Cpc classification
International classification
Abstract
A bridge sliding device includes a slide rail assembly, a first sliding component on the rail, and a second sliding component on the first. The second component locks at the start of the first, and the bridge deck truss's weight causes the first component's end to tilt slightly, allowing it to easily cross the junction between the temporary support platform and the bridge pier. This facilitates the smooth crossing of both the first and second components over the junction. Once the first sliding component is in place, the second component unlocks and continues sliding, increasing the travel distance of the bridge deck truss. The device ensures smoother movement of the components, enhancing construction efficiency.
Claims
1. A bridge sliding device, comprising: a slide rail assembly, the slide rail assembly comprising a rail configured to span across a temporary support platform and a bridge pier, the rail arranged along a transverse direction from the temporary support platform toward the bridge pier; a first sliding component slidably disposed on the rail, the first sliding component having a sliding start end and a sliding end opposite each other in the transverse direction; and a second sliding component unlockably locked to the sliding start end of the first sliding component, the second sliding component capable of sliding from the sliding start end to the sliding end of the first sliding component, the second sliding component configured to support a bridge deck truss, wherein the length of the second sliding component is less than the length of the first sliding component, and the length of the first sliding component is less than the length of the rail.
2. The bridge sliding device according to claim 1, further comprising a locking assembly, the locking assembly disposed on the first sliding component, wherein in an initial state, the locking assembly is configured to lock the second sliding component at the sliding start end of the first sliding component, and after the first sliding component slides into position, the locking assembly is configured to release the lock on the second sliding component.
3. The bridge sliding device according to claim 2, wherein the locking assembly comprises a locking pin, a locking pushrod, and a pushrod reset mechanism, the first sliding component having a first locking hole on a side facing the second sliding component, the second sliding component having a second locking hole on a side facing the first sliding component, one end of the locking pin inserted into the first locking hole and the other end capable of being inserted into the second locking hole; the first sliding component further having a moving hole communicating with the first locking hole, the moving hole running through the sliding end, one end of the locking pushrod reciprocally disposed in the moving hole along the transverse direction, the pushrod reset mechanism configured to apply a reset force along the transverse direction to the locking pushrod, wherein movement of the locking pushrod within the moving hole drives the locking pin to move from the second locking hole to the first locking hole, thereby disengaging the second locking hole.
4. The bridge sliding device according to claim 3, wherein the locking pushrod has a relief groove on a side facing the first locking hole, the other end of the locking pushrod extending out of the moving hole, the locking pushrod moving from the sliding end to the sliding start end to align the relief groove with the first locking hole, enabling the locking pin to drop from the second locking hole into the first locking hole and the relief groove; or wherein one end of the locking pin is inserted into the moving hole through the first locking hole, the portion of the locking pin within the moving hole having a locking groove on a side facing the locking pushrod, the locking groove forming a contact slope, the contact slope inclined in the transverse direction away from the second locking hole, the one end of the locking pushrod capable of contacting the contact slope; locking assembly further comprising a locking reset mechanism configured to apply a reset force to the locking pin along the direction from the first locking hole to the second locking hole.
5. The bridge sliding device according to claim 1, wherein the sliding end of the first sliding component is provided with a stop, the first sliding component having a sliding slot arranged in the transverse direction, the second sliding component slidably disposed within the sliding slot, the second sliding component capable of sliding within the sliding slot and contacting the stop.
6. The bridge sliding device according to claim 1, further comprising a limiting member, the limiting member movably disposed on the rail, the direction of movement of the limiting member relative to the rail being the transverse direction, the first sliding component capable of sliding on the rail and contacting the limiting member.
7. The bridge sliding device according to claim 1, wherein the length of the first sliding component is less than the length of the temporary support platform in the transverse direction.
8. The bridge sliding device according to claim 1, wherein the friction coefficient between the first sliding component and the rail is less than the friction coefficient between the second sliding component and the first sliding component.
