Method for the assembly of frustoconical concrete towers and concrete tower assembled using said method

Abstract

The present invention relates to a method for the assembly of frustoconical concrete towers comprising a step of placing and positioning of at least one subset of a tower section formed by at least two segments in an area close to the base of the tower, a step of assembling the subset of the tower section by attaching at least two segments, so that the assembled subset is freestanding and a step of stacking the assembled subset onto an immediately lower tower section.

Claims

1. A method for the assembly of frustoconical concrete towers comprising the following steps: a step of placing and positioning of at least one subset of a tower section formed by at least two dowels in an area on or adjacent to a base of a tower; a step of assembling the at least one subset of a tower section by joining at least two dowels, such that an assembled subset is freestanding; and a step of stacking the assembled subset onto an immediately lower tower section.

2. The method of claim 1 wherein the step of placing and positioning of at least one subset of a tower section comprises the following steps prior to the step of assembling the at least one subset: a step of placing one by one all dowels of the at least two dowels forming the tower section in the area on or adjacent the base of the tower at ground level; a step of positioning each one of all dowels forming the tower section in relation to adjacent dowels in a manner that dimensional tolerances of the tower section ensures that it is possible to carry out the step of stacking the assembled subset onto an immediately lower tower section.

3. The method of claim 2 further comprising, prior to the step of stacking the assembled subset and subsequent to the step of positioning each one of all dowels that form the tower section: a step of arranging control elements to control a relative positioning between each one of all dowels in areas of each one of all dowels accessible from tower platforms.

4. The method of claim 3 wherein the step of arranging control elements to control the relative positioning between dowels performs identification, prior to stacking, of a reference position of remaining dowels of the tower section that are not part of the at least one subset relative to the at least one subset or of the reference position of at least two subsets relative to each other of the at least two subsets.

5. The method of claim 4 further comprising a step to control the relative positioning between dowels subsequent to the step of stacking the tower section that the dowels of the at least two dowels form and prior to stacking a tower section immediately above, wherein it is ensured that the remaining dowels of the tower section are positioned relative to the at least one subset according to the reference position identified by the elements to control the relative positioning, in a manner as in the area on or adjacent to the base of the tower at ground level, or that the at least two subsets are positioned relative to each other in the same manner as in the in the area on or adjacent to the base of the tower at ground level.

6. The method of claim 2 wherein the area on or adjacent the base of the tower, pre-assembly bases are provided, wherein the step of placing and positioning of at least one subset of a tower section formed by at least two dowels is carried out and wherein the method comprises: a step of preparing the pre-assembly bases where horizontality and flatness of such pre-assembly bases are ensured and which further allows to ensure verticality and taper of the tower prior to the step of placing one by one all dowels forming the tower section on the pre-assembly bases.

7. The method of claim 2 wherein the step of placing and positioning of at least one subset of a tower section, comprises, between the step of placing one by one all dowels and the step of positioning each of the dowels: a step of obtaining verticality and taper of the tower regarding the tower section, which in turn comprises a step of certifying the verticality of the tower which allows correction of relative positions between the dowels, and between the dowels and pre-assembly bases.

8. The method of claim 1 wherein the step of stacking the assembled subset onto an immediately lower tower section comprises a step of positioning the at least one subset at a height.

9. The method of claim 8 wherein the step of positioning the at least one subset at a height is performed by replicating a horizontal surface of the pre-assembly base on an upper surface of an immediately lower tower section prior to the step of stacking the assembled subset, by means of shims placed in three points per subset and/or dowel in predetermined angular positions which are the same for all sections.

10. The method of claim 9 wherein in the predetermined angular positions where the shims are placed, wedges to control verticality are placed, so that a sum of the horizontal surface defined by the shims plus the horizontal surface of the wedges will make it possible to replicate a position achieved in the pre-assembly base, once at least two subsets are stacked.

11. The method of claim 8 wherein the step of stacking the assembled subset onto an immediately lower tower section comprises a step of checking a centre position of the subset to ensure its coincidence with a vertical axis of the tower or otherwise adjusting the centre position of the subset to match the vertical axis of the tower.

12. The method of claim 11 wherein subsequently, another subset or remaining dowels of the tower section are stacked, and are again positioned by means of the step to control a relative positioning between dowels until relative positioning control elements give a position achieved in the pre-assembly bases.

