System and method for moving stuck objects in a well
11629569 · 2023-04-18
Assignee
Inventors
Cpc classification
E21B23/0416
FIXED CONSTRUCTIONS
E21B31/1135
FIXED CONSTRUCTIONS
E21B37/04
FIXED CONSTRUCTIONS
E21B23/042
FIXED CONSTRUCTIONS
E21B23/0411
FIXED CONSTRUCTIONS
E21B31/107
FIXED CONSTRUCTIONS
International classification
E21B23/04
FIXED CONSTRUCTIONS
E21B31/107
FIXED CONSTRUCTIONS
Abstract
A thru-tubing recover string (10) and method of moving a stuck object (14) in tubing in a well (16). A bottom hole assembly (22) is connected to a work string and includes a first (32) and a second tool (34), each tool configured to apply a force to the object in order to move the object (14), the first force being an impulse force, the second force being a static force, and the tools being operable independently so that an operator can apply either force in the event that application of one type of force on the object fails to move the object. Embodiments are described for the first tool (32) being a hammer tool or a jar and the second tool being a pulling tool such as a jack. The invention finds application in removing stuck objects such as plugs or actuating elements on tools such as sliding sleeves in production tubing.
Claims
1. A thru-tubing recovery string for moving an object in a well bore, comprising: a bottom hole assembly configured to connect to a work string, the bottom hole assembly including: a coupling tool configured to attach to the object to be moved; a first tool configured to apply a first force to the object in order to move the object; a second tool configured to apply a second force to the object in order to move the object; wherein: the first force is an impulse force and the second force is a static force; and the first tool and the second tool operate independently.
2. The thru-tubing recovery string according to claim 1 wherein the first tool is a hammer tool.
3. The thru-tubing recovery string according to claim 1 wherein the first tool is a jar.
4. The thru-tubing recovery string according to claim 1 wherein the second tool is a pulling tool.
5. The thru-tubing recovery string according to claim 1 wherein the coupling tool is a fishing tool being one selected from a group comprising: a spear, a grapple and an overshot.
6. The thru-tubing recovery string according to claim 1 wherein the bottom hole assembly includes a hydraulic disconnect.
7. The thru-tubing recovery string according to claim 1 wherein the bottom hole assembly includes an accelerator.
8. The thru-tubing recovery string according to claim 1 wherein the bottom hole assembly includes an anchor wherein the anchor is set to hold the bottom hole assembly in a fixed position while the second tool is operated.
9. The thru-tubing recovery string according to claim 1 wherein the bottom hole assembly includes a scraper.
10. The thru-tubing recovery string according to claim 1 wherein the first tool is a hammer, the second tool is a pulling tool, the bottom hole assembly further comprising a third tool, being a jar, providing a third force and wherein the third force is greater than the first force.
11. The thru-tubing recovery string according to claim 1 wherein the bottom hole assembly has a diameter of 3.5 inches (88.9 mm) or less on run-in.
12. The thru-tubing recovery string according to claim 1 further comprising the work string, the work string being a tubular conduit selected from the group consisting of coiled tubing and jointed pipe.
13. A method of moving an object in a well bore, comprising the steps: (a) providing a thru-tubing recovery string comprising: a bottom hole assembly configured to connect to a work string, the bottom hole assembly including: a coupling tool configured to attach to the object to be moved; a first tool configured to apply a first force to the object in order to move the object; a second tool configured to apply a second force to the object in order to move the object; wherein: the first force is an impulse force and the second force is a static force; and the first tool and the second tool operate independently; (b) connecting the bottom hole assembly of the thru-tubing recovery string to the work string; (c) running the thru-tubing recovery string through tubing in the well bore; (d) attaching the coupling tool to the object; (e) operating the first tool to apply the first force to the object; and, (f) operating the second tool to apply the second force to the object.
14. The method of moving an object in a tubular string according to claim 13 wherein the steps (e) and (f) are performed in reverse order.
15. The method of moving an object in a tubing string according to claim 13 wherein the first tool is operated hydraulically by application of fluid pressure through the work string.
16. The method of moving an object in a tubing string according to claim 13 wherein the second tool is operated hydraulically by application of fluid pressure through the work string.
