation facility, the jetty main function is to receive LNG from tankers-gas carriers.

[0101] Division of the GBS to compartments depends on its functional design, including specialization of the integrated production complex. In general, the GBS is designed to have three types of compartmentsballast compartments, hydrocarbon storage compartments, auxiliary and engineering compartments.

[0102] In case of a GBS LNG plant, GBS central part 1 comprises six main compartments (FIG. 5). Two compartments 6 along the GBS centerline are intended for hydrocarbon storage, four side compartments 7 can both be used as ballast compartments and additional storage compartments for hydrocarbons, e.g. condensate. In case of wet storage of hydrocarbons with variable water level, compartments 7 are both ballast compartments and storage compartments for hydrocarbons and/or respective processed products. The auxiliary and engineering compartments 16 as well as additional hydrocarbon storage compartments 17 are located between the main compartments 6, 7.

[0103] Additional ballast compartments 20 (FIG. 2, FIG. 4) are located under main hydrocarbon storage compartments 6 between base slab 4 and support slab 13 for main hydrocarbon storage tanks 6, 7.

[0104] GBS protruding part 3 (FIG. 5) accommodates ballast compartments 8 and auxiliary and engineering compartments 15. In case of GBS LNG plant, protruding part 3 on the sides comprises mostly ballast compartments 8 while on the short ends it comprises mostly auxiliary and engineering compartments 15. Seabed 29 and water level 30 in the body of water are shown on FIG. 2 to 4.

[0105] Compartments may be separated by transverse partitions, except for main LNG storage compartments 6. In this case, openings are made inside the ballast compartments for ballast water to flow through, and passages for personnel and penetrations for communications are made in the auxiliary and engineering compartments.

[0106] The integrated production complex on a gravity-based structure is connected to the shore by two piperacks 26, in which piping and cabling are laid, as well as three evacuation bridges 27 for personnel movement and evacuation, when needed. The piperacks and bridges are made as steel bridge structures mounted on supports. Said supports are located on GBS top slab 2 on one end, and on quayside 28 on the other.