Method and related devices for carrying out TBM excavation and expansion blasting using a blast protector and a cart
09568295 ยท 2017-02-14
Inventors
Cpc classification
E21D9/12
FIXED CONSTRUCTIONS
International classification
E21D9/12
FIXED CONSTRUCTIONS
E21D9/00
FIXED CONSTRUCTIONS
F42D3/04
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
Abstract
The present invention relates to a method and related devices for carrying out TBM excavation and expansion blasting, which uses a blast protector and a cart to expand a pilot tunnel by blasting after the pilot tunnel has been formed; and which specifically includes: a step of forming a pilot tunnel; a step of forming a horizontal or vertical blast hole; a step of installing a blast protector within the pilot tunnel; a step of blasting the upper and lower halves of the pilot tunnel to expand the upper and lower halves; and a step of removing the debris formed during the blasting of the upper and lower halves, by dumping the debris into a cart. Accordingly, the rail and cable are protected from the debris formed during the blasting, and working efficiency is improved.
Claims
1. A construction method using a plurality of blasting protectors, the construction method comprising: excavating a pilot tunnel using a tunnel boring machine (TBM); drilling a transverse or longitudinal charge hole on an upper half section of the pilot tunnel; connecting and installing the plurality of blasting protectors that partition the upper half section and a lower half section at the front and the rear at the inside of the pilot tunnel; enlargement blasting the upper half section of the pilot tunnel using the transverse or longitudinal charge hole; and loading and carrying mucks stacked on the upper of the plurality of blasting protectors by the enlargement blasting in a muck car moving to a first lower space of one upper blasting protector of the plurality of blasting protectors, wherein the muck car is moved to a second lower space between the upper blasting protector on which the mucks are stacked and the upper blasting protector on which the mucks are removed by moving the upper blasting protector on which the mucks are removed, and wherein two of the plurality of blasting protectors are spread and the loading and carrying of mucks in the muck car is through or between the two spread blasting protectors.
2. The construction method of claim 1, wherein the excavating step comprises a step of installing a cable at the bottom of the pilot tunnel; and a step of installing a rubber cover plate to cover the cable.
3. The construction method of claim 1, further comprising: moving one upper blasting protector of the plurality of blasting protectors on which the mucks are removed; installing a lower blasting protector for protecting a rail or a cable installed at the bottom of the pilot tunnel; drilling a longitudinal charge hole on both sides of the lower half section of the pilot tunnel; enlargement blasting the lower half section of the pilot tunnel using the longitudinal charge hole; and loading and carrying mucks stacked on the lower blasting protector by the enlargement blasting in the muck car.
4. A plurality of blasting protectors, the plurality of blasting protectors comprising: an arch type plate for partitioning an inside of a pilot tunnel into an upper half section and a lower half section; a hydraulic support installed in both side end portions in close contact with an inner surface of the pilot tunnel; a hydraulic foldable support for mounting on a muck car when moving and installed in a lower portion thereof, a support jaw formed in a front end portion of an arch type plate form; and a hydraulic extension plate whose end portion is latched and supported by the support jaw of the arch type plate by protraction and retraction in a front-rear direction at both sides of a rear end portion of the arch type plate form.
5. The plurality of blasting protectors of claim 4, further comprising: a variable blade for adjusting a lateral width and installed at an upper portion of side end portions in which the hydraulic support is installed.
6. The plurality of blasting protectors of claim 5, wherein a rubber blade is coupled to an end portion of the variable blade.
7. The plurality of blasting protectors of claim 4, wherein another hydraulic support is installed at the bottom of the hydraulic extension plate protruded from a front end portion of the upper blasting protectors to be used for finishing and supports the protruded hydraulic extension plate.
