Method and Apparatus for Producing a Synthetic Tensile Member with a Precise Length and Enhanced Stability
20170356133 · 2017-12-14
Inventors
Cpc classification
F16G11/02
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
D07B7/022
TEXTILES; PAPER
F16G11/146
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
D07B1/02
TEXTILES; PAPER
International classification
D07B9/00
TEXTILES; PAPER
Abstract
A method for producing a synthetic tensile member having a precisely known and stable length. The invention, also comprises equipment configured to carry out the method. A tensile member is prepared by attaching terminations to an assembly of synthetic filaments. The tensile member is then attached to a loading apparatus that subjects the tensile member to a pre-defined loading process. The tensile member is thereby conditioned to a stable length. The length is then measured and a length adjusting component is incorporated into the tensile member to create a precise and stabilized length that is configured for the tensile member's particular application.
Claims
1. A method for producing a synthetic tensile member assembly having a precise and stable length for application across a known distance, comprising: a. providing a synthetic tensile member having a first end and a second end; b. providing a first termination on said first end, said first termination having a first attachment reference; c. providing a second termination on said second end, said second termination having a second attachment reference; d. whereby said synthetic tensile member, said first termination, and said second termination are united to form said synthetic cable assembly; e. applying a predetermined tension profile to said synthetic cable assembly in order to set a stable overall length between said first and second attachment references; f. determining said stable overall length between said first and second attachment references; and g. adding a length-adjustment component to said second termination in order to create a third attachment reference so that a length between said first and third attachment references matches said known distance.
2. The method for producing a synthetic tensile member assembly as recited in claim 1, wherein said length-adjustment component comprises an extension link added to said second termination.
3. The method for producing a synthetic tensile member assembly as recited in claim 1, wherein said length-adjustment component comprises: a. providing an extended tang on said second termination; and b. providing said third attachment reference on said extended tang.
4. The method for producing a synthetic tensile member assembly as recited in claim 1, wherein: a. said second termination includes a thimble with an open center; and b. said length-adjustment component comprises a thimble block with a cross bore.
5. The method for producing a synthetic tensile member assembly as recited in claim 1, wherein: a. said second termination includes a threaded shaft; and b. said length-adjustment component comprises an extension bushing placed on said threaded shaft, with said extension bushing including a bearing surface.
6. The method for producing a synthetic tensile member assembly as recited in claim 1, wherein: a. said second termination includes an eye with a first cross bore; and b. said length-adjustment component comprises a plug configured to fit in said first cross bore, said plug including an offset second cross bore.
7. The method for producing a synthetic tensile member assembly as recited in claim 1, wherein: a. said second termination includes a thimble with an open center; and b. said length-adjustment component comprises an extension link connected to said thimble.
8. The method for producing a synthetic tensile member assembly as recited in claim 1, wherein: a. said second termination includes a posterior bearing surface; and b. said length-adjustment component comprises a bushing installed against said posterior bearing surface.
9. The method for producing a synthetic tensile member assembly as recited in claim 1, wherein: a. said second termination includes a posterior bearing surface; and b. said length-adjustment component comprises a correction block having an overhang configured to bear against said posterior bearing surface.
10. The method for producing a synthetic tensile member assembly as recited in claim 1, further comprising: a. providing a third and fourth termination between said first and second terminations; and b. attaching said length-adjustment component between said third and fourth terminations.
11. A method for producing a synthetic tensile member assembly having a precise and stable length for application across a known distance, comprising: a. providing a synthetic tensile member having a first end and a second end; b. providing a first termination on said first end, said first termination having a first attachment reference; c. providing a second termination on said second end, said second termination having a second attachment reference; d. whereby said synthetic tensile member, said first termination, and said second termination are united to form said synthetic cable assembly; e. applying multiple pulls to said synthetic cable assembly in order to set a stable overall length between said first and second attachment references; f. determining said stable overall length between said first and second attachment references; and g. adding a length-adjustment component to said second termination in order to create a third attachment reference so that a length between said first and third attachment references matches said known distance.
12. The method for producing a synthetic tensile member assembly as recited in claim 11, wherein said length-adjustment component comprises an extension link added to said second termination.
13. The method for producing a synthetic tensile member assembly as recited in claim 11, wherein said length-adjustment component comprises: a. providing an extended tang on said second termination; and b. providing said second attachment reference on said extended tang.
14. The method for producing a synthetic tensile member assembly as recited in claim 11, wherein: a. said second termination includes a thimble with an open center; and b. said length-adjustment component comprises a thimble block with a cross bore.
15. The method for producing a synthetic tensile member assembly as recited in claim 11, wherein: a. said second termination includes a threaded shaft; and b. said length-adjustment component comprises an extension bushing placed on said threaded shaft, with said extension bushing including a bearing surface.
