MODULAR STRUCTURE FOR PROVIDING ON-SITE PROTECTION
20230065334 · 2023-03-02
Inventors
Cpc classification
E04B1/34336
FIXED CONSTRUCTIONS
E04B1/3522
FIXED CONSTRUCTIONS
E04C2003/0495
FIXED CONSTRUCTIONS
E04C3/08
FIXED CONSTRUCTIONS
B66C17/00
PERFORMING OPERATIONS; TRANSPORTING
E04C2003/0486
FIXED CONSTRUCTIONS
E04B1/342
FIXED CONSTRUCTIONS
E04B1/34384
FIXED CONSTRUCTIONS
E04G21/242
FIXED CONSTRUCTIONS
International classification
E04G21/24
FIXED CONSTRUCTIONS
E04B1/35
FIXED CONSTRUCTIONS
E04B1/343
FIXED CONSTRUCTIONS
E04B1/342
FIXED CONSTRUCTIONS
Abstract
The present invention relates to a modular assembly, a site factory, for at least partially enclosing a site during construction of a structure. The modular assembly comprising: a plurality of portal frames, each portal frame comprising two columns and a roof beam, each column and roof beam comprising a plurality of pre-assembled units; a jack-up frame for each column; at least two first rails, each of the first rails being mounted to at least one of the roof beams; at least one second rail slidably mounted to the at least two first rails; and a plurality of panels of a flexible material configured to provide a full enclosure of the site and mounted above the roof beam. The or each second rail is configured to slidably receive at least one lifting device. The pre-assembled units are configured o be connected on site, and lifted using said jack-up frames, to form the portal frames, and wherein each first rail, and the or each second rail are configured to be mounted on the portal frames on site.
Claims
1.-20. (canceled)
21. A modular assembly for at least partially enclosing a site during construction of a structure, the modular assembly comprising: a plurality of portal frames, each portal frame comprising two columns and a roof beam, each column and roof beam comprising a plurality of pre-assembled units; a jack-up frame for each column; at least two first rails, each of the first rails being mounted to at least one of the roof beams; at least one second rail slidably mounted to the at least two first rails; and a plurality of panels of a flexible material configured to provide a full enclosure of the site and mounted above the roof beam; wherein, the or each second rail is configured to slidably receive at least one lifting device; wherein, the pre-assembled units are configured to be connected on site, and lifted using said jack-up frames, to form the portal frames, and wherein each first rail, and the or each second rail are configured to be mounted on the portal frames on site.
22. A modular assembly according to claim 21, wherein each said first rail is mounted to a plurality of roof beams.
23. A modular assembly according to claim 21, wherein said at least two first rails are mounted such that the distance between the respective centres of said first rails is between about 10 m and about 20 m.
24. A modular assembly according to claim 21, comprising at least one set of second rails, each set comprising a pair of second rails slidably mounted to the at least two first rails, wherein each pair of second rails are spaced apart by a plurality of separation members and configured to receive at least one lifting device configured for use on a double rail system.
25. A modular assembly according to claim 21, further comprising foundation rails configured to allow movement of the assembly.
26. A modular assembly according to claim 25, wherein each portal frame is carried by a bogie, each bogie being configured to be slidably mounted on one of said foundation rails.
27. A modular assembly according to claim 25, wherein the assembly comprises two parts, each part comprising a plurality of portals, each part being slidable independently on said foundation rails such that the parts can be divided once assembled.
28. A modular assembly according to claim 21, further comprising at least one edge rail system mounted adjacent an edge of the assembly, the or each edge rail system comprising: at least two third rails each of the third rails being mounted to at least one of the roof beams; at least one fourth rail slidably mounted to the at least two third rails to form an edge rail system and configured to slidably receive at least one lifting device, wherein said at least one fourth rail is configured to be alignable with said at least one second rail to enable transfer of a lifting device between the at least one second rail and the at least one fourth rail.
29. A modular assembly according to claim 28, comprising at least two said edge rail systems, each said edge rail system disposed adjacent a respective edge of the assembly.
30. A modular assembly according to claim 21, further comprising at least one lifting device slidably mounted to the at least one second rail.
