METHOD FOR USING AERATED AUTOCLAVED CONCRETE IN RESIDENTIAL AND COMMERCIAL CONSTRUCTION
20260015850 ยท 2026-01-15
Inventors
Cpc classification
E04B1/161
FIXED CONSTRUCTIONS
International classification
E04B1/16
FIXED CONSTRUCTIONS
Abstract
A method for construction using a panel and plank system that may optionally be made of Aerated Autoclaved Concrete (AAC), wherein wall panels are delivered, erected and attached to structural forms and braced with properly designed shoring/struts with form ties and specifically designed panel ties. Intermediate bracing is installed at midspan locations where spans are short and there is a possibility of wall buckling. Floor/roof planks are set on top of the walls being cognizant of bearing surface requirements. The deformed and post-tension reinforcing steel is set/installed and any miscellaneous detailing is completed. Thin AAC panels can be installed as form liners for added insulation where dimensions accommodate them. Structural grout or small aggregate concrete is placed, consolidated/vibrated, and finished and allowed to cure to minimum required strengths. Roof pours are given a crown to allow proper drainage.
Claims
1. A method for constructing a building having at last one level, the level comprising an integral monolithic superstructure using planks and panels comprising an air-entrained or foam-based material in combination with cast-in-place concrete, the method comprising: placing a first set of planks, panels, or planks and panels in a vertical orientation on a construction site to define one or more vertical walls of the superstructure; providing and securing temporary shoring and formwork adjacent to the first set of panels and planks to define form cavities at selected intervals for cast-in-place columns and vertical reinforcement in the form of rebar or prestressed cables; placing a second set of planks, panels, or planks and panels in a generally horizontal orientation atop the first set to form at least a partial floor or ceiling surface, while leaving defined voids for the placement of cast-in-place beams; casting concrete into the form cavities between, adjacent to, and above the planks and panels to form structural columns, beams, and horizontal surfaces as a continuous monolithic pour, thereby integrating the cast-in-place concrete with the generally weaker air-entrained or foam-based panels and planks to form a composite structure; wherein the structural columns and beams formed by the cast-in-place concrete are sized and reinforced to accommodate increased the structural loading; and the horizonal beams and columns include rebar bent to form a cup-shape and including vertical rebar members extending vertically upwardly to at least a level at or sufficiently near the level of the upper surface of the floor planks to ensure that the, the upper ends of the vertical rebar elements are covered by later-poured concrete; and wherein the planks and panels remain in place while the concrete of the structural columns and beams is poured to function as formwork and after the concrete is cured, remain in place permanently to function as interior surfaces, exterior surfaces, or insulation, and wherein the cast-in-place concrete provides the primary structural strength of the superstructure.
2. The method of claim 1, wherein the planks and panels are comprised of an inert, inorganic, vapor-permeable material having a lower density than concrete, thereby reducing the potential for latent moisture condensation within the matrix and making the system suitable for environments containing humidity-sensitive electronic equipment.
3. The method of claim 1, wherein the cast-in-place concrete is formed in spatial relationship with the planks and panels to provide integrated vertical and horizontal structural support.
4. The method of claim 1, wherein the planks and panels function as stay-in-place formwork while the concrete is pour and during curing and thermal insulation thereafter, the cast-in-place concrete when cured providing the primary structural integrity of the superstructure.
5. The method of claim 1, wherein spaces formed between or adjacent to the planks and panels define initially empty regions to receive and hold for poured concrete and to act as forms for concrete cast-in-place columns, beams, or reinforcement zones that become part of a continuous concrete frame when the poured concrete is cured.
6. The method of claim 1, further comprising pouring cast-in-place concrete to form a network of structural beams atop or within the horizontal surface formed by the planks and panels.
7. The method of claim 1, wherein the planks and panels are composed of an inorganic, chemically stable, vapor-permeable, low-density, and non-combustible material that is exhibiting passive fire-resistant and thermally insulating.