17. The method of moving an object in a tubing string according to claim 13 wherein an anchor on the bottom hole assembly is set in the tubing for operation of the second tool.
18. The method of moving an object in a tubing string according to claim 13 wherein the method includes the step of cleaning an inner surface of the tubing.
19. The method of moving an object in a tubing string according to claim 13 wherein the method includes a further step between steps (e) and (f) wherein the further step comprises operating a third tool to apply a third force to the object wherein the third force is greater than the first force and the first tool is a hammer tool, the second tool is a pulling tool and the) third tool is a jar.
20. The method of moving an object in a tubing string according to claim 13 wherein the method includes a further step between steps (e) and (f) wherein the further step comprises operating a third tool to apply a third force to the object wherein the third force is less than the first force and the first tool is a jar, the second tool is a pulling tool and the third tool is a hammer tool.
Description
(1) Embodiments of the present invention will now be described, by way of example only, with reference to the accompanying drawings of which:
(2)
(3)
(4)
(5)
(6)
(7) Referring initially to
(8) The tubing 16 is preferably small bore tubing, say 4.5 inches (114.3 mm) in diameter typical of production tubing run inside liner 18 or casing in a well 20. The work string 12 is a tubular conduit as is known in the art and is preferably coiled tubing but may be jointed pipe having an outer diameter sized to pass through the tubing 16.
(9) The thru-tubing recovery string 10 includes a bottom hole assembly 22 which is coupled to a first end 24 of coiled tubing 12 run from the surface of the well 20 as is known in the art. The use of coiled tubing 12 allows deployment from a floating vessel as is known in the art and removes the requirement for a rig to be brought to the well 20. Such an arrangement is found in completions and intervention work allowing operations on the well 20 to be performed without removing the production tubing.
(10) The bottom hole assembly 22 includes, in order from a first end 26: a coupling tool 28 configured to attach to the object 14 to be moved; a disconnect 30; a first tool 32 configured to apply a first force to the object 14 in order to move the object 14; a second tool 34 configured to apply a second force to the object 14 in order to move the object 14; a scraper 36; an anchor 38; an accelerator 40 and a further disconnect 42. Parts may be formed integrally on a single tool body or may be constructed separately and joined together by box and pin sections as is known in the art. The order may be varied as long as it does not affect the overall operation of the bottom hole assembly 22 and some parts are optional, such as the scraper 36 and the number of disconnects 30,42. All parts are operated mechanically or hydraulically so that no electrical connections are required. Operation is by varying flow rate of fluid pumped through the bore 44 of the coiled tubing 12 which bore extends through the parts of the bottom hole assembly 22, and by tension and release of the coiled tubing 12 string at surface.
(11) The coupling tool 28 may be any fishing tool as is known in the industry. Spears, grapples and/or overshots can be used and choice may be dependent upon the type and position of the object 14 which needs to be moved. The object 14 may be thru-tubing string parts, well tools and other apparatus which have become stuck within the well bore. Alternatively, the object 14 may be a component part which needs to be released to move such as plugs and sliding sleeves which have previously been set in the tubing 16. It will be appreciated that this is a non-exhaustive list of possible objects 14.
(12) The first tool 32 is a hammer tool or a jar as are known in the art. The hammer tool operates by application of a small load typically by tensioning from a pull at surface and then flow through the bore 44 activates a shuttle valve which cyclically raises and releases an anvil or hammer to create an impact on a surface. The force of this impact is transmitted to through the assembly 22 to the object 14. The force of each strike is relatively small, but it is repeated continuously as the shuttle valve is moved up and down. The force is considered as an impulse force as each strike is instantaneous, sudden and of short duration. An example of a hammer tool is disclosed in U.S. Pat. No. 7,073,610, incorporated herein by reference.
(13) Jars are known which, typically by application of tension on the string 10, can store energy up on a compression spring which is released to cause a sudden impact of an anvil. The impulse force applied on impact being greater than the force of a single impact of a hammer tool, but the jar needs to be ‘re-cocked’ to impart a second blow. An example of a jar is as described in U.S. Pat. No. 4,333,542 and incorporated herein by reference.
(14) In conjunction with a jar or hammer tool, an accelerator 40 may be included. Accelerators 40 are known to provide an enhancement to the action of the jar and thus increase the force applied. The accelerator 40 is typically mechanically operated and located above the jar in the bottom hole assembly 22.
