MULTI-LINK CONSTRUCTION ELEMENT AND METHOD FOR ASSEMBLING SAME
20170009454 ยท 2017-01-12
Inventors
- Larisa Arkadievna Molokhina (Moscow, RU)
- Ilya Valerievich Molokhin (Moscow, RU)
- Olga Mikhailovna Kozlova (Balashikha Moskovskaya obl., RU)
- Vera Alexandrovna Bekreneva (Moscow, RU)
- Roman Alexandrovich Bekrenev (Moscow, RU)
Cpc classification
E04C5/08
FIXED CONSTRUCTIONS
E01C9/06
FIXED CONSTRUCTIONS
E04C3/20
FIXED CONSTRUCTIONS
E04C2/00
FIXED CONSTRUCTIONS
E04C3/29
FIXED CONSTRUCTIONS
E04C2003/0486
FIXED CONSTRUCTIONS
E04C5/085
FIXED CONSTRUCTIONS
E04C5/06
FIXED CONSTRUCTIONS
E04C1/00
FIXED CONSTRUCTIONS
E04C5/07
FIXED CONSTRUCTIONS
E04C5/01
FIXED CONSTRUCTIONS
International classification
E04C5/01
FIXED CONSTRUCTIONS
E01C9/06
FIXED CONSTRUCTIONS
E04C5/07
FIXED CONSTRUCTIONS
Abstract
The present set of inventions relates to the field of building and in particular to building constructions and to processes for manufacturing building constructions comprising tensioned and non-tensioned tendons and can be used to construct residential, public and office buildings and constructions as well as for reconditioning or restoring the same.
The technical result consists of the provision of relatively long-extended constructions or complicated shape constructions working as a single pre-tensioned construction and characterized by high carrying capacity, stability and rigidity.
Said technical result is obtained by the fact that in a multi-component building member comprising at least two components and pre-tensioned tendons, each component is made as a tendons module comprising an initial and a final supporting elements with holes for the pre-tensioned tendons and with a stand for placing anchors and tensioning arrangements; and a reinforcing cage located between said supporting elements and comprising an upper and a lower elements in the form of a grid with a cellular structure, the cells having the shape of an equilateral polyhedron, and at least one median element under the form of a space reinforcement structure comprising inclined reinforcement bars forming equilateral polyhedral pyramids oppositely oriented in space, the pre-tensioned tendons of the first component being anchored at the initial and final supporting elements of the same, the pre-tensioned tendons of each following component being anchored at the final elements of the previous and the current components.
Said technical result is obtained as well by the fact that in a process for assembling the multi-component building member, the median, the upper and the lower components of the tendons module are preassembled, attached between the initial and the final supporting elements, the tendons are inserted and then pre-tensioned, wherein, starting with the second tendons module of the construction, the anchor of the pre-tensioned tendons is mounted on the final supporting element of the previous tendons module, whereas a tensioning arrangement is mounted on the final supporting element of the pre-tensioned tendons module.
Claims
1. A multi-component building member comprising at least two components and pre-tensioned tendons, characterized in that each component is made as a tendons module comprising an initial and a final supporting elements with holes for the pre-tensioned tendons and with a stand for placing anchors and tensioning arrangements, and a reinforcing cage located between said supporting elements and comprising an upper and a lower elements in the form of a grid with a cellular structure, the cells having the shape of an equilateral polyhedron, and at least one median element under the form of a space reinforcement structure comprising inclined reinforcement bars forming equilateral polyhedral pyramids oppositely oriented in space, the pre-tensioned tendons of the first component being anchored at the initial and final supporting elements of the same, the pre-tensioned tendons of each following component being anchored at the final elements of the previous and the current components.
2. A multi-component building member of claim 1, characterized in that it is additionally provided with lateral supporting elements situated at the angle of 0<<180 to the longitudinal axis of the building member with the provision of a preliminary tensioning in the direction at the angle of 0<<180 to the longitudinal axis of the building member.
3. A multi-component building member of claim 1, characterized in that the use is made of bar tendons as pre-tensioned tendons.
4. A multi-component building member of claim 1, characterized in that the use is made of rope tendons as pre-tensioned tendons.
5. A multi-component building member of claim 4, characterized in that it is additionally provided with tubular channel forming devices for making the rope tendons.
6. A multi-component building member of claim 1, characterized in that at least one of the elements of the reinforcing cage is made monolithic.
7. A multi-component building member of claim 1, characterized in that the upper and/or lower elements and/or the reinforcement bars of the median element in a tendons module can be made of metal or of composite materials on the basis of basalt or carbon, or of fiber glass, or of polymer materials, or of polymer materials with reinforcing additives.
