PORTAL PILE DRIVER AND CAST-IN-PLACE PILE CONSTRUCTION METHOD
20250043642 ยท 2025-02-06
Assignee
Inventors
- Ying Peng (Haiko, CN)
- Guijiao Peng (Haikou, CN)
- Huayuan Li (Haikou, CN)
- Songbin Chen (Haikou, CN)
- Haitong Chen (Haikou, CN)
- Yanji Tan (Haikou, CN)
Cpc classification
E21B7/023
FIXED CONSTRUCTIONS
International classification
E21B19/15
FIXED CONSTRUCTIONS
E21B7/02
FIXED CONSTRUCTIONS
Abstract
A portal pile driver, and a cast-in-place pile construction method are provided, relating to the technical field of pile foundation construction. The portal pile driver includes a portal frame, a pile frame platform, a moving assembly, and a lifting assembly. The portal frame is erected at one side of the pile frame platform, and a power head is installed on the portal frame. A loading zone is located at the pile frame platform, and a projection of a central shaft of the power head on the pile frame platform is located in an extension direction of the loading zone. The moving assembly is located at one side or each of both sides of the loading zone, and multiple drill pipes are horizontally distributed on the moving assembly, and each drill pipe is perpendicular to a plane where the portal frame is located.
Claims
1. A portal pile driver, comprising a portal frame, a pile frame platform, a moving assembly, and a lifting assembly; wherein the portal frame is erected on one side of the pile frame platform, a power head capable of ascending and descending is installed on the portal frame, and the power head is able to be detachably connected to one end of any drill pipe moved to a position below the power head; a loading zone is located at a position of the pile frame platform at one side of the portal frame, and a projection of a central shaft of the power head on the pile frame platform is located in an extension direction of the loading zone; the moving assembly is located at one side or each of both sides of the loading zone, a plurality of drill pipes are horizontally distributed on the moving assembly, and each drill pipe is perpendicular to a plane where the portal frame is located; the moving assembly is configured for moving on a horizontal plane in a direction parallel to the plane where the portal frame is located, so as to convey the plurality of drill pipes to the loading zone in turn; the lifting assembly comprises a picking part, the picking part is configured for grasping the drill pipe at the loading zone; the lifting assembly is configured for pivoting relative to the pile frame platform, so as to drive the drill pipe grasped by the picking part to switch from a horizontal state to an upright state and to move to the position below the power head in the pivoting process; wherein the moving assembly comprises a plurality of sliding mechanisms, and the plurality of sliding mechanisms are distributed at intervals in a direction perpendicular to the plane where the portal frame is located, and the plurality of sliding mechanisms are configured for supporting the plurality of drill pipes and moving the plurality of drill pipes; and in the direction perpendicular to the plane where the portal frame is located, the picking part at the loading zone and the plurality of sliding mechanisms are distributed in a staggered manner; wherein the plurality of sliding mechanisms are of a telescopic structure, and configured for driving the drill pipe supported by the plurality of sliding mechanisms to ascend and descend in a process of extending and retracting the plurality of sliding mechanisms; wherein each sliding mechanism is provided with a first clamping position and a second clamping position distributed at an interval, first clamping positions of the plurality of sliding mechanisms are distributed in a straight line so as to support a drill pipe, and second clamping positions of the plurality of sliding mechanisms are distributed on another straight line to support another drill pipe.
2. The portal pile driver according to claim 1, wherein the pile frame platform is provided with a plurality of guide rails, the plurality of guide rails are distributed at intervals in the direction perpendicular to the plane where the portal frame is located, and each guide rail extends in the direction parallel to the plane where the portal frame is located; and the plurality of sliding mechanisms and the plurality of guide rails are slidably connected in one-to-one correspondence.
3. The portal pile driver according to claim 1, wherein the lifting assembly comprises a mechanical arm, and a jacking driving mechanism, and the picking part is a mechanical gripper; the mechanical arm comprises a hinged end, and a suspension end, the hinged end of the mechanical arm is hinged with the pile frame platform, and the suspension end of the mechanical arm is suspended; and the mechanical gripper is installed on the mechanical arm, an output end of the jacking driving mechanism is connected to the mechanical arm, the jacking driving mechanism is configured for driving the mechanical arm to pivot relative to the pile frame platform, so as to make the mechanical arm switch between the horizontal state and the upright state.
4. The portal pile driver according to claim 3, wherein the hinged end of the mechanical arm is located between the portal frame and the loading zone, and the mechanical gripper is installed on an arm surface, facing away from the pile frame platform, of the mechanical arm; or the mechanical gripper is installed on an arm surface, facing the pile frame platform, of the mechanical arm, and a turntable mechanism is installed on the pile frame platform, the hinged end of the mechanical arm is hinged to the turntable mechanism, and the turntable mechanism is configured for driving the mechanical arm to rotate about a central axis of the mechanical arm.
5. The portal pile driver according to claim 3, wherein an extension frame is connected to one side, provided with the portal frame, of the pile frame platform, the hinged end of the mechanical arm is hinged to the extension frame, the mechanical arm is able to be erected at one side, facing away from the loading zone, of the portal frame after passing through the portal frame in a process of pivoting relative to the pile frame platform; and the mechanical gripper is installed on an arm surface, facing the pile frame platform, of the mechanical.