9. A bridge construction system, comprising: a temporary support platform, the temporary support platform set up on one side of a bridge pier; and a bridge sliding device, wherein the bridge sliding device comprises: a slide rail assembly, the slide rail assembly comprising a rail configured to span across a temporary support platform and a bridge pier, the rail arranged along a transverse direction from the temporary support platform toward the bridge pier; a first sliding component slidably disposed on the rail, the first sliding component having a sliding start end and a sliding end opposite each other in the transverse direction; and a second sliding component unlockably locked to the sliding start end of the first sliding component, the second sliding component capable of sliding from the sliding start end to the sliding end of the first sliding component, the second sliding component configured to support a bridge deck truss, wherein the length of the second sliding component is less than the length of the first sliding component, and the length of the first sliding component is less than the length of the rail, wherein the slide rail assembly spanning the temporary support platform and the bridge pier, the first sliding component capable of sliding along the rail from the temporary support platform to the bridge pier, and the second sliding component capable of sliding from the sliding start end to the sliding end of the first sliding component.
10. The bridge construction system of claim 9, further comprising a pushing assembly, the pushing assembly set up on the temporary support platform, the pushing assembly configured to push the bridge deck truss in the transverse direction; and/or further comprising a jacking assembly, the jacking assembly set up on the temporary support platform, the jacking assembly capable of moving up and down relative to the temporary support platform and configured to lift the bridge deck truss from the second sliding component.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1) The drawings that form part of this application are intended to provide a further understanding of the invention. The exemplary embodiments of the invention and their descriptions are used to explain the invention and do not constitute an undue limitation of the invention.
(2) To clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for the description of the embodiments are briefly introduced below. It is evident that the following described drawings are merely some embodiments of the invention. For those skilled in the art, other drawings can be obtained based on these drawings without inventive effort.
(3) Additionally, the drawings are not drawn to scale, and the relative sizes of the various components are shown illustratively in the drawings and are not necessarily drawn to actual scale. In the drawings:
(4)
(5)
(6)
(7)
(8)
(9) The following reference numerals are used in the drawings: 10, bridge construction system; 100, temporary support platform; 200, bridge sliding device; 210, slide rail assembly; 212, rail; 214, limiting member; 220, first sliding component; 221, sliding start; 222, sliding end; 223, first locking hole; 224, moving hole; 225, stop; 226, sliding slot; 230, second sliding component; 231, second locking hole; 240, locking assembly; 241, locking pin; 2411, locking groove; 2412, contact slope; 242, locking pushrod; 2422, relief groove; 243, pushrod reset mechanism; 244, locking reset mechanism; 20, bridge pier; 30, bridge deck truss.
DETAILED DESCRIPTION
(10) To make the above objectives, features, and advantages of this application more apparent, the specific embodiments of this application are described in detail below in conjunction with the drawings. In the following description, numerous specific details are set forth to provide a thorough understanding of this application. However, this application can be implemented in many other ways different from those described herein, and those skilled in the art can make similar modifications without departing from the essence of this application. Therefore, this application is not limited by the specific embodiments disclosed below.
(11) Referring to
(12) Referring also to
(13) During construction, temporary support platforms 100 are first set up on both sides of the bridge pier 20, and then the slide rail assembly 210 is set up across the temporary support platforms 100 and the bridge pier 20, so that the rail 212 of the slide rail assembly 210 is arranged in the transverse direction a of the bridge deck truss 30. Due to the higher deformation resistance of the bridge pier 20 compared to the temporary support platform 100, the pressure from the bridge deck truss 30 on the temporary support platform 100 will cause it to deform, leading to a height difference between the temporary support platform 100 and the bridge pier 20, affecting the movement of the bridge deck truss 30 in the transverse direction a. If, to overcome the height difference caused by the deformation of the temporary support platform 100, the height of the temporary support platform 100 is set higher than that of the bridge pier 20 during installation, then due to the height difference between the temporary support platform 100 and the bridge pier 20 in the initial state, the slide rail assembly 210 cannot be effectively and reliably installed on the bridge pier 20, which affects the installation reliability of the slide rail assembly 210 with the bridge pier 20. This, in turn, although solving the height difference issue caused by the pressure of the bridge deck truss 30 on the temporary support platform 100, raises the problem of the installation reliability of the slide rail assembly 210, affecting the stability of the bridge deck truss 30 as it moves on the slide rail assembly 210 in the transverse direction a.
