Method of Manufacturing a Precast Concrete Utility Vault
20250262797 ยท 2025-08-21
Inventors
Cpc classification
E02D2250/0023
FIXED CONSTRUCTIONS
B28B1/14
PERFORMING OPERATIONS; TRANSPORTING
International classification
Abstract
A method for manufacturing a precast concrete utility vault is disclosed, focusing on fabricating a single-piece, rectangular lower riser section using an upside-down monolithic pour of reinforced concrete. The method employs a formwork system configured to form a lower riser section with four walls, a slab section, and a sump channel, ensuring precise dimensions and high structural integrity. The upside-down pouring technique facilitates uniform concrete distribution and efficient curing, producing a robust vault component suitable for housing large electrical transformers. The method enhances manufacturing efficiency and product reliability through a streamlined, single-pour process.
Claims
1. A method of fabricating a single-piece, precast concrete rectangular lower riser section for a utility vault, said rectangular lower riser section comprising four lower riser walls joined by a slab section, said slab section having an upper surface and a sump channel along one of said lower riser walls, said method comprising: a) providing a formwork system comprising a structural mold and forms configured to form: i) said rectangular lower riser section with four lower riser walls having: A) a thickness of between about 8 inches and 12 inches, B) a length of between about 10 feet and 14 feet, C) a width of between about 10 feet and 12 feet, D) a height of between about 5 feet and 7 feet, E) an upper section, and F) a top surface; ii) a slab section joining said four lower riser walls and having an upper surface and a sump channel along one of said lower riser walls; b) orienting said formwork system in an upside-down configuration; c) performing a monolithic pour of reinforced concrete mix into said formwork system; and, d) curing said reinforced concrete mix in said formwork system.
2. The method of claim 1, further wherein said formwork system has dimensional tolerances of: a) plus or minus 0.25 inches for any lower riser section dimension of five feet or less, b) plus or minus 0.375 inches for any lower riser section dimension greater than five feet and less than ten feet, and c) plus or minus 0.50 inches for any lower riser section dimension of ten feet or greater.
3. The method of claim 2 wherein said structural mold is formed using reinforcing bars of billet steel that are wire-tied at all contact points with plastic-coated tie wire and epoxy coated.
4. The method of claim 1, further wherein said formwork system is configured to form said upper section of said lower riser walls with an outer portion and an inner portion, said inner portion extending between about 4 inches and about 8 inches beyond said outer portion and having a thickness of between about 4.5 inches and 5.5 inches.
5. The method of claim 4 wherein said wherein said formwork system is configured to form said sump channel with a depth of between about 1.5 feet and about 2.5 feet below said upper surface and a width of between about 2 feet and about 3 feet.
6. The method of claim 1 where said formwork system is configured to provide each of said upper sections of said lower riser walls with an inner portion, a middle portion, and an outer portion, said middle portion being recessed between about 3.5 inches and about 4.5 inches below each of said inner portion and said outer portion and having a width of between about 3 inches and about 4 inches.
7. The method of claim 6 where said formwork system is configured to provide said middle portion with a plurality of cylindrical apertures positioned centrally therein and having a diameter of between about 0.75 inches and about 1.5 inches, each of said cylindrical apertures having an upper end terminating at an opening in said middle portion and extending vertically downward through said lower riser wall.
8. The method of claim 1, wherein said reinforced concrete mix is 5,000 psi concrete.
9. The method of claim 8, wherein said reinforced concrete mix is prepared using at least 650 pounds of cement per cubic yard.
10. A method of fabricating a single-piece, precast concrete rectangular lower riser section for a utility vault, said rectangular lower riser section comprising four lower riser walls joined by a slab section, said slab section having an upper surface and a sump channel along one of said lower riser walls, said method comprising: a) providing a formwork system comprising a structural mold and forms configured to form: i) said rectangular lower riser section with four lower riser walls having: A) a thickness of between about 8 inches and 12 inches, B) a length of between about 10 feet and 14 feet, C) a width of between about 10 feet and 12 feet, D) a height of between about 5 feet and 7 feet, E) an upper section, and F) a top surface; wherein said top surface of said bottom riser walls comprises a plurality of receiving portions aligned and configured to correspond to a plurality of projecting portions in an upper riser section so that, when the upper riser section is aligned with and placed on said lower riser section, each of said plurality of receiving portions and the plurality of projecting portions engages with each other to secure said lower riser section and the upper riser section to each other; b) orienting said formwork system in an upside-down configuration; c) performing a monolithic pour of reinforced concrete mix into said formwork system; and, d) curing said reinforced concrete mix in said formwork system.
