Abstract
Disclosed invention comprises innovations in the fabrication process and the associated design methodology for producing refined prestressed concrete elements/components. The innovations disclosed are fabrication using multiple stages, the use of ultra high strength materials for only critical subcomponents, utilizing thinner sections made of ultra high strength materials, and a unique method of inducing and controlling camber. The embodiments of this invention enable the accelerated construction of concrete structures that are both durable and cost effective. This disclosure demonstrates the significant improvements to the prior art in the areas of durability, constructability, and cost reduction for prestressed concrete components. The embodiments presented in this disclosure are for bridge superstructure applications.
Claims
1. A method of reducing camber variance among beams during fabrication, the method comprising: applying prestress and/or post tension to a lower flange of a beam either before casting and curing of the lower flange and/or after the casting and curing of the lower flange, thereby forming a compressed lower flange of the beam; applying an external force to the compressed lower flange to introduce a first amount of camber, which is of the compressed lower flange; and during the applying of the external force, disposing a web of the beam on the compressed lower flange thereby resulting in a second amount of camber, which is of the beam.
2. The method of claim 1, wherein the applying of the prestress includes prestressing of strands of the lower flange.
3. The method of claim 1, wherein the applying of the post tension includes applying the post tension to tendons of the lower flange.
4. The method of claim 1, wherein the applying of the prestress to the lower flange of the beam does not apply prestress and/or post tension to the web of the beam.
5. The method of claim 1, wherein the disposing of the web further includes disposing a top flange of the beam on the compressed lower flange in the same process as the disposing of the web.
6. The method of claim 1, wherein the applying of the external force to the compressed lower flange includes applying the external force to about a centroid of the compressed lower flange.
7. The method of claim 1, further comprising: after the applying of the prestress and before the applying of the external force, shoring the compressed lower flange.
8. The method of claim 1, wherein the applying of the external force to the compressed lower flange includes setting the compressed lower flange to a desired geometric shape.
9. A method of reducing camber variance among beams during fabrication, the method comprising: applying prestress and/or post tension to a lower flange of a beam either before casting and curing of the lower flange and/or after the casting and curing of the lower flange, thereby forming a compressed lower flange of the beam; shoring the compressed lower flange of the beam; applying an external force to the compressed lower flange to set the compressed lower flange to a desired geometric shape and introduce a first amount of camber, which is of the compressed lower flange; and during the applying of the external force, disposing a web and a top flange of the beam on the compressed lower flange to form a completed beam thereby resulting in a second amount of camber, which is of the completed beam.
Description
DESCRIPTION OF DRAWINGS
[0017]
[0018] In
[0019]
[0020] Refer to
[0021]
[0022] Item 1ps is the Prestressing strands for applying precompression to Item 1.
[0023] Item 2if is the interface between UHPC and HPC within Item 2.
[0024] Item 2r is the reinforcement within Item 2.
[0025] Item 3bm is the bottom mat of reinforcement within Item 3.
[0026] Item 3tm is the top mat of reinforcement within Item 3.
[0027] Item 4bm is the projection of the 3bm into Item 4.
[0028] Item 4tm is the projection of the 3tm into Item 4.
[0029]
[0030] For identifications of Items 1, 2, 3 and 4 refer to
[0031] For identifications of Items 3tm, 3bm, 4tm and 4bm refer to
[0032]
[0033] This connection also utilizes field-cast UHPC, as well as an innovative shape that is part of this invention. This shape allows for faster installation and reduction of the amount of UHPC required per unit length of these connections.
[0034] For identifications of Items 1, 2, 3 and 4 refer to
[0035] For identifications of Items 3tm, 3bm, 4tm and 4bm refer to
[0036]
[0037] Thinner sections are used for the web and top flange of this embodiment. The innovation of utilizing ribs or stiffeners to increase the structural capacity of thin concrete components made of ultra high strength materials such as UHPC is demonstrated in this embodiment, which is not used in the first preferred embodiment HDBT. All subcomponents of GDBT are made using UHPC (or other similar materials.)
[0038] Item 1g is the Bottom Flange of the GDBT independently fabricated and prestressed before the Web and the Deck are added in the second stage of fabrication.
[0039] Item 2g is the thin web plate stiffened using Item 2gf web stiffeners.