31. A modular assembly according to claim 21, wherein the pre-assembled units of the portal frames are formed from trusses.
32. A modular assembly according to claim 21, further comprising a plurality of end trusses.
33. A modular assembly according to claim 21, wherein the plurality of portals are of at least two differing heights.
34. A modular assembly according to claim 21, wherein the panels are formed from a thermal fabric.
35. A modular assembly according to claim 34, wherein the thermal fabric is a PVC coated polyester.
36. A modular assembly according to claim 21, further comprising panels of noise reducing material.
37. A method of assembling the modular assembly according to claim 21, the method comprising the steps of: positioning a plurality of jack up frames; providing a plurality of pre-assembled units and using said jack up frames to synchronously build up a plurality of portal frames from the pre-assembled units, each portal frame comprising two columns and a roof beam; mounting at least two first rails to at least one roof beam; slidably mounting at least one second rail to the at least two first rails; slidably mounting at least one lifting device to at least one second rail; and mounting a plurality of furled panels of a flexible material on top of the portal frame; wherein the mounting steps take place after the roof beams are connected to the respective columns, and before the columns are built-up to the required height.
38. A method according to claim 37, including providing foundation rails configured to allow movement of the assembly wherein the modular assembly is assembled adjacent the construction site and then slid along the rails to the site, wherein the step of positioning the plurality of jack-up frames comprises rolling said jack-up frames along said foundation rails.
39. A kit of parts for a modular assembly for at least partially enclosing a site during construction of a structure, the kit comprising: a plurality of pre-assembled units for forming a plurality of portal frames, each portal frame comprising two columns and a roof beam; a pair of jack up frames for each portal frame; a plurality of first rails; at least one second rail; and a plurality of pre-furled panels of a flexible material.
40. Use of a modular assembly according to claim 21, the modular assembly providing a site factory for the construction of a structure.
Description
[0061] The invention will be further described, by way of example only, with reference to the accompanying drawings in which:
[0062]
[0063]
[0064]
[0065]
[0066]
[0067]
[0068]
[0069]
[0070]
[0071]
[0072]
[0073]
[0074]
[0075] The modular assembly comprises a plurality of portal frames 102. The use of portal frames allows the creation of a wide-span enclosure which can provide a dear space uninterrupted by intermediary columns. Each portal frame comprises two columns 104 and a roof beam 106. The joints between the roof beam and the columns are rigid, allowing the bending moment in the beam to be transferred to the columns. The roof beam can therefore span large distances and thus provides the uninterrupted space. The modular assembly comprises a series of substantially parallel portal frames that run down the length thereof. Typically the portal frames are 5 to 25 metres apart. The modular assembly shown in
[0076] In a preferred embodiment the modular assembly is built upon skid rails 112, each side of the modular assembly being supported by two skid rails. This allows the modular assembly to be moved after it is assembled if it is not built directly over the site. This may be the case if the structure is e.g. a nuclear reactor. In this case the skid rails are laid before any pre-assembled units are delivered to the site or any assembly takes place.
[0077] All the elements of the modular assembly are supplied in pre-assembled units and brought to the construction site in separate pieces. These pre-assembled units are of a size that they can be delivered to the site by lorry. Typically this will be in the region of 16 m by 4 m by 4 m max. Once delivered to the site the pre-assembled units are bolted or otherwise connected together to form the columns and roof beams of the modular assembly.
[0078] The size of the assembled portal frames are dependent upon the size of the structure which is to be constructed within the modular assembly. Typically the height may be in the region of 60 m with the width being in the region of 120 m, and the length being in the region of 200 m. These dimensions are relevant to the nuclear industry. However the invention is not limited to such dimensions.
[0079]
[0080] The foundations of the modular assembly consist of two strip foundations that are designed for the specific ground conditions of the site. The strip foundation comprises a pair of rails 202 on which a bogie mounted jack-up tower 204 is located. The jack-up towers 204 and bogies are constructed from pre-assembled units. The foundation rails are configured to allow movement of the modular assembly in the direction of the rails. The jack-up towers are pre-assembled at ground level, or are delivered pre-assembled.