11. The method of claim 10, further wherein said formwork system has dimensional tolerances of: a) plus or minus 0.25 inches for any lower riser section dimension of five feet or less, b) plus or minus 0.375 inches for any lower riser section dimension greater than five feet and less than ten feet, and c) plus or minus 0.50 inches for any lower riser section dimension of ten feet or greater.
12. The method of claim 11 wherein said structural mold is formed using reinforcing bars of billet steel that are wire-tied at all contact points with plastic-coated tie wire and epoxy coated.
13. The method of claim 10, further wherein said formwork system is configured to form said upper section of said lower riser walls with an outer portion and an inner portion, said inner portion extending between about 4 inches and about 8 inches beyond said outer portion and having a thickness of between about 4.5 inches and 5.5 inches.
14. The method of claim 13 wherein said formwork system is configured to form said sump channel with a depth of between about 1.5 feet and about 2.5 feet below said upper surface and a width of between about 2 feet and about 3 feet.
15. The method of claim 10 where said formwork system is configured to provide each of said upper sections of said lower riser walls with an inner portion, a middle portion, and an outer portion, said middle portion being recessed between about 3.5 inches and about 4.5 inches below each of said inner portion and said outer portion and having a width of between about 3 inches and about 4 inches.
16. The method of claim 15 where said formwork system is configured to provide said middle portion with a plurality of cylindrical apertures positioned centrally therein and having a diameter of between about 0.75 inches and about 1.5 inches, each of said cylindrical apertures having an upper end terminating at an opening in said middle portion and extending vertically downward through said lower riser wall.
17. The method of claim 10, wherein said reinforced concrete mix is 5,000 psi concrete.
18. The method of claim 17, wherein said reinforced concrete mix is prepared using at least 650 pounds of cement per cubic yard.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0016]
[0017]
[0018]
[0019]
[0020]
[0021]
[0022]
DETAILED DESCRIPTION
[0023] The following description, in conjunction with the accompanying drawings, details a method for manufacturing a precast concrete utility vault, focusing on the fabrication of the rectangular lower riser section using an upside-down monolithic pour. This method is designed to produce a robust, single-piece component suitable for housing large electrical transformers, such as 2500 kVA, 277/480V units.
Overview of the Vault
[0024] A utility vault typically comprises a base (slab section), vertical walls forming a rectilinear shape, and a roof, creating an enclosure for utility components. The present method targets the lower riser section, which includes four walls and a slab with a sump channel, formed as a single piece in a controlled environment (e.g., a concrete plant) and later assembled with an upper riser section at the installation site.
[0025]
[0026]
[0027]
[0028]
[0029]
[0030]
[0031] Also shown in
[0032]
[0033]
[0034]
[0035] The formwork system is also configured to form a sump channel with a specific depth and width, which facilitates the drainage of water and prevents water accumulation in the vault. Additionally, the formwork system is configured to provide each upper section of the lower riser walls with an inner portion, a middle portion, and an outer portion, with the middle portion being recessed and having a width that allows for the inclusion of a plurality of cylindrical apertures. These apertures are designed to contain coil rods, which facilitate the joining of riser sections. The formwork system has dimensional tolerances to ensure that the lower riser section is formed with precision, contributing to the overall structural integrity of the utility vault.
[0036] In step 41, the process involves performing a monolithic pour of reinforced concrete mix into the formwork system. This step ensures the integrity and strength of the lower riser section of the utility vault. The reinforced concrete mix, specified as 5,000 psi concrete, is prepared using at least 650 pounds of cement per cubic yard. This preparation ensures that the concrete achieves the desired strength and durability necessary for the structural demands of the utility vault. The monolithic pour involves a continuous and uninterrupted pouring process, which helps in minimizing the formation of joints or weak points within the concrete structure. This method creates a single-piece, precast concrete rectangular lower riser section that is robust and capable of withstanding the environmental and load conditions it may encounter. The reinforced concrete mix is poured into the formwork system, which is configured to form the lower riser section with precise dimensions and features, such as the sump channel and cylindrical apertures. The formwork system is oriented in an upside-down configuration to facilitate the pouring process and ensure that the concrete fills all areas of the mold uniformly. This step is followed by the curing process, which is critical in achieving the final strength and stability of the concrete structure. The curing process involves maintaining the concrete at a suitable temperature and humidity level to allow the cement to hydrate properly, thereby enhancing the overall durability and longevity of the utility vault.