13. The method of claim 12 wherein subsequent to the step of stacking for each of the at least one subset of the tower section, the method comprises a step of attachment between at least two subsets of the tower section or between the at least one subset and the remaining dowels of the tower section by arranging provisional attachment elements, so that the tower section is provided with additional stability at least until the step of stacking of the at least two subsets or of the at least one subset and the remaining dowels of a tower section immediately above has been performed.

14. The method of claim 13, further comprising a step of executing permanent attachments between the at least two subsets, or between the at least one subset and the remaining dowels, which is performed once completed the stacking of the assembled subset and the remaining dowels forming each tower section.

15. The method of claim 14 wherein the step of executing permanent attachments between the at least two subsets, or between the at least one subset and the remaining dowels comprises a step of performing vertical concrete joints.

16. The method of claim 14 wherein the step of executing the permanent attachments between the at least two subsets, or between the at least one subset and the remaining dowels is performed once a nacelle of a wind turbine has been mounted.

17. The method of claim 16 further comprising a step of executing permanent attachments between adjacent sections performed subsequent to the step of executing permanent attachments between the at least two subsets or between the at least one subset and the remaining dowels.

18. The method of claim 1 wherein the step of assembling the at least one subset of the tower section by attaching at least two dowels, such that the assembled subset is freestanding, is accomplished by attaching two adjacent dowels.

19. The method of claim 1 wherein the step of assembling the at least one subset of the tower section by attaching at least two dowels, such that the assembled subset is freestanding, is accomplished by attaching two diametrically opposed dowels.

20. The method of claim 1 further comprising a step of stacking at least a remaining dowel or at least another assembled subset onto an immediately lower tower section to form the tower section, wherein the tower section is formed by at least one assembled subset and at least a remaining dowel to complete the tower section or by at least two assembled subsets respectively, wherein the step of stacking at least a remaining dowel or at least another assembled subset is subsequent to the step of stacking the assembled subset onto an immediately lower tower section.

Description

BRIEF DESCRIPTION OF THE DRAWINGS

(1) FIG. 1 shows a perspective view of the step of positioning, one at a time, all the dowels that form a tower section in an area near the base of the tower of the method of the present invention according to a first preferred embodiment.

(2) FIG. 2 shows a plan view of the step of positioning each of the dowels that form the tower section relative to the adjacent dowels of the method of the present invention according to a first preferred embodiment.

(3) FIG. 3 shows a perspective view of the step of assembling a subset of the tower section formed by at least two adjacent dowels of the method of the present invention according to a first preferred embodiment.

(4) FIG. 4 shows a plan view of FIG. 3.

(5) FIG. 5 shows a perspective view of the step of stacking the assembled subset onto an immediately lower tower section of the method of the present invention according to a first preferred embodiment.

(6) FIG. 6 shows a perspective view of the step of attachment performed between the section subsets of the method of the present invention according to a first preferred embodiment.

(7) FIG. 7 shows a perspective view of the step of permanent attachment performed between the subsets of each section of the method of the present invention according to a first preferred embodiment.

(8) FIG. 8 shows a perspective view of the step of positioning, one at a time, all the dowels that form a tower section in an area near the base of the tower of the method of the present invention according to a second preferred embodiment.

(9) FIG. 9 shows a plan view of the step of positioning each of the dowels that form the tower section relative to the adjacent dowels of the method of the present invention according to a second preferred embodiment.

(10) FIG. 10 shows a perspective view of the step of assembling a subset of the tower section formed by at least two diametrically opposite dowels of the method of the present invention according to a second preferred embodiment.

(11) FIG. 11 shows a plan view of FIG. 10.

(12) FIG. 12 shows a perspective view of the step of stacking the assembled subset onto an immediately lower tower section of the method of the present invention according to a second preferred embodiment.

(13) FIG. 13 shows a perspective view of the step of attachment between the subset and the remaining dowels of the section of the method of the present invention according to a second preferred embodiment.

(14) FIG. 14 shows a perspective view of the step of permanent attachment performed between subsets and remaining dowels of each section of the method of the present invention according to a second preferred embodiment.

(15) FIG. 15 shows an exploded view of the provisional attachments executed by three-point mooring of the surface in contact with the lower surface at the height of the horizontal joint defined between them of the step of provisional attachment between an upper section and a lower section.

