CUTOUT SYSTEMS AND METHODS
20170113708 ยท 2017-04-27
Inventors
- Remo Ferrari (East Brunswick, NJ, US)
- Torsten Pannier (Jersey City, NJ, US)
- James R. Krietemeyer (Brooklyn, NY, US)
Cpc classification
B61L27/40
PERFORMING OPERATIONS; TRANSPORTING
B61L3/16
PERFORMING OPERATIONS; TRANSPORTING
B61L27/04
PERFORMING OPERATIONS; TRANSPORTING
B61L15/0081
PERFORMING OPERATIONS; TRANSPORTING
B61L15/0072
PERFORMING OPERATIONS; TRANSPORTING
B61L27/20
PERFORMING OPERATIONS; TRANSPORTING
B61L15/0058
PERFORMING OPERATIONS; TRANSPORTING
International classification
B61L27/00
PERFORMING OPERATIONS; TRANSPORTING
Abstract
Systems and methods for controlling a train may override wayside interface units (WIUs) and/or override wayside devices. An example control system may comprise a transceiver configured to receive a status from a WIU and an on board unit (OBU) coupled to the transceiver. The OBU may be configured to override the command from the WIU and ignore a status from another wayside device associated with the WIU. The OBU may enforce all positive train control commands other than commands from sources associated with the overridden WIU.
Claims
1. A control system for controlling a train, the control system comprising: a transceiver configured to receive data from a wayside interface unit (WIU), the WIU being configured to monitor a plurality of wayside devices and transmit data describing status of each of the plurality of wayside devices; and an on board unit (OBU) coupled to the transceiver and configured to: determine that the train is approaching the WIU; determine that a state of a first wayside device monitored by the WIU is incorrect based on the data received by the transceiver from the WIU or the state of the first wayside device monitored by the WIU is unknown based on a failure by the transceiver to receive the data from the WIU; based on the determination of incorrect or unknown state, prompt a user for an override of the first wayside device monitored by the WIU; receive the override; allow the train to proceed past the first wayside device monitored by the WIU; ignore data originating from another wayside device monitored by the WIU; and enforce positive train control restrictions received from sources other than sources monitored by the WIU during a time period to which the override applies.
2. The control system of claim 1, wherein the OBU is further configured to determine that the train has stopped before prompting the user for the override.
3. The control system of claim 1, wherein the OBU is further configured to cancel the override after a predetermined time elapses from a time when the override is received and respond to data originating from wayside devices monitored by the WIU after the override is canceled.
4. The control system of claim 1, wherein the OBU is further configured to enforce train operation specified by data received by the transceiver and originating from sources not associated with the WIU.
5. (canceled)
6. The control system of claim 1, wherein the OBU is further configured to prompt the user for the override when the train reaches a predetermined distance from the WIU.
7. A method for controlling a train, the method comprising: determining, with an on board unit (OBU), that the train is approaching a wayside interface unit (WIU), the WIU being configured to monitor a plurality of wayside devices and transmit data describing status of each of the plurality of wayside devices; determining, with the OBU, that a state of a first wayside device monitored by the WIU is incorrect based on data received by a transceiver from the WIU or the state of the first wayside device monitored by the WIU is unknown based on a failure by the transceiver to receive the data from the WIU; based on the determination of incorrect or unknown state, prompting, with the OBU, a user for an override of the WIU; receiving, with the OBU, the override; allowing, with the OBU, the train to proceed past the first wayside device monitored by the WIU; ignoring, with the OBU, data originating from another wayside device monitored by the WIU; and enforcing, with the OBU, positive train control restrictions received from sources other than sources monitored by the WIU during a time period to which the override applies.
8. The method of claim 7, further comprising determining, with the OBU, that the train has stopped before prompting the user for the override.
9. The method of claim 7, further comprising canceling, with the OBU, the override after a predetermined time elapses from a time when the override is received and respond to data originating from wayside devices monitored by the WIU after the override is canceled.
