Continuous annealing furnace and continuous annealing method for steel strips
09702020 ยท 2017-07-11
Assignee
Inventors
Cpc classification
F27D17/10
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
C23C2/0035
CHEMISTRY; METALLURGY
C23C2/00344
CHEMISTRY; METALLURGY
C23C2/0038
CHEMISTRY; METALLURGY
C23C2/28
CHEMISTRY; METALLURGY
F27B9/28
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
International classification
F27D17/00
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
C23C2/00
CHEMISTRY; METALLURGY
F27B9/28
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
C23C2/02
CHEMISTRY; METALLURGY
C23C2/28
CHEMISTRY; METALLURGY
Abstract
The invention provides a vertical annealing furnace including a heating zone and a soaking zone without any partition wall therebetween. The furnace has furnace-to-refiner gas suction openings disposed in a lower portion of a joint between the soaking zone and a cooling zone and in the heating zone and/or the soaking zone except a region extending 6 m in a vertical direction and 3 m in a furnace length direction both from a steel strip inlet at a lower portion of the heating zone. The furnace has refiner-to-furnace gas ejection openings disposed in a region in the joint between the soaking zone and the cooling zone, the region being located above the pass line in the joint, and in a region in the heating zone located above 2 m below the center of upper hearth rolls in the vertical direction.
Claims
1. A continuous annealing furnace for a steel strip comprising a heating zone, a soaking zone and a cooling zone disposed in this order and configured to transport the steel strip in upward and/or downward directions, a joint connecting the soaking zone and the cooling zone being disposed at an upper portion of the furnace, the heating zone and the soaking zone having no partition wall therebetween, the furnace being a vertical annealing furnace and being configured such that an atmosphere gas is supplied from outside the furnace into the furnace, the gas in the furnace is discharged through a steel strip inlet at a lower portion of the heating zone while part of the gas in the furnace is suctioned and introduced into a refiner equipped with an oxygen removal device and a dehumidifier to lower the dew point by the removal of oxygen and water in the gas, the refiner being disposed outside the furnace, and the gas with the lowered dew point is returned into the furnace, the furnace having gas suction openings disposed in a lower portion of the joint between the soaking zone and the cooling zone and at least one of in the heating zone and the soaking zone, the heating zone being free from any gas suction openings in a region extending 6 m in a vertical direction and 3 m in a furnace length direction both from the steel strip inlet at a lower portion of the heating zone, the furnace having gas ejection openings disposed in a region in the joint between the soaking zone and the cooling zone, the region being located above a pass line in the joint, and in a region in the heating zone, the region being located above a position 2 m below the center of upper hearth rolls in the vertical direction.
2. The continuous annealing furnace for a steel strip according to claim 1, wherein the gas ejection openings in the heating zone have an ejection width W0 satisfying W0/W > wherein W is the furnace width of the heating zone plus the soaking zone, the ejection width W0 of the gas ejection openings being defined as the distance in the furnace length direction between the most upstream gas ejection opening and the most downstream gas ejection opening in the heating zone.
3. The continuous annealing furnace for a steel strip according to claim 1, wherein the gas suction opening disposed in the lower portion of the joint between the soaking zone and the cooling zone is disposed in a choked gas flow channel in the lower portion of the joint between the soaking zone and the cooling zone.
4. The continuous annealing furnace for a steel strip according to claim 1, wherein the gas suction openings are disposed in a plurality of positions in the heating zone and/or the soaking zone, and the furnace has dew point detection units of dew point meters disposed in the vicinity of the gas suction openings in the plurality of positions, the dew point detection units being configured to detect the dew points of the gas in the furnace.
5. The continuous annealing furnace for a steel strip according to claim 1, wherein the cooling zone is configured to transport the steel strip therethrough in a single pass.
6. The continuous annealing furnace for a steel strip according to claim 1, wherein the furnace includes a hot dip galvanization facility downstream from the annealing furnace.
7. The continuous annealing furnace for a steel strip according to claim 6, wherein the hot dip galvanization facility includes a galvannealing apparatus.
8. A continuous annealing method for a steel strip, characterized by continuously annealing a steel strip with the continuous annealing furnace for a steel strip described in claim 4 in such a manner that the dew point of a gas in the furnace is measured with the dew point meters disposed at the heating zone and/or the soaking zone, and the gas in the furnace is suctioned preferentially through the gas suction opening disposed in a position where a higher value of dew point has been measured.
9. The continuous annealing furnace for a steel strip according to claim 2, wherein the gas suction opening disposed in the lower portion of the joint between the soaking zone and the cooling zone is disposed in a choked gas flow channel in the lower portion of the joint between the soaking zone and the cooling zone.
10. The continuous annealing furnace for a steel strip according to claim 2, wherein the gas suction openings are disposed in a plurality of positions in the heating zone and/or the soaking zone, and the furnace has dew point detection units of dew point meters disposed in the vicinity of the gas suction openings in the plurality of positions, the dew point detection units being configured to detect the dew points of the gas in the furnace.
11. The continuous annealing furnace for a steel strip according to claim 3, wherein the gas suction openings are disposed in a plurality of positions in the heating zone and/or the soaking zone, and the furnace has dew point detection units of dew point meters disposed in the vicinity of the gas suction openings in the plurality of positions, the dew point detection units being configured to detect the dew points of the gas in the furnace.
12. The continuous annealing furnace for a steel strip according to claim 9, wherein the gas suction openings are disposed in a plurality of positions in the heating zone and/or the soaking zone, and the furnace has dew point detection units of dew point meters disposed in the vicinity of the gas suction openings in the plurality of positions, the dew point detection units being configured to detect the dew points of the gas in the furnace.