(16) FIG. 16 shows a plan view of FIG. 15.

(17) FIG. 17 shows a perspective view of the struts taken to the opposite side of the lower section used in the step a provisional connection between an upper section and a lower section.

PREFERRED EMBODIMENT OF THE INVENTION

(18) In a preferred embodiment of the invention, the method for the assembly of frustoconical concrete towers comprises the following steps: a step of pre-assembly base (2, 12) preparation, wherein the horizontality and flatness of said pre-assembly bases (2) are ensured, further ensuring the verticality and taper of the concrete tower; a step of placing and positioning of at least one subset of a tower section formed by at least two dowels in an area near the base of the tower where in this preferred embodiment all the dowels (1, 11) that form the tower section are placed and positioned one by one onto the pre-assembly bases (2, 12), wherein the placing and positioning step comprises: a step of placing one by one all the dowels (1, 11) forming the tower section in the area near the base of the tower onto the pre-assembly bases (2, 12) at ground level; a step of obtaining the verticality and taper of the concrete tower for that section, by using struts or similar means between the dowels (1, 11) and the ground or pre-assembly bases (2, 12), or by means of wedges or similar means between the pre-assembly base (2, 12) and the lower surface of the dowels (1, 11), as sometimes due to imperfections in the concrete, the angle between the side walls and the lower wall of the dowels (1, 11) is not the proper angle; this step in turn comprises a step of certifying tower verticality by means of a system of targets with pointers or plumb lines enabling the correction of the relative positions between dowels (1, 11), and between dowels (1, 11) and pre-assembly bases (2, 12) where necessary; a step of positioning each of the dowels (1) that form the tower section relative to the adjacent dowels (1) to ensure the dimensional tolerances of the finished section; a step of arranging control elements (3, 13) to control the relative positioning between dowels (1, 11) in areas of these dowels (1, 11) which may be accessed from tower platforms, wherein said positioning control elements (3, 13) serve to identify the position, prior to stacking, of the reference position of the remaining dowels (11) of the section that is not part of the subset (14) relative to said subset (14), or of the reference position of subsets (4) relative to each other; a step of assembling a subset (4, 14) of the tower section formed by at least two dowels (1, 11), by joining said dowels (1, 11), such that the subset (4, 14) is freestanding; The attachment between two dowels (1, 11) may be permanent or provisional. If the attachment is permanent (6), according to a first embodiment shown in FIGS. 1 to 7 for a subset (4) formed by at least two adjacent dowels (1), mortar is used for permanent attachment (6) between dowels (1) and it comprises a step of implementing the vertical joints between adjacent dowels (1). For this purpose, formwork is arranged along the vertical sides of the dowels (1) to contain the inner volume and then pour in the mortar. If the attachment is provisional, according to a second preferred embodiment shown in FIGS. 8 to 14 for a subset (14) formed by at least two dowels (11) diametrically opposite each other, the attachment of said dowels (11) is carried out by provisional attachment means (19) to provide rigidity and stability to the subset (14). The provisional attachment means (19) between dowels (11) diametrically opposite each other is performed by means of beams or girders restricting relative movement between dowels (11). a step of stacking the assembled subset (4, 14) onto an immediately lower tower section, comprising a step of positioning the subset (4, 14) at height.

(19) Because, due to manufacturing tolerances, there may be differences between dowels (1, 11), the resulting upper surface is not always flat or horizontal. In a preferred embodiment, the step of positioning the subset (4, 14) at height is performed by conducting a replica of the horizontal surface of the pre-assembly base (2, 12) on the upper surface of the immediately lower tower section prior to the step of stacking the assembled subset (4, 14), by means of shims (22) placed in three points per subset (4, 14) and/or dowel (1, 11), at predetermined angular positions which are the same for all sections, wherein said shims (22) are fixed to the dowels (1, 11), wherein verticality control wedges (23) are placed in those same angular positions where the shims (22) are placed. Therefore, the sum of the horizontal surface defined by the shims (22) and that of the wedges (23) makes it possible to replicate the position achieved in the pre-assembly base (2, 12), once subsets (4, 14) have been stacked.

