COAL BUMP CONTROL METHOD FOR SECTIONAL HYDRAULIC FRACTURING REGIONS OF NEAR VERTICAL ULTRA THICK COAL SEAM
20230160305 · 2023-05-25
Assignee
- UNIVERSITY OF SCIENCE AND TECHNOLOGY BEIJING (Beijing, CN)
- North China Institute of Science and Technology (Langfang City, CN)
- Beijing Anke Xingye Science and Technology Co., Ltd. (Beijing, CN)
Inventors
- Sitao ZHU (Beijing, CN)
- Gaoang WANG (Beijing, CN)
- Fuxing JIANG (Beijing, CN)
- Gang Yao (Beijing, CN)
- Tao Zhou (Beijing, CN)
- Jinhai LIU (Beijing, CN)
- Huan LI (Beijing, CN)
- Zhen KONG (Beijing, CN)
- Qingbo HE (Beijing, CN)
- Xiaocheng QU (Beijing, CN)
- Quande WEI (Beijing, CN)
- Yitong HUANG (Beijing, CN)
- Shaohua SUN (Beijing, CN)
Cpc classification
E21C37/12
FIXED CONSTRUCTIONS
International classification
Abstract
The present disclosure provides a coal bump control method for sectional hydraulic fracturing regions of a near vertical ultra thick coal seam. The method includes: deepening a main shaft from a mining level to a fracturing level; excavating a cross-hole from a roof rock layer of a coal seam at the fracturing level to enter a coal seam being mined, and excavating a roadway along the strike of the coal seam; and drilling hydraulic fracturing boreholes in a dedicated fracturing roadway along an inclination angle of the coal seam to the coal seam above the roadway, wherein the length of the borehole makes the borehole in communication with a goaf, and the spacing of the boreholes along the strike and the sectional spacing of the boreholes in an inclination direction are designed according to the parameters of fracturing equipments and the fracturing length.
Claims
1. Coal bump control method for sectional hydraulic fracturing regions of a near vertical ultra thick coal seam, comprising the following steps: S1: deepening a main shaft from a mining level to a fracturing level; S2: excavating a cross-hole from a roof rock layer of a coal seam at the fracturing level to enter a coal seam being mined, and excavating a roadway along a strike of the coal seam at the fracturing level to serve as a dedicated roadway for hydraulic fracturing construction, that is, a fracturing roadway; S3: constructing inclined fracturing boreholes from the fracturing roadway to an upper coal seam, wherein the boreholes are ended at a center of a thickness of the upper coal seam, and an angle α and a length L of each fracturing borehole are obtained from the thickness d of the coal seam and an vertical distance H according to following formulas,
n=L/R
l=H/n in the formulas: l is the sectional height of each fracturing borehole, R is a single maximum fracture radius of the fracturing equipments, n is number of fracturing sections, L is the length of each fracturing borehole, and H is the vertical distance between the mining level of the coal seam and the goaf above the coal seam; S4: arranging the fracturing boreholes in a row spacing from a cutting hole of a stoping face to a stop line in sequence along the strike of the coal seam, wherein the row spacing of the fracturing boreholes is designed according to parameters of the fracturing equipments; S5: operating the fracturing equipments to perform inclined sectional hydraulic fracturing on a coal body with high elastic energy in one of the fracturing boreholes; S6: moving the fracturing equipments along the strike of the coal seam after a fracturing operation of a first fracturing section is completed, performing the fracturing operation of a next fracturing section according to the designed row spacing of the fracturing boreholes in the same manner as for the first fracturing section until all of the fracturing boreholes have been performed with the fracturing operation, to complete fracturing operations of the coal body with high elastic energy on the mining face; and S7: after the fracturing operations are completed, remaining the fracturing roadway as a stoping roadway of the fracturing level.
2. The coal bump control method for sectional hydraulic fracturing regions of a near vertical ultra thick coal seam according to claim 1, wherein in S1, deepening the main shaft to a level which has a vertical depth of 100 m away from the mining level, and weakening a high-stress coal seam of the overall level in advance.
