MANUFACTURING PROCEDURE FOR CEILING TRIMS FOR VEHICLES
20170334102 · 2017-11-23
Inventors
- Miguel Ángel Grande (Burgos, ES)
- Javier Merino (Burgos, ES)
- José Ignacio Palomino (Burgos, ES)
- Fernando Salazar (Burgos, ES)
Cpc classification
B32B38/1866
PERFORMING OPERATIONS; TRANSPORTING
B29C51/082
PERFORMING OPERATIONS; TRANSPORTING
B29K2475/00
PERFORMING OPERATIONS; TRANSPORTING
B29K2105/0097
PERFORMING OPERATIONS; TRANSPORTING
International classification
B29C39/12
PERFORMING OPERATIONS; TRANSPORTING
B60R13/02
PERFORMING OPERATIONS; TRANSPORTING
Abstract
A manufacturing procedure for ceiling trims for vehicles, the structure of which comprises at least one first coating sheet and at least one second coating sheet that extend along one of the sides of the first sheet, joined via a layer of heat-stable polyurethane adhesive, comprising a step of applying a gas-phase catalyst on such sheets through a thermoforming mould that starts before the mould is completely closed and ends before the mould is completely opened. As a result of said application of a gas-phase catalyst we prevent the use of demoulding agents to facilitate extraction of the ceiling trim formed inside the mould.
Claims
1. A manufacturing procedure for ceiling trims for vehicles comprising the following steps: a)arranging a layer “sandwich” (1) formed by at least one first sheet (1.1) a second coating sheet (1.2) that covers one of the sides (1.1.1) of the first sheet (1.1) and a first layer of unactivated heat-stable polyurethane adhesive (1.3) between said at least first sheet (1.1) and said second coating sheet (1.2) in order to join them, b)introducing said sandwich (1) inside a hot thermoforming mould (2) comprising a first half of the mould (2.1) and a second half of the mould (2.2), the temperature of which lies in the range between 100 and 150° C., c)applying a gas-phase catalyst (3.3) on the sandwich (1) through the first half of the mould (2.1) that is in contact with the second coating sheet (1.2) with a pressure of more than 2 bar, d)closing the thermoforming mould (2) and thus applying pressure on the sandwich (1), p1 e)opening the mould (2) for the evacuation of any excess moisture in the sandwich (1) as excess gas, f)closing the mould (2) to complete the curing of the first layer of heat-stable polyurethane adhesive, g)opening the mould (2) and extracting the ceiling trim (10), wherein Step c) is started before the end of Step d) wherein Step c) ends before the end of Step e), and wherein Step d), once Step c) has started, is performed by maintaining the introduction of the gas-phase catalyst (3.3) at a pressure of more than 2 bar through the first half of the mould (2.1) and maintaining the circulation of the gas-phase catalyst (3.3) through the sandwich (1).
2. A manufacturing procedure for ceiling trims for vehicles according to claim 1 wherein the second coating sheet (1.2) is a non-decorative or a decorative coating sheet.
3. A manufacturing procedure for ceiling trims for vehicles according to claim 1 wherein the sandwich (1) comprises a third decorative or non-decorative coating sheet (1.4) that covers the other side (1.1.2) of the first sheet (1.1) and a second layer of heat-stable polyurethane adhesive (1.5) between them to join them together.
4. A manufacturing procedure for ceiling trims for vehicles according to claim 3 wherein the application of the gas-phase catalyst (3) is also performed through the second half of the mould (2.2) in contact with the third decorative or non-decorative coating sheet (1.4).
5. A manufacturing procedure for ceiling trims for vehicles according to claim 1 wherein the first sheet (1.1) is part of an assembly formed by several superimposed sheets (1.1, 1.6, 1.7).
6. A manufacturing procedure for ceiling trims for vehicles according to claim 1 wherein the pressure of the gas-phase catalyst in Steps c) and d) is equal to or less than 15 bar.
Description
DESCRIPTION OF THE FIGURES
[0022] This specification is supplemented with a set of figures illustrating the preferred embodiment, which are never intended to limit the invention.