13. The continuous annealing furnace for a steel strip according to claim 2, wherein the cooling zone is configured to transport the steel strip therethrough in a single pass.
14. The continuous annealing furnace for a steel strip according to claim 3, wherein the cooling zone is configured to transport the steel strip therethrough in a single pass.
15. The continuous annealing furnace for a steel strip according to claim 4, wherein the cooling zone is configured to transport the steel strip therethrough in a single pass.
16. The continuous annealing furnace for a steel strip according to claim 9, wherein the cooling zone is configured to transport the steel strip therethrough in a single pass.
17. The continuous annealing furnace for a steel strip according to claim 10, wherein the cooling zone is configured to transport the steel strip therethrough in a single pass.
18. The continuous annealing furnace for a steel strip according to claim 11, wherein the cooling zone is configured to transport the steel strip therethrough in a single pass.
19. The continuous annealing furnace for a steel strip according to claim 12, wherein the cooling zone is configured to transport the steel strip therethrough in a single pass.
20. The continuous annealing furnace for a steel strip according to claim 2, wherein the furnace includes a hot dip galvanization facility downstream from the annealing furnace.
21. The continuous annealing furnace for a steel strip according to claim 3, wherein the furnace includes a hot dip galvanization facility downstream from the annealing furnace.
22. The continuous annealing furnace for a steel strip according to claim 4, wherein the furnace includes a hot dip galvanization facility downstream from the annealing furnace.
23. The continuous annealing furnace for a steel strip according to claim 5, wherein the furnace includes a hot dip galvanization facility downstream from the annealing furnace.
24. The continuous annealing furnace for a steel strip according to claim 9, wherein the furnace includes a hot dip galvanization facility downstream from the annealing furnace.
25. The continuous annealing furnace for a steel strip according to claim 10, wherein the furnace includes a hot dip galvanization facility downstream from the annealing furnace.
26. The continuous annealing furnace for a steel strip according to claim 11, wherein the furnace includes a hot dip galvanization facility downstream from the annealing furnace.
27. The continuous annealing furnace for a steel strip according to claim 12, wherein the furnace includes a hot dip galvanization facility downstream from the annealing furnace.
28. The continuous annealing furnace for a steel strip according to claim 13, wherein the furnace includes a hot dip galvanization facility downstream from the annealing furnace.
29. The continuous annealing furnace for a steel strip according to claim 14, wherein the furnace includes a hot dip galvanization facility downstream from the annealing furnace.
30. The continuous annealing furnace for a steel strip according to claim 15, wherein the furnace includes a hot dip galvanization facility downstream from the annealing furnace.
31. The continuous annealing furnace for a steel strip according to claim 16, wherein the furnace includes a hot dip galvanization facility downstream from the annealing furnace.
32. The continuous annealing furnace for a steel strip according to claim 17, wherein the furnace includes a hot dip galvanization facility downstream from the annealing furnace.
33. The continuous annealing furnace for a steel strip according to claim 18, wherein the furnace includes a hot dip galvanization facility downstream from the annealing furnace.
34. The continuous annealing furnace for a steel strip according to claim 19, wherein the furnace includes a hot dip galvanization facility downstream from the annealing furnace.
35. A continuous annealing method for a steel strip, characterized by continuously annealing a steel strip with the continuous annealing furnace for a steel strip described in claim 10 in such a manner that the dew point of a gas in the furnace is measured with the dew point meters disposed at the heating zone and/or the soaking zone, and the gas in the furnace is suctioned preferentially through the gas suction opening disposed in a position where a higher value of dew point has been measured.
36. A continuous annealing method for a steel strip, characterized by continuously annealing a steel strip with the continuous annealing furnace for a steel strip described in claim 11 in such a manner that the dew point of a gas in the furnace is measured with the dew point meters disposed at the heating zone and/or the soaking zone, and the gas in the furnace is suctioned preferentially through the gas suction opening disposed in a position where a higher value of dew point has been measured.
37. A continuous annealing method for a steel strip, characterized by continuously annealing a steel strip with the continuous annealing furnace for a steel strip described in claim 12 in such a manner that the dew point of a gas in the furnace is measured with the dew point meters disposed at the heating zone and/or the soaking zone, and the gas in the furnace is suctioned preferentially through the gas suction opening disposed in a position where a higher value of dew point has been measured.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1)
(2)
(3)
(4)
DETAILED DESCRIPTION OF EMBODIMENTS OF THE INVENTION
(5) A continuous hot dip galvanization line for steel strips includes an annealing furnace upstream to a coating bath. Usually, the annealing furnace includes a heating zone, a soaking zone and a cooling zone disposed in this order from the upstream to the downstream of the furnace. A preheating zone may be sometimes disposed upstream to the heating zone. The annealing furnace is connected to the coating bath via a snout. The inside of the furnace extending from the heating zone to the snout is maintained in a reducing atmosphere gas or in a non-oxidizing atmosphere. The heating zone and the soaking zone involve radiant tubes (RT) as heating units to indirectly heat the steel strip. The reducing atmosphere gas is usually H.sub.2N.sub.2 gas and is introduced into appropriate positions inside the furnace between the heating zone and the snout. On the line, the steel strip is heated and annealed at prescribed temperatures in the heating zone and the soaking zone, then cooled in the cooling zone, then transported through the snout into the coating bath in which the steel strip is hot dip galvanized, and optionally further subjected to galvannealing.