3. The coal bump control method for sectional hydraulic fracturing regions of a near vertical ultra thick coal seam according to claim 1, wherein in S3, constructing the fracturing boreholes in the fracturing roadway to perform the hydraulic fracturing before stoping on a working face of a current mining stage.
4. The coal bump control method for sectional hydraulic fracturing regions of a near vertical ultra thick coal seam according to claim 1, wherein in S3, the length of each fracturing borehole makes the each fracturing borehole in communication with the goaf, a fracturing range is the overall thickness of the coal seam, and the sectional height of each fracturing borehole is 20 m under limitation of the fracturing equipments.
5. The coal bump control method for sectional hydraulic fracturing regions of a near vertical ultra thick coal seam according to claim 1, wherein in S4, the row spacing of the boreholes is arranged along the strike, and the row spacing of the boreholes is two times bigger than a fracturing radius.
6. The coal bump control method for sectional hydraulic fracturing regions of a near vertical ultra thick coal seam according to claim 1, wherein in S5, during hydraulic fracturing, when a pressure of a water injection pump rises to a fracturing pressure of the coal body, maintaining a discharge pressure of the water injection pump to expand fractures; and when the discharge pressure of the water injection pump suddenly rises from a continuously stable value to another value at which the discharge pressure does not change any longer, ending a fracturing operation of the first fracturing section.
7. The coal bump control method for sectional hydraulic fracturing regions of a near vertical ultra thick coal seam according to claim 1, wherein in S6, the fracturing operation occurs earlier than the stoping operation occurs on the working face, and the fracturing operation is at least 200 m ahead of the stoping face.
8. The coal bump control method for sectional hydraulic fracturing regions of a near vertical ultra thick coal seam according to claim 1, wherein in S7, after the fracturing operation is completed, closing the fracturing roadway after support for the fracturing roadway is strengthened such that the fracturing roadway is configured as a stoping roadway to be operated when the coal seam at the fracturing level is mined in stages, so as to reduce construction cost.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0027]
[0028]
[0029]
[0030]
[0031] Reference signs in the drawings: 1—main shaft; 2—fracturing roadway connecting cross-hole; 3—fracturing roadway; 4—-fracturing borehole; 5—stoping roadway connecting cross-hole; 6—stoping roadway of coal seam being mined; 7—stoping roadway of coal seam to be mined; 8—coal seam being mined; 9—coal seam to be mined; 10—goaf of coal seam being mined; 11—goaf of coal seam to be mined; 12—roof rock layer; 13—rock pillar between coal seams; 14—floor rock layer; 15—hole packer; 16—water tank; 17—pump; 18—shut-off valve; 19—tee joint; 20—pressure gauge; 21—pressure sensor; 22—diameter variable joint; 23—straight joint; 24—water injection fracturing pipe; and 25—hole packer pressurizing pipe.
DETAILED DESCRIPTION OF THE EMBODIMENTS
[0032] To make the technical problems to be solved, technical solutions, and advantages of the present disclosure clearer, detailed description is made below in combination with the accompanying drawings and embodiments.
[0033] The present disclosure provides a coal bump control method for sectional hydraulic fracturing regions of a near vertical ultra thick coal seam.
[0034] The method includes the following steps:
[0035] S1: deepening a main shaft from a mining level to a fracturing level;
[0036] S2: excavating a cross-hole from a roof rock layer of a coal seam at the fracturing level to enter a coal seam being mined, and excavating a roadway along the strike of the coal seam at the fracturing level to serve as a dedicated roadway for hydraulic fracturing construction, that is, a fracturing roadway;
[0037] S3: constructing inclined fracturing boreholes from the fracturing roadway to the upper coal seam, wherein the boreholes are ended at the center of the thickness of the upper coal seam, and the angle α and the length L of each fracturing borehole are obtained from the thickness d of the coal seam and the vertical distance H according to following formulas.