Description
BRIEF DESCRIPTION OF DRAWINGS
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
(17)
(18)
(19)
(20) TABLE-US-00001 10: pilot tunnel 11: TBM 12: rail 13: cable 14: muck car 20a, 20c, 20b: charge hole 21: drill 100: upper blasting protector 110: hydraulic support 120: hydraulic foldable support 130: variable blade 140: rubber blade 150: support jaw 160: hydraulic extension plate 170: another hydraulic support of 200: rubber cover plate hydraulic extension plate 300: lower blasting protector 500: prop
BEST MODES FOR CARRYING OUT THE INVENTION
(21) A construction method of TBM excavation and enlargement blasting using a blasting protector and a muck car according to the present invention, the construction method including:
(22) step of excavating a pilot tunnel using a tunnel boring machine (TBM);
(23) step of drilling a transverse or longitudinal charge hole on an upper half section of the pilot tunnel;
(24) step of connecting and installing a plurality of blasting protectors that partition the upper half section and a lower half section at the front and the rear at the inside of the pilot tunnel;
(25) step of enlargement blasting on the upper half section of the pilot tunnel using the charge hole; and
(26) step of loading and carrying mucks stacked on the upper blasting protector by the enlargement blasting in a muck car moving to a lower space of the upper blasting protector.
(27) Further, a blasting protector for TBM excavation and enlargement blasting according to the present invention, the blasting protector including:
(28) a hydraulic support formed in an arch type plate form to partition the inside of the pilot tunnel into an upper half section and a lower half section by installing at the inside of a pilot tunnel excavated by a TBM and installed in both side end portions close contacting with an inner surface of the pilot tunnel; and
(29) a hydraulic foldable support for mounting on a muck car when moving and installed in a lower portion thereof.
MODES FOR CARRYING OUT THE INVENTION
(30) An exemplary embodiment of the present invention will be described in detail with reference to the attached drawings.
(31) As shown in
(32) Step of excavating the pilot tunnel 10 uses a tunnel boring machine (TBM) 11, as shown in
(33) Step of excavating the pilot tunnel 10 includes step of installing a rubber cover plate 200 for covering the cable 13. The rubber cover plate 200 protects the cable 13 from drop of various equipments or tools as well as mucks and may be formed in, for example, an arch form using a rubber material, as shown in
(34) Step of drilling transverse or longitudinal charge holes 20a and 20b on the upper half section of the pilot tunnel 10 is performed using a drill 21, as shown in
(35) The upper blasting protector 100 that partitions an upper half section and a lower half section may be installed using the muck car 14 at the inside of the pilot tunnel 10, as shown in
(36) For this purpose, a means for adjusting a height of the upper blasting protector 100 should be installed on the muck car 14 or a lower portion of the upper blasting protector 100. As an example of a means for adjusting a height of the upper blasting protector 100, a hydraulic foldable support 120 installed in a lower portion of the upper blasting protector 100 is illustrated, as shown in
(37) At step of enlargement blasting on the upper half section of the pilot tunnel 10 using the transverse charge hole 20a and the longitudinal charge hole 20c, blasting should be performed in a form of gradually enlarging from the inside to an outer edge of the pilot tunnel 10. In this case, as shown in
(38) At step of loading and carrying the mucks stacked on the upper blast protector 100 by the enlargement blasting in the muck car 14, before the enlargement blasting, it is good to move the muck car 14 under the upper blasting protector 100. Therefore, as shown in
(39) In a process of loading mucks stacked on the upper blasting protector 100 in the muck car 14, the muck car 14 is moved under between the front and rear upper blasting protector 100, after the front and rear upper blasting protector 100 is spread, the mucks may be loaded in the muck car 14 through the spread gap and be carried out, as shown in
(40) Further, an TBM excavation and enlargement blasting method according to an exemplary embodiment of the present invention includes step of moving and installing the upper blasting protector 100; step of installing the lower blasting protector 300 for covering the bottom of the pilot tunnel 10; step of drilling the longitudinal charge hole 20c at both sides of a lower half section of the pilot tunnel 10; step of enlargement blasting a lower half section of the pilot tunnel 10 using the charge hole 20c; and step of loading and carrying mucks stacked on the lower blasting protector 300 in the muck car 14 by the enlargement blasting.
(41) Step of moving and installing the upper blasting protector 100 is performed in reverse order of installation of the upper blasting protector. That is, after moving the muck car 14 under the upper blasting protector 100, the upper blasting protector 100 is mounted in the muck car and is transported.