10. The method of claim 7, further comprising enforcing, with the OBU, train operation specified by data received by the transceiver and originating from sources not monitored by the WIU.
11. (canceled)
12. The method of claim 7, wherein the OBU prompts the user for the override when the train reaches a predetermined distance from the WIU.
13. A control system for controlling a train, the control system comprising: a transceiver configured to receive a command from a wayside interface unit (WIU) configured to monitor a plurality of wayside devices and transmit data describing status of each of the plurality of wayside devices; and an on board unit (OBU) coupled to the transceiver and configured to: override the command from the WIU; ignore data originating from a wayside device monitored by the WIU; and enforce all positive train control restrictions received from sources other than sources monitored by the WIU during a time period to which the override applies.
14. The control system of claim 13, wherein the OBU is further configured to: determine that the train is approaching the WIU, the WIU being associated with a plurality of wayside devices; determine that a state of a first wayside device associated with the WIU is incorrect based on data received by the transceiver from the WIU or the state of the first wayside device monitored by the WIU is unknown based on a failure by the transceiver to receive the data from the WIU; and based on the determination of incorrect or unknown state, prompt a user for an override of the WIU.
15. The control system of claim 13, wherein the OBU is further configured to cancel the override after a predetermined time elapses from a time when the command is overridden and respond to data originating from wayside devices monitored by the WIU after the override is canceled.
16. A method for controlling a train, the method comprising: receiving, with a transceiver, a command from a wayside interface unit (WIU) configured to monitor a plurality of wayside devices and transmit data describing status of each of the plurality of wayside devices; overriding, with an on board unit (OBU), the command from the WIU; ignoring, with the OBU, data originating from another wayside device monitored by the WIU; and enforcing, with the OBU, all positive train control restrictions received from sources other than sources monitored by the WIU during a time period for which the command from the WIU is overridden.
17. The method of claim 16, further comprising: determining, with the OBU, that the train is approaching the WIU the WIU being configured to monitor a plurality of wayside devices; determining, with the OBU, that a state of the first wayside device monitored by the WIU is incorrect based on data received by a transceiver from the WIU or the state of the first wayside device monitored by the WIU is unknown based on a failure by the transceiver to receive the data from the WIU; and based on the determination of incorrect or unknown state, prompting, with the OBU, a user for an override of the WIU.
18. The method of claim 16, further comprising canceling, with the OBU, the override after a predetermined time elapses and responding to data originating from wayside devices monitored by the WIU after the override is canceled.
19. A control system for controlling a train, the control system comprising: a transceiver configured to receive positive train control (PTC) commands; and an on board unit (OBU) coupled to the transceiver and configured to: place train control in an initial PTC mode; receive a PTC override command; place train control in a PTC override mode for a predetermined time period in response to the PTC override command; while train control is in the PTC override mode during the predetermined time period, receive at least one PTC command and update train control requirements based on the received at least one PTC command; while train control is in the PTC override mode during the predetermined time period, monitor a position of the train; and after the predetermined time period elapses, place train control in the initial PTC mode and the monitored position of the train.
20. The control system of claim 19, wherein placing train control in the PTC mode comprises controlling the train in accordance with the at least one PTC command received while train control was in the PTC override mode.
21. The control system of claim 19, wherein the OBU is further configured to display a timer indicating when the predetermined time period will elapse while train control is in the PTC override mode.
22. The control system of claim 19, wherein the OBU is further configured to: prompt a user for a confirmation of the override command; and receive the confirmation before placing train control in the PTC override mode.
23. A method for controlling a train, the method comprising: receiving, with an on board unit (OBU), initialization data; placing, with the OBU, train control in a positive train control (PTC) mode according to the initialization data; receiving, with the OBU, a PTC override command; placing, with the OBU, train control in a PTC override mode for a predetermined time period in response to the PTC override command; while train control is in the PTC override mode during the predetermined time period, receiving, with the OBU, at least one PTC command and updating, with the OBU, train control requirements based on the received at least one PTC command; while the train control is in the PTC override mode during the predetermined time period, monitoring, with the OBU, a position of the train; and after the predetermined time period elapses, placing, with the OBU, train control in the PTC mode according to the initialization data and the monitored position of the train.