(6) Because the furnace in the continuous hot dip galvanization line (CGL) is connected to the coating bath via the snout, the gas introduced into the furnace is discharged through the entrance of the furnace except for unavoidable gas escape such as leakage from the furnace body. That is, the gas in the furnace flows from the downstream to the upstream of the furnace reverse to the direction in which the steel strip is moved. Because steam (H.sub.2O) has a lower specific gravity than N.sub.2 gas which occupies the major proportion of the atmosphere, the dew point in a multi-pass vertical annealing furnace tends to be higher at an upper portion in the furnace.
(7) To efficiently decrease the dew point, it is important that the atmosphere gas in the furnace do not stagnate (the atmosphere gas do not stagnate at an upper portion, a middle portion and a lower portion in the furnace) so that the dew point will not increase in the upper portion of the furnace. It is also important to know sources of water that increases the dew point. Possible sources of water (H.sub.2O) are furnace walls, steel strips, entry of outside air through the furnace entrance, and entry of water from the cooling zone and the snout. Leaks in radiant tubes and in furnace walls can possibly serve as water supply sources.
(8) The dew point exerts larger influences on coating properties with increasing temperature of the steel strip. The influences become particularly marked when the steel strip temperature is in the range of 700 C. and above in which the steel strip shows higher reactivity with oxygen. Accordingly, the dew point in the latter half of the heating zone and in the soaking zone where the steel strip has an elevated temperature will significantly affect coating properties. In the case where there are no physical division (such as a partition wall) between the heating zone and the soaking zone, the atmosphere is continuous from the heating zone to the soaking zone and this fact requires that the dew point be efficiently reduced in the entire region of the furnace including the heating zone and the soaking zone.
(9) Specifically, it is advantageous to be able to shorten, prior to the steady operation of continuous heat treatment of a steel strip or when the water concentration and/or the oxygen concentration in the furnace atmosphere has increased during the steady operation, a period of time that the water concentration and/or the oxygen concentration in the furnace atmosphere be lowered to such a level where the dew point of the entire furnace atmosphere is lowered to 30 C. or below at which stable production of steel strips is feasible.
(10) It is also advantageous that the dew point be lowered to 40 C. or below at which excellent suppression is possible of the oxidation of elements such as silicon and manganese. Ideally, dew point reduction is appropriately performed only in a region where the steel strip has a high temperature. However, as mentioned above, a furnace having a heating zone and a soaking zone which are not separated from each other causes a difficulty in lowering the dew point locally in the heating zone Or the soaking zone. Thus, dew point reduction should be carried out in the entirety of the heating zone and the soaking zone. A lower dew point is more advantageous in terms of coating properties. Thus, it is preferable to be able to decrease the dew point to 45 C. or below, and more preferably to 50 C. or below.
(11) According to an embodiment of the invention, the dew point of the atmosphere gas is decreased by introducing part of the atmosphere gas in the furnace to a refiner disposed outside the furnace which has an oxygen removal device and a dehumidifier to lower the dew point by the removal of oxygen and water in the gas, and thereafter returning the gas having the lowered dew point into the furnace. This process involves the following arrangements 1) to 3) of gas suction openings through which the gas in the furnace is introduced into the refiner, and gas ejection openings through which the gas having the lowered dew point is returned from the refiner into the furnace.
(12) 1) A high-dew point gas from the coating pot side finds its way to an upper portion of the cooling zone. Further, the entry of outside air through the cooling zone and the snout has to be prevented. From these viewpoints, the stagnation of the atmosphere gas at this region should be prevented. Thus, a gas suction opening for the introduction to the refiner is disposed in this region. While this suction of the gas may prevent the occurrence of gas stagnation in this region, the suctioning can possibly decrease the furnace pressure in the vicinity of this region to a negative pressure. Thus, a gas ejection opening is disposed in a joint between the soaking zone and the cooling zone, and the gas returning from the refiner is ejected therethrough. To make sure that there will be no stagnation of the gas, the gas ejection opening is desirably disposed in the furnace wall above the pass line in the soaking zone-cooling zone joint while the gas suction opening is desirably disposed in a throat section that is a lower part of the joint between the soaking zone and the cooling zone or in a choked portion of the gas flow channel such as near seal rolls. The gas suction opening is preferably located within 4 m, and more preferably within 2 m from a cooling device (a cooling nozzle) in the cooling zone, because the gas suction opening excessively remote from the cooling device causes the steel sheet to be exposed to the high-dew point gas for a long time before the start of cooling, thus causing a risk that elements such as silicon and manganese can be concentrated at the surface of the steel sheet. Further, the gas suction opening and the gas ejection opening are desirably disposed at least 2 m away from each other. If the suction opening and the ejection opening are too close to each other, the gas that is suctioned through the suction opening will contain a small proportion of high-dew point gas (the low-dew point gas returned from the refiner will represent a large proportion of the gas suctioned), resulting in a decrease in the efficiency of furnace dehumidification.
(13) 2) Ideally, a furnace gas suction opening in a heating zone and a soaking zone is disposed in a location where the dew point becomes highest. In the case, however, where the heating zone and the soaking zone are not physically separated by a partition wall, the location where the dew point becomes highest in the soaking zone is not fixed to a specific region but changes in accordance with, for example, operation conditions. Thus, it is preferable that gas suction openings be disposed in a plurality of positions in the heating zone and the soaking zone so that the gas in the furnace can be suctioned through any of the above mentioned plurality of positions. It is also desirable that the dew point of the gas in the furnace be measured in the vicinity of the plurality of suction openings and the gas in the furnace be preferentially suctioned selectively through the suction opening disposed in the location where a higher dew point has been measured. The gas suction openings are disposed in the furnace except a region extending 6 m in the vertical direction and 3 m in the furnace length direction both from a steel strip inlet at a lower portion of the heating zone. This is because, if the gas suction openings are disposed within 6 m in the vertical direction and within 3 m in the furnace length direction from the steel strip inlet at a lower portion of the heating zone, the probability is increased for an exterior gas to be drawn into the furnace to possibly increase the dew point.