(15) The second tool 34 is a pulling tool. These may be referred to as jacks. A suitable design of a pulling tool 46 is shown in
(16) Pulling tool 46 comprises an outer housing 48 with an upper connection to another part in the bottom hole assembly 22. A mandrel 50 is located in the bore 52 of the housing 48 with a series of pistons 54 mounted on the mandrel 50 extending over an annular bore 56 between the mandrel 50 and the housing 48. While only three pistons 54a-c are shown there may by any number to cause sufficient force increase based on the combined surface area of the faces 58 of each piston. The outer housing 48 includes stops 60 arranged in the annular bore 56 between the pistons 54. The mandrel 50 extends from the lower end 62 of the housing 48 and includes a coupling piece 64 to attach the mandrel 50 to a lower part of the bottom hole assembly 22. Ports 66 through the mandrel 50 allow fluid under pressure to be entered between the piston faces 58 and stops 60 to thereby move the pistons 54 and with them the mandrel 50 upwards in the bore 52. This pulls those parts of the bottom hole assembly 22 connected to the coupling piece 64 upwards towards the outer housing 48. The pulling tool 46 also includes a locking mechanism 68 to prevent movement of the mandrel 50 relative to the housing 48 until the tool is required to be used, the locking mechanism being resettable in the well 20. Further, the pulling tool 46 includes a signalling mechanism 70 to provide an indication when the tool 46 has stroked and pulled the coupling piece 64 as close to the housing 48 as possible and the tool 46 is fully contracted. As described above the multiple piston surface areas on faces 58 provide a multiplication of the force available for pulling the object 14. A static force is applied through the mandrel 50 to pull the object 14 with the pulling tool 46. This force is much greater than that available from a hammer tool and is of longer duration than that of a jar as used in the first tool 32.
(17) It will be appreciated that to operate the pulling tool 46, the outer housing 48 must be anchored to the tubing 16. As the outer housing 48 is connected to the work string 10 and the parts of the bottom hole assembly 22 above the pulling tool 46, an anchor can be located on the bottom hole assembly 22 at any suitable position above the pulling tool 46 and work independently of the pulling tool 46.
(18) A suitable anchor 38 is illustrated in
(19) Disconnects 30,42 are mounted in the bottom hole assembly 22 as are known in the art. These are hydraulic disconnects which allow the bottom hole assembly 22 or parts thereof to be parted from the coiled tubing to enable retrieval of the thru-tubing recovery string 10 in the event that the object 14 cannot be moved or that a tool in the bottom hole assembly 22 fails. The hydraulic disconnects 30,42 can operate by application of a predefined pressure through the bore 44 to activate a release mechanism or via a drop ball used to block circulation through the bore 44 and enable the application of the release pressure.
(20) The bottom hole assembly 22 may optionally include a cleaning tool. The cleaning tool is used to clean an inner wall of the tubing 16 so that the anchor 38 will set correctly. In the embodiment shown in
(21) The blades have a sloped surface 99, so that if they are extended and the thru-tubing recovery string 10 is pulled, it will not stick as a result of the blades 94 meeting nipples, joints or other protrusions on the surface of the inner wall of the tubing 16.
(22) In use, the bottom hole assembly 22 is constructed by connecting the coupling tool 28 to a disconnect 30 which in turn is connected to the first tool 32. The first tool 32 is connected to the second tool 34 which in turn is connected to the scraper 36. The anchor 38 is connected to the scraper 36 and to the accelerator 40 before a final disconnect 42 is connected. The bottom hole assembly 22 is connected to a work string, which in this embodiment is a coiled tubing string, when the final disconnect is connected to the first end 26 of the coiled tubing 12.
(23) In this run-in configuration the slips 74 on the anchor 38 and the scraper blades are both retracted. The mandrel 50 on the pulling tool 46 is fully extended from the lower end 62 of the outer housing 48. The thru-tubing recovery string 10 is then run in the well 20 through the tubing 16 and tagged. Cleaning by scraping may then be performed with the scraper 36 actuated and the bottom hole assembly 22 moved inside the tubing 16 so as to remove debris on the walls of the tubing 16. Fluid is also circulated through the bore 44, out of the first end 26 and up the annulus between the string 10 and tubing 16 to assist in removing the debris and further cleaning the tubing 16. The coupling tool 28 is then attached to the object 14 and the string 10 is fixed at that point in the well 20. Pulling on the string 10 at surface will determine if the object 14 is stuck. Such pulling also allows tension to be placed on the string 10 for the operation of the tools 32,34,38.
