A TRE ASSEMBLE PERMANENT COLUMN FORMWORK AND MANUFACTURING METHOD THEREOF
20220325542 · 2022-10-13
Inventors
- Shiping YIN (Xuzhou, CN)
- Zhangtao PENG (Xuzhou, CN)
- Xiuxian LI (Xuzhou, CN)
- Yuntao HUA (Xuzhou, CN)
- Xudong REN (Xuzhou, CN)
- Yingde ZHAO (Xuzhou, CN)
- Haofeng LONG (Xuzhou, CN)
- Haonan CONG (Xuzhou, CN)
Cpc classification
B28B23/0006
PERFORMING OPERATIONS; TRANSPORTING
B28B23/02
PERFORMING OPERATIONS; TRANSPORTING
Y02A30/30
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
International classification
Abstract
The present invention discloses a TRC assemble permanent column formwork and a manufacturing method thereof, which belongs to the technical field of reinforced concrete building construction. The TRE assemble permanent column formwork comprises first panels, second panels, circumferential bolts, longitudinal bolts, nuts and gaskets; the formwork is manufactured from an engineered cementitious composite ECC and a woven fabric net; the first panels are used for assembling the column formwork at the two ends of a column, and the second panels are used for assembling the column formwork in the middle section of the column; the panels are provided with preformed bolt holes, and the bolt holes among the panels are corresponding to each other for bolt connections; the bolts include circumferential bolts and longitudinal bolts. The TRE permanent column formwork provided by the present invention can reduce material waste, labor cost, and project cost. Besides, the panels have advantages of easy and firm assembling, convenient transportation and low manufacturing cost, and the formwork has great application prospects.
Claims
1. A TRE assemble permanent column formwork, comprising first panels (1), second panels (2), circumferential bolts (4), longitudinal bolts (5), nuts and gaskets, wherein the first panels (1) are used for assembling the column formwork at the two ends of a column, the second panels (2) are used for assembling the column formwork in the middle section of the column, the panels are provided with preformed bolt holes (3) at assembling positions, and the bolt holes among the panels are corresponding to each other; the first panel (1) and the second panel (2) are in an arc shape respectively; the first panel (1) has a circular sector-shaped flat surface at the top end, a bottom end of the first panel (1) is provided with a boss, a left end of the first panel (1) is provided with a circumferential boss, and a right end of the first panel (1) is provided with a groove to be fitted with the circumferential boss; the second panel (2) has a groove at the top end and at the bottom end respectively to be fitted with the boss at the bottom end of the first panel (1), a left end of the second panel (2) is provided with a circumferential boss, and a right end of the second panel (2) is provided with a groove to be fitted with the circumferential boss; both the circumferential bolt (4) and the longitudinal bolt (5) comprise bolt heads and bolt rods at head end and at the tail end wherein the bolt rod of the circumferential bolt (4) is arc, while the bolt rod of the longitudinal bolt (5) is straight; the shape of the bolt head is a solid body formed by two semi-ellipsoidal surfaces angled with respect to each other and curved surfaces between the circumferences of the two semi-ellipsoidal surfaces; the major axes of the two semi-ellipsoidal surfaces are different from each other, the two ends of the bolt head have male threads, the semi-ellipsoidal surface of the bolt head with a shorter major axis is provided with female threads at the center, the bolt rod is connected with the bolt heads through threads, and the shape of the bolt holes is a groove to be fitted with the bolt head; the first panel (1) and the second panel (2) are manufactured from an engineered cementitious composite ECC and a woven fabric net (6), the woven fabric net (6) is arranged at the central part of the panel.
2. The TRE assemble permanent column formwork according to claim 1, wherein the woven fabric net (6) is in an arc shape corresponding to the panel, and is at the same distance from the inner diameter and the outer diameter of the column formwork.
3. The TRE assemble permanent column formwork according to claim 2, wherein a single column comprises 8 first panels and 4N second panels, wherein N is a natural number greater than or equal to 1.
4. The TRE assemble permanent column formwork according to claim 1, wherein all of the bolts, nuts and gaskets are made of FRP material.
5. The TRE assemble permanent column formwork according to claim 4, wherein the FRP material of the bolts may be any of AFRP, BFRP, CFRP and GFRP.