24. The method of claim 23, wherein placing train control in the PTC mode comprises controlling the train in accordance with the at least one PTC command received while train control was in the PTC override mode.
25. The method of claim 23, further comprising displaying, with the OBU, a timer indicating when the predetermined time period will elapse while the train control is in the PTC override mode.
26. The method of claim 23, further comprising: prompting, with the OBU, a user for a confirmation of the override command; and receiving, with the OBU, the confirmation before placing train control in the PTC override mode.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0017]
[0018]
[0019]
[0020]
[0021]
[0022]
DETAILED DESCRIPTION OF SEVERAL EMBODIMENTS
[0023] Systems and methods described herein may provide cutout functionality called override which may specifically and temporarily overcome issues arising from a faulty component of the ITC-PTC system while continuously providing the maximum available level of safety. Override may be accompanied by applicable corrective actions and may satisfy the mandated reporting responsibilities of railroads.
[0024] The systems and methods described herein may provide cutout functionality not only for the situations described in the background, but also for additional situations. Specifically, these approaches may handle the case where there is no wayside status received for a wayside device in a configurable amount of time, for example. In such a case, if no wayside status is received (e.g., signal device status not received), the OBU may assume the wayside device must be indicating a STOP. This assumption may be made in order to provide a maximum level of safety. The approaches described herein may override specific aspects of PTC enforcement within the OBU related to failures in other PTC subsystems without a significant decrease in the operational safety provided by the OBU. The approaches may include the following: [0025] An override WIU approach that disables enforcement of signals from wayside devices associated with a specific WIU; and [0026] An override wayside device approach that disables enforcement of signals for a single wayside device.
[0027] It is assumed that hazard detectors are treated as signal devices in both approaches.
Override WIU Approach
[0028] The override WIU approach may disable enforcement of signals from all wayside devices associated with a specific WIU with which the OBU has communication failures. It should be understood that a single WIU may be associated with (configured to transmit status for) one or multiple wayside devices of the same or different types. As used herein, wayside device includes a wide variety of devices for which it may be desirable to transmit a status including, without limitation, signal devices (i.e., a device located on a side of the track with colored lights that indicate how a train may proceed along a section of track associated with the device), crossing gates, track switches/points, avalanche detection circuits, track integrity circuits, bridge alignment circuits and the like. This approach may address the use case where the crew can see that a wayside device indicates that it is safe to proceed yet, since the wayside device status is unknown to the OBU (e.g., no wayside status message (WSM) received for that signal), the OBU may enforce a stop and hold the train until the WIU communication failure is resolved. An example of this may be a signal device indicating clear but the OBU preventing the train from passing the signal device. In this case it may be inappropriate for railroad operations to issue an authority to pass signal at stop to continue operation of the train because the signal device is not at stop. Further, issuing authority to pass signal at stop may require the train to proceed past the clear signal device at restricted speed, while the override WIU approach may allow traversal at track speed. The override WIU approach may provide a high degree of operational safety with smooth movement, limited user interaction, and no need for re-initialization.
[0029]
[0030] If the override prompt is confirmed, the OBU may disable enforcement of signals from all wayside devices associated with WIU 160 for which the OBU has not received status or has received incorrect status, for example all wayside devices in the area 130 served by the WIU 160. The OBU may know which wayside devices are associated with the WIU 160 by checking a database that may be part of the OBU or in communication with the OBU (e.g., on the train or elsewhere). The database may contain data associating each WIU along the track with specific wayside devices (e.g., signals, switches, hazard detectors, etc.). Thus, as the train passes additional wayside devices without status or with incorrect status 140, the train may proceed without enforcement of unknown or incorrect status (e.g., proceed without enforcement of signals 260 of
[0031] If the OBU receives status from the WIU 160 for which the OBU has disabled enforcement (e.g., signal received 270 of
Override Wayside Device Approach
[0032] The override wayside device approach may override the speed restriction associated with an individual wayside device where WIU status has not been received for that wayside device in a configurable time, or where incorrect status has been received. The override wayside device approach may be similar to the override WIU approach in that it addresses the use case where the crew can see that a wayside device indicates clear, yet the OBU prevents movement due to a WIU communication failure. However, unlike the override WIU approach, the override wayside device approach may override PTC enforcement for a single individual wayside device. The override wayside device approach may provide a high degree of operational safety with moderate user interaction and no need for re-initialization.