8. The method of claim 1, wherein the temporary shoring is reusable and configured to support the planks and panels during concrete placement and curing, and is further adapted to support the staging of construction materials and placement equipment while the concrete is placed and cured.
9. The method of claim 1, wherein the cast-in-place concrete is poured into interconnected cavities to form a poured monolithic structural skeleton comprised of vertical and horizontal structural members that are monolithically interconnected without intervening mechanical connections between them and previously poured and cured concrete structural components using cold joints.
10. The method of claim 1, wherein the cast-in-place beams have a medial vertical plane through the length thereof and an average thickness at the medial vertical plane greater than the thickness of the adjacent floor or ceiling planks, thereby to provide adequate support for the floor or ceiling planks and to accommodate embedded utility sleeves, conduits, or service pathways for mechanical, electrical, or data systems.
11. The method of claim 1, wherein the method can employ a superstructure having a first intended size and a second other size, the method further comprising, at any time prior to the step of pouring the concrete, changing the first intended size of the superstructure to the second size by using supplemental or different configurations of shoring, bracing, or additional formwork.
12. A method for constructing a building having at least two vertically adjacent levels, each of the two vertically adjacent levels comprising an integral monolithic superstructure using planks and panels comprising an air-entrained or foam-based material in combination with cast-in-place concrete, the method comprising, for each level: placing a first set of planks, panels, or planks and panels in a vertical orientation on a construction site to define one or more vertical walls of the superstructure; providing and securing temporary shoring and formwork adjacent to the first set of panels and planks to define form cavities at selected intervals for cast-in-place columns and vertical reinforcement in the form of rebar or prestressed cables; placing a second set of planks, panels, or planks and panels in a generally horizontal orientation atop the first set of planks, panels, or planks and panels to form at least a partial floor or ceiling surface, while leaving defined voids for the placement of cast-in-place beams; casting concrete into the form cavities between, adjacent to, and above the planks and panels to form structural columns, beams, and horizontal surfaces as a continuous monolithic pour, thereby integrating the cast-in-place concrete with the generally weaker air-entrained or foam-based panels and planks to form a composite structure; wherein the structural columns and beams formed by the cast-in-place concrete are sized and reinforced with rebar, wire mesh and/or pre-tensioned bars or cables to accommodate structural loading; and the horizonal beams include at least rebar bent to form an upwardly open longitudinally-elongated cup-shape, the beams further including vertical rebar members extending vertically upwardly to at least a level at or sufficiently near the level of the upper surface of the floor planks to ensure that the upper ends of the vertical rebar elements are covered by later-poured concrete when cured; wherein the planks and panels remain in place when the concrete of the structural columns and beams is poured to function as formwork until the concrete is cured, and thereafter remain in place after the cast-in-place concrete of the structural columns and beams is cured to function as interior surfaces, exterior surfaces and/or insulation, and wherein the cast-in-place concrete provides the primary structural strength of the superstructure, and wherein, once the panels, planks and forms are positioned and held in place to define the cavities for forming the cast-in-place beams and columns for the at least two levels, concrete is poured in place in all the cavities of the at least two levels in a substantially continuous manner to form, when the concrete is cured, a poured monolithic structural superstructure encompassing the at least two adjacent levels comprised of vertical and horizontal structural members that are monolithically interconnected without intervening mechanical connections between them and or with previously installed structural components using cold joints.