(14) Using the above-mentioned bridge sliding device 200, since the first sliding component 220 is set on the rail 212, and the second sliding component 230 is set on the first sliding component 220, and the second sliding component 230 is shorter than the first sliding component 220, when the first sliding component 220 is aligned with the temporary support platform 100, the second sliding component 230 is locked onto the sliding start 221 of the first sliding component 220, and the bridge deck truss 30 is set on the second sliding component 230. The weight of the bridge deck truss 30, applied through the second sliding component 230 to the sliding start 221 of the first sliding component 220, causes the sliding end 222 of the first sliding component 220 to slightly tilt upwards. As the first sliding component 220 slides on the rail 212, the sliding end 222 of the first sliding component 220 can easily cross the junction between the temporary support platform 100 and the bridge pier 20. When the second sliding component 230 moves with the first sliding component 220 to the junction, the sliding end 222 of the first sliding component 220 has already moved onto the bridge pier 20, allowing the sliding start 221 of the first sliding component 220 to more easily cross the junction, thereby making it easier for the second sliding component 230 to cross the junction as well. After the first sliding component 220 is in position, the locking of the second sliding component 230 relative to the first sliding component 220 can be released, allowing the bridge deck truss 30 to push the second sliding component 230 to continue sliding from the sliding start 221 to the sliding end 222 of the first sliding component 220, increasing the travel distance of the bridge deck truss 30 in the transverse direction a. This bridge sliding device 200, by utilizing the cooperation between the first sliding component 220 and the second sliding component 230, allows the second sliding component 230 to more smoothly cross the junction between the temporary support platform 100 and the bridge pier 20, ensuring the efficiency of the bridge deck truss's incremental launching construction.
(15) In one embodiment, the bridge construction system 10 further includes a pushing assembly (not shown), which is set on the temporary support platform 100 and is used to push the bridge deck truss 30 in the transverse direction a. During construction, the bridge deck truss 30 is set on the second sliding component 230, and the pushing assembly pushes the bridge deck truss 30 along the transverse direction a, allowing the bridge deck truss 30 to move using the second sliding component 230 and the first sliding component 220 sliding on the rail 212, thereby achieving the movement of the bridge deck truss 30. By providing the pushing assembly, power can be provided for the movement of the bridge deck truss 30.
(16) In one embodiment, the bridge construction system 10 further includes a jacking assembly (not shown), which is set on the temporary support platform 100. The jacking assembly can move up and down relative to the temporary support platform 100 and is used to lift the bridge deck truss 30 from the second sliding component 230. When the bridge deck truss 30 is moved into place through the first sliding component 220 and the second sliding component 230, the jacking assembly rises relative to the temporary support platform 100 to lift the bridge deck truss 30 from the second sliding component 230, allowing the bridge deck truss 30 to separate from the second sliding component 230. At this time, the slide rail assembly 210, the first sliding component 220, and the second sliding component 230 can be disassembled from the bridge pier 20. The jacking assembly then lowers the bridge deck truss 30, placing the bridge deck truss 30 on the bridge pier 20, achieving the purpose of moving the bridge deck truss 30 to the bridge pier 20 and positioning it on the pier.
(17) Specifically, the jacking assembly can be a jack. The number of jacking assemblies can be two, with each jacking assembly set on the temporary support platform 100 on either side of the bridge pier 20, allowing the bridge deck truss 30 to be lifted from both sides, increasing the reliability of lifting the bridge deck truss 30.
(18) As shown in
(19) Of course, in other embodiments, the length of the first sliding component 220 can be greater than the length of the temporary support platform 100 in the transverse direction a. In the initial state, the sliding end 222 of the first sliding component 220 would already be positioned on the bridge pier 20, and the sliding start 221 of the first sliding component 220 would be on the temporary support platform 100, further avoiding the need for the first sliding component 220 to span the junction between the temporary support platform 100 and the bridge pier 20 during sliding.