[0081] Each portal frame 102 comprises two columns 104 and a roof beam 106. The columns 104 of each portal frame are built-up simultaneously, and in a synchronised manner such that the roof of the assembly remains substantially horizontal. Each column comprises a plurality of pre-assembled units 206. Each pre-assembled unit 206 comprises a truss structure as described above. The lowermost, as shown, pre-assembled units 206 are positioned at the correct location by means of the bogie and form an erection frame 208. However, as will be appreciated, once the portal is fully formed the pre-assembled unit 206 forms the joint between the column 104 and the roof beam 106 and so becomes the uppermost pre-assembled unit of the column. The jack-up tower 204 is then used to build-up the columns 104 to the required height by adding further pre-assembled column units. The erection frames 208 are part of the portal frame and remain in position throughout.
[0082]
[0083] As each pre-assembled unit 206 is added to the column 104 it is locked off and tie bars are connected between each portal frame 102. The tie bars are provided for stability only and do not form part of the load bearing structure. Additional diagonal bracing members are provided between the portals, in both the plane of the walls and of the roof, to provide the modular assembly with sufficient rigidity, for example to withstand side loads, such as wind loads.
[0084] Once the columns have reached a certain height the roof beam 106 may be assembled. For example, the roof beam may be assembled, and connected to the corresponding columns after the first pre-assembled units of each column are in place, and connected to the erection frame. The roof beam is assembled at low level from a plurality of pre-assembled units 210.
[0085] At least two longitudinal (first) rails 502 are bolted or otherwise fixed below the roof beam 106 before the columns are built-up to full height. In the example shown in the figures, in particular in
[0086] At least one transverse (second) rail 504, is slidably mounted to the at least two main longitudinal rails 502 by bogies 600, The transverse rails are slidably mounted such that they are substantially perpendicular to the longitudinal rails. In preferred examples, as shown in the figures, the transverse rails are provided in pairs, spaced apart by spacing members. The transverse rails in a set are spaced apart by about 3 m. In the embodiment shown in the figures, in particular in
[0087] Both the longitudinal rails and the transverse rails, and indeed the lifting devices, and any other components, such as lighting, that are connected to the roof beams, are added before the columns are jacked to full height. The assembly of the longitudinal rails and transverse rails relative to the roof are best illustrated in
[0088] As can be seen in
[0089] As stated above the main longitudinal rails 502 are positioned below the roof beam and are supported by the roof beam. The transverse rails 504 are positioned below the main longitudinal rails and are slidably mounted on the main longitudinal rails. The transverse rails are mounted on the longitudinal rails by means of overhead bogies which allows the transverse rails to run along the longitudinal rails and thus along the length of the modular assembly. The lifting devices are mounted on the transverse rails by means of bogies on the underside thereof. This allows the lifting devices to run along the underside of the transverse rails and thus across the width of the modular assembly. The arrangement of the longitudinal rails and the transverse rails thus allows the lifting devices to move up and down the modular assembly as required. This allows the lifting devices to be precisely manoeuvred into a required location. Multiple lifting devices can be moved to construction hot spots as construction intensity moves around the site. The lifting devices are unobstructed within the enclosure.
[0090] In order to enable precision building, means for determining the relative position of the or each lifting device, and lifting hook, as compared to the modular assembly are provided. The means for determining the relative position of the or each lifting device and lifting hook comprises a plurality of sensors configured to respectively determine the position of the or each transverse rail supporting the lifting device relative to the longitudinal rails supporting the or each transverse rail, and configured to determine the position of the or each lifting device relative to the or each transverse rail supporting the or each lifting device. The means for determining the relative position of the or each lifting device, further comprises means for determining the relative position of the lifting hook of the lifting device relative to the lifting device.
[0091] The lifting devices may be cranes. The cranes can move along the width and length of the modular assembly as described above.
[0092] As described above,
[0093] Before the roof is jacked-up to full height, rolls of fabric 900 are also installed on the upper side of the roof, as shown in
[0094] Tie bars are fixed between each roof beam for stability, and support, before the rolls of fabric are positioned.
[0095] The rolls of fabric 900 located on the upper side of the roof beam 106 are unfurled down either side of the assembly once the modular assembly is assembled and locked in position and equipment, such as the lifting devices, is installed inside. The rolls of fabric can be delivered to the site by lorry.