(14) 3) An upper portion of the heating zone is substantially free from the flow of the furnace gas and the atmosphere gas stagnates there easily due to its structure. Accordingly, the dew point in this region tends to be high. Thus, openings are disposed in the upper portion of the heating zone to eject therethrough the gas that has returned from the refiner. To control stagnation, the gas ejection openings are advantageously disposed at as high a position as possible in the heating zone. It is therefore preferred that the gas ejection openings be disposed at least in a region located above a position 2 m below the center of upper hearth rolls in the heating zone in the vertical direction (in a region above the 2 m level in the vertical direction).
(15) If the gas ejection openings disposed in the upper portion of the heating zone have an excessively small value of ejection width W0, the effectiveness in preventing the gas stagnation at the upper portion of the heating zone is lowered. Thus, the ejection width W0 of the gas ejection openings in the upper portion of the heating zone preferably satisfies W0/W> wherein W is the furnace width of the heating zone plus the soaking zone (the total furnace width). Here, the ejection width W0 of the gas ejection openings in the heating zone is the distance in the furnace length direction between the most upstream gas ejection opening and the most downstream gas ejection opening in the heating zone (see
(16) The present invention is based on the above viewpoints.
(17) Hereinbelow, embodiments of the invention will be described with reference to
(18)
(19) In
(20) A joint 13 between the soaking zone 4 and the cooling zone 5 is disposed in an upper portion of the furnace above the cooling zone 5. In the joint 13, a roll is disposed which guides the steel strip 1 delivered from the soaking zone 4 to travel in a downward direction. In order to prevent the atmosphere in the soaking zone 4 from entering the cooling zone 5 and to prevent the entry of radiation heat from the furnace walls of the joint into the cooling zone 5, the exit at a lower portion of the joint that continues to the cooling zone 5 defines a throat section (a throat-like structure having a smaller sectional area of the steel strip channel) and seal rolls 12 are disposed in the throat section 14.
(21) The cooling zone 5 is composed of a first cooling zone 5a and a second cooling zone 5b. The first cooling zone 5a has a single pass for the steel strip.
(22) Reference sign 15 denotes an atmosphere gas supply system 15, through which an atmosphere gas is supplied from the outside to the inside of the furnace and the atmosphere gas is fed into the refiner 10 through a gas introduction pipe 16 and out of the refiner 10 through a gas delivery pipe 17.
(23) The feed rates and the supply of the atmosphere gas into the heating zone 3, the soaking zone 4, the cooling zone 5 and subsequent zones in the furnace may be individually adjusted or terminated with use of valves (not shown) and flow meters (not shown) disposed in the course of the atmosphere gas supply system 15 to the respective zones. In order to chemically reduce oxides present on the surface of the steel strip and to save the cost of the atmosphere gas, a usual atmosphere gas supplied into the furnace has a composition including 1 to 10 vol % H.sub.2 and the balance of N.sub.2 and inevitable impurities. The dew point of such an atmosphere gas is about 60 C.
(24) Gas suction openings to introduce the furnace gas into the refiner are disposed in a choked gas flow channel in a lower portion of the joint 13 between the soaking zone 4 and the cooling zone 5, for example, the throat section 14, and also in the heating zone 3 and/or the soaking zone 4 except a region extending 6 m in the vertical direction and 3 m in the furnace length direction both from a steel strip inlet at a lower portion of the heating zone 3 (see
(25) Gas ejection openings to return a gas whose dew point has been decreased in the refiner back into the furnace are disposed in the joint 13 between the soaking zone 4 and the cooling zone 5 and also in the heating zone 3. The gas ejection opening in the joint 13 between the soaking zone 4 and the cooling zone 5 is disposed above the pass line. The gas ejection opening in the heating zone 3 is disposed in a region located above a position 2 m below the center of the upper hearth rolls in the heating zone 3 in the vertical direction. Preferably, the gas ejection openings are disposed in a plurality of positions in the heating zone.
(26)
(27) The furnace-to-refiner gas suction openings have a diameter of 200 mm. A single opening (22e) is disposed in the throat section that is a lower portion of the joint 13 between the soaking zone 4 and the cooling zone 5. Further, a total of four pairs (22a to 22d) that are each a pair of two suction openings 1 m away from each other in the furnace length direction are disposed, one at 1 m below the center of the upper hearth rolls in the soaking zone, one at of the furnace height in the soaking zone (at the center in the height direction), one at 1 m above the center of the lower hearth rolls in the soaking zone, and one in the center of the heating zone (at of the furnace height and in the middle in the furnace length direction).
(28) The refiner-to-furnace gas ejection openings have a diameter of 50 mm. One (23e) is disposed in an exit-side furnace wall of the joint between the soaking zone and the cooling zone, specifically, at 1 m above the pass line and 1 m below the ceiling wall. Other four (23a to 23d) are disposed 1 m below the center of the upper hearth rolls in the heating zone with intervals of 2 m in the furnace length direction, starting from the position in the heating zone that is 1 m away from the entrance-side furnace wall.
(29) The dew point detection units 24 of dew point meters are configured to detect the dew points of the gas in the furnace. The units are disposed in the joint between the soaking zone and the cooling zone, in the middle between the respective two suction openings disposed in the soaking zone and the heating zone, and in the middle between the third and fourth ejection openings in the heating zone counted from the entrance-side furnace wall (in the middle between the ejection openings 23c and 23d).