6. The portal pile driver according to claim 1, further comprising a self-adjusting counterweight assembly, a monitoring system, and a control system; wherein the self-adjusting counterweight assembly is installed on one side, away from the portal frame, of the pile frame platform, and comprises a moving portion capable of moving in the direction perpendicular to the plane where the portal frame is located; the self-adjusting counterweight assembly and the monitoring system are both connected to the control system, and the monitoring system is configured for monitoring a weight change at the portal frame of the portal pile driver, and the control system is configured for calculating an amount of moving of the moving portion according to the weight change monitored by the monitoring system, and driving the moving portion to move in the direction perpendicular to the plane where the portal frame is located according to the moving amount.
7. A cast-in-place pile construction method carried out by the portal pile driver according to claim 1, and the method comprising following steps: S1: starting the moving assembly to convey one of the plurality of drill pipes on the moving assembly to the loading zone; S2: starting the lifting assembly, enabling the picking part to grasp the drill pipe at the loading zone, enabling the lifting assembly to pivot after the moving assembly is away from the loading zone, so as to drive the drill pipe grasped by the picking part to switch from the horizontal state to the upright state and move to the position below the power head; S3: connecting a top end of the drill pipe grasped by the picking part to the power head, and then enabling the picking part to release the grasped drill pipe; S4: driving the power head to descend to move the drill pipe connected below the power head to a top end of a drill pipe buried at a designed pile location of a cast-in-place pile, and connecting a bottom end of the drill pipe connected below the power head to the top end of the buried drill pipe; S5: continuing to drive the power head to descend and starting the power head, thus enabling the drill pipe connected below the power head to rotate and drill into soil at the designed pile location of the cast-in-place pile; S6: separating the power head from the drill pipe connected below the power head, and driving the power head to ascend; and S7: repeating steps of S1 to S6 to connect the plurality of drill pipes on the moving assembly in turn and drill the plurality of drill pipes into the soil at the designed pile location of the cast-in-place pile.
8. The portal pile driver according to claim 2, wherein the lifting assembly comprises a mechanical arm, and a jacking driving mechanism, and the picking part is a mechanical gripper; the mechanical arm comprises a hinged end, and a suspension end, the hinged end of the mechanical arm is hinged with the pile frame platform, and the suspension end of the mechanical arm is suspended; and the mechanical gripper is installed on the mechanical arm, an output end of the jacking driving mechanism is connected to the mechanical arm, the jacking driving mechanism is configured for driving the mechanical arm to pivot relative to the pile frame platform, so as to make the mechanical arm switch between the horizontal state and the upright state.
9. The portal pile driver according to claim 2, further comprising a self-adjusting counterweight assembly, a monitoring system, and a control system; wherein the self-adjusting counterweight assembly is installed on one side, away from the portal frame, of the pile frame platform, and comprises a moving portion capable of moving in the direction perpendicular to the plane where the portal frame is located; the self-adjusting counterweight assembly and the monitoring system are both connected to the control system, and the monitoring system is configured for monitoring a weight change at the portal frame of the portal pile driver, and the control system is configured for calculating an amount of moving of the moving portion according to the weight change monitored by the monitoring system, and driving the moving portion to move in the direction perpendicular to the plane where the portal frame is located according to the moving amount.
10. A cast-in-place pile construction method carried out by the portal pile driver according to claim 2, and the method comprising following steps: S1: starting the moving assembly to convey one of the plurality of drill pipes on the moving assembly to the loading zone; S2: starting the lifting assembly, enabling the picking part to grasp the drill pipe at the loading zone, enabling the lifting assembly to pivot after the moving assembly is away from the loading zone, so as to drive the drill pipe grasped by the picking part to switch from the horizontal state to the upright state and move to the position below the power head; S3: connecting a top end of the drill pipe grasped by the picking part to the power head, and then enabling the picking part to release the grasped drill pipe; S4: driving the power head to descend to move the drill pipe connected below the power head to a top end of a drill pipe buried at a designed pile location of a cast-in-place pile, and connecting a bottom end of the drill pipe connected below the power head to the top end of the buried drill pipe; S5: continuing to drive the power head to descend and starting the power head, thus enabling the drill pipe connected below the power head to rotate and drill into soil at the designed pile location of the cast-in-place pile; S6: separating the power head from the drill pipe connected below the power head, and driving the power head to ascend; and S7: repeating steps of S1 to S6 to connect the plurality of drill pipes on the moving assembly in turn and drill the plurality of drill pipes into the soil at the designed pile location of the cast-in-place pile.
11. A cast-in-place pile construction method carried out by the portal pile driver according to claim 3, and the method comprising following steps: S1: starting the moving assembly to convey one of the plurality of drill pipes on the moving assembly to the loading zone; S2: starting the lifting assembly, enabling the picking part to grasp the drill pipe at the loading zone, enabling the lifting assembly to pivot after the moving assembly is away from the loading zone, so as to drive the drill pipe grasped by the picking part to switch from the horizontal state to the upright state and move to the position below the power head; S3: connecting a top end of the drill pipe grasped by the picking part to the power head, and then enabling the picking part to release the grasped drill pipe; S4: driving the power head to descend to move the drill pipe connected below the power head to a top end of a drill pipe buried at a designed pile location of a cast-in-place pile, and connecting a bottom end of the drill pipe connected below the power head to the top end of the buried drill pipe; S5: continuing to drive the power head to descend and starting the power head, thus enabling the drill pipe connected below the power head to rotate and drill into soil at the designed pile location of the cast-in-place pile; S6: separating the power head from the drill pipe connected below the power head, and driving the power head to ascend; and S7: repeating steps of S1 to S6 to connect the plurality of drill pipes on the moving assembly in turn and drill the plurality of drill pipes into the soil at the designed pile location of the cast-in-place pile.