(24) If the object 14 is stuck, the first tool 32 is actuated. If the first tool 32 is a hammer tool, an overpull on the string 10 and the circulation of fluid through the bore 44, will set up the cyclic hammering which applies a first force repeatedly to the object 14. This vibratory motion may be sufficient to dislodge material around the object 14 which is preventing its movement. If the object 14 is freed, tension is released on the string 10 and the object 14 can be moved by pulling on the string 10 from surface. The pull may move the object 14 to actuate a tool if the object 14 is an actuating member such as a sliding sleeve. Alternatively, the object 14 may be pulled from the well 20 if the object is a plug or stuck piece of apparatus. If a release of tension is not detected, the first tool 32 is stopped, a pull can be tried again to see if the object 14 has released.
(25) Where the first tool 32 is a jar, an overpull can be used to set the jar and the accelerator 40, if present. A sudden release of energy is created to apply a force on the object 14. This force may be an impact force or a pulling force. While the jar can be reset and further jarring actions performed, this is not necessary as, if the object 14 fails to be released, the second tool 34 can be used. In this way, the portion of the coiled tubing 12 which is located over the goose neck at surface is not repeatedly tensioned as is required for repeated jarring, which could cause fatigue and breakage of the coiled tubing 12.
(26) If the object 14 remains fixed in position, the second tool 34 can be actuated. In a preferred embodiment the second tool is a pulling tool 46. If the first tool 32, being a hammer tool or a jar, does not release the object 14 for movement, then the anchor 38 is set as described with reference to
(27) It will be appreciated that the first tool 32 and the second tool 34 can be operated in any order. It may be advantageous to first apply the static force when an object is considered to be large or heavy. The static force will move the object vertically thereby moving it along the tubing. By then applying an impulse force the object can be separated from the tubing so that its passage to the surface is easier.
(28) The disconnects 30,42 are available for use if any part of the bottom hole assembly 22 itself becomes stuck in the tubing 16. Use of the disconnects 30,42 are as known in the art. The lower disconnect 30 may also be used if the object 14 is a stuck object which cannot be moved with the thru-tubing recovery string 10 and therefore needs to be milled out. Alternatively, the lower disconnect 30 may be released once the object 14 has been moved, when the object 14 is an actuating element of a tool. In this way, the coupling tool 28 does not require to have a release mechanism.
(29) In a further embodiment, a third force is applied via a third tool 33.
(30) The selection of the hammer tool or the jar as the first tool 132 with the other being the third tool 33 can be based on the operational requirements of the both these tools and which would operate best above the other in the string. Each tool 132,134,33 operates independently and thus can be operated in any order as selected by the operator at surface.
(31) It will be appreciated that while only tools are shown connected to each other on the bottom hole assemblies 22,122, tubular sections may be present between the tools to space them out and/or further tools may be incorporated.
(32) The principle advantage of the present invention is that it provides apparatus and method for freeing a stuck object in a well using a thru-tubing recovery string which can apply both an impulse first force and a static second force on the object in order to move the object.
(33) A further advantage of the present invention is that it provides a thru-tubing recovery string which can be used in small diameter production tubing to recover objects and operate tools within the tubing.
(34) A still further advantage of at least one embodiment of the present invention is that it provides a thru-tubing recovery string in which a jar, a hammer tool and a pulling tool can be operated independently, ‘on-demand’ and repeatedly without requiring electrical connections.
(35) The foregoing description of the invention has been presented for the purposes of illustration and description and is not intended to be exhaustive or to limit the invention to the precise form disclosed. The described embodiments were chosen and described in order to best explain the principles of the invention and its practical application to thereby enable others skilled in the art to best utilise the invention in various embodiments and with various modifications as are suited to the particular use contemplated. Therefore, further modifications or improvements may be incorporated without departing from the scope of the invention herein intended with the invention being defined within the scope of the claims.