[0033]
[0034] The override WIU approach and the override wayside device approach may allow trains to pass wayside devices without stopping at each wayside device and allow trains to pass wayside devices at track speed (not restricted speed as with pass signal at stop). Each approach may allow the OBU to remain in the active mode and provide near full PTC protection. Each approach may only be triggered in case of failed communication with a wayside device or incorrect wayside device state identified by the crew, thus allowing safe and normal WIU communication when available. The override WIU approach and the override wayside device approach may limit the need for crew interaction in these situations, as the crew may not have to explicitly cut the OBU back in through the HMI. Each approach may be used without abbreviated initialization, as the OBU may maintain messaging with the BOS, other WIUs, and its own datasets. This may reduce errors which can occur during abbreviated initialization that would force a full train initialization.
Timer-Based Override Approach
[0035] At any time while the OBU is providing PTC functionality, the train crew may be able to initiate a temporary override. Once a temporary override is initiated, PTC functionality may be disabled for a specified amount of time indicated by a timer. When the timer expires, the OBU may automatically return to a state providing full PTC functionality.
[0036] By processing PTC messages and monitoring train movement while operating in the PTC override mode, the OBU may allow PTC operation to resume promptly upon expiration of the timer, because the scope of allowable operations for the location in which the train is operating will be known. The OBU may not need to receive updated information from the crew and/or railroad back office to resume PTC enforcement. Instead, the OBU may be able to effectively resume PTC enforcement from before PTC override occurred, taking into account PTC changes based on received wayside device statuses and/or train progress, without reentering information that was used to initialize the OBU at the start of the trip. Examples of tasks that may need not be performed upon return to PTC operation may include crew member employee name and ID number entry, clearance number, train ID, etc.; train makeup, manifest, type, etc.; trip information (times, route, etc.); route information, track database, etc. from back office; back office verification of information entered by crew; system tests; etc.
[0037] In the timer-based approach, the OBU may always automatically transition back to PTC after the cutout period elapses. Thus, the OBU cannot be left indefinitely in a state where PTC is disabled. Also, the crew may not have to explicitly cut back to PTC in the OBU through the HMI. The OBU may maintain communication with all external systems (e.g., WIU, back offices) and may maintain navigation so no additional crew tasks are required on PTC cut-in.
Train Control
[0038]
[0039] As shown in
[0040] As shown in
[0041] As shown in
[0042] While various embodiments have been described above, it should be understood that they have been presented by way of example and not limitation. It will be apparent to persons skilled in the relevant art(s) that various changes in form and detail can be made therein without departing from the spirit and scope. In fact, after reading the above description, it will be apparent to one skilled in the relevant art(s) how to implement alternative embodiments.
[0043] In addition, it should be understood that any figures that highlight the functionality and advantages are presented for example purposes only. The disclosed methodology and system are each sufficiently flexible and configurable such that they may be utilized in ways other than that shown.
[0044] Although the term at least one may often be used in the specification, claims and drawings, the terms a, an, the, said, etc. also signify at least one or the at least one in the specification, claims, and drawings.
[0045] Finally, it is the applicant's intent that only claims that include the express language means for or step for be interpreted under 35 U.S.C. 112(f). Claims that do not expressly include the phrase means for or step for are not to be interpreted under 35 U.S.C. 112(f).