[0040] Item 3gp is the thin deck plate stiffened transversely using Item 3gf (Plate Stiffeners), stiffened longitudinally along the edges of Item 3gp by Item 3eb (the Edge Beam) and longitudinally along the middle using 3bm (the Middle Beam).
[0041] 3tc is the Blackout for top connection and 3bc is the Blackout for bottom connection for use with connection shown in
[0042]
[0043]
[0044] Item 3cb is a Bolting System for applying compression into the Item 3cb epoxy-applied Mating Surface between the Item 3eb.
[0045]
[0046] Item 201 is the sides and bottom of the prestressing bed made using UHPC.
[0047] Item 202 is the Anchoring steel plate at the dead end of the prestressing system.
[0048] Item 201 is the Anchoring Steel Plate at the dead end of the prestressing system.
[0049] Item 201 Stressing steel plate for gang stressing of strands at the live end of the prestressing system.
[0050] Item 205 is the Stressing Jacks for gang stressing of strands at the live end of the prestressing system.
[0051]
[0052]
[0053] Item 1pt is the Tendons for post-tensioning and Item 1ptd is the Grouted Duct for post tensioning.
[0054]
[0055]
[0056]
[0057]
[0058]
[0059]
[0060]
[0061]
[0062]
[0063]
[0064]
[0065]
[0066]
[0067]
DETAILED DESCRIPTION OF THE EXEMPLARY EMBODIMENTS
[0068] This invention comprises innovations in the fabrication process of prestressed concrete components and associated changes in the design methodology that will significantly reduce, if not fully eliminate, inadequacies of the prior art. Included in this disclosure are descriptions of exemplary embodiments of these innovations and their utility in the areas of cost reduction, improved durability, and acceleration of on-site construction.
[0069] All descriptions herein with reference to the figures are not limiting and should be understood as features of varying details of the presented embodiment. The features, components, elements, and/or aspects of the illustrations can be reorganized, resequenced, and/or interchanged with other materials without effectively departing from the disclosed invention. The geometry of the components are also exemplary and can be altered without effectively affecting or limiting the disclosed invention. The drawings and associated descriptions of the preferred embodiments of the invention shall be treated as an example and is intended for making the invention readily apparent to those with ordinary skill in the art. The presentation of the preferred embodiments of the invention shall not be regarded as limiting since the invention is capable of other embodiments and can be practiced or carried out in multiple ways.
Description of the Preferred First Embodiment
[0070]
[0071] Staged fabrication is used in this embodiment. The bottom flange, top flange, and the web are subcomponents of an HDBT whereas the unit after combining the process of combining them into one is defined as a concrete component, the completed HDBT.
[0072] Bottom Flange (Item 1) is a subcomponent of HDBT which is fabricated using UHPC and prestress is applied to it before remaining portions of the HDBT. Web (Item 2) and Flange (Item 3) are added to it as the second stage of the fabrication.
[0073] Use of UHPC for the bottom flange only is another innovation used in this embodiment of this invention. The primary benefit of this innovation is the drastic improvement in the durability of HDBT over DBTs produced using the state of the art. It has significantly higher durability than HPC in terms of freeze-thaw degradation resistance, scaling deterioration, resistance to chloride penetration, and abrasion resistance. It also has a low permeability and significantly reduced water absorption which makes the material attractive for use in harsh environments. The high tensile strength and ductility of UHPC reduces the likelihood of cracking the bottom flange, which prevents chloride penetration through cracks alleviating a major concern in prestressed concrete components made using HPC.
[0074] In addition the high compressive strength of UHPC enables using smaller bottom flanges, as less material is needed to resist the prestressing force. This will result in reduced shipping weight for individual HDBT units and the total dead load of superstructures constructed using them. To develop desired positive camber for the completed HDBT, the bottom flange is shored and set to the desired geometric shape as exemplified in
[0075] The inability to control camber of DBTs produced using state of the art fabrication process is a well known issue. The use of HDBTs produced using this innovation eliminates the need for the significant remedial measures employed during the installation of DBTs as well as the required overlays necessary to obtain a smooth riding surface.