(20) Alternatively, when the subset (4, 14) is stacked, a check is made to verify that the centre of the subset (4, 14) coincides with the vertical axis of the tower, otherwise it is adjusted to match. Subsequently, the other subset (4) is stacked, for the case of two subsets (4) per section, or the remaining dowels (11), and the following step to control relative positioning between dowels is implemented: a step of controlling the relative positioning between dowels subsequent to the step of stacking the section they form and prior to stacking the section immediately above by means of positioning control elements (3, 13) arranged in the step of arrangement of the control elements (3, 13) to control the relative positioning between dowels (1, 11) ensuring that the remaining dowels (11) of the section are positioned relative to the subset (14) according to the reference position identified by the relative positioning control elements (3, 13), i.e., in the same manner as in the positioning bases (2, 12), or that the subsets (4) are positioned relative to each other in the same manner as in the positioning bases (2).

(21) The first of the subsets (4, 14) to be stacked will be the one incorporating a flight of steps required to access the upper part of the subset (4, 14) and thereby allow removal of the hook from a crane used to lift said subset (4, 14).

(22) The steps of assembling and stacking the assembled subset (4) are repeated as many times for each of the sections forming the concrete tower, as number of subsets (4) in the section in the event that this section is formed by subsets (4) in which permanent attachment (6) has been carried out between dowels (1) prior to stacking, as shown in FIGS. 1 to 7, whereas for the case of a subset (14) formed by at least two diametrically opposite dowels (11), it is necessary to perform a step of stacking of each of the remaining dowels (11) of the section which are not part of the subset (14) assembled on the tower section immediately below.

(23) Subsequent to the step of stacking each of the subsets (4) of the section, the method comprises a step of attachment performed between the section subsets (4), for the embodiment shown in FIGS. 1 to 7, or between the subset (14) and the remaining dowels (11) section by arranging provisional attachment elements (5, 15), so as to provide the section with additional stability at least until carrying out the step of stacking the assembled subsets (4), or subsets (14) and remaining dowels (11) of a section immediately above.

(24) Such provisional attachment elements (5, 15) between subsets (4), or subsets (14) and remaining dowels (11) may include lugs and hydraulic jacks arranged in accessible areas of the subsets (4), or of the subsets (14) and the remaining dowels (11), at least one in the upper area of the section such that it is accessible from the top.

(25) Subsequent to the step of attachment performed between the subset (14) of the section and the remaining dowels (11) of the section by arranging provisional attachment elements (15) for the embodiment shown in FIGS. 8 to 14, the method comprises a step of removing the provisional attachment means (19) between the dowels (11) of the subset (14).

(26) The method further comprises a step of executing permanent attachments (6, 16) between subsets (4), or between subsets (14) and remaining dowels (11), which are performed once all subsets (4, 14) and dowels (11) which form all the sections of the concrete tower have been stacked and ensuring the proper positioning between them.

(27) The method further comprises a step of provisional attachment between subsets or remaining dowels and the lower section of the concrete tower once the step of stacking the assembled subset has been carried out.

(28) The provisional attachment step is performed by means of provisional attachments that can be executed by mooring (20) at three points of the surface in contact with the lower surface at the height of the horizontal joint defined between them or with struts (21) taken to the opposite side of the lower section.

(29) Preferably each of the sections is angularly staggered with respect to the lower section so that the permanent attachments (6, 16) do not run in a continuous line along the tower, improving the stability thereof.

(30) Said step of executing the permanent attachments (6, 16) between subsets (4), or between subsets (14) and remaining dowels (11), comprises a step of performing vertical concrete joints. In order that the mortar used in the vertical concrete joints is confined within an enclosed cavity, preassembled sealant elements or inflatable elements are placed along the vertical concrete joints as a formwork.

(31) In turn, so that the mortar does not flow towards the horizontal joint between the sections, covers which inferiorly seal the vertical joints are arranged prior to the assembly of the upper section.

(32) Preferably, the step of executing the permanent attachments (6, 16) between subsets (4), or between subsets (14) and remaining dowels (11) is performed once a nacelle (7) of the wind turbine has been mounted.

(33) Preferably, the method further comprises a step of executing permanent attachments (8, 18) between adjacent sections, which is performed subsequent to the step of executing permanent attachments (6, 16) between subsets (4), or between subsets (14) and the remaining dowels (11), and more preferably, the step of executing the permanent attachments (8, 18) between adjacent sections is carried out from the highest section to the lowest section of the tower, wherein this step of execution of a permanent attachments (8, 18) between adjacent sections comprises a step of performing horizontal concrete joints.