[0096] The fabric used for the fabric rolls must be flexible enough to be supplied as rolls of fabric. Once the rolls are unfurled the fabric panel is rolled out to form the roof and the walls of the modular assembly. The fabric is rolled down the sides of the assembly and seals the modular assembly. The panels are tightened and locked off. It is possible to locate site offices directly adjacent the portal frames. In this case the fabric may unfurl to cover these. Such an embodiment would allow direct access to the interior of the modular assembly through the site offices. In this instance the length of the roll would be increased to accommodate the extra surface area to be covered.
[0097] The fabric may have the thermal qualities necessary to regulate the temperature within the modular assembly. A possible fabric could be PVC coated polyester. However, a person skilled in the art will understand that any suitable material may be used. The invention is not limited to the named material. Different fabrics may be used for different environments, depending on the specific requirements of each site. For example more heavy duty protection may be required to significantly reduce noise impact and additional screening may be provided. To reduce noise impact the fabric may comprise a composite material or be formed of a double skin with a suitable filler in between.
[0098] It is also important to control the humidity within the site factory enclosure. To that end equipment such as heaters and de-humidifiers may be introduced into the enclosure.
[0099] Once the portals of the assembly have been jacked-up to full height, the end trusses 108 are bolted or otherwise connected to either end of the assembly. The end trusses are connected to the portal frames located at each end of the assembly, and are provided with at least one doorway formed of the fabric panels (not shown). Once the end trusses are in place, the rolls of fabric arranged to cover the end walls of the assembly are unfurled, and fixed in place.
[0100] It will be noted that the figures show portals of two different heights. It is therefore not essential that the entire modular assembly has the same height.
[0101] The modular assembly, in the example shown in the figures, is constructed in two sections; a first section disposed away from a first end of the primary construction site, and a section disposed away from a second end of the construction site. Once each section of the modular assembly is complete, each section is moved into position over the construction site to form a complete enclosure (as shown in
[0102] In use, the modular assembly provides environmental protection for a construction site. The construction can take place within the sealed space of the assembly with significantly reduced influence of external factors. Equally the construction activity will have reduced impact on the outside environment.
[0103] The key determinant of construction productivity is material handling, and as described above, the present modular assembly is provided with a plurality of lifting devices to enable that material handling. Each lifting device provides a “20 tonne hook”, such that the hooks can be located at any point within the assembly. Using a “swarm” of such “20 tonne hooks” the lifting capacity at any point in the modular assembly can be significantly increased, and the present example allows for individual lifts of up to 170 tonnes.
[0104] The construction materials would be supplied to stockpile and processing areas provided at the ends of the modular assembly. The materials are then transferred from these areas, for example using the edge rail system as described above.
[0105] As explained above the modular assembly of the example shown in the figures is built upon skid rails. As described above, this allows construction of the modular assembly to take place adjacent to the area of the actual construction site. This feature also allows the modular assembly to be split. Splitting the modular assembly provides a side opening which may allow a particularly heavy or large piece of equipment to enter the assembly. The assembly may then slide again to close the opening. The assembly may also be slid back along the rails to dis-assemble the modular assembly away from the completed structure.
[0106]
[0107] As can be seen when a construction site is covered by the modular assembly the activity that can take place is fairly constant. This is due to the fact that exterior variables have a smaller impact on the activity. Compared to a conventional uncovered construction where the amount of activity is hugely variable, the present modular assembly, a site factory, provides significant advantages. The huge variation in building activity can be due to factors such as adverse weather conditions or even just the amount of light available. Having a constant amount of activity allows better forward planning as to how long a project may take, and will likely reduce build time, and reduce costs. It also allows more efficient planning of when parts of the construction site need to be delivered.
[0108] The modular assembly remains in place throughout the construction of the structure. This may be several years but will be significantly shorter than if the construction took place outside of the modular assembly. When the construction is finished the modular assembly may be dis-assembled. The dis-assembled units can then be transported away from the site by lorry. The dis-assembled units may be used at another site.
[0109] It will be understood by those skilled in the art that the scope of the invention is not limited to the embodiments described above. This written description uses examples to disclose the invention and also to enable any person skilled in the art to practice the invention.