(30) The atmosphere gas suction openings are disposed in a plurality of positions in the heating zone and the soaking zone for the following reasons.
(31) Regardless of the presence or absence of a partition wall between the heating zone and the soaking zone, the distribution of dew point in the furnace varies significantly depending on the status in the furnace (for example, the degree of breakage of the radiant tubes and the seals in the furnace body). It is however the case that the presence of a partition wall limits the flow of gas in the furnace to make it easy to determine where the refiner-to-furnace gas ejection opening and the furnace-to-refiner gas suction opening should be disposed in order to efficiently decrease the dew point. In the absence of a partition wall, on the other hand, the flow of gas in the furnace becomes complicated and the locations of the suction opening and the ejection opening connected to or from the refiner need to be changed in accordance with the status of the dew point. In particular, the suction opening needs to be disposed in a position where the atmosphere has a higher dew point because otherwise the furnace cannot be dehumidified efficiently, resulting in a failure to obtain the desired dew point or a need for increasing the size of the furnace facility. By providing the gas suction openings in a plurality of positions, the gas can be efficiently suctioned from the position where the dew point is high. Thus, the dew point may be decreased to the desired level without involving a large furnace facility.
(32) The atmosphere gas suctioned through the gas suction opening may be introduced into the refiner through any of furnace-to-refiner gas introduction pipes 16a to 16e and through a furnace-to-refiner gas introduction pipe 16. The amounts of the suction of the furnace atmosphere gas through the suction openings may be individually controlled by adjusting or terminating with use of valves (not shown) and flow meters (not shown) disposed in the course of the gas introduction pipes 16a to 16e.
(33) The gas that has been deoxidized and dehumidified in the refiner to a reduced dew point may be ejected into the furnace through any of the ejection openings 23a to 23e via a refiner-to-furnace gas delivery pipe 17 and any of refiner-to-furnace gas delivery pipes 17a to 17e. The amounts of the ejection of the gas into the furnace through the ejection openings may be individually controlled by adjusting or terminating with use of valves (not shown) and flow meters (not shown) disposed in the course of the gas delivery pipes 17a to 17e.
(34)
(35) In a process of annealing and galvanizing the steel strip 1 in the above continuous hot dip galvanization line, the steel strip is annealed by being heated to a prescribed temperature (for example, about 800 C.) while it is transported through the heating zone 3 and the soaking zone 4, and is thereafter cooled to a prescribed temperature in the cooling zone 5. After the cooling, the steel strip is hot dip galvanized by being soaked into the coating bath 7 through the snout 6. After the steel strip is lifted from the coating bath, the coating amount is adjusted to a desired amount with the gas wiping nozzles 8 disposed above the coating bath. After the coating amount is adjusted, the steel strip is galvannealed as required with the heating device 9 disposed above the gas wiping nozzles 8.
(36) During the above process, an atmosphere gas is supplied into the furnace through the atmosphere gas supply system 15. The type, the composition and the method for the supply of the atmosphere gas may be conventional. Usually, H.sub.2N.sub.2 gas is used for an atmosphere gas, and the gas is supplied into the heating zone 3, the soaking zone 4, the cooling zone 5 and subsequent zones in the furnace.
(37) By the operation of the blower 33, the atmosphere gas is suctioned from the heating zone 3, the soaking zone 4, and the throat section 14 that is a lower portion of the joint 13 between the soaking zone 4 and the cooling zone 5 through the furnace-to-refiner gas suction openings 22a to 22e. The atmosphere gas that has been suctioned is sequentially passed through the heat exchanger 30 and the cooler 31 and thereby the atmosphere gas is cooled to about 40 C. or less. The atmosphere gas is then cleaned through the filter 32, deoxidized with the oxygen removal device 34, and dehumidified with the dehumidifier 35 or 36, thereby decreasing the dew point to about 60 C. Switching between the dehumidifiers 35 and 36 may be performed by operating the selector valves 46 and 51.
(38) The gas whose dew point has been decreased is passed through the heat exchanger 30 and is then returned to the heating zone 3 and to the joint 13 between the soaking zone 4 and the cooling zone 5 through the refiner-to-furnace gas ejection openings 23a to 23e. The gas having the lowered dew point passes through the heat exchanger 30, and thereby the temperature of the gas to be ejected into the furnace can be increased.
(39) The gas in the furnace is continuously suctioned through the gas suction opening 22e in the throat section 14 that is a lower portion of the joint 13 between the soaking zone 4 and the cooling zone 5. The furnace gas may be suctioned through all of the gas suction openings 22a to 22d disposed in the heating zone 3 and the soaking zone 4 simultaneously, or may be suctioned through any gas suction openings in two or more positions, or may be preferentially suctioned through any one gas suction opening disposed in a high-dew point region that is selected based on the dew point data obtained with the dew point meters.
(40) It is not indispensable to eject the gas to the joint 13 between the soaking zone 4 and the cooling zone 5 (the gas ejection through the ejection opening 23e). The gas ejection to the heating zone 3 is indispensable. The gas may be ejected through any one or more of the refiner-to-furnace gas ejection openings 23a to 23d. When the gas is ejected through plural openings, the ejection width W0 of the gas ejection openings preferably satisfies W0/W> wherein W is the furnace width of the heating zone plus the soaking zone.