16. The method for producing a synthetic tensile member assembly as recited in claim 11, wherein: a. said second termination includes an eye with a first cross bore; and b. said length-adjustment component comprises a plug configured to fit in said first cross bore, said plug including an offset second cross bore.
17. The method for producing a synthetic tensile member assembly as recited in claim 11, wherein: a. said second termination includes a thimble with an open center; and b. said length-adjustment component comprises an extension link connected to said thimble.
18. The method for producing a synthetic tensile member assembly as recited in claim 11, wherein: a. said second termination Includes a posterior bearing surface; and b. said length-adjustment component comprises a bushing installed against said posterior bearing surface.
19. The method for producing a synthetic tensile member assembly as recited in claim 11, wherein: a. said second termination includes a posterior bearing surface; and b. said length-adjustment component comprises a correction block having an overhang configured to bear against said posterior bearing surface.
20. The method for producing a synthetic tensile member assembly as recited in claim 11, further comprising: a. providing a third and fourth termination between said first and second terminations; and b. attaching said length-adjustment component between said third and fourth terminations.
Description
BRIEF DESCRIPTION OF THE SEVERAL VIEWS OF THE DRAWINGS
[0029]
[0030]
[0031]
[0032]
[0033]
[0034]
[0035]
[0036]
[0037]
[0038]
[0039]
[0040]
[0041]
[0042]
[0043]
[0044]
[0045]
[0046]
REFERENCE NUMERALS IN THE DRAWINGS
[0047] 10 cable
[0048] 12 strand
[0049] 18 anchor
[0050] 19 passage
[0051] 20 potted region
[0052] 22 collector
[0053] 24 load transferring feature
[0054] 26 receiver
[0055] 28 jacket
[0056] 30 cable assembly
[0057] 32 loading block
[0058] 34 parallel assembly
[0059] 36 termination
[0060] 38 loading fixture
[0061] 40 static fixture
[0062] 42 extension link
[0063] 44 first cross bore
[0064] 45 first attachment reference
[0065] 46 second cross bore
[0066] 47 second attachment reference
[0067] 48 tang
[0068] 50 pin
[0069] 52 first clevis
[0070] 54 second clevis
[0071] 56 extended tang
[0072] 58 reference axis
[0073] 60 cross bore
[0074] 62 thimble
[0075] 64 strands
[0076] 66 jacket
[0077] 68 thimble block
[0078] 70 threaded shaft
[0079] 72 extension bushing
[0080] 74 mating surface
[0081] 76 bearing surface
[0082] 78 through bore
[0083] 80 fusion
[0084] 82 eye
[0085] 84 cross bore
[0086] 86 plug
[0087] 88 offset cross bore
[0088] 90 spliced eye
[0089] 92 bushing half
[0090] 94 correction block
[0091] 96 overhang
DETAILED DESCRIPTION OF THE INVENTION
[0092] A cable made according to the present invention will generally have a first termination on its first end and a second termination on its second end. The first termination will have a first attachment reference—such as the center axis of a first cross bore through the first termination. The second termination will likewise have a second attachment reference—such as the center axis of a second cross bore through the second termination.
[0093] Returning to
[0094]
[0095] The second termination is attached to loading fixture 38. A predetermined tension profile is then applied through loading fixture 38. Second attachment reference 47 on the second termination is the center line of a pin joint used to attach the second termination to loading fixture 38 (Note that the second attachment reference could be at some other point along the assembly and need not coincide with the attachment point).
[0096] This tension profile may assume many forms, but it is preferable to include a pull test to a higher load than is anticipated in the end-use application. Where practical, it is also preferable to include multiple pulls to better condition the cable.
[0097]
[0098] The tension profile is configured to fully “bed” (“set”) both the terminations and the lay of the cable itself. The length of the overall assembly will tend to extend for some period and then stabilize. Once the length has stabilized, the distance between the first attachment reference on the first termination and the second attachment reference on the second termination is determined. Two carefully pre-cut and terminated cable assemblies may have lengths that are very nearly the same. However, the length variation will tend to grow with the bedding process.
[0099] This step may be accomplished in many ways. As one example, if the first and second attachment references are simple cross bores through tangs on the terminations, then closely fitted dowels can be placed in these cross bores. The assembly can then be placed under a suitable tension level and the distance between the dowels can be measured.
[0100] In many instances it will be desirable to design the cable and terminations so that the bedded cable assembly winds up being a bit short. A length-adjustment component may then be added to bring the overall assembly of the now-stabilized cable to the proper length. There are many ways to provide such a length-adjustment component. The following embodiments illustrate some of these ways.