13. A method for constructing a building having between three and twenty vertically adjacent levels, all the vertically adjacent levels together comprising an integral monolithic superstructure using planks and panels comprising an air-entrained or foam-based material in combination with cast-in-place concrete, the method comprising, for each level: placing a first set of planks, panels, or planks and panels in a vertical orientation on a foundation for the lowest level or on the next lower level for all successively higher levels, to define one or more vertical walls of the superstructure; providing and securing temporary shoring and formwork adjacent to the first set of panels and planks to define form cavities at selected intervals for cast-in-place columns and vertical reinforcement in the form of rebar, wire mesh and/or prestressed cables or bars; placing a second set of planks, panels, or planks and panels in a generally horizontal orientation atop the first set of planks, panels, or planks and panels to form at least a partial floor or ceiling surface, while leaving defined voids for the placement of cast-in-place beams; casting concrete into the form cavities between, adjacent to, and above the planks and panels to form structural columns, beams, and horizontal surfaces as a continuous monolithic pour, beginning at the lowest level and then each successively higher level, thereby integrating the cast-in-place concrete with the generally weaker air-entrained or foam-based panels and planks to form a composite structure; wherein the structural columns and beams formed by the cast-in-place concrete are sized and reinforced to accommodate the structural loading; wherein the horizonal beams include rebar bent to form a cup-shape and including vertical rebar members extending vertically upwardly to at least a level that ensures that the upper ends of the vertical rebar elements are covered by later-poured concrete for the beam; wherein the planks and panels remain in place when the concrete of the structural columns and beams is poured to function as formwork until the concrete is cured, and thereafter remain in place after the cast-in-place concrete of the structural columns and beams is cured to function as interior surfaces, exterior surfaces or insulation, and wherein the cast-in-place concrete provides the primary structural strength of the superstructure; and wherein, once the panels, planks and forms are positioned and held in place to define the cavities for forming the cast-in-place beams and columns for the at least two floors, concrete is poured in place into all the cavities of the levels, beginning with the lowest level and then the next higher level in order, in a substantially continuous manner, to form, when the concrete is cured, a poured monolithic structural superstructure encompassing the vertical and horizontal members monolithic structural members of all level such that they are monolithically interconnected without intervening mechanical connections between them or to other previously installed structural components using cold joints.
14. The method of claim 1, wherein the one or more vertical walls of the superstructure include at least two spaced-apart vertical exterior walls, each of which is disposed in at least two separate axially-aligned sections having opposed and spaced-apart ends to form a gap between them, wherein the method further comprises: placing an internal demising wall comprised of panels formed of air-entrained or foam-based material, the panels having respective ends, at least one of which ends being positioned adjacent an interior side of the gap to at least partially close-off the interior side of the gap; and placement of interior and exterior vertical forms covering remaining open internal and external portions of the gap to form a closed-at-the-sides vertically-oriented cavity to receive and hold poured concrete to form a cast-in-place column in the cavity.
15. A method for creating a building having an integral monolithic superstructure having between one and twenty levels, the method comprising the steps of: placing a foundation having a plurality of predetermined horizontally spaced apart column locations having a width to support a lowest level; on the lowest level, placing a plurality of predetermined horizontally spaced apart column locations having a width thereon, each of which is axially aligned with one of the plurality of predetermined horizontally spaced apart column locations having a width, for each successively higher level of the between one and twenty levels, beginning at the next higher level: setting a first set of vertically oriented shoring having a width adjacent to an interior side of the horizontally spaced apart column locations, the width being sufficiently wide to cover the interior side of each respective space for the vertical supporting columns to be formed in the horizontally spaced apart column locations and having a width, and a portion of the ends of the first set of construction material on either side of each of the horizontally spaced apart column locations; placing a first set of vertically oriented construction materials that include planks, panels, or planks and panels comprising a foam material and having a length, width, ends, a thickness and lower and upper edges, the first set of construction materials for the lowest level being supported by the foundation, and the first set of vertically oriented construction materials for each successively higher level being supported by the next lower level, the