(41) By virtue of the aforementioned arrangement of the furnace-to-refiner gas suction openings and the refiner-to-furnace gas ejection openings, and also by appropriate control of the amounts in which the gas is suctioned or ejected through the respective suction openings or the respective ejection openings, the atmosphere gas is prevented from stagnating in the upper portion, the middle portion and the lower portion of the furnace in the soaking zone and the former half of the cooling zone and consequently the increase in dew point at the upper portion of the furnace can be prevented.
(42) It is, of course, the case that a higher rate of gas supply into the refiner is more advantageous in order to decrease the dew point. However, a high flow rate requires wider pipe diameters and larger dehumidification and deoxidation facilities, incurring an increase in facility costs. It is therefore important that the target dew point be achieved with a minimum flow rate of the gas introduced into the refiner. The aforementioned arrangement of the furnace-to-refiner gas suction openings and the refiner-to-furnace gas ejection openings makes it possible to decrease the flow rate of the gas into the refiner required to obtain the desired dew point.
(43) As a result, it becomes possible to reduce the time required, prior to the steady operation of continuous heat treatment of a steel strip or when the water concentration and/or the oxygen concentration in the furnace atmosphere has increased during the steady operation, to decrease the water concentration and/or the oxygen concentration in the furnace atmosphere to such a level where the dew point of the furnace atmosphere is lowered to 30 C. or below at which stable production of steel strips is feasible. In this manner, a decrease in productivity may be prevented. Further, it is possible to reduce the dew point of the atmosphere in the soaking zone and the joint between the soaking zone and the cooling zone to 40 C. or below, or further to 45 C. or below. Furthermore, the atmosphere gas can be prevented from stagnating in the upper portion, the middle portion and the lower portion of the furnace in the latter half of the heating zone, and the dew point of the atmosphere in the latter half of the heating zone, the soaking zone and the joint between the soaking zone and the cooling zone can be decreased to 45 C. or below, or further to 50 C. or below.
(44) The dew point of the gas in the furnace is measured with dew point meters disposed in a plurality of positions, and the gas in the furnace is suctioned preferentially through the suction opening disposed in a position where a higher dew point has been measured. In this manner, the furnace-to-refiner gas flow rate required to obtain the desired dew point may be decreased.
(45) Although any preheating furnace is not disposed upstream the heating zone in the CGL described above, the line may include a preheating furnace.
(46) While the above embodiments of the invention illustrate CGL, the invention may be applied to a continuous annealing line (CAL) in which a steel strip is continuously annealed.
(47) According to the functions described hereinabove, it becomes possible to reduce the time required, prior to the steady operation of continuous heat treatment of a steel strip or when the water concentration and/or the oxygen concentration in the furnace atmosphere has increased during the steady operation, to decrease the water concentration and/or the oxygen concentration in the furnace atmosphere to such a level where the dew point of the furnace atmosphere is lowered to 30 C. or below permitting stable production of steel strips. That is, a decrease in productivity may be prevented. Further, the inventive configurations allow the furnace atmosphere to stably maintain a low dew point of 40 C. or below where little problems occur in terms of pick-up defects and damages to furnace walls and also at which excellent suppression is possible of the formation of oxides of easily oxidizable elements such as silicon and manganese in the steel that have become concentrated at the surface of steel strips during annealing. As a result, easy manufacturing becomes possible of steels such as Ti-containing IF steel which do not favor operation in a high-dew point atmosphere.
EXAMPLE 1
(48) A dew point measurement test was carried out in an ART type (all radiant type) CGL illustrated in
(49) The furnace had openings through which the atmosphere gas from outside of the furnace is supplied at a total of six locations in the soaking zone, namely, at three locations arranged in the furnace length direction both at 1 m and 10 m above the hearth bottom on the drive side, and at a total of sixteen locations in the heating zone, namely, at eight locations arranged in the furnace length direction both at 1 m and 10 m above the hearth on the drive side. The dew point of the atmosphere gas to be supplied was 60 C.
(50) Furnace-to-refiner gas suction openings and refiner-to-furnace gas ejection openings were disposed as illustrated in
(51) The refiner included dehumidifiers with a synthetic zeolite, and an oxygen removal device with a palladium catalyst.
(52) Steel strips having a sheet thickness of 0.8 to 1.2 mm and a sheet width of 950 to 1000 mm were tested under as uniform conditions as possible at an annealing temperature of 800 C. and a line speed of 100 to 120 mpm. The alloy components in the steel strips are described in Table 1.
(53) While supplying H.sub.2N.sub.2 gas (H.sub.2 concentration 10 vol %, dew point 60 C.) as an atmosphere gas, the dew point of the atmosphere without operation of the refiner (the initial dew point) was obtained as the base value (34 C. to 36 C.) and the dew point after 1-hour operation of the refiner was studied. The dew point was measured in the centers of the furnace widths of the heating zone and the soaking zone, at the same height as the gas suction openings or the gas ejection openings. To measure the dew point in a lower portion of the heating zone, an additional dew point detection unit (a dew point detection unit 25 in
(54) TABLE-US-00001 TABLE 1 (mass %) C Si Mn S Al 0.12 1.3 2.0 0.003 0.03
(55) The initial dew points at the respective positions in the furnace and the effects in dew point reduction in accordance with the locations of refiner suction are described in Table 2.