[0038] in the formulas: α is the angle of each fracturing borehole, H is the vertical distance between the mining level of the coal seam and a goaf above the coal seam, and d is the thickness of the coal seam:
[0039] a sectional height l of each fracturing borehole is obtained by the power of fracturing equipments and the length L of each fracturing borehole according to following formulas.
n=L/R
l=H/n
[0040] in the formulas: l is the sectional height of each fracturing borehole, R is a single maximum fracture radius of the fracturing equipments, n is the number of fracturing sections, L is the length of each fracturing borehole, and H is the vertical distance between the mining level of the coal seam and the goaf above the coal seam.
[0041] S4: arranging the fracturing boreholes in row spacing from cutting hole of stoping face to stop line in sequence along the strike of the coal seam, wherein the row spacing of the fracturing boreholes is designed according to the parameters of the fracturing equipments.
[0042] S5: operating the fracturing equipments to perform inclined sectional hydraulic fracturing on a coal body with high elastic energy in one of the fracturing boreholes.
[0043] S6: moving the fracturing equipments along the strike of the coal seam after a fracturing operation of a first fracturing section is completed, performing the fracturing operation of a next fracturing section according to the designed row spacing of the fracturing boreholes in the same manner as for the first fracturing section until all of the fracturing boreholes have been performed with the fracturing operation, to complete the fracturing operations of the coal body with high elastic energy on the mining face.
[0044] S7: after the fracturing operations are completed, remaining the fracturing construction roadway as a stoping roadway of the fracturing level according to a principle that one roadway has a plurality of purposes.
[0045] The present disclosure will be described below in combination with a specific implementation mode.
[0046] As shown in
[0047] S1: deepening a main shaft 1 to a level which has the vertical depth of 100 m away from a stoping face, excavating a fracturing roadway connecting cross-hole 2 in the main shaft 1 from a roof rock layer 12 of a coal seam at a fracturing level to enter a mining coal seam, and simultaneously, excavating a stoping roadway connecting cross-hole 5 to a stoping roadway 6 of coal seam being mined.
[0048] S2: excavating a roadway along the strike of the coal seam at the fracturing level to serve as a dedicated roadway for hydraulic fracturing construction, that is, a fracturing roadway 3.
[0049] S3: constructing inclined fracturing boreholes 4 from the roof of the fracturing roadway to the upper part of a mining level, constructing obliquely upward fracturing boreholes in the fracturing roadway to the upper coal seam along the strike vertical to the working face, wherein the length of each fracturing borehole makes the each fracturing borehole in communication with a goaf 10 of coal seam being mined, and the fracturing range is the overall thickness of the coal seam being mined 8.
[0050] S4: arranging the fracturing boreholes 4 in a row spacing from cutting hole of stoping face to stop line along the strike of the coal seam in the fracturing roadway 3, and the row spacing of the fracturing boreholes 4 is two times bigger than the fracturing radius.
[0051] S5: performing sectional hydraulic fracturing on the coal seam being mined 8 through the fracturing boreholes 4, turning on a pump 17 to inject high-pressure water within a water tank 16 into an inner cavity of a hole packer through a hole packer pressurizing pipe 25, and closing a way of a shut-off valve 18 to the hole packer pressurizing pipe 25 after the hole packer 15 is expanded and the pressure of the inner cavity thereof reaches a working pressure, so as to complete a hole packing operation. (As shown in
[0052] S6: moving the fracturing equipments along the strike of the coal seam after the fracturing operation of the first fracturing section is completed. Performing the fracturing operation of a next section according to designed row spacing of the fracturing boreholes as for the first fracturing section until all of the fracturing boreholes have been performed with the fracturing operation, wherein the above operations are cycled, to complete the fracturing operations of the coal body with high elastic energy on the mining face.
[0053] S7: remaining the fracturing construction roadway 3 as a stoping roadway 3 of the fracturing level.
[0054] As shown in
[0055] The foregoing descriptions are preferred implementation modes of the present disclosure. It should be noted that those of ordinary skill in the art may make a number of improvements and refinements without departing from the principle of the present disclosure. These improvements and refinements should also be regarded as the scope of protection of the present disclosure.