12. A cast-in-place pile construction method carried out by the portal pile driver according to claim 4, and the method comprising following steps: S1: starting the moving assembly to convey one of the plurality of drill pipes on the moving assembly to the loading zone; S2: starting the lifting assembly, enabling the picking part to grasp the drill pipe at the loading zone, enabling the lifting assembly to pivot after the moving assembly is away from the loading zone, so as to drive the drill pipe grasped by the picking part to switch from the horizontal state to the upright state and move to the position below the power head; S3: connecting a top end of the drill pipe grasped by the picking part to the power head, and then enabling the picking part to release the grasped drill pipe; S4: driving the power head to descend to move the drill pipe connected below the power head to a top end of a drill pipe buried at a designed pile location of a cast-in-place pile, and connecting a bottom end of the drill pipe connected below the power head to the top end of the buried drill pipe; S5: continuing to drive the power head to descend and starting the power head, thus enabling the drill pipe connected below the power head to rotate and drill into soil at the designed pile location of the cast-in-place pile; S6: separating the power head from the drill pipe connected below the power head, and driving the power head to ascend; and S7: repeating steps of S1 to S6 to connect the plurality of drill pipes on the moving assembly in turn and drill the plurality of drill pipes into the soil at the designed pile location of the cast-in-place pile.
13. A cast-in-place pile construction method carried out by the portal pile driver according to claim 5, and the method comprising following steps: S1: starting the moving assembly to convey one of the plurality of drill pipes on the moving assembly to the loading zone; S2: starting the lifting assembly, enabling the picking part to grasp the drill pipe at the loading zone, enabling the lifting assembly to pivot after the moving assembly is away from the loading zone, so as to drive the drill pipe grasped by the picking part to switch from the horizontal state to the upright state and move to the position below the power head; S3: connecting a top end of the drill pipe grasped by the picking part to the power head, and then enabling the picking part to release the grasped drill pipe; S4: driving the power head to descend to move the drill pipe connected below the power head to a top end of a drill pipe buried at a designed pile location of a cast-in-place pile, and connecting a bottom end of the drill pipe connected below the power head to the top end of the buried drill pipe; S5: continuing to drive the power head to descend and starting the power head, thus enabling the drill pipe connected below the power head to rotate and drill into soil at the designed pile location of the cast-in-place pile; S6: separating the power head from the drill pipe connected below the power head, and driving the power head to ascend; and S7: repeating steps of S1 to S6 to connect the plurality of drill pipes on the moving assembly in turn and drill the plurality of drill pipes into the soil at the designed pile location of the cast-in-place pile.
14. A cast-in-place pile construction method carried out by the portal pile driver according to claim 6, and the method comprising following steps: S1: starting the moving assembly to convey one of the plurality of drill pipes on the moving assembly to the loading zone; S2: starting the lifting assembly, enabling the picking part to grasp the drill pipe at the loading zone, enabling the lifting assembly to pivot after the moving assembly is away from the loading zone, so as to drive the drill pipe grasped by the picking part to switch from the horizontal state to the upright state and move to the position below the power head; S3: connecting a top end of the drill pipe grasped by the picking part to the power head, and then enabling the picking part to release the grasped drill pipe; S4: driving the power head to descend to move the drill pipe connected below the power head to a top end of a drill pipe buried at a designed pile location of a cast-in-place pile, and connecting a bottom end of the drill pipe connected below the power head to the top end of the buried drill pipe; S5: continuing to drive the power head to descend and starting the power head, thus enabling the drill pipe connected below the power head to rotate and drill into soil at the designed pile location of the cast-in-place pile; S6: separating the power head from the drill pipe connected below the power head, and driving the power head to ascend; and S7: repeating steps of S1 to S6 to connect the plurality of drill pipes on the moving assembly in turn and drill the plurality of drill pipes into the soil at the designed pile location of the cast-in-place pile.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0043] To describe the technical solutions of the specific embodiments of the present disclosure or in the prior art more clearly, the following briefly introduces the accompanying drawings required for describing the specific embodiments or the prior art. Apparently, the accompanying drawings in the following description show merely some embodiments of the present disclosure, and those of ordinary skill in the art may still derive other drawings from these accompanying drawings without creative efforts.
[0044]
[0045]
[0046]
[0047]
[0048]
[0049]
[0050]
[0051]
[0052]
[0053]
[0054]
[0055]
[0056]
[0057]
[0058]
[0059]
[0060]
[0061]
[0062]
[0063]
[0064]
[0065]
[0066]
[0067]
[0068]
[0069]
[0070]
[0071]
[0072]
[0073]
[0074]
[0075]
[0076]
[0077]
[0078]
[0079] In the drawings: 1 portal frame; 10 power head; 100 positioning part; 11 fixed rod; 12 lifting rod; 2 pile frame platform; 20 guide rail; 21 turntable mechanism; 22 extension frame; 3 moving assembly; 30 sliding mechanism; 300 first clamping position; 301 second clamping position; 302 pulley; 303 scissor mechanism; 304 sliding support; 4 lifting assembly; 40 picking part; 41 mechanical arm; 5 original drill pipe; 6 spare drill pipe; 7 traveling assembly; 8 self-adjusting counterweight assembly; 9 control system.