first set of vertically oriented construction materials for each level forming one or more vertical walls of the integral monolithic superstructure, the ends of the first set of construction materials being spaced apart horizontally and endwise on the foundation for the lowest level and on the next lowest level for each successively higher level, at the predetermined horizontally spaced apart column locations to leave a sufficient space for the vertical supporting columns but sufficiently close together that the first set of vertically oriented shoring covers a portion of the ends of the first set of construction material on either side of each of the horizontally spaced apart column locations; setting a second set of vertically oriented shoring having a width adjacent to an exterior side of the horizontally spaced apart column locations, the width being sufficiently wide to cover the exterior side of the space for the vertical supporting columns and a portion of the ends of the first set of construction material on either side of each of the horizontally spaced apart column locations such that the space for each of the vertical supporting columns is substantially enclosed on all vertical sides; placing a second set of construction materials that include planks, panels, or planks and panels on an inner portion of a topmost edge of the first set of construction materials to form a horizontal surface of the integral monolithic superstructure while leaving an outer portion of the top edge of the first set of construction materials uncovered by the horizontal surface, the horizontal surface having a thickness and an upper surface having a height greater than the height of the topmost horizonal edge of the first set of construction material; placing a perimeter vertically oriented and horizontally elongated form around the topmost portion of the exterior perimeter of the upper portion of the first set of construction materials of each level, the form having a top edge higher than the upper surface of the horizontal surface, the form in combination with the topmost horizontal edge of the first set of construction materials uncovered by the horizontal surface of the second set of construction materials, the adjacent edge of the horizontal surface, and the second set of vertically oriented shoring, forming an open-at-the-top generally circumferential space, the bottom portion of which is in communication with the upper ends of each of the horizontally spaced apart column locations; beginning with the lowermost level, pouring mortar, concrete or a mix thereof into the open-at-the-top portion of each generally circumferential space at the top of the level, to substantially fill it and each of the horizontally spaced apart column locations of the level, and to cover at least a portion of an upper surface of the horizontal surface of the second set of construction materials for the level with a predetermined thickness of the mortar, concrete or a mix thereof; and then, for each successively higher level, pouring mortar, concrete or a mix thereof into an open-at-the-top portion of each generally circumferential space at the top of the level, to substantially fill it and each of the horizontally spaced apart column locations of the level, and to cover at least a portion of an upper surface of the horizontal surface of the second set of construction materials for the level with a predetermined thickness of the mortar, concrete or a mix thereof, until the mortar, concrete or a mix thereof has filled all the generally circumferential spaces and horizontally spaced apart column locations for each level, the mortar, concrete or a mix thereof being poured in a substantially continuous manner to form, when cured, a poured monolithic superstructure encompassing all levels and being comprised of vertical and horizontal monolithic structural members that are monolithically interconnected without intervening mechanical connections between them or to previously installed structural components using cold joints, and, for each level; and removing the first set of vertically oriented shoring and the second set of vertically oriented shoring while permanently retaining the foam material as part of the completed building having an integral monolithic superstructure.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0014] For a more complete understanding of this disclosure, reference is now made to the following description, taken in conjunction with the accompanying drawings, in which:
[0015]
[0016]
[0017]
[0018]
[0019]
[0020]
[0021]
[0022]
[0023]
[0024]
[0025]
[0026]
[0027]
[0028]
[0029]
[0030]
[0031]
[0032]
[0033]
[0034]
[0035]
[0036]
[0037]
[0038]
[0039]
[0040]
[0041]
[0042]
DETAILED DESCRIPTION
[0043] Disclosed herein is a method to construct and assemble an integrated monolithic superstructure using panels and planks, where the panels, planks, or both panel and planks are made of aerated autoclaved concrete (AAC).
[0044] The method can include developing a structure that is conceptually designed for a more conducive application of the System. An assessment of purpose, required design criteria, space needs, etc. and the development of the conceptual design should be guided in a manner that is conducive the use of this system. If the design is already conceptually established, then a skilled, properly trained architect, engineer, qualified contractor, or AAC rep should assess the conceptual design and design criteria and make recommendations that render the use of the system more practical for the specific application.