(42) At step of installing the lower blasting protector 300 for covering the bottom of the pilot tunnel 10, the lower blasting protector 300 has a configuration different from the upper blasting protector 100, and the lower blasting protector 300 covers a minimum bottom or the rail 12 for moving the muck car 14 to the pilot tunnel 10 and is formed to protect the cable 13. In this case, before installing the lower blasting protector 300, by previously delivering the muck car 14 to the inside of the pilot tunnel 10, the upper blasting protector is moved and installed, and after enlargement blasting, mucks are carried out using the muck car 14.
(43) At step of drilling the longitudinal charge hole 20c at both sides of a lower half section of the pilot tunnel 10, as shown in
(44) At step of performing enlargement blasting of a lower half section of the pilot tunnel 10 using the charge hole 20c, in a form of gradually enlarging from the inside to an outer edge of the pilot tunnel 10, blasting should be performed.
(45) Step of loading and carrying mucks stacked on the lower blasting protector 300 in the muck car 14 by the enlargement blasting includes step of loading mucks stacked on the lower blasting protector 300 and the ground in the muck car using a backhoe.
(46) As shown in
(47) When enlargement blasting is performed, the upper blasting protector 100 bears an impact and a pressure due to heavily dropping mucks, and the upper blasting protector 100 is formed in an arch type plate form to support a load of mucks stacked on the upper blasting protector 100.
(48) The hydraulic support 110 is installed in both side end portions and is installed to incline toward a lower portion. Therefore, the hydraulic support 110 close contacts with both sides of the pilot tunnel 10 to support the blasting protector 100 not to move downward. At both side end portions of the blasting protector 100, a plurality of hydraulic supports 110 are installed in the same gap at the front and the rear. In this case, in order to prevent the hydraulic support from directly receiving a blasting impact, another hydraulic prop 500 is driven in a direction perpendicular to the hydraulic support.
(49) As described above, the hydraulic foldable support 120 is a means for adjusting a height of the upper blasting protector 100, and in a state in which the hydraulic foldable support 120 is mounted in the muck car 14, by spreading the hydraulic foldable support 120, a height of the upper blasting protector 100 is raised, and when the hydraulic foldable support 120 is installed in the pilot tunnel 10, by folding the hydraulic foldable support 120, a height of the upper blasting protector 100 is lowered. As described above, the upper blasting protector 100 may be installed in an intermediate portion of the inside of the pilot tunnel 10 through adjustment of a height of the hydraulic foldable support 120. The hydraulic foldable support 120 is fixed and supported to the bottom of the inside of the muck car.
(50) At an upper portion of both side end portions in which the hydraulic support 110 is installed, a variable blade 130 for adjusting a lateral width is installed. As shown in
(51) By coupling a rubber blade 140 to an end portion of the variable blade 130, close contacting with the pilot tunnel 10 can be further improved.
(52) In a front portion of the upper blasting protector 100, a support jaw 150 installed, as shown in
(53) In the upper blasting protector 100 used for finishing, at both sides of a front end portion, the hydraulic extension plate 160 for protracting and retracting in the front-rear direction is installed, and at both sides of a rear end portion, the hydraulic extension plate 160 for protracting and retracting in the front-rear direction is protruded to be connected to an adjacent arch shape plate. Further, at the bottom of the protruded hydraulic extension plate 160 coming from a front end portion of the upper blasting protector 100 used for finishing, another hydraulic support 170 of the hydraulic extension plate is installed to support the protruded hydraulic extension plate 160.
(54) According to the present invention, upon enlargement blasting using the upper blasting protector 100, by preventing damage of the rail 12 and the cable 13 by mucks, a cost is reduced and safety is enhanced.
(55) Further, even after enlargement blasting, going in and out to a tunnel face of TBM and movement of the muck car 14 are smoothly performed through under the upper blasting protector 100 and thus a work of entire steps such as TBM 11 excavation and enlargement blasting of the pilot tunnel 10 and carrying out of mucks can be simultaneously performed and thus a period of works can be reduced.
(56) Further, by simply moving and loading mucks stacked on the upper blasting protector 100 in the muck car 14 disposed under the upper blasting protector using a backhoe, a carrying work of the mucks can be more conveniently and rapidly performed.