[0023]
[0024]
[0025]
[0026]
[0027]
DETAILED DESCRIPTION OF THE INVENTION
[0028] We shall now detail the sequence of steps shown in
[0029] The first step, step a) comprises arranging a layer “sandwich” (1) formed by at least one first sheet (1.1) a second coating sheet (1.2) that covers one of the sides of the first sheet (1.1) and a first layer of unactivated heat-stable polyurethane adhesive (1.3) between said at least first sheet (1.1) and said second coating sheet (1.2) in order to join them.
[0030] The term “unactivated” relates to a state of the heat-stable polyurethane adhesive in which the chemical reaction, which results in its curing in a reasonable time corresponding to the usual time cycles in a ceiling trim manufacturing procedure, cannot occur.
[0031] In the particular case of heat-stable polyurethane adhesives contemplated by the invention, it refers to an adhesive to which the corresponding catalyst has not been added, which is a necessary component in order to produce its activation, in a previous step to step b) of introducing the layered sandwich (1) inside the mould (2).
[0032] The following step of the procedure, step b) comprises introducing the sandwich (1) inside a hot thermoforming mould (2) comprising a first half of the mould (2.1) and a second half of the mould (2.2), the temperature of which lies in the range between 100 and 150° C.
[0033] In order to perform the opening and closing movements of said mould (2), at least one of the halves of the mould (2.1, 2.2) can move between a first position in which the halves (2.1, 2.2) of the mould (2) are at a maximum separation, the mould (2) thus being completely open, and a second position in which the mould (2) is completely closed.
[0034] Thus, when the halves (2.1, 2.2) of the mould (2) reach said first position the step of opening the mould (2) would be complete, and when the halves (2.1, 2.2) of the mould (2) reach the second position the step of closing the mould (2) would be completed.
[0035] Once the sandwich (1) in introduced inside a mould (2), step c) of the procedure is carried out, which comprises the application of a gas-phase catalyst (3.3).
[0036] Said gas-phase catalyst (3.3) may be for example, steam, DABCO® (trademark of Air Products & Chemicals), diluted in water as a gas phase, an organometallic compound such as DBTL (dibutyl tin dilaurate) diluted in water as a gas phase or a diluted in water as a gas phase.
[0037] The beginning of this step c) is performed before the completion of step d), which comprises the closing of the mould (2), and the end of step c) is performed before the completion of step e), comprising the opening of the mould (2) to evacuate any excess moisture.
[0038] We must take into account that step d) of closing the mould (2) starts with the beginning of the movement of bringing the two halves (2.1, 2.2) of the mould (2) together and ends when said movement stops, resulting in the closing of the mould (2); and step e) of opening the mould (2) starts when the movement of separating the two halves (2.1, 2.2) of the mould (2) starts and ends when said movement stops, resulting in a completely open mould (2).
[0039] Therefore, the beginning of the application of the gas-phase catalyst can be performed: [0040] before the start of step d) of closing the mould (2), that is, before the start of the movement of bringing the halves (2.1, 2.2) of the mould (2) together to produce the closing of the mould (2), [0041] after having started step d) of closing the mould (2), that is, before the start of the movement of bringing the halves (2.1, 2.2) of the mould (2) together to produce the closing of the mould (2), [0042] or simultaneously at the beginning of step d) of closing the mould (2), that is, when initiating the movement of bringing together the halves (2.1, 2.2) of the mould (2) to produce the closing of the mould (2). Regarding the end of the application of the gas-phase catalyst (3.3), this can be performed: [0043] before the end of step d) of closing the mould (2), that is, during the movement of bringing the halves (2.1, 2.2) of the mould (2) together to produce the closing of the mould (2), [0044] after the end of step d) of closing the mould (2), that is, once the movement of bringing the halves (2.1, 2.2) of the mould (2) together to produce the closing of the mould (2) is completed, [0045] after the start of step e) of opening the mould (2) to evacuate any excess moisture, that is, during the movement of separating the two halves (2.1, 2.2) of the mould (2) to produce the opening of the mould (2), [0046] or simultaneously to any of the last two options, that is, either at the end of the movement of bringing together the two halves (2.1, 2.2) of the mould (2) which produces the closing of the mould (2), or at the beginning of the movement of separating the two halves (2.1, 2.2) of the mould (2) that causes the opening of the mould.