[0037] In step 42, the curing of the reinforced concrete mix within the formwork system is undertaken. This process involves allowing the concrete to set and gain strength over time, ensuring the structural integrity of the lower riser section. The curing process achieves the desired properties of the concrete, such as its compressive strength and durability. The formwork system, which has been previously oriented in an upside-down configuration, provides the necessary support and shape for the concrete as it cures. The reinforced concrete mix, which has been poured monolithically into the formwork system, consists of a specific composition, including 5,000 psi concrete prepared with at least 650 pounds of cement per cubic yard. This composition contributes to the overall strength and stability of the lower riser section once the curing process is complete. The curing process is conducted in a controlled environment to minimize the presence of air pockets, excess moisture, and other contaminants that could compromise the quality of the concrete. The curing time and conditions, such as temperature and humidity, are carefully managed to ensure optimal results. The cured lower riser section is then ready for further processing or assembly as part of the utility vault system.
[0038] For each of the construction joints described herein, a bonding or similar compound, such as uniweld bonding compound, may be applied to the facing surfaces of the upper riser section and/or of the lower riser section prior to placing the upper riser section on the lower riser section.
1. Providing a Formwork System
[0039] The process begins with a formwork system comprising a structural mold and forms tailored to create the lower riser section with: [0040] Four Lower Riser Walls: Thickness between about 8 and 12 inches, length between about 10 and 14 feet, width between about 10 and 12 feet, and height between about 5 and 7 feet. [0041] Slab Section: Joins the four walls, featuring an upper surface and a sump channel along one wall (depth between about 1.5 and 2.5 feet, width between about 2 and 3 feet). [0042] Upper Section of Walls: Configured for engagement with an upper riser section, potentially including inner and outer portions (inner portion extending 4-8 inches beyond outer, thickness 4.5-5.5 inches) or receiving portions (e.g., slots or recessed middle portions).
[0043] The formwork ensures dimensional precision with tolerances of: [0044] 0.25 inches for dimensions 5 feet. [0045] 0.375 inches for dimensions >5 feet and <10 feet. [0046] 0.50 inches for dimensions 10 feet.
[0047] Reinforcing bars (e.g., billet steel rebar, 0.5-inch diameter), wire-tied with plastic-coated tie wire and epoxy-coated, may be embedded within the mold for added strength.
2. Orienting the Formwork System
[0048] The formwork is oriented upside-down. In this configuration, the slab section forms the top of the mold, and the open top of the lower riser section (which will face upward in the final vault) is at the bottom during pouring. This orientation allows concrete to flow downward from the slab into the wall forms, ensuring uniform distribution and minimizing voids.
3. Performing a Monolithic Pour
[0049] A reinforced concrete mix-preferably 5,000 psi concrete with at least 650 pounds of cement per cubic yard-is poured into the upside-down formwork in a single, continuous operation. The pour begins at the slab section, filling the mold downward through the wall forms. This monolithic approach eliminates seams, enhancing structural integrity, and leverages gravity to settle the concrete evenly across all features, including the sump channel and wall configurations.
4. Curing the Concrete
[0050] After pouring, the concrete cures within the formwork under controlled conditions (e.g., regulated temperature and humidity) to minimize defects like air pockets or shrinkage cracks. The result is a single-piece lower riser section with a weight of about 50,000 to 65,000 pounds, ready for transport and assembly.
Additional Features and Configurations
[0051] The method may incorporate: [0052] Sump Channel: Formed with precise depth (1.5-2.5 feet) and width (2-3 feet) via formwork inserts. [0053] Wall Engagement Features: The upper section may include: [0054] Inner and outer portions (inner extending 4-8 inches beyond outer, thickness 4.5-5.5 inches). [0055] Inner, middle, and outer portions (middle recessed 3.5-4.5 inches below inner/outer, width 3-4 inches), with optional cylindrical apertures (diameter 0.75-1.5 inches) for securing mechanisms (e.g., coil rods). [0056] Receiving portions (e.g., slots for metal plates from the upper riser section). [0057] Reinforcement: Rebar placement ensures durability under transformer loads and environmental stresses.
[0058] The upside-down monolithic pour provides: [0059] Structural Integrity: Seamless construction withstands significant loads. [0060] Precision: Tight tolerances ensure compatibility with upper riser sections. [0061] Efficiency: Single-pour process reduces time and labor compared to multi-step methods. [0062] Adaptability: Formwork adjustments allow for various wall and sump configurations.
Assembly Context
[0063] Post-curing, the lower riser section is transported to the installation site, positioned, and joined with an upper riser section (e.g., via construction joints as in
[0064] By the present disclosure a method of manufacturing a precast concrete utility vault's lower riser section using an upside-down monolithic pour has been described. By integrating precise formwork, reinforcement, and controlled curing, the method provides a durable, dimensionally accurate product optimized for housing large electrical transformers.
[0065] While the present method has been described with reference to particular embodiments, it will be understood by those skilled in the art that various changes may be made and equivalents may be substituted for elements thereof without departing from the intended scope. In addition, modifications may be made to adapt a particular situation or material to these teachings without departing from the intended scope.