[0076] The form is assembled over the shored bottom flange to produce the desired geometric shape of the completed HDBT and reinforcement, as needed for the desired structural capacity, is placed within the form as exemplified in
[0077] The form is filled with HPC and cured until the desired level of concrete compressive strength is achieved as exemplified in
[0078] Once the HPC in the form reaches the desired strength, the forms are removed and the completed HDBT is moved to storage as exemplified in
[0079] An innovative design methodology has been developed incorporating the effects of the fabrication process for the preferred first embodiment of this invention. The structural analysis included all phases of the stage fabrication to capture stress accumulation and strain compatibility between stages. The model captures composite action under DC2, DW, and live load. The system is evaluated using multiple criteria including the deflections under Live Load (LL) and Dead Load (DL), design checks for temporary stresses before losses, and stresses at service limit states after losses.
[0080] A finite element model is provided to exemplify the design methodology. The model in this example is constructed using a 125 feet single span highway bridge design using the AASHTO LRFD design specifications for highway bridges. The UHPC bottom flange, including the prestressing tendon, is modeled as a beam element with a single tendon element of equivalent area located at the center of gravity of prestressing strands. The web and the deck of HDBT is modeled using shell elements. The support conditions at the ends are pin-rollers. The wearing surface and parapets are defined as area loads and line loads, respectively. The parapets do not contribute to the stiffness of the structure. The reinforcement in the web and the deck was not explicitly modeled. A schematic representation of the overall model used in the example is shown in
[0081] Two different cross sections were evaluated in the example. One section has a total depth of five feet while the other has a depth of six feet. The five-foot-deep section is included as it has a comparable depth to a steel girder superstructure with a similar span length. The six-foot-deep section has a smaller bottom flange and fewer prestressing tendons compared to the five foot section. This section is included to show the versatility of this innovative design methodology. The material properties of UHPC in sample analysis provided below is for illustration of the novel design methodology developed as part of the present invention and shall not be regarded as limiting.
[0082] The specified UHPC compressive strength is f.sub.d=14.0 ksi at the release of strands and f′.sub.c=22 ksi at 28 days.
[0083] The Elastic modulus specified UHPC is 8,000 ksi.
[0084] Time-dependent properties of UHPC and HPC are used to capture the effect of the staged fabrication sequence.
[0085] HPC compressive strength is 10 ksi and the Elastic modulus is 5,000 ksi.
[0086] The creep, shrinkage and stiffness parameters are calculated according to CEB/FIP-90.
[0087] The prestressing force is applied using 0.6 inch diameter strands stressed to 44 kips.
[0088] The strands are Grade 270.
[0089] The strand group is modeled with a single tendon component of equivalent area located at the center of gravity of the tendons.
[0090] A multi-step structural analysis process with time-dependent material properties is used to capture effects of the different stages of the fabrication. The first step is the analysis of the UHPC bottom flange with precompression and with UHPC compressive strength of 14 ksi. Additional information is provided
[0091] The second step of analysis is the application of a distributed load necessary to generate the required camber and corresponding stresses.
[0092] At HPC strength of 7 ksi, the distributed load is removed, and the complete self-weight of the beam is added to the composite section of the HDBT as the third step of the analysis. This corresponds to when the beam can be lifted from the shoring.
[0093] At HPC strength of 10 ksi, the load patterns for the barrier and wearing surface are added to the superstructure model as the fourth step.
[0094] The fifth step is when the live load is applied to the structure using a moving load case with floating lanes. The corresponding live load factors for each case are incorporated in the design load combinations.
[0095] Section cuts at mid-span and the end of the span as shown in
[0096] Compressive stresses at different stages of the fabrication, as well as in the in-service condition of this example, based on the model of the example schematic is provided in
[0097] Tensile stresses during the in-service condition of this example based on the model of the example schematic is provided in
[0098] Capacity to Demand ratios of this example based on the model of the example schematic is provided in
[0099] The staged fabrication of the HDBT component results in an interface between the UHPC and HPC components of the web. Two methods are used to evaluate the structural performance of this interface. Hand calculations and model-based analysis are used to determine the interface shear at this location. Results of these two methods are given
Improvements Over the Prior Art by the Preferred First Embodiment
[0100] The preferred first embodiment of the present invention, HDBT, will significantly reduce, if not fully eliminate, all inadequacies of the prior art described in this disclosure.