[0045] The AAC manufacturer adjusts their product characteristics (compressive strengths and internal reinforcing requirements), the manufacturer can design material characteristics to meet thermal and compressive strength requirements for the building and local code criteria/standard. Top wall panels should have a higher compressive strength where needed to accommodate live and dead loads during construction activities. A structural design technician designs the IMS to accommodate the performance standards of the structure, the performance standards, and deflection criteria of the substructure to minimize failures or cracking. Bearing soils tests are always required.
[0046] The AAC planks and panels are manufactured in the factory, then cut to exact dimensions (but minimizing the number of unique dimensions) required for assembly to eliminate the process of field cutting to fit. Standard sizes can be used, which also allows for the interchangeability of panels or planks. Pre-cutting to exact lengths at the factory allows for fashioning panels/planks in an environment with the facilities to perform fashioning quicker and more efficiently. Pre-cutting also allows the field erectors to work quickly and without delays caused by custom field cuts. Limited Uniform sizes, consistent with typical residential room dimensions, allow for easy staging on delivery vehicles, easy interchangeability of damaged or missing panels/planks, and easy coordination at the jobsite. Limited Uniform sizes also allows AAC distributors to stock panels and planks, which would otherwise be considered custom manufactured and potentially eliminate delays caused by remanufacturing of damaged or missing panels and planks.
[0047] Panels and planks are reverse staged (last loaded on the truck are the first set on in place on site) on delivery vehicles so that, when construction site conditions permit, panels and planks can be picked from the truck and set directly in place. AAC is a low strength concrete that is damaged relatively easily. Repairs can be made but take time and cause delays. Reduced handling means a reduced risk of damage and delays. Moving materials multiple times takes time and causes delays. Reverse staging on delivery vehicles mean products can be set in place right from the delivery vehicles, eliminating delays caused by staging materials multiple times, and the cost of repairing damage caused by excessive handling. Dual tandem, short-wheel-based, soft-ride trailers allow delivery to areas where road access is tight (such as residential neighborhoods) because one trailer can be dropped, while one is delivered, and minimizing damage from transport.
[0048] Prior to delivery of components an appropriate design foundation or substructure is constructed. AAC is non-ductileit will only accommodate a minimum amount of deflection before it cracks, this is especially true for wall panels. The performance standards and deflection criteria of the substructure should be such that it minimizes failures or cracking. Bearing soils tests are always required to determine substructure design criteria. Additionally, bond-breaking materials and thin expansion joint materials are used in strategic locations. These materials help arrest and isolate potential movement throughout the IMS wall system. They also mitigate cracking caused by the thermal expansion and contraction differentials of the different materials.
[0049] Prior to placing any wall panels, vertical wall forms are erected at strategic locations (corners, mid-wall integral columns, and as mid span bracing to prevent buckling on longer wall spans). They are set, braced, and plumbed using a combination of rigid or cable struts and shores, and specially designed ties and connections 205. Shoring and braces are anchored to the substructure or flooring system using properly designed removable anchors, or adjacent wall panels. These forms and braces serve two purposes: to function as forms for the cast-in-place structural grout/concrete mix for the IMS, and to plumb and temporarily and safely brace and shore the wall systems, and allows for planks to safely bear on panel walls. The forms and braces hold the panels in an arrangement that is in accordance with the floor plan. One of the key factors of the system is the monolithic casting of the entire Internal/Integral Monolithic Structure Superstructure at one time. The forms sandwich the ends of the panels (one form on the outside face and one on the inside face) and are held in place with through-wall form ties at each horizontal panel joint. The form ties can be re-usable or disposable snap ties, or re-usable She-Bolt, Wing-Nut or other removable through wall or sleeved tie. The forms are specifically designed with elongated and oversized form tie holes at panel joint locations to accommodate a limited amount of field tolerance deviations, and to allow the walls to be re-plumbed after the panels are in erected. This is important because the floor and roof planks can be cut to size at the factory, and the bearing requirements for the end of the panels is specific. Field adjustment capabilities are needed to make sure that the distance between the tops of the bearing walls is exact. Plumbing, temporarily and safely bracing, and shoring the wall systems allows erection of the wall panels and floor planks continuously without interruption, and without the use and cost of a permanent external superstructure. As shown in