DETAILED DESCRIPTION OF THE EMBODIMENTS
[0080] To make the objectives, technical solutions and advantages of the present disclosure more clearly, the following clearly and completely describes the technical solutions in the embodiments of the present disclosure with reference to the accompanying drawings in the embodiments of the present disclosure. Apparently, the described embodiments are merely a part rather than all of the embodiments of the present disclosure. The components of the embodiments of the present disclosure generally described and illustrated in the drawings herein can be arranged and designed in a variety of different configurations. The following detailed description of the embodiments of the present disclosure provided in the accompanying drawings is not intended to limit the claimed scope of the present disclosure, but merely represents selected embodiments of the present disclosure. All other embodiments obtained by those of ordinary skill in the art based on the embodiments of the present disclosure without creative efforts shall fall within the scope of protection of the present disclosure.
EMBODIMENT
[0081] As shown in
[0082] The portal pile driver provided by the embodiment is configured for the construction of a cast-in-place pile, and partially suitable for a cast-in-place pile with a long construction length. In order to reduce the height of the pile driver, a drilling tool suitable for the portal pile driver can be divided into multiple drill pipes, one of the multiple drill pipes is provided with a drill bit, which is regarded as an original drill pipe 5, and the rest are spare drill pipes 6. Prior to constructing the cast-in-place pile, the drilling tool satisfying a drilling depth can be selected according to the design length requirements of the cast-in-place pile first, and then the original drill pipe 5 with the drill bit of the drilling tool can be connected below the power head 10 on the portal frame 1, and the multiple spare drill pipes 6 of the drilling tool can be horizontally distributed on the moving assembly 3 in turn. It should be noted that although the portal frame 1 is erected on one side of the pile frame platform 2, and the original drill pipe 5 is connected below the power head 10 installed on the portal frame 1, as the pile frame platform 2 is further provided with the moving assembly 3 and multiple spare drill pipes 6 on the moving assembly 3 are horizontally distributed, a large number of erected drill pipes will not be accumulated at the portal frame 1 on the pile frame platform 2 in this case, the center of gravity of the pile driver is free of shifting to the portal frame 1, and meanwhile, the multiple spare drill pipes 6 horizontally distributed can play a role in balancing weight, thus effectively ensuring the balance stability of the portal pile driver.
[0083] In the process of constructing a cast-in-place pile, the original drill pipe 5 and the spare drill pipes 6 need to be connected in turn to form a drilling tool satisfying the design length requirements of the cast-in-place pile. Specifically, the portal pile driver is moved to a construction area of the cast-in-placed pipe, and the power head 10 is located above a designed pile location of the cast-in-place pile, and then, as shown in
[0084] By repeating the above processes of moving the spare drill pipe 6, pivoting the spare drill pipe 6, connecting the spare drill pipe 6 to the power head 10, lowering the power head 10, connecting the spare drill pipe 6 to the original drill pipe 5, and drilling the spare drill pipe 6 into the soil, the multiple spare drill pipes 6 can be connected and drilled into the soil in turn, and thus a drilling tool formed by connecting the multiple drilling pipes can be drilled into the soil at the designed pile location of the cast-in-place pile. The drilling tool can satisfy the design length requirements of the cast-in-place, and can be used in constructing the cast-in-place pile.
[0085] After the picking part 40 grasps the spare drill pipe 6 at the loading zone, in order to prevent the lifting assembly 4 and the moving assembly 3 from interfering with each other in the subsequent process of moving the spare drill pipe 6, as shown in
[0086] It should be noted that in the process of connecting the multiple spare drill pipes 6 in turn, the horizontally distributed spare drill pipes 6 that have not moved to the loading zone on the pile frame platform 2 can continue to play the role of counterweight to ensure the balance and stability of the portal pile driver. Meanwhile, because each spare drill pipe 6 will be driven into the soil after being connected, the weight at the portal frame 1 is free of increasing continuously with the progress of the pipe connecting operation. Even if the pipe connecting operation enters the later stage, and there are no horizontal spare drill pipes 6 distributed on the pile frame platform, the center of gravity of the portal pile driver is still free of shifting to the portal frame, and the stability of the portal pile driver can still be guaranteed.
[0087] It also should be noted that no matter a connection process between the original drill pipe 5 and the power head 10, the connection process between the spare drill pipe 6 and the power head 10, or the connection process between two adjacent drill pipes, manual connection or automatic connection can be adopted.
[0088] The automatic connection mode may be achieved using a connector assembly with an elastic pin. Specifically, the connector assembly includes a male connector and a female connector, one of which is provided with an elastic pin and the other is provided with a slot. When the male connector and the female connector are butted, the elastic pin can be automatically inserted into the slot, and the elastic pin can be withdrawn from the slot when pressed under the action of an external force, and at this time, the male connector and the female connector can be separated from each other. Further, each of the power head 10 and the bottom end of the spare drill pipe 6 may be provided with the female connector, and the top end of each drill pipe may employ the male connector. When the spare drill pipe 6 is horizontally placed on the moving assembly 3, the male connector of the spare drill pipe 6 perpendicular to the plane where the portal frame 1 is arranged adjacent to the portal frame 1, and the female connector of the spare drill pipe 6 can be arranged far away from the portal frame 1.
[0089] In addition, in order to improve the connection accuracy between the power head 10 and the spare drill pipe 6, the power head 10 may be provided with a positioning part 100, the positioning part 100 is configured to abut against a circumferential side wall of the spare drill pipe 6 to limit the spare drill pipe 6 when the spare drill pipe 6 is erected below the power head 10, and thus the spare drill pip 6 can be stably located below the power head 10.
