SUBSEA FLOWMETER CONNECTOR ASSEMBLY
20170328163 ยท 2017-11-16
Inventors
- Alireza Shirani (Houston, TX, US)
- Marcus Lara (Cypress, TX, US)
- Akshay Kalia (Houston, TX, US)
- Gustavo Gonzalez (Cypress, TX, US)
- Randy Kimberling (Houston, TX, US)
Cpc classification
E21B43/013
FIXED CONSTRUCTIONS
International classification
E21B33/038
FIXED CONSTRUCTIONS
E21B43/017
FIXED CONSTRUCTIONS
Abstract
A subsea connector assembly with flowmeter incorporated therein. The assembly is particularly configured for securing a flexible flowline at subsea production managing hardware such as at a manifold at a seabed or Christmas tree at a well head. Incorporating a flowmeter into the connector as opposed to such comparatively larger scale hardware ultimately saves substantial material, transport, installation, footspace and other costs.
Claims
1. A subsea connector assembly for use at a subsea oilfield below a sea surface, the assembly comprising: a landing base for fluidly coupling to a subsea production managing hardware at the oilfield to receive production therefrom; an extension for fluidly coupling to a flexible flowline to accommodate the production toward the surface; and a flowmeter fluidly coupled to each of the base and extension for monitoring a flow of the production therethrough.
2. The subsea connector assembly of claim 1 wherein the flowmeter is one of a single phase flowmeter, a multi-phase flowmeter, a gamma ray flowmeter and a venturi flowmeter.
3. The subsea connector assembly of claim 1 wherein the flowmeter includes a housing configured to support production fluid processing.
4. The subsea connector assembly of claim 1 wherein the flowmeter is located at a separable joint between the base and the extension.
5. The subsea connector assembly of claim 1 wherein the extension is a gooseneck extension with a termination for securing the coupling.
6. The subsea connector assembly of claim 5 further comprising a support with a first end coupled to the gooseneck extension and a second end coupled to the base.
7. An oilfield system comprising: a first production managing structure; a second production managing structure; a flexible flowline for carrying production from the first structure to the second; and a flowmeter equipped connector assembly for fluidly coupling an end of the flexible flowline to one of the first and second production managing structures.
8. The oilfield system of claim 7 wherein the production managing structures are selected from a group consisting of a manifold, a Christmas tree, a pipeline, a pipeline end termination and a pipeline end manifold.
9. The oilfield system of claim 8 wherein the first production managing structure is a Christmas tree for directing the production from a specific well over the flexible flowline to the second production managing structure, the second production managing structure being a manifold for combining the production from the specific well with production from other wells.
10. The oilfield system of claim 7 wherein the end of the flexible flowline is a first end and the flowmeter equipped connector assembly is coupled to the first production managing structure, the system further comprising another connector assembly coupled to a second end of the flexible flowline for fluid coupling to the second production managing structure.
11. The oilfield system of claim 10 wherein the other connector assembly includes one of a flowmeter and a separable joint to optionally accommodate a flowmeter.
12. A method of monitoring production fluid from a specific well in a group of wells at a seabed, the method comprising: installing a flowmeter equipped connector assembly at a production managing structure to fluidly couple a flexible flowline to the structure, the flexible flowline being dedicated to the specific well; and flowing production fluid from the specific well and through the flowmeter of the assembly before combining with production fluid from other wells of the group.
13. The method of claim 12 further comprising measuring the production fluid through the flowmeter for one of temperature, constitution, consistency, particulate and erosion during the flowing.
14. The method of claim 12 wherein the flowmeter is incorporated into a housing that additionally supports fluid processing of the production fluid.
15. The method of claim 14 wherein the additional fluid processing is one of pumping, gas injection, steam injection, chemical injection, chemical treatment, pressure boosting, water electrolysis, materials injection, gas separation, water separation, sand/debris separation, hydrocarbon separation and a processing with a fluid turbine.
16. The method of claim 12 wherein the production managing structure is one of a manifold and a Christmas tree at a well, the flowing of the production fluid comprising flowing production fluid from the Christmas tree to the manifold over the flexible flowline.
17. The method of claim 16 wherein the combining takes place at the manifold, the method further comprising directing the combined production fluid to surface away from the seabed.
18. The method of claim 12 further comprising: acquiring a subsea connector assembly with a base for coupling to the production managing structure, an extension for coupling to the flexible flowline and a seperable joint; separating flanges of the separable joint; and securing tubing of the flowmeter to each flange to equip the assembly with the flowmeter.
19. The method of claim 12 wherein the flowmeter is one of a single phase flowmeter, a multi-phase flowmeter, a gamma ray flowmeter and a veturi flowmeter.