[0101]
[0102] Extension link 42 is provided to increase the effective length of the cable assembly. The extension link includes first clevis 52 and second clevis 54. The extension link also includes first cross bore 44 and second cross bore 46. First cross bore 44 is aligned with the cross bore in tang 48 and pin 50 is inserted to connect the extension link to the second termination. Second cross bore 46 is offset a distance “D” from first cross bore 44. In this example the second cross bore 46 becomes a third attachment reference. If one then measures the distance from the first attachment reference (on the opposite end of the cable) and the new third attachment reference created by the presence of second cross bore 46, the overall length of the cable will be increased.
[0103] To improve accuracy, it is preferable to take the length measurements while the cable assembly is under a fixed reference load. The reference load is preferably as close as possible to the load anticipated for the end-use application.
[0104] The process as applied in this exemplary embodiment may then be summarized as follows:
[0105] 1. A known distance is the target value needed for the cable's desired installation at the anticipated reference load;
[0106] 2. The cable is created with an overall length that is marginally too short for the known distance and defined reference load;
[0107] 3. The cable undergoes the setting process depicted in
[0108] 4. The distance between the first and second attachment references is accurately determined;
[0109] 5. An offset distance between the second attachment reference and a desired third attachment reference is calculated; and
[0110] 6. An extension link 42 of suitable length is manufactured (or possibly pulled from inventory) and attached to the second termination, where the extension link provides the additional distance needed for the cable to have the correct overall length.
[0111] Using exemplary numbers, the known distance for a particular installation is 30.260 meters. Once manufactured and set (as depicted in
[0112]
[0113]
[0114]
[0115]
[0116] Up to this point the second and third attachment references have been the centerlines of cross bores. This will not always be the case, as there are many different components used to attach terminations to external components.
[0117] The second termination 36 in this example includes a long threaded shaft 70. The cable assembly is attached to an external object by passing threaded shaft 70 through a hole in a thick steel plate and then threading a nut onto the exposed end of the threaded shaft. The nut is then tightened. Bearing surface 76 on termination 36 provides the desired second attachment reference.
[0118] In this example—once the cable assembly is set as shown in
[0119] The mated assembly is shown in
[0120]
[0121]
[0122] In the prior examples a cable that was marginally too short was extended by the addition of a length-adjustment component. In other instances the cable will be made marginally too long and the length-adjustment component will need to shorten its effective length.
[0123]
[0124] In the preceding examples the length-adjustment component has been added to an end of the cable assembly. It is also possible to add the length-adjustment component to an intermediate location.
[0125] Cables have been used as the examples in this disclosure, but the reader should bear in mind the fact that the principles disclosed apply to many other types of tensile members. These include synthetic rope/cable/cord grommets, choked assemblies, reeved block assemblies, and looped slings or pendants where a loop of filaments, strands, or cables are wound around two end points, and the two end points thereby become terminations.
[0126] Additionally, the inventive process is not specific to the termination type/method or length correction component. The examples are merely meant to represent a design based on certain termination configurations. These designs are not to be viewed as limiting, like that of the tensile member, they will vary broadly from application to application—and countless variations are possible.
[0127] The invention includes many other functional variations that are assumed throughout the examples, such as:
[0128] 1. An embodiment in which a length-adjustment component is added to both ends of the cable. In many applications this is preferable and should be assumed to be the case in all embodiments in this disclosure. The simplified depiction of a second termination receiving a length adjustment feature is simply meant to assume that at least one end, if not both ends receive such a component;
[0129] 2. An embodiment in which multiple length-adjustment components are “stacked” or otherwise configured for use on at least one end of the cable;
[0130] 3. An embodiment in which the length-adjustment component is simply a modification of a component already on the cable (such as milling away a final load bearing surface or drilling a cross bore hole on the termination body itself as examples);
[0131] 4. An embodiment in which the length-adjustment component is tamper resistant so that it cannot be easily modified in the field;
[0132] 5. An embodiment in which the length-adjustment component is made visibly out of alignment should it be out of factory setting;
[0133] 6. A configuration in which adjustment is possible in both directions, such that a tensile member can be made at the target length, and length correction can be designed to be either shorter or longer. (For example, the cable length and bushing halves 92 in
[0134] 7. An embodiment in which the inventive process and length adjustment component is made to the strand or sub-rope of a larger tensile member. In most eases this would include similar length adjustment components with all or most of the loaded subcomponents. This can be used to balance subcomponents within a large assembly, just as if they were individual tension members requiring matched and stable lengths.
[0135] Although the preceding description contains significant detail, it should not be construed as limiting the scope of the invention but rather as providing illustrations of the preferred embodiments of the invention. Those skilled in the art will be able to devise many other embodiments that carry out the present invention. Thus, the language used in the claims shall define the invention rather than the specific embodiments provided.