[0090] Compared with the prior art, by horizontally placing multiple drill pipes on the orderly moving assembly 3 and grasping and lifting each drill pipe point-to-point through the lifting assembly 4, the multiple drill pipes horizontally placed at different stations can be sent to the same position (below the power head 1) in the portal frame 1 in turn by a single stroke route of the lifting assembly 4, such that the processes of conveying the drill pipes, connecting drill pipes and drilling the drill pipes into the soil can be carried out completely and orderly. Meanwhile, the portal pile driver can balance the pile driver by horizontally distributing multiple drill pipes on the moving assembly 3, so as to ensure the stability of the portal pile driver. In the process of connecting the drill pipes, the center of gravity of the portal pile driver can be kept from shifting to the portal frame 1 by using the process of drilling the drill pipes into the soil after the drill pipes are connected and the horizontally distributed drill pipes that have not been connected, so as to keep the use stability of the portal pile driver.
[0091] As can be seen from the embodiment that the portal pile driver may achieve the ordered placement of the spare drill pipes 6, and thus the spare drill pipes 6 can be safely, stably and reliably located on the portal pile driver, without causing the center of gravity of the portal pile driver to shift and overturn. Meanwhile, as the moving assembly 3 can move in orderly along a simple route on the pile frame platform 2, each spare drill pipe 6 can be automatically moved to the loading zone and aligned with the picking part 40 of the lifting assembly 4, and then the spare drill pipe 6 can be switched from the horizontal state to the upright state and located below the power head 10 through a pivoting action of the lifting assembly 4. Therefore, the portal pile driver provided by this embodiment can complete the work of taking, conveying and connecting the drill pipes through three simple continuous actions of orderly placing the drill pipes horizontally, moving the drill pipes horizontally and pivoting the drill pipes. The problems of poor stability and not smoothly connecting the pipes of the existing pile driver are overcome.
[0092] In this embodiment, a vertical force applying mechanism for driving the power head 10 to ascend or descend may be installed on the portal frame 1. The vertical force applying mechanism may employ an air cylinder, an oil cylinder and other telescopic driving devices. It should be noted that the structure of the vertical force applying mechanism is not limited, which may employ any device capable of driving the power head 10 to ascend and descend. For example, the vertical force applying mechanism may also employ a chain device, or a winch device.
[0093] As shown in
[0094] Further, each upright column of the portal frame 1 may be formed by slidably connecting a fixed rod 11 and a lifting rod 12, and the power head 10 is fixedly connected to the lifting rod 12. The vertical force applying mechanism may be installed on the portal frame 1, an output end of the vertical force applying mechanism is connected to the power head 10. The vertical force applying mechanism is configured for driving the power head 10 to ascend or descend, and meanwhile, the lifting rod 12 can be driven by the power head 10 to vertically slide on the fixed rod 11. In this case, the fixed rod 11 and the lifting rod 12 may form a slide rail structure, thus effectively improving the lifting stability of the power head 10 on the portal frame 1.
[0095] In this embodiment, in order to facilitate the movement of the portal pile driver, a traveling assembly 7 may also be installed at the bottom of the pile frame platform 2. Further, in this embodiment, the traveling assembly 7 is preferably a crawler traveling mechanism or a walking-frame traveling mechanism. In order to improve the supporting strength of the pile frame platform 2 in the portal pile driver, in this embodiment, the pile frame platform 2 preferably includes a housing, and a supporting structure installed in the housing. The supporting structure is formed by connecting multiple force-bearing rod members.
[0096] As shown in
[0097] As shown in
[0098] It should be noted that when multiple sliding mechanisms 30 are provided, and each sliding mechanism 30 is configured for supporting multiple spare drill pipes 6, each spare drill pipe 6 can be accurately moved to the loading zone by adjusting the moving stroke of the sliding mechanism 30.
[0099] It also should be noted that the picking part 40 at the loading zone and the multiple sliding mechanisms 30 are distributed in a staggered manner in the direction perpendicular to the plane where the portal frame 1 is located, which can prevent a situation that the spare drill pipe 6 is hard to be moved in place due to the mutual obstruction between the picking part 40 and the sliding mechanisms 30.
[0100] In addition, in order to prevent the spare drill pipe 6 on the sliding mechanism 30 moved to the loading zone and the picking part 40 from interfering with each other, as shown in
[0101] As shown in
[0102] As shown in
[0103] As shown in
[0104] The guide tail 20 not only can limit a moving direction of the sliding mechanism 30, but also can reduce the friction between the sliding mechanism 30 and the pile frame platform 2, thus improving the moving smoothness of the sliding mechanism 30.
[0105] Further, the number of moving assemblies 3 is even, and the even number of moving assemblies 3 are divided into two groups, and the two groups of moving assemblies 3 are symmetrically distributed on both sides of the loading zone. When the even number of moving assemblies 3 are symmetrically distributed, the distribution of the moving assemblies 3 can be more orderly and uniform, and the distribution of the spare drill pipes 6 are more orderly and uniform, thus effectively improving the counterweight balance of the portal pile driver.
[0106] As shown in
[0107] The first clamping positions 300 on the multiple sliding mechanisms 30 are configured for supporting a spare drill pipe 6, and the second clamping positions 301 on the multiple sliding mechanisms 30 are configured for supporting another spare drill pipe 6, and at this time, each moving assembly 3 can support two drill pipes.