20. The method of claim 12 wherein the production managing structure is selected from a group consisting of a manifold, a Christmas tree, a pipeline, a pipeline end termination and a pipeline end manifold.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0011]
[0012]
[0013]
[0014]
[0015]
[0016]
[0017]
[0018]
DETAILED DESCRIPTION
[0019] In the following description, numerous details are set forth to provide an understanding of the present disclosure. However, it will be understood by those skilled in the art that the embodiments described may be practiced without these particular details. Further, numerous variations or modifications may be employed which remain contemplated by the embodiments as specifically described.
[0020] Embodiments are described with reference to certain subsea operations utilizing a flowmeter equipped connector assembly. For example, operations in which a cluster of wells at a seabed are each fluidly coupled to a dedicated flowmeter equipped connector assembly before production is combined at a manifold is described. In the embodiment shown, this takes place at a tree over each well with production advancing through a flexible flowline to the manifold. However, a variety of different layouts may take advantage of the unique connector assembly as detailed herein. For example, the connectors may be positioned at the manifold on the other end of the flowline or at various points in between. Indeed, so long as a unique connector of comparatively reduced profile is utilized to accommodate the flowmeter in place of incorporating the flowmeter with the underlying tree, manifold or other large scale equipment, appreciable benefit may be realized.
[0021] Referring now to
[0022] Continuing with reference to
[0023] In the embodiment shown, base 140 and extension 130 flanges are provided for fluidly and securely connecting to lower 190 and upper 195 tubing hardware at either side of the noted flowmeter 150. The insertion of this intervening structure has an affect on the architecture and overall profile of the assembly 100. Therefore, in the embodiment shown, an added support 177 is provided for stabilizing the gooseneck extension 110 relative the base 175.
[0024] With added reference to
[0025] Referring now to
[0026] The above described reduction in size for the manifolds 200, 250 is achieved due to the disassociation flowmeters from the large scale manifold hardware. This is because when a flowmeter is incorporated directly into the host production structure, such as a manifold or tree, the flowmeter requires correspondingly large scale piping, frame support and other matching hardware. However, with added reference to
[0027] Continuing with reference to
[0028] Referring now to
[0029] The oilfield 201 accommodates embodiments of the reduced profile manifolds 200, 250 and connector assemblies 100 as depicted in
[0030] As a practical matter, this type of arrangement means that the production from each well may be tracked individually. This may be of benefit to operators monitoring production, for example, to track and make adjustments to operations where appropriate on a well by well basis. This also provides benefit where the wells are of differing ownership. That is, where collected production at the surface is to be allocated to different owners of different wells, it may be important to know, from an accounting perspective, which wells produced which amount of the production. Once more, this is achieved without the requirement of substantially enlarging the size of the trees (e.g. 375, 377, 380, 390) or the manifolds (e.g. 200 or 250) to accommodate incorporated flowmeters.
[0031] Continuing with reference to
[0032] It is worth noting that the assembly 100 is depicted at the trees 375, 377, 380, 390 in the embodiment shown. However, in other embodiments, the flowmeter equipped connector assembly 100 may instead be secured at the other end of the flexible line 300 (e.g. at the manifold 200, 250). By the same token, the assemblies 100 may work effectively through either vertical or horizontal connection. Furthermore, in other embodiments utilizing a different layout, the assemblies 100 may be secured to a hub at a pipeline, a pipeline end termination (PLET), a pipeline end manifold (PLEM) or other suitable subsea or even surface production equipment structure. So long as flowmetering is able to intervene through a connector 100 in advance of combining production from differing wells, appreciable benefit may be realized.
[0033] Referring now to
[0034] Referring now to
[0035] Referring now to
[0036] Referring now to
[0037] Whatever the sequence of installation, the use of the flowmeter equipped connector allows for the monitoring of production through the structure as noted at 580. More specifically, this monitoring takes place on a well by well or well specific basis prior to the combining of the production with production from any other well. Thus, in addition to efficiencies detailed hereinabove a reliable manner of production accounting takes place for each specific well.
[0038] Embodiments described above provide a new and unique form of subsea hardware that disassociates flowmeter functionality from large scale equipment that manages well production on a well by well or well specific basis. This allows for flowmeter functionality without dramatically increasing the size of manifolds, Christmas trees and other such equipment to accommodate a flowmeter. Thus, dramatic savings may be realized in equipment expenses as well as costs in terms of installation time.
[0039] The preceding description has been presented with reference to presently preferred embodiments. Persons skilled in the art and technology to which these embodiments pertain will appreciate that alterations and changes in the described structures and methods of operation may be practiced without meaningfully departing from the principle, and scope of these embodiments. Furthermore, the foregoing description should not be read as pertaining only to the precise structures described and shown in the accompanying drawings, but rather should be read as consistent with and as support for the following claims, which are to have their fullest and fairest scope.