6. A method for manufacturing the panels of a TRE assemble permanent column formwork, comprising the following steps: step 1: determining the dimensions of TRE panels according to the dimensions of the column to be poured; step 2: selecting a laminated wood formwork as a mold for panel forming, and supporting the wood formwork according to the dimensions and shapes of the panels, wherein there are two types of wood formworks in shape used for fabricating two types of panels, and the upper part of the mold employs an overturn and hinged mold opening/closing means, and lateral supporting is required when the wood formwork is supported; step 3: cutting a rigid plastic foam board according to the dimensions of a side formwork of the wood formwork, bonding the rigid plastic foam board to the inner side of the side formwork, drilling holes in the column formwork at positions where bolt holes need to be reserved to mount prefabricated PVC plastic hole-forming model, wherein the hole-forming model is divided into two types: prefabricated circumferential PVC plastic hole-forming models (7) and prefabricated longitudinal PVC plastic hole-forming models (8), for preforming circumferential bolt holes and longitudinal bolt holes required for the panels respectively; step 4: applying a mold releasing agent inside the mold; step 5: cutting a woven fabric net according to the dimensions and shape of the mold; wherein the woven fabric net is woven from several types of fibers selected from carbon fibers, aramid fibers, alkali-resistant glass fibers, basalt fibers, polyethylene fibers, and polyvinyl alcohol fibers; the woven fabric net is woven from different types of fibers in combination in the weft direction and warp direction; step 6: cutting steel wire mesh according to the required dimensions and shape of the woven fabric net, attaching the woven fabric net to the steel wire mesh, and then uniformly applying epoxy resin coating solution on the woven fabric net with a brush while paying attention to the uniformity of application and avoiding any missing coating, so that the connection between the fibers of the woven fabric net is closer to prevent any deformation of the woven fabric net during ECC pouring; step 7; treating the woven fabric net by sand blasting before the epoxy resin coating solution is cured, the sand used for sand blasting is silica sand; step 8: air-drying the woven fabric net in a dry and ventilated environment; step 9: mounting the woven fabric net on the central part of the mold; step 10: closing the overturn and hinged mold opening/closing means on the top part of the mold, wherein the panel employs a horizontal pouring method, leaving only one notch for material pouring; step 11: pouring ECC, vibrating the mold once when about ¼ pouring work is completed to expel air bubbles in the ECC and improve the compactness of the ECC, repeating the above-mentioned process for several times until the entire mold is fully filled with the ECC, then opening the overturn and hinged mold opening/closing means and carrying out a surface finishing procedure; step 12: keeping the mold in appropriate humidity and temperature conditions for curing for 28 days after the pouring is finished; finally removing the mold and entering into the stacking stage, piling up the panels.
7. The method for manufacturing the panels of a TRE assemble permanent column formwork according to claim 6, wherein the epoxy resin coating solution used in the step 6 is prepared with the following method: mixing epoxy resin, a curing agent, and a diluent in a ratio of 2:2:1 intensively to a homogeneous state in a closed environment, so as to obtain the epoxy resin coating solution.
8. The method for manufacturing the panels of a TRE assemble permanent column formwork according to claim 6, wherein the ECC used in the step 11 is prepared with the following method: step 1: preparing the following materials: 442 kg/m.sup.3 P.O42.5 Portland cement, 821 kg/m.sup.3 Grade I coal ash, 455 kg/n 140-280-mesh quartz sand, 9.7 kg/m.sup.3 high-performance water reducer Sika poly-carboxylic acid with the water reducing rate of 30%, 0.63 kg/m.sup.3 thickener, 354 kg/m.sup.3 tap water, and chopped fibers in volume fraction of 2%; step 2: pouring the cement, quartz sand, coal ash, and thickener into an agitator and agitating for 2-3 min, pouring tap water with dissolved high-performance water reducer Sika poly-carboxylic acid into the agitator and agitating for 6-8 min after the materials are uniformly mixed, then continually adding the chopped fibers uniformly, after all of the fibers are added into the agitator, agitating further for 3-5 min; thus, the preparation of the ECC is completed.
9. The method for manufacturing the panels of a TRE assemble permanent column formwork according to claim 6, wherein the appropriate curing conditions in the step 12 are: temperature: (20±1)° C., humidity: ≥95%.
10. The method for manufacturing the panels of a TRE assemble permanent column formwork according to claim 8, wherein the chopped fibers are mixed from one or more types of non-metal fibers that are different from each other in performance, including basalt fibers, polypropylene fibers, polyvinyl alcohol fibers, polyethylene fibers, carbon fibers, and glass fibers, etc.
Description
BRIEF DESCRIPTION OF DRAWINGS
[0038]
[0039]
[0040]
[0041]
[0042]
[0043]
[0044]
EMBODIMENTS
[0045] Hereunder the present invention will be further described with reference to the accompanying drawings.
[0046] As shown in
[0047] A single column comprises 8 first panels and 4N second panels, wherein N is a natural number greater than or equal to 1. All of the bolts, nuts and gaskets are made of FRP material. The FRP material of the bolts may be any of AFRP. BFRP. CFRP and GFRP. Bolts made of a FRP material have effectively improved chloride corrosion resistance and can enhance corrosion resistance of the permanent formworks.