[0108] As shown in
[0109] If the sliding mechanism 30 is of a telescopic structure in this case, the slider may be a hood with an opening at the bottom, and the sliding mechanism 30 also includes a bottom plate and a scissor mechanism 303. The bottom plate is arranged at the bottom of the slider, and the pulley 302 is installed on a bottom surface of the bottom plate, and the scissor mechanism 303 is connected between a top surface of the bottom plate and an inner wall of the slider. The scissor mechanism 303 is formed by hinging multiple connecting rods and can be extended or retracted, thus driving the hollow slider to ascend or descend relative to the bottom plate.
[0110] Further, when the first clamping position 300 and the second clamping position 301 are both clamping grooves, the first clamping groove 300 and the second clamping position 301 may be located at the same height, and in this case, the first clamping position 300 and the second clamping position 301 may be distributed at the top of the sliding mechanism 30 at intervals in a moving direction of the sliding mechanism 30.
[0111] Alternatively, as shown in
[0112] As shown in
[0113] To prevent the first clamping position 300 and the second clamping position 301 from interfering with each other, as shown in
[0114] When the first clamping position 300 and the second clamping position 301 are both supporting plates, the sliding supports 304 of the multiple sliding mechanisms 30 of the moving assembly 3 may be successively moved in batches. Specifically, as shown in
[0115] After the sliding support 304 provided with the first clamping position 300 is moved back to the original position, the spare drill pipe 6 at the second clamping position 301 of the sliding support 304 can be moved to the loading zone. It should be noted that as the multiple sliding mechanisms 30 of the moving assembly 3 are distributed at intervals in the direction perpendicular to the plane where the portal frame 1 is located, when the spare drill pipe 6 is no longer supported on the first clamping position 300 of the sliding supports 304, the moving process of the sliding support 304 with the second clamping position 301 is no longer hindered by the spare drill pipe 6 at the first clamping position 300. In this case, only the sliding support 304 with the second clamping position 301 of the sliding mechanism 30 is pushed to move in the direction parallel to the plane where the portal frame 1 is located by an external force until the spare drill pipe 6 at the second clamping position 301 is moved to the loading zone.
[0116] In addition, when the first clamping position 300 and the second clamping position 301 are both supporting plates and the sliding mechanism 30 is of a telescopic structure, the sliding support 304 may employ a telescopic support. Specifically, the sliding support 304 includes a horizontal rod with a perforation and a vertical rod perpendicularly connected to the horizontal rod. A sliding rod is slidably connected to the vertical rod, and the first clamping position 300 or the second clamping position 301 is arranged at one side of the sliding rod. In this case, the expansion and retraction of the sliding support 304 can be achieved by sliding the slide rod on the vertical rod, thereby driving the first clamping position 300 or the second clamping position 301 to ascend and descend.
[0117] As shown in
[0118] In this embodiment, the pile frame platform 2 may also be provided with a movement driving mechanism which is configured for applying an external force to the moving assembly 3, so as to push the moving assembly 3 to move on the pile frame platform 2. Further, the movement driving mechanism may employ an air cylinder, an oil cylinder, and other telescopic driving devices, or a conveying device including a motor and a conveyor chain.
[0119] It should be noted that the sliding mechanism 30 of the moving assembly 3 provided by the embodiment is not limited to be provided with the first clamping position 300 and the second clamping position 301, but also can be additionally provided with a third clamping position, a fourth clamping position and other clamping positions according to actual needs. Moreover, the structural form of the sliding mechanism 300 is not limited to above two, and any structure capable of orderly conveying the spare drill pipe 6 to the loading zone in a simple route can be adopted.
[0120] As shown in
[0121] The jacking driving mechanism may employ an air cylinder, an oil cylinder and other telescopic driving devices. The open and close of the mechanical gripper may be achieved in a mechanical or pneumatic manner. Correspondingly, the mechanical gripper may employ an electric gripper, or a pneumatic gripper.
[0122] The mechanical arm 41 in the lifting assembly 4 provided by this embodiment is configured for switching between the horizontal state and the upright state under the driving of the jacking driving mechanism, thus driving the spare drill pipe 6 to switch between the horizontal state and the upright state. The spare drill pipe 6 can be accurately located below the power head 10 when pivoting to the upright state, and thus the mechanical arm 41 may only pivot in the range of 0-90 degrees.
[0123] In order to improve the use flexibility of the mechanical arm 41, it is preferred that the length of the mechanical arm 41 is less than that of the spare drill pipe 6, and the picking part 41 may be installed at the suspension end of the mechanical arm 41 at this time.
[0124] As shown in
[0125] When the hinged end of the mechanical arm 41 is located between the portal frame 1 and the loading zone, in order to ensure that the spare drill pipe 6 can be accurately located below the power head 10 when pivoted to the upright state, after the mechanical gripper on the mechanical arm 41 grasps the spare drill pipe 6, the spare drill pipe 6 should be located on one side, close to the portal frame 1, of the mechanical arm 41. Therefore, the mechanical gripper can be directly installed on the arm surface, facing away from the pile frame platform 2, of the mechanical arm 41. Alternatively, the mechanical gripper can be installed on the arm surface, facing the pile frame platform 2, of the mechanical arm 41, and a turntable mechanism 21 is provided to allow the erected mechanical arm 41 to rotate, so as to drive the spare drill pipe 6 to steer.