(56) TABLE-US-00002 TABLE 2 Dew points Upper portion Center of Lower portion Upper portion Center of Lower portion of soaking soaking of soaking of heating heating of heating Base Joint zone zone zone zone zone zone No. conditions C. C. C. C. C. C. C. 1 A 35.0 33.3 35.7 36.9 34.5 35.2 35.1 2 A 52.0 52.1 52.4 52.9 52.9 52.1 51.9 3 A 50.1 47.3 46.2 45.9 46.1 47.2 44.6 4 A 50.5 47.5 46.4 45.1 45.7 48.0 43.9 5 A 50.9 48.3 49.6 47.3 46.7 48.8 46.9 6 A 51.2 51.6 51.3 51.2 51.0 51.3 50.9 7 A 52.5 48.1 47.8 48.6 50.3 48.2 48.3 8 A 47.1 43.4 42.9 42.5 41.8 40.8 38.9 9 A 49.7 49.1 48.7 48.4 48.1 47.8 45.3 10 B 35.3 34.9 32.2 36.8 35.5 35.4 35.3 11 B 51.7 51.3 50.7 51.5 52.2 50.9 51.1 12 B 50.3 47.9 46.3 45.2 45.8 48.1 43.6 13 B 50.5 47.3 46.8 45.3 45.9 47.6 43.3 14 B 51.1 49.2 49.5 47.1 45.5 47.6 46.5 15 B 51.4 50.7 50.9 51.0 50.9 50.3 50.3 16 B 52.5 46.7 47.3 48.8 49.2 48.2 48.4 17 B 51.4 47.3 49.9 50.6 44.6 49.7 50.0 18 C 35.5 35.2 35.9 36.2 36.1 33.7 35.4 19 C 51.2 51.0 50.5 50.6 51.5 50.4 50.3 20 C 50.7 47.3 46.2 45.8 45.2 44.4 43.3 21 C 51.2 46.4 46.4 44.8 47.0 45.6 43.9 22 C 51.0 49.2 49.1 47.5 49.7 47.2 47.1 23 C 51.4 50.3 50.4 50.3 50.6 50.3 50.1 24 C 52.0 46.4 46.3 49.0 48.3 47.9 48.1 25 C 45.2 46.1 48.0 48.3 48.6 48.2 47.6 26 D 35.7 35.3 35.1 31.7 35.9 35.6 35.8 27 D 51.5 51.3 50.8 51.0 51.2 50.9 50.3 28 D 50.5 47.8 45.8 45.8 45.1 44.8 43.9 29 D 51.3 47.8 46.8 45.4 48.3 47.6 43.4 30 D 50.8 49.1 49.0 47.2 50.1 48.1 47.4 31 D 51.3 50.1 50.2 51.0 50.7 50.5 50.4 32 D 51.9 47.1 47.2 49.6 49.1 48.5 48.9 Rates of suction at furnace-to-refiner gas suction openings Upper portion Center of Lower portion Center of Heating zone*) Heating zone*) Lower portion of soaking soaking of soaking heating X = 2 m X = 4 m of joint zone zone zone zone Y = 5 m Y = 7 m No. Nm.sup.3/hr Nm.sup.3/hr Nm.sup.3/hr Nm.sup.3/hr Nm.sup.3/hr Nm.sup.3/hr Nm.sup.3/hr 1 0 0 0 0 0 0 0 2 300 1200 0 0 0 0 0 3 300 1200 0 0 0 0 0 4 300 1200 0 0 0 0 0 5 300 1200 0 0 0 0 0 6 300 1200 0 0 0 0 0 7 300 0 1200 0 0 0 0 8 300 0 0 0 0 1200 0 9 300 0 0 0 0 0 1200 10 0 0 0 0 0 0 0 11 300 0 1200 0 0 0 0 12 300 0 1200 0 0 0 0 13 300 0 1200 0 0 0 0 14 300 0 1200 0 0 0 0 15 300 0 1200 0 0 0 0 16 300 1200 0 0 0 0 0 17 300 0 1200 0 0 0 0 18 0 0 0 0 0 0 0 19 300 0 0 0 1200 0 0 20 300 0 0 0 1200 0 0 21 300 0 0 0 1200 0 0 22 300 0 0 0 1200 0 0 23 300 0 0 0 1200 0 0 24 300 0 0 1200 0 0 0 25 300 0 0 0 1200 0 0 26 0 0 0 0 0 0 0 27 300 0 0 1200 0 0 0 28 300 0 0 1200 0 0 0 29 300 0 0 1200 0 0 0 30 300 0 0 1200 0 0 0 31 300 0 0 1200 0 0 0 32 300 0 0 0 1200 0 0 Rates of ejection at refiner-to- furnace gas ejection openings Upper portion Upper portion Upper portion Upper portion of heating of heating of heating of heating zone - first zone - second zone - third zone - fourth opening from opening from opening from opening from Joint entrance side entrance side entrance side entrance side No. Nm.sup.3/hr Nm.sup.3/hr Nm.sup.3/hr Nm.sup.3/hr Nm.sup.3/hr Remarks 1 0 0 0 0 0 Comparative Example (base of A) 2 300 300 300 300 300 Inventive Example (optimum A case) 3 0 1200 0 0 0 Inventive Example 4 0 0 0 0 1200 Inventive Example 5 0 600 600 0 0 Inventive Example 6 0 400 400 400 0 Inventive Example 7 300 300 300 300 300 Inventive Example 8 300 300 300 300 300 Comparative Example, Suction openings in the heating zone were disposed outside the inventive range. 9 300 300 300 300 300 Inventive Example 10 0 0 0 0 0 Comparative Example (base of B) 11 300 300 300 300 300 Inventive Example (optimum B case) 12 0 1200 0 0 0 Inventive Example 13 0 0 0 0 1200 Inventive Example 14 0 600 600 0 0 Inventive Example 15 0 400 400 400 0 Inventive Example 16 0 400 400 400 0 Inventive Example 17 300 *300 *300 *300 *300 Inventive Example, Ejection openings in the heating zone were disposed 4 m below the center of upper hearth rolls. 18 0 0 0 0 0 Comparative Example (base of C) 19 300 300 300 300 300 Inventive Example (optimum C case) 20 0 1200 0 0 0 Inventive Example 21 0 0 0 0 1200 Inventive Example 22 0 600 600 0 0 Inventive Example 23 0 400 400 400 0 Inventive Example 24 0 400 400 400 0 Inventive Example 25 *300 300 300 300 300 Inventive Example, Ejection opening in the joint was disposed 1 m below the pass line. 26 0 0 0 0 0 Comparative Example (base of D) 27 300 300 300 300 300 Inventive Example (optimum D case) 28 0 1200 0 0 0 Inventive Example 29 0 0 0 0 1200 Inventive Example 30 0 600 600 0 0 Inventive Example 31 0 400 400 400 0 Inventive Example 32 0 400 400 400 0 Inventive Example *X and Y represent locations of suction openings. X indicates the distance (m) from the steel strip inlet in the furnace length direction. Y indicates the distance from the steel strip inlet in the vertical direction.