8. A multi-component building member of claim 1, characterized in that the space between the reinforcement bars of the median element of the tendons module is filled with a filler.
9. A multi-component building member of claim 8, characterized in that as a filler, use can be made of concrete or polymer materials, or of polymer materials with reinforcing additives, or of soundproofing materials, or of heat-insulating materials.
10. A multi-component building member of claim 1, characterized in that the upper and/or lower elements are made with a possibility to attach panels.
11. A multi-component building member of claim 1, characterized in that in the space between the reinforcement bars of the median element of the tendons module, tubes for supply lines are placed, at least a part of the last being made with inspection holes to provide a possibility for mounting operations or for diagnosing the supply line condition.
12. A multi-component building member of claim 1, characterized in that means for contactless electromagnetic supply are provided for example for supplying electric cars moving on the roadbed.
13. A multi-component building member of claim 1, characterized in that it is provided with means for heating the same, located between the tendons of the median element in the tendons module.
14. A multi-component building member of claim 1, characterized in that at least a part of the reinforcement bars of the median element in the tendons module is provided with free length parts to insure a contact with the cast-in-place or underlying layer.
15. A process for assembling a multi-component building member, characterized in that the median, the upper and the lower elements of the tendons module are preassembled, attached between the initial and the final supporting elements, the tendons are inserted and then are pre-tensioned, wherein, starting with the second tendons module of the construction, the anchor of the pre-tensioned tendons is mounted on the final supporting element of the previous tendons module, and a tensioning arrangement is mounted on the final supporting element of the pre-tensioned tendons module.
16. Assembling process of claim 15, characterized in that the pre-tensioning is additionally carried out in the direction at the angle of 0<<180 to the longitudinal axis of the building member, the pre-tensioned tendons being placed into additional lateral supporting elements of the tendons module, located at the angle of 0<<180 to the longitudinal axis of the building member.
17. Assembling process of claim 15, characterized in that the pre-tensioning is additionally carried out at least in a plane perpendicular to the plane of longitudinal tensioning.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0019] The essence of the present set of inventions is illustrated by the drawings in which:
[0020]
[0021]
[0022]
[0023]
[0024]
[0025]
[0026]
EMBODIMENTS OF THE SET OF INVENTIONS
[0027] A multi-component building member comprises at least two components and pre-tensioned tendons. The strength of the construction is determined by structural features of each member, by the mass-size characteristics of the same and by the quality of assembling.
[0028] Each member is made as a tendons module. The construction of the tendons module used in a multi-component building member comprises elements assembled according to the principle of preferable tetrahedron structures into a single unit. The tendons module comprises an initial (1) and a final (2) supporting elements and a reinforcing cage (3) located between said supporting elements and comprising an upper (4) and a lower (5) elements in the form of a grid with a cellular structure, the cells having the shape of an equilateral polyhedron, and at least one median element (6) under the form of a space reinforcement structure comprising inclined reinforcement bars forming equilateral polyhedral pyramids oppositely oriented in space. Thus, the load on the nodal points is distributed upon the axial guides of all the tendons elements. The reinforcing cage can be made of metal or of composite materials on the basis of basalt or carbon, or of fiber glass, or of polymer materials, or of polymer materials with reinforcing additives. Besides, at least one of the elements of the reinforcing cage can be made monolithic, when necessary.
[0029] The tendons modules are tensioned following the procedure of placing pre-tensioned tendons (7) that are further tensioned. For this purpose, the initial (1) and the final (2) supporting elements are provided with holes (8) for the pre-tensioned tendons and with a stand (9) for placing anchors (10) and tensioning arrangements (11). The pre-tensioned tendons of the first component are anchored onto the initial and final supporting elements of the same, whereas the pre-tensioned tendons of each following component are anchored onto the final elements of the previous and the current components. Besides, the loads are redistributed in all the combined components thanks to a diagram of the pre-tensioned tendons and to the transfer of said stresses onto the nodal elements of the cages to be coupled. The pre-tensioned tendons can pass in the cage in one or several directions simultaneously. The location of the pre-tensioned tendons in the tendons module and the value of the previous tensioning are determined by the project working loads of a multi-component building member during the operation of the same. The pre-stressed tendons are tensioned preferably perpendicularly to bending loads, whereas the points of placing the pre-stressed tendons, the number of members to be tensioned and the value of the pre-tensioning are determined by calculation or experimentally. The pre-stressed tendons in a tendons module can be distributed irregularly and can shift from the module center to the sides of maximal tensile stresses. The possibility to place the pre-stressed tendons in several directions provides the operation of the construction in the cases when there exist not only bending loads but loads combined with torque.