[0126] Specifically, for the case of directly installing the mechanical gripper on the arm surface, facing away from the pile frame platform 2, of the mechanical arm 41, as shown in
[0127] For the case of installing the mechanical gripper on the arm surface, facing the pile frame platform 2, of the mechanical arm 41, as shown in
[0128] The turntable mechanism 21 may employ a rotary driving device including a motor.
[0129] In this embodiment, after the mechanical gripper grasps the spare drill pipe 6 by adjusting the position of the mechanical arm 41, the spare drill pipe 6 can be located at one side, close to the portal frame 1, of the mechanical arm 41. Specifically, as shown in
[0130] As shown in
[0131] In addition, in order to prevent the mechanical arm 41 from hindering the connection process of the spare drill pipes 6, as shown in
[0132] It should be noted that in order to prevent the extension frame 22 from hindering the connecting and drilling process of the drill pipes, a position of the extension frame 22 corresponding to the power head 10 need to be provided with through holes for the power head 10 and the drill pipe to pass through.
[0133] In order to improve the balance of the portal pile driver, the preferred portal pile driver in this embodiment further includes a counterweight structure, and the counterweight structure is installed on one side, opposite to the portal frame 1, of the portal frame platform 2, thus preventing the center of gravity of the pile driver from shifting to one side of the portal frame 1. In this embodiment, preferably, the counterweight structure is a self-adjusting counterweight assembly 8. Further, the portal pile driver includes a monitoring system, and a control system 9. The self-adjusting counterweight assembly 8 is installed on one side, away from the portal frame 1, of the portal frame platform 2, and includes a moving portion capable of moving in a direction perpendicular to the plane where the portal frame 1 is located. The self-adjusting counterweight assembly 8 and the monitoring system are both connected to the control system 9. The monitoring system is configured to monitor a weight change at the portal frame 1 of the portal pile driver, and the control system 9 is configured to calculate a amount of moving of the moving portion according to the weight change monitored by the monitoring system, and to drive the moving portion to move in the direction perpendicular to the plane where the portal frame 1 is located according to the moving amount.
[0134] The self-adjusting counterweight assembly 8 may employ a telescopic structure. In this case, the moving portion is a telescopic end of the self-adjusting counterweight assembly 8, the monitoring system is configured for sensing the weight change at the portal frame 1 of the portal pile driver, and the control system 9 can control the telescopic amount of the self-adjusting counterweight assembly 8 according to a monitoring result of the monitoring system, such that the self-adjusting counterweight assembly 8 can automatically extend or retract according to the weight change at the portal frame 1 to adjust a torque of one side, away from the portal frame 1, of the pile driver platform 2, thus changing the center of gravity of the portal pile driver and maintaining the balance of the portal pile driver.
[0135] Further, the self-adjusting counterweight assembly 8 may employ an oil cylinder. In practical application, the self-adjusting counterweight assembly 8 may also employ a slide block slidably connected to the pile frame platform 2. The monitoring system may include a weight sensor, and the control system 9 may employ a programmable logic controller, or a single microcomputer. The control system 9 may also be connected to the moving assembly 3, and the moving assembly 3 can be controlled by the control system 9 to move in a preset path, and there is no need of a cab on the portal pile driver.
[0136] In conclusion, according to the portal pile driver provided by this embodiment, the spare drill pipes 6 can be placed on the moving assembly 3 in parallel, then moved transversely in order to be conveyed to the loading zone. Afterwards, by means of the pivoting process of the lifting assembly 4, the multiple spare drill pipes 6 can be orderly sent to a position below the power head 10 on the portal frame 1 in a simple route, so as to be connected. The portal pile driver can complete the processes of grasping and connecting the drill pipes through simple actions, and the construction requirements of a super-long pile can be satisfied by connecting the drill pipes, and the height of the portal frame 1 does not need to be set too high. Therefore, the portal pile machine provided by this embodiment can achieve the construction of cast-in-place piles with different pile lengths in spaces with different heights (including low spaces such as tunnels) by horizontally placing and orderly combining the drill pipes, and automatically, highly and safely connecting the drill pipes on the premise of using the low portal frame 1.
[0137] It can be seen that the portal pile driver provided by this embodiment breaks the traditional design concept that the height of the upright column and the length of the drilling tool must satisfy the design pile length in the current mainstream heavy pile driver, and solves the problem that the vertical pre-fixed spare heavy drilling tool often causes the center of gravity of the pile driver to shift, resulting in the overweight front end of the pile driver. The portal pile driver provided by this embodiment is a subversive technology to the existing pile driver, can achieve the lowering of the portal frame 1, the flat laying of the drill pipes and automatic connection of the drill pipes, and is an efficient, energy-saving, safe, high-automatic and low-cost piling machinery.
[0138] It also should be noted that when a spare heavy drilling tool is vertically fixed to one side of the upright column of the existing portal frame 1 of the pile driver in advance, in order to ensure the balance of the center of gravity of the pile driver, a counterweight has to be added, thus a phenomenon that the weight of the pile driver is often increased from 150 tons to more than 300 tons when driving a pile of 70 meters occurs, which increases the construction cost. Moreover, in order to ensure the safety of the pile, steel plates need to be laid in a large area on the construction site before construction, which further increases the construction cost. According to the portal pile driver provided by this embodiment, the drilling depth of the drilling tool is not limited to the length of a single drilling tool by laying the drill pipes flat, and there is no need of increasing the counterweight to guarantee the balance of the center of gravity of the pile driver. For this alone, the weight of the portal pile driver provided by this embodiment can be reduced by 30-40% compared with the existing pile driver, thus effectively reducing the manufacturing cost of the pile driver. In addition, the portal pile driver provided by this embodiment employs a vertical force applying mechanism to cooperate with the power head 10 at the portal frame 1, such that the soil can be squeezed during the drilling process of the drill pipe, and a pile hole can be dug by rotation, the construction without taking soil is achieved, and the purposes of energy saving and emission reduction are achieved.