(20) In one embodiment, the friction coefficient between the first sliding component 220 and the rail 212 is less than the friction coefficient between the second sliding component 230 and the first sliding component 220. When the bridge deck truss 30 is pushed along the transverse direction a, since the friction coefficient between the first sliding component 220 and the rail 212 is less than that between the second sliding component 230 and the first sliding component 220, it will cause the first sliding component 220 to slide first on the rail 212, or the sliding speed of the first sliding component 220 on the rail 212 to be greater than that of the second sliding component 230 on the first sliding component 220. Therefore, when the first sliding component 220 has not slid into place, the second sliding component 230 moves slowly or does not move on the sliding start 221 of the first sliding component 220, effectively locking the second sliding component 230 onto the first sliding component 220. Thus, when the first sliding component 220 spans the junction between the temporary support platform 100 and the bridge pier 20, the second sliding component 230 has not yet slid to the sliding end 222 of the first sliding component 220, allowing the sliding end 222 of the first sliding component 220 to smoothly slide onto the bridge pier 20, and the second sliding component 230 then slides from the sliding start 221 to the sliding end 222 of the first sliding component 220, smoothly crossing the junction between the temporary support platform 100 and the bridge pier 20.
(21) Referring to
(22) Specifically, the locking assembly 240 includes a locking pin 241, a locking pushrod 242, and a pushrod reset mechanism 243. The first sliding component 220 has a first locking hole 223 on the side facing the second sliding component 230, and the second sliding component 230 has a second locking hole 231 on the side facing the first sliding component 220. One end of the locking pin 241 is inserted into the first locking hole 223, and the other end can be inserted into the second locking hole 231. The first sliding component 220 also has a moving hole 224 communicating with the first locking hole 223, which runs through the sliding end 222. The locking pushrod 242 is movably inserted into the moving hole 224 along the transverse direction a, and the pushrod reset mechanism 243 applies a reset force along the transverse direction a to the locking pushrod 242. The locking pushrod 242 moves within the moving hole 224, driving the locking pin 241 to move from the second locking hole 231 to the first locking hole 223, disengaging the second locking hole 231.
(23) In the locked state, one end of the locking pin 241 is inserted into the first locking hole 223, and the other end is inserted into the second locking hole 231, using the locking pin 241 to prevent the second sliding component 230 from moving relative to the first sliding component 220. After the first sliding component 220 moves into place, the locking pushrod 242 is pushed to move within the moving hole 224, driving the locking pin 241 to move from the second locking hole 231 to the first locking hole 223, disengaging the second locking hole 231, and at this time, the pushrod reset mechanism 243 stores energy. After the locking pin 241 exits the second locking hole 231, the lock on the second sliding component 230 is released, allowing the second sliding component 230 to slide on the first sliding component 220. In one embodiment, when the bridge sliding device 200 is reused, the pushrod reset mechanism 243 releases the stored energy, resetting the locking pushrod 242, and the locking pin 241 resets, allowing the locking pin 241 to reinsert into the second locking hole 231 from the first locking hole 223.
(24) In one embodiment, one end of the locking pin 241 is inserted through the first locking hole 223 into the moving hole 224. The portion of the locking pin 241 located within the moving hole 224 has a locking groove 2411 on the side facing the locking pushrod 242, and the locking groove 2411 forms a contact slope 2412, inclined along the transverse direction a, away from the second locking hole 231. One end of the locking pushrod 242 can contact the contact slope 2412. The locking assembly 240 further includes a locking reset mechanism 244 that applies a reset force to the locking pin 241 along the direction from the first locking hole 223 to the second locking hole 231.
(25) After the first sliding component 220 moves into place, the locking pushrod 242 is pushed within the moving hole 224 in the opposite direction along the transverse direction a, towards the locking groove 2411 of the locking pin 241. The locking pushrod 242 contacts the contact slope 2412, using the contact slope 2412 to press down the locking pin 241, causing the locking pin 241 to move from the second locking hole 231 to the first locking hole 223, disengaging the second locking hole 231. At this time, the locking reset mechanism 244 is compressed and stores energy, and the pushrod reset mechanism 243 is also compressed and stores energy. After releasing the push on the locking pushrod 242, the locking reset mechanism 244 releases the stored energy, resetting the locking pin 241, and the pushrod reset mechanism 243 releases the stored energy, resetting the locking pushrod 242.