[0101] No tension will be developed at the top fiber of the top flange and the web near both ends of the HDBT through the staged fabrication method. The prestress is imparted into the bottom flange as an independent unit therefore no other part of the HDBT will experience tension.
[0102] The limitation in design efficiency in the state of the art due to the maximum tension on the top flange caused by the negative effects of prestress is completely eliminated.
[0103] With the secondary effects of prestress removed, there is a reduced risk of concrete deck deterioration which substantially improves the durability of the superstructure.
[0104] Fabrication is made easier and cheaper as the present invention negates the need for the draping of stands as well as the debonding of strands near the ends of a prestressed concrete component to reduce tension in the deck.
[0105] The present invention also negates the need for the special treatments of the anchorage zones in prestressed components which eases the fabrication process and reduces cost.
[0106] The camber variations from piece to piece of HDBT will be insignificantly low since the camber is measured and controlled by the shoring of the bottom flange before the rest of the HDBT is added to it. HDBTs will not need corrective measures when assembled in the field to construct the final structure.
[0107] Even though UHPC is a highly desirable material for producing durable concrete components, its use in the fabrication of concrete components is not common practice due to its significantly higher cost. In HDBT, UHPC usage is strategically limited to the bottom flange encasing the prestressing strands, which is the most vulnerable and critical part of any prestressed concrete component. The durability of HDBT is significantly enhanced by this approach while balancing a minimal cost increase from the UHPC use.
[0108] Since the compressive strength of UHPC is significantly higher than HPC, the size of the bottom bulb can be reduced significantly thereby reducing the overall weight of the HDBT compared to DBT made using traditional HPC.
Description of the Preferred Second Embodiment
[0109] Another embodiment of this invention, GDBT, could be used as an alternative to HDBT for the bridge superstructure in
[0110] The fabrication process for GDBTs is similar to that of HDBTs except that form work for webs and the flanges are capable of producing thinner sections with stiffeners. The innovation of utilizing ribs or stiffeners to increase the structural capacity of thin concrete components made of ultra high strength materials, such as UHPC, is demonstrated in this embodiment, which is not used in the first preferred embodiment (HDBT). All subcomponents of GDBT are made using UHPC (or other similar materials). The fabrication of the bottom flanges and the process for inducing camber is similar to the process used for the production of HDBTs.
[0111] The design and analysis process for GDBTs are essentially similar to that of HDBTs except the finite element model reflects section properties of thinner and stiffened webs and top flanges. UHPC (or other similar materials) are used for webs and flanges instead of that of HPC in the case of HDBTs and associated material properties are to be used for the design and analysis.
Improvements Over the Prior Art by the Preferred Second Embodiment
[0112] The preferred second embodiment of the present invention, GDBT, will also significantly reduce, if not fully eliminate, all inadequacies of the prior art described in this disclosure.
[0113] No tension will develop at the top fiber of the top flange and the web near both ends of the GDBT by the use of the staged fabrication method. The prestress is imparted into the bottom flange as an independent unit thereby no part of the GDBT will experience tension as a secondary effect.
[0114] The limitation in design efficiency in the state of the art due to the maximum tension on the top flange as a negative byproduct of prestress is completely eliminated.
[0115] With no tension from the secondary effects of prestress, the durability of the deck is substantially improved.
[0116] Fabrication is made easier and cheaper as the present invention negates the need for the draping of stands as well as the debonding of strands near the ends of a prestressed concrete component to reduce tension in the deck.
[0117] The present invention also negates the need for the special treatments of the anchorage zones in prestressed components which eases the fabrication process and reduces cost.
[0118] The camber variations from piece to piece of GDBT will be insignificantly small since the camber is measured and controlled by the shoring of the bottom flange before the rest of the GDBT is added to it. GDBTs will not need corrective measures when assembled in the field to construct the final structure.
[0119] Since GDBTs are using thin stiffened components for the web and the deck, the quantity of UHPC needed for its fabrication is substantially lower than DBTs using state of the art fabrication methods. Reduction in the quantity of UHPC needed for GDBT will limit the cost increase and make GDBTs economically viable.
[0120] GDBTs are substantially lower in weight compared to all superstructure types (steel or prestressed concrete) constructed using the state of the art.
[0121] GDBTs are substantially higher in durability compared to all superstructure types (steel or prestressed concrete) constructed using the state of the art.