[0047] In order to carry out the application of the gas-phase catalyst (3.3), the mould (2) comprises means (3) for applying the gas-phase catalyst that in turn comprise means (3.1) for generating the gas-phase catalyst (3.3), and conducts (3.2) provided therein that allow transporting the gas-phase catalyst (3.3) from the means (3.1) for generating the gas-phase catalyst to the interior of the mould (2).
[0048] The application of the gas-phase catalyst (3.3) is performed through the first half of the mould (2.1) that is in contact with the second coating sheet (1.2).
[0049] According to a variant of the invention, as shown in
[0050] The application of the gas-phase catalyst (3.3) on the sandwich (1) results in the activation of the adhesive forming part of the first heat-stable polyurethane adhesive layer (1.3) as a result of the effect of the gas-phase catalyst (3.3).
[0051] Moreover, said application of the gas-phase catalyst (3.3) is performed with sufficient pressure to allow said gas-phase catalyst (3.3) to access the entire heat-stable polyurethane adhesive and thus allow its activation. Said pressure is greater than the atmospheric pressure and particularly 2 bars, and in a specific case it is in a range between 2 and 15 bar.
[0052] Moreover, the application of the gas-phase catalyst (3.3)results in the creation of a barrier between the first heat-stable polyurethane adhesive layer (1.3) and the surface (2.1.1) forming the first half of the mould (2) as a result of the pressure exerted by the gas-phase catalyst (3.3) on the first layer of heat-stable polyurethane adhesive (1.3).
[0053] Finally, and as shown in detail D represented in
[0054] In the variant shown in
[0055] This variant therefore contemplates a sandwich the structure of which also consists of a third coating sheet (1.4) joined to the other side of the first sheet (1.1) via a second heat-stable polyurethane adhesive layer (1.5), as shown in the examples represented in
[0056] Step d) is then performed, comprising the closing of the thermoforming mould (2) and thus the application of pressure on the sandwich (1). This step d), once step c) is started, is performed by maintaining the introduction of the gas-phase catalyst (3.3) at a pressure of more than 2 bar through the first half of the mould (2.1) and maintaining the circulation of the gas-phase catalyst (3.3) through the sandwich (1).
[0057] Said pressure of the gas-phase catalyst (3.3) results in the discharge thereof from inside the mould (2) as shown in
[0058] Due to the barrier formed by the curing of a part (1.3.1) of the adhesive corresponding to the heat-stable polyurethane adhesive layer (1.3), said adhesive cannot pass through the second coating sheet (1.2) and therefore cannot reach the surface (2.1.1) corresponding to the first half of the mould (2.1).
[0059] After step d) comes step e), comprising the opening of the mould (2) to evacuate any excess moisture from the sandwich (1) as excess gas in order to prevent the occurrence of moisture in the sandwich (1) as a result of the excess of gas-phase catalyst (3.3) applied thereto.
[0060] Step f) is then performed, comprising closing the mould (2) to complete the curing of the first heat-stable polyurethane adhesive layer (1.3), or of said first heat-stable polyurethane adhesive layer (1.3) and the second heat-stable polyurethane adhesive layer (1.5) according to the variant contemplated in
[0061] Finally, in order to complete the procedure we have step g), comprising the opening of the mould (2) and the extraction of the ceiling trim (10) with its final shape and all of the cured adhesive.
[0062] Regarding the configuration of the structure of sheets and layers making up the sandwich (1),
[0063] The first of these represented in
[0064] The first sheet (1.1), as shown in the example represented in
[0065] The second coating sheet (1.2) may comprise a non-decorative coating or a decorative coating.
[0066] The sandwich may also comprise, as shown in