(26) Referring to
(27) Referring to
(28) In one embodiment, the slide rail assembly 210 further includes a limiting member 214, which is set on the rail 212, and the first sliding component 220 can slide on the rail 212 and contact the limiting member 214. By setting the limiting member 214, the sliding position of the first sliding component 220 can be limited. When the first sliding component 220 moves in the direction of the limiting member 214, the locking pushrod 242 first contacts the limiting member 214, causing the limiting member 214 to push the locking pushrod 242, allowing the locking pushrod 242 to unlock the second sliding component 230 from the locking pin 241. After the first sliding component 220 contacts the limiting member 214, the locking pushrod 242 drives the locking pin 241 to unlock the second sliding component 230, allowing the second sliding component 230 to continue sliding on the first sliding component 220.
(29) Specifically, the limiting member 214 is movably set on the rail 212, and the direction of movement of the limiting member 214 relative to the rail 212 is the transverse direction a. By controlling the movement of the limiting member 214 on the rail 212, the sliding position of the first sliding component 220 can be limited, thereby limiting the movement position of the bridge deck truss 30, improving the accuracy of placing the bridge deck truss 30 on the bridge pier 20.
(30) Furthermore, the limiting member 214 is retractable relative to the rail 212. By retracting the limiting member 214 relative to the rail 212, it can be adjusted to determine whether the limiting member 214 limits the position of the first sliding component 220, adapting to different situations of lateral movement of the bridge deck truss 30.
(31) The above-mentioned bridge sliding device 200, through the cooperation of the first sliding component 220 and the second sliding component 230, allows the bridge deck truss 30 to smoothly cross the junction between the temporary support platform 100 and the bridge pier 20 during lateral movement, effectively ensuring the efficiency of the bridge deck truss 30 incremental launching construction.
(32) In the description of this application, it should be understood that terms such as center, longitudinal, transverse, length, width, thickness, upper, lower, front, rear, left, right, vertical, horizontal, top, bottom, inside, outside, clockwise, counterclockwise, axial, radial, circumferential, and similar terms indicating orientation or positional relationships are based on the orientation or positional relationships shown in the drawings. These terms are provided to facilitate the description of the present application and to simplify the description, rather than to indicate or imply that the referenced device or component must have a specific orientation, be constructed, or operate in a specific orientation. Therefore, these terms should not be construed as limiting the present application.
(33) Moreover, terms such as first and second are used for descriptive purposes only and should not be construed as indicating relative importance or implicitly specifying the number of technical features referred to. Thus, features defined as first and second may explicitly or implicitly include at least one of those features. In the description of this application, the term multiple means at least two, for example, two, three, etc., unless otherwise explicitly specified.
(34) In this application, unless otherwise explicitly specified and defined, terms such as installation, connection, coupling, fixing, and similar terms should be understood broadly. For example, they may refer to fixed connections, removable connections, or integral formations; they may refer to mechanical connections or electrical connections; they may refer to direct connections or indirect connections through intermediate media; they may refer to the internal communication of two components or the interaction relationship between two components, unless otherwise explicitly specified. For those skilled in the art, the specific meanings of these terms in this application can be understood based on the specific context.
(35) In this application, unless otherwise explicitly specified and defined, descriptions such as on or under for the first feature relative to the second feature may mean direct contact between the first and second features or indirect contact through intermediate media. Moreover, on, above, and over for the first feature relative to the second feature may mean that the first feature is directly above or diagonally above the second feature, or merely that the first feature is at a higher horizontal level than the second feature. Under, below, and beneath for the first feature relative to the second feature may mean that the first feature is directly below or diagonally below the second feature, or merely that the first feature is at a lower horizontal level than the second feature.
(36) It should be noted that if a component is described as being fixed to or arranged on another component, it can be directly on the other component or there may also be an intermediary component. If a component is described as being connected to another component, it can be directly connected to the other component or there may also be an intermediary component. Furthermore, the terms vertical, horizontal, upper, lower, left, right, and similar expressions used in this application are for descriptive purposes only and do not represent the only embodiments.
(37) The various technical features of the above-described embodiments can be combined in any suitable manner. For simplicity of description, not all possible combinations of the above technical features are described. However, as long as there is no contradiction between these technical features, it should be considered within the scope of the present disclosure.
(38) The above-described embodiments only express a few embodiments of the present application. Their descriptions are specific and detailed, but they should not be understood as limiting the scope of the patent claims. It should be noted that for those skilled in the art, without departing from the concept of the present application, several modifications and improvements can be made. These all fall within the scope of the present application. Therefore, the scope of the patent should be defined by the appended claims.