(57) The base conditions were divided into four groups A to D by the locations where the highest dew point was measured in the furnace except in the lower portion of the heating zone. In Inventive Examples, a dew point of 40 C. or below was obtained under all the base conditions. In Inventive Examples, a particularly low dew point was obtained when the gas was ejected from the refiner to the inside of the heating zone over a gas ejection width that was larger than of the furnace width of the heating zone plus the soaking zone, or when the gas was ejected to the joint between the soaking zone and the cooling zone. A low dew point of 50 C. or below was obtained when the gas was suctioned to the refiner preferentially from a location where a higher dew point had been measured and also when the gas was ejected from the refiner to the inside of the heating zone over a gas ejection width that was or more of the furnace width of the heating zone plus the soaking zone.
EXAMPLE 2
(58) Trends of dew point decrease were studied with the ART type (all radiant type) CGL illustrated in
(59) The conditions in a conventional method (without the use of the refiner) were such that the atmosphere gas supplied into the furnace had a composition including 8 vol % H.sub.2 and the balance of N.sub.2 and inevitable impurities (dew point 60 C.), the rate of gas supply to the cooling zone and subsequent zones was 300 Nm.sup.3/hr, the rate of gas supply to the soaking zone was 100 Nm.sup.3/hr, the rate of gas supply to the heating zone was 450 Nm.sup.3/hr, the steel strips had a sheet thickness of 0.8 to 1.2 mm and a sheet width of 950 to 1000 mm (the alloy components in the steel were the same as in Table 1), the annealing temperature was 800 C., and the line speed was 100 to 120 mpm.
(60) The conditions in the inventive method were the same as the above conditions and further included the use of the refiner. The initial state of dew point was similar to the base conditions A in EXAMPLE 1 (in which the dew point was highest at the upper portion of the soaking zone). Based on this, the suction performing locations and other configurations were determined in accordance with the conditions of No. 2 (optimum conditions A) in EXAMPLE 1 shown in Table 2. The results of the study are described in
(61) In the conventional method, it took approximately 40 hours to decrease the dew point to 30 C. or below, and the dew point remained above 35 C. even after 70 hours. In contrast, the inventive method was able to decrease the dew point to 30 C. or below in 6 hours, to 40 C. or below in 9 hours, and to 50 C. or below in 14 hours.
(62) Prior to the steady operation of continuous heat treatment of a steel strip or when the water concentration and/or the oxygen concentration in the furnace atmosphere has increased during the steady operation, the continuous annealing furnace for steel strips according to the present invention can quickly decrease the water concentration and/or the oxygen concentration in the furnace atmosphere to such a level where the dew point of the furnace atmosphere is lowered to 30 C. or below at which stable production of steel strips is feasible.
(63) With use of the continuous annealing furnace for steel strips according to the present invention, a high-strength steel strip containing easily oxidizable elements such as silicon and manganese can be continuously annealed in a way that reduces the problematic occurrence of pick-up defects and damages to furnace walls without any partition wall between the soaking zone and the heating zone.
REFERENCE SIGNS LIST
(64) 1 STEEL STRIP
(65) 2 ANNEALING FURNACE
(66) 3 HEATING ZONE
(67) 4 SOAKING ZONE
(68) 5 COOLING ZONE
(69) 5a FIRST COOLING ZONE
(70) 5b SECOND COOLING ZONE
(71) 6 SNOUT
(72) 7 COATING BATH
(73) 8 GAS WIPING NOZZLES
(74) 9 HEATING DEVICE
(75) 10 REFINER
(76) 11a UPPER HEARTH ROLL
(77) 11b LOWER HEARTH ROLL
(78) 12 SEAL ROLLS
(79) 13 JOINT
(80) 14 THROAT
(81) 15 ATMOSPHERE GAS SUPPLY SYSTEM
(82) 16 FURNACE-TO-REFINER GAS INTRODUCTION PIPE
(83) 17 REFINER-TO-FURNACE GAS DELIVERY PIPE
(84) 22a to 22e FURNACE-TO-REFINER GAS SUCTION OPENINGS
(85) 23a to 23e REFINER-TO-FURNACE GAS EJECTION OPENINGS
(86) 24, 25 DEW POINT DETECTION UNITS
(87) 30 HEAT EXCHANGER
(88) 31 COOLER
(89) 32 FILTER
(90) 33 BLOWER
(91) 34 OXYGEN REMOVAL DEVICE
(92) 35, 36 DEHUMIDIFIERS
(93) 46, 51 SELECTOR VALVES