[0050] Specific pre-erection tasks are undertaken to prepare the area. Wall panels 101 are tongue and groove to allow precise edge-to-edge fit and alignment. Some field fashioning and panel prep is required to accommodate the form ties 103 that pass through the walls at the panel joints 203, and panel ties 805 that connect panel ends to adjacent panels or to the integral column. Wall panels 101 arrive at the job site, reverse staged on delivery vehicles. The preferred method is to set the panels 101 and planks 1201 directly from a truck even if it requires using 2 cranes to expedite unloading. Not all site conditions will allow this. The wall panels 101 can be set on edge horizontally, with a gap of 6-10 between the ends of the panels. This gap can eventually form the integral column element 307 of IMS (see
[0051] The vertical structural forms 401 have form ties 103 at four locations at each panel joint 203 and additional locations on walls that require intermediate anti-buckling bracing (see
[0052] Once panel setting & erection (preliminary cutting, pre-drilling, trimming, etc.) for the panel ties 805, form ties 103 & anchors/fasteners 1301 has been completed, and a panel tie 805 is connected to one end of the panel 101, the panel 101 is hoisted to its final placement location in the system. Another worker can receive and guide the panel into place. That same worker can also: install form ties 103 at the ends of the panels; install form ties 103 at the locations of the intermediate anti-buckling bracing where needed; attach the loose end of the panel tie 805 on this panel 101, to the previously set panel on the opposite side of the gap; top panel-install form tie or perforated strap or sleeve for removable/reusable form tie; secure the outer form ties 103 with compatible form-tie ends (wale, wing nuts, or other base that allows minor adjustment and minor wall width fluctuations); secure and tighten the form tie 103 on the lower edge of the wall panel; install intermediate anti-buckling bracing/stiffeners 401/shoring struts 107/anchors 109 at midspan locations when/where there is a possibility of wall buckling (see
[0053] Floor plank erection and setting may be seen in
[0054] The deformed and post-tension reinforcing steel is set/installed and any miscellaneous detailing is completed. Lay and chair reinforcing per that manufacturer's and/or structural engineer's requirements. Install perimeter reinforcing steel in the perimeter beams. Lay WWF if there is any possibility that the concrete topping 1705 may develop cracks. Reinforce openings as detailed by engineer. Install other imbedded devices, shoring/bracing anchors, davits, etc.
[0055] Remaining wall perimeter beam forms are installed. Fastener cleats 1303 on the face of the walls a distance below the top edge of the walls to support the perimeter beam form boards (as seen in the sectional view of
[0056] One or more additional levels can be added to the building by repeating the above steps with further sets of planks and panels on top of the first level built. Additional levels can be the same size as the first level or a different size. If the additional level is the same size as the first level, the additional level walls can be placed at the point where the first level vertical walls meet the horizontal surface formed by the planks.
[0057] Place structural grout or small aggregate concrete mix. Consolidate, vibrate, and finish per engineering requirements. Allow concrete to cure to minimum required strengths. Mix strength of the concrete may be determined by the engineer. Roof pours are given a crown and slope of approximately 1/16 to per ft to allow proper drainage.
[0058] Forms, bracing, shoring, removable anchors and struts are removed. Concrete is patched, additional thin AAC cladding is applied over exposed concrete to provide added insulation and a uniform surface for applied finishes.
[0059] Further embodiments of the invention depicted in
[0060]
[0061] Each of the wall sections 1805 can be comprised of horizontally-stacked panels 101 (only the topmost of which can be seen in
[0062] As with the embodiments of
[0063] In the example depicted in
[0064] At the corners of the walled structure 1800, there are intentional gaps 1817 between the panel 101 ends of approximately 6-10 inches, that will eventually be filled with concrete to become the corner concrete column elements of the superstructure of the IMS). Where greater strength of the column elements is desired, such as for a commercial building or a multi-level structure, the corner gaps 1817 can be made larger to any degree desired or required by strength requirements.