[0048] A method for manufacturing the panels of a TRE assemble permanent column formwork comprises the following steps:
[0049] step 1: determining the dimensions of TRE panels to facilitate transportation according to the dimensions of the column to be poured;
[0050] step 2: selecting a laminated wood formwork as a mold for panel forming, and supporting the wood formwork according to the dimensions and shapes of the panels, wherein there are two types of wood formworks in shape used for fabricating two types of panels, and the upper part of the mold employs an overturn and hinged mold opening/closing means, and lateral supporting is required when the wood formwork is supported to prevent lateral deformation during ECC pouring:
[0051] step 3: cutting a rigid plastic foam board according to the dimensions of a side formwork of the wood formwork, bonding the rigid plastic foam board to the inner side of the side formwork, drilling holes in the column formwork at positions where bolt holes need to be reserved to mount the prefabricated PVC plastic hole-forming model, wherein the hole-forming model is divided into two types: prefabricated circumferential PVC plastic hole-forming models 7 and prefabricated to longitudinal PVC plastic hole-forming models 8, as shown in
[0052] step 4: applying a mold releasing agent inside the mold to facilitate removal of the permanent formwork;
[0053] step 5: cutting a woven fabric net according to the dimensions and shape of the mold; wherein is the woven fabric net is woven from several types of fibers selected from carbon fibers, aramid fibers, alkali-resistant glass fibers, basalt fibers, polyethylene fibers and polyvinyl alcohol fibers; the woven fabric net is woven from different types of fibers in combination in the weft direction and warp direction;
[0054] step 6: cutting steel wire mesh according to the required dimensions and shape of the woven fabric net, attaching the woven fabric net to the steel wire mesh, and then uniformly applying epoxy resin coating solution on the woven fabric net with a brush while paying attention to the uniformity of application and avoiding any missing coating, so that the connection between the fibers of the woven fabric net is closer to prevent any deformation of the woven fabric net during ECC pouring; the epoxy resin coating solution is prepared with the following method: mixing epoxy resin, a curing agent, and a diluent in a ratio of 2:2:1 intensively to a homogeneous state in a closed environment, so as to obtain the epoxy resin coating solution.
[0055] step 7; treating the woven fabric net by sand blasting before the epoxy resin coating is cured, the sand used for sand blasting is silica sand;
[0056] step 8: air-drying the woven fabric net in a dry and ventilated environment;
[0057] step 9: mounting the woven fabric net on the central part of the mold;
[0058] step 10: closing the overturn and hinged mold opening/closing means on the top part of the mold, wherein the panel employs a horizontal pouring method, and leaves only one notch for material pouring, to ensure no deformation, close fitting and no grout leakage during continuous production;
[0059] step 11: pouring ECC, which has good workability and fluidity, vibrating the mold once when about ¼ pouring work is completed to expel air bubbles in the ECC and improve the compactness of the ECC, repeating the above-mentioned process for several times until the entire mold is fully filled with the ECC, then opening the overturn and hinged mold opening/closing means and carrying out a surface finishing procedure;
[0060] step 12: keeping the mold in appropriate humidity and temperature conditions for curing for 28 days after the pouring is completed; finally, removing the mold, and entering into stacking stage, piling up the modes; the appropriate curing conditions are: temperature: (20±1) ° C., humidity: ≥95%.
[0061] The ECC used in the step 11 is prepared with the following method:
[0062] step 1: preparing the following materials: 442 kg/m.sup.3 P.O42.5 Portland cement, 821 kg/m.sup.3 Grade I coal ash, 455 kg/m.sup.3 140-280-mesh quartz sand, 9.7 kg/m.sup.3 high-performance water reducer Sika poly-carboxylic acid with the water reducing rate of 30%, 0.63 kg/m.sup.3 thickener, 354 kg/m.sup.3 tap water and chopped fibers in volume fraction of 2%;
[0063] step 2: pouring the cement, quartz sand, coal ash, and thickener into an agitator and agitating for 2-3 min., pouring tap water with dissolved high-performance water reducer Sika poly-carboxylic acid into the agitator and agitating for 6-8 min, then continually adding the chopped fibers uniformly, after all of the fibers are added into the agitator, agitating further for 3-5 min; thus, the preparation of the ECC is completed: wherein the chopped fibers are mixed from one or more types of non-metal fibers that are different from each other in performance, including basalt fibers, polypropylene fibers, polyvinyl alcohol fibers, polyethylene fibers, carbon fibers, and glass fibers, etc.