[0139] It should be noted that, compared with CN202688997U, the portal pile driver provided by this embodiment provides a specific technical solution of lowering the height and the center of gravity of the portal frame 1 and increasing the length of the constructed pile.
[0140] Compared with the technical solution of CN208950504U, which can increase the piling depth only by one time, and increases the hidden danger of the unstable center of gravity of the pile driver, the portal pile driver provided by this embodiment can achieve more times of piling depth in a case of enhancing the stability of the pile driver without increasing the height of the pile driver (the portal pile driver provided by this embodiment does not need to consider the unstable center of gravity caused by the erected drill pipes, and the piling depth can be increased by adding the number or length of spare drill pipes 6).
[0141] Compared with CN203851446U, through the vertical force applying mechanism, the power head 10 on the portal frame 1 and the connector assembly with an elastic pin, the portal pile driver provided by this embodiment also has complex functions that cannot be associated with the agricultural technical field, such as rotating the drilling tool, drilling down, lifting the drilling tool and automatically connecting the drill pipes. In addition, according to the portal pile driver provided by this embodiment, a single-column upright column of the traditional pile driver can be replaced with the portal frame 1, and thus the spare drill pipe 6 can be directly moved into the portal frame 1, or directly pass through the portal frame 1, without bypassing the single-column upright column and taking a complicated route.
[0142] Compared with CN209556966U, according to the portal pile driver provided by this embodiment, the moving assembly 3 can be moved away after the drill pipe is grasped by the picking part 40, and there is no free fall of the drill pipe in the whole process. In the operating process, multiple drill pipes can be automatically conveyed to the loading zone in turn by pre-programming the control system 9 of the portal pile driver, such that the pick-up part 40 can automatically pick up multiple drill pipes in turn without manpower or other auxiliary machinery to convey the drill pipes.
[0143] Compared with CN110939132A, the self-adjusting counterweight assembly 8 of the portal pile driver provided by this embodiment can cooperate with the control system 9 and the monitoring system, so as to have the characteristics of rapid adjustment. According to the portal pile driver provided by this embodiment, the mode for adjusting the horizontal center of gravity position by changing the torque is more in line with the requirements of the portal pile driver provided by this embodiment.
[0144] However, about the piling machinery provided by CN216381270U, CN105756060A and CN107023267B, due to the limitation of the traditional single-column upright column structure, the grasping and moving processes of the corresponding drill pipes have to bypass the single upright column, which in turn leads to the complicated mechanism of the pile machinery and difficulty in simplification. Although the erection of the drill pipes 6 is beneficial to the conveying and connecting of the drill pipes, the instability of the pile foundation is caused. However, according to the portal pile driver provided by this embodiment, a way of laying the spare drill pipes 6 flat is provided, combined with the improvement of the whole machine structure, the process of grasping and moving the drill pipe can be achieved smoothly when employing the low portal frame 1. Compared with the piling machinery with erected drill pipes, the portal pile driver provided by this embodiment is safer, and more stable. Meanwhile, by laying the drill pipes flat, the contact area between the drill pipes and the pile frame platform 2 can be increased, the point load when placing the drill pipe vertically is changed into a surface load with smaller pressure after the drill pipe is placed flat. The strength requirement of the pile driver can be reduced, and thus the manufacturing cost of the pile driver is reduced.
[0145] As shown in
[0153] Steps S1-S7 of the cast-in-place pile construction method provided by this embodiment are all the connecting processes of the drill pipes laid flat on the pile frame platform 2, i. e. the connecting processes of the spare drill pipe 6 mentioned above. However, the original drill pipe 5 with the drill bit is usually directly connected below the power head 10 to ready for drilling. Therefore, the cast-in-place pile construction method provided by this embodiment may further include steps of S01 and S02 before the step of S1: [0154] S01: moving the portal pile driver to a construction area of the cast-in-place pile, and enabling the power head 10 on the portal driver 1 of the portal pile driver to be located above the designed pile location of the cast-in-place pile; and [0155] S02: connecting the drill pipe with the drill bit below the power head 10 on the portal frame 1 of the portal pile driver, lowering the power head 10 and starting the power head 10 to drive the drill pipe with the drill bit to rotate and drill into the soil at the designed pile location of the cast-in-place pile.
[0156] The cast-in-place construction method provided by this embodiment is carried out by the portal pile driver, and through the cast-in-place pile construction method, the pile driver can be balanced by distributing the multiple drill pipes horizontally on the moving assembly 3, so as to guarantee the stability of the portal pile driver. In the process of the connecting the drill pipes, the center of gravity of the portal pile driver is continuously kept from shifting to the portal frame 1 by the drilling down process after the drill pipes are connected and the horizontally distributed drill pipes that have not been connected, thus continuing to guarantee the use stability of the portal pile driver.
[0157] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present disclosure rather than limiting. Although the present disclosure has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that it is still possible to modify the technical solution recorded in the foregoing embodiments, or to replace some technical features with equivalents. However, these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of various embodiments of the present disclosure.