[0065] The gaps 1810 and 1817 are partially enclosed by the opposed ends of the panels 101 forming wall sections 1805. To complete closure of the sides of the gaps 1810 and 1817, forms 201 and/or 901 can be placed at the inside and outside sides of the remaining open areas of mid-wall gaps 1810 and corner gaps 1817 to form a closed-at-the-sides and open-at-the-top gap. Forms 201 and 901 can be the same construction as the examples depicted in
[0066] As depicted in
[0067] As shown, the ends of the panels 101 of the demising wall section 1805 partially enclose an inside-facing portion of the gaps 1810, the remaining sides of the gaps being closed by forms such as forms 201 and/or 901. These forms are maintained in place by, for example, ties 103 and/or snap-ties 305, not shown in
[0068] Of course, using the same technique, any number of arrangements of external walls sections 1805 and/or demising wall sections 1805 can be employed to form a great variety of shapes and sizes for the walled structure, not limited to the rectangular shape and single demising wall depicted.
[0069] Turning now to
[0070] As depicted, planks 1201 can be placed with their ends extending over a portion of the two external wall sections 1805 forming the long sides of the walled structure 1800 for support during construction and thereafter. At the short sides of the rectangular structure, the nearest edge of the planks 1201 nearest the short side wall sections 1805 can be placed on or near the upper edge of the of the short side wall sections 1805. Similarly, in the interior of the structure, at the demising wall 1805, the nearest edge of the planks 1201 nearest the demising wall 1805 can be placed on or near the upper edge of the of the demising wall 1805.
[0071]
[0072] For clarity and simplicity,
[0073]
[0074] Load-bearing beam 1203 includes longitudinal rebar or tension cable members 1701, like those depicted in
[0075] The cup-shaped rebar members 2020 include upwardly extending rebar elements 2025 that have upper ends that terminate just below upper side of the planks 1201, and not so high that their upper ends will extend through the concrete topping 1705 forming the floor or ceiling.
[0076] Load-bearing beams 1203 can be positioned without a wall 1805 beneath them, as depicted in
[0077] Load bearing beams 1203 can also be positioned over any of the walls 1805, including the demising wall 1805 or side walls 1805, as depicted in, for example,
[0078]
[0079] As depicted in
[0080]
[0081] Since, as depicted, the concrete would not yet be fully cured, a longitudinal cup-shaped soffit form 1601 supports the still-uncured concrete beam 1203. The soffit 1601, in turn, is supported by a strut 107, until the concrete has cured. When the concrete is cured, soffit 1601 and strut 107 can then be removed.
[0082] When the concrete is cured, the inverted T-shaped beam 1203 is stronger than the shapes of the beams 1203 and 1203 depicted in
[0083]
[0084]
[0085]
[0086]
[0087] The foregoing embodiments of
[0088] Except to the extent of the distinctions specifically described for the embodiments of
[0089] Although the present disclosure and its advantages have been described in detail, it should be understood that various changes, substitutions and alterations can be made herein without departing from the spirit and scope of the disclosure as defined by the appended claims. Moreover, the scope of the present application is not intended to be limited to the particular embodiments of the process, machine, manufacture, composition of matter, means, methods and steps described in the specification. As one of ordinary skill in the art will readily appreciate from the disclosure, processes, machines, manufacture, compositions of matter, means, methods, or steps, presently existing or later to be developed that perform substantially the same function or achieve substantially the same result as the corresponding embodiments described herein may be utilized according to the present disclosure. Accordingly, the appended claims are intended to include within their scope such processes, machines, manufacture, compositions of matter, means, methods, or steps.