[0030] The construction of the supporting elements enables prestressing of pre-tensioned tendons both for individual tendons modules and for a joint tensioning of two or more tendons modules with the use of single pre-tensioned tendons, the stresses being transferred to the cage nodal elements only.
[0031] Arch structures are distinguished by a particular complexity in building for being submitted to a complex system of bending and torsional loads in various directions. A possibility to provide calculated prestressing of such structures with a strengthening effect of the same at the points of maximal stretching stresses will enable one to solve a lot of engineering tasks in the building of light-weight roofs, arch bridges, pedestrian overpasses, etc. To build arch structures with the prestress effect using single pre-tensioned tendons, the components to be linked are provided, in the linking planes, with bevels enabling an arcuated profile to an arch assembled with a multitude of components.
[0032] As pre-tensioned tendons, use can be made of bars and ropes of metal, polymers (carbon, Dacron), carbon plastics.
[0033] The structure of the supporting and stretching elements enables to carry out a repeated, complete or partial assembling of the construction as well as the tensioning adjusting and control of the pre-stressed tendons in operation.
[0034] The tendons cages are assembled (assembly from the left to the right) as follows:
[0035] 1. Assembling the tendons cage that is fixed between the supporting elements.
[0036] 2. At least one bar or wire rope of the pre-tensioned tendons is passed through a respective hole of the initial supporting element of the first tendons module and attached by an anchor on the initial supporting element. Then the pre-tensioned tendons are passed via the first and the following tendons modules through the holes of the final supporting element of the first module and the hole of the initial supporting element of the following module, and they are tensioned with a respective device, such as a turnbuckle.
[0037] 3. Starting with the second tendons module in the structure, the anchor of the pre-tensioned tendons is installed onto the final supporting element of the previous tendons module and the stretching arrangement is installed onto the final supporting element of the tendons module being pre-tensioned, after that the tendons are tensioned with the help of a respective device, such as a turnbuckle.
[0038] 4. The operations are further repeated. In this case, the right and left supporting elements of each module are butted up one against the other via supporting surfaces and transmit the stretching force to the entire assembly.
[0039] Such a sequence of the assembling procedure provides for building multi-component constructions long of many kilometers, for example a roadway, that operate like a single pre-tensioned structure, which is impossible at a different process of assembling due to the limitations imposed by the strength of pre-tensioned tendons and by the length of the same as well as by the complicated procedure of passing the pre-tensioned tendons through an assembled structure of many kilometers long. Besides, such an assembly can be disassembled at one section, for example, for repairs and then reassembled, when necessary, which is impossible when a roadway long of many kilometers is tensioned with single pre-tensioned tendons.
[0040] In the case when the tendons module is filled with a filler but when it is necessary to keep a possibility to disassemble and to reassemble the modules, tubular channel forming means are inserted into the tendons module through which the pre-tensioned tendons are passed.
[0041] To improve the operation of a construction having a single horizontal row of pre-tensioned tendons with the height of the last, the pre-tensioned tendons are shifted relative to the center of the tendons module in the direction of maximal bending loads. In the case of use of several horizontal rows of pre-tensioned tendons in the height of the last, the pre-tensioned tendons of each horizontal row can be stretched with a different force, the stressing force being increased in the direction of maximal bending loads (i.e. in the direction of the maximal bending).
[0042] If during operation the construction is subjected not only to bending loads perpendicular to the tendons module plane, but torques are observed as well, the construction can be submitted to a pre-tensioning both across the tendons module and in a direction at the angle 0<<180 to the longitudinal axis of the building member (
[0043] When it is necessary to provide bends (for example, a roadway turn or an ascending grade of the same) while keeping the effect of tensioning with single pre-tensioned tendons, the pads of the supporting elements are provided, in respective points of a tendons module, with a bevel in the necessary direction.
[0044] The main features of the constructions built on the basis of the described tendons module can be as follows: [0045] a uniform load distribution on the entire surface of the construction independently of the point of the load applied to the upper part of the construction: whether the load is distributed upon the whole surface or it is distributed only on the surface of a single cell; [0046] vibratory loads are dampened inside the construction itself.
[0047] The combination of these features enables one to eliminate the vibration problem, to reduce the road maintenance and repair costs, to improve the strength characteristics of runways together with a reduced cost of the same, to reduce the weight of wall and ceiling panels thanks to the use of lighter fillers, to provide seismic stability of buildings, to use cantilever building construction on slopes. All this highly improves ecological safety of the building and maintenance of roads together with the economy efficiency of the same.
[0048] The above features enable to use multi-component building members based on a tendons module in the highway, airport, building and other structures engineering.