Walkway installation, as well as a vessel with such a walkway installation
09797101 · 2017-10-24
Assignee
Inventors
Cpc classification
B63B27/14
PERFORMING OPERATIONS; TRANSPORTING
International classification
E01D15/24
FIXED CONSTRUCTIONS
B63B27/14
PERFORMING OPERATIONS; TRANSPORTING
Abstract
A walkway installation includes a base (1) intended to be fastened to a support construction, such as to the deck (5) of a ship (6), as well as a base bridge part (2) that is connected at one end so it can be rotated around an upright base axis of rotation (11) with the base. Furthermore, a main bridge part (4) is positioned on the other end of the base bridge part (1) as well as a hinge construction between the base bridge part (1) and the main bridge part (2). The hinge construction has an upright main axis of rotation (12) and an auxiliary axis of rotation (13) aligned transversely to the upright main axis of rotation and transversely to the main bridge part. By rotating the gangplank parts, the installation may be adjusted in a reliable and quick way in relation to a fixed object or another vessel.
Claims
1. A walkway installation, comprising a base intended to be fastened to a support construction, a base bridge part that is connected with the base at one end so it can be rotated around an upright base axis of rotation, a main bridge part on the other end of the base bridge part as well as a hinge construction between the base bridge part and the main bridge part, wherein the hinge construction comprises an upright main axis of rotation and an auxiliary axis of rotation aligned transversely to the upright main axis of rotation as well as transversely to the main bridge part, wherein the base bridge part can rotate around only the upright base axis of rotation, and wherein the walkway installation further comprises a main drive provided between the hinge construction and the base bridge part for adjusting the main bridge part around the main axis of rotation.
2. The walkway installation according to claim 1, wherein the walking surface of the base bridge part is flat or level, or is provided with steps.
3. The walkway installation according to claim 1, wherein at the end of the main bridge part away from the hinge construction, a platform is suspended so it can rotate around an axis of rotation that is essentially parallel to the auxiliary axis of rotation as well as a possibly floating body on the platform.
4. The walkway installation according to claim 3, wherein the platform has a walking surface that is essentially parallel to the walking surface of the base bridge part.
5. The walkway installation according to claim 1, wherein the main bridge part is implemented as a staircase with rotatable steps which are preferably parallel to the walking surface of the base bridge part and/or the walking surface of the platform.
6. The walkway installation according to claim 1, wherein the hinge construction comprises a gangplank intermediate piece or intermediate platforms that works together via the main axis of rotation with the base bridge part and via the auxiliary axis of rotation with the main bridge part.
7. The walkway installation according to claim 6, wherein the main drive is provided between the gangplank intermediate piece and the base bridge part for adjusting the main bridge part around the main axis of rotation.
8. The walkway installation according to claim 6, wherein an auxiliary drive is provided between the gangplank intermediate piece and the main bridge part for adjusting the main bridge part around the auxiliary axis of rotation.
9. The walkway installation according to claim 6, wherein a base drive is provided between the base and the base bridge part for adjusting the base bridge part around the main axis of rotation.
10. The walkway installation according to claim 7, wherein an operating mechanism is provided comprising a movement reference unit to establish relative movements of the free end of the main bridge part in relation to an object, as well as a control unit for controlling the main drive and/or the auxiliary drive and/or the base drive on the basis of the control signals given by the movement reference unit.
11. The walkway installation according to claim 1, wherein the base axis of rotation and the main axis of rotation are parallel and/or the auxiliary axis of rotation is aligned perpendicular in relation to the base axis of rotation and/or the main axis of rotation.
12. The walkway installation according to claim 1, wherein the base bridge part and the main bridge part are provided with a barrier on both opposite sides, and/or the gangplank intermediate piece is provided with a barrier.
13. The walkway installation according to claim 1, wherein the main axis of rotation is arranged eccentrically in relation to the base bridge part and the main bridge part in such a way that the base bridge part and the main bridge part can be brought parallel next to each other in a collapsed condition.
14. The walkway installation according to claim 1, wherein the base is implemented with dimensions in accordance with those of the base of an ISO container and ISO connectors are attached to the four corners.
15. A vessel comprising a walkway installation according to claim 1.
16. The walkway installation according to claim 1, wherein the support construction comprises a deck of a ship.
17. The walkway installation according to claim 7, wherein the main drive comprises a hydraulic piston/cylinder unit.
18. The walkway installation according to claim 8, wherein the auxiliary drive comprises one or more hydraulic piston/cylinder mechanism.
19. The walkway installation according to claim 9, wherein the base drive comprises a hydraulic piston/cylinder mechanism.
20. A method for operating a walkway installation comprising a base intended to be fastened to a support construction, a base bridge part that is connected with the base at one end so it can be rotated around an upright base axis of rotation, a main bridge part on the other end of the base bridge part as well as a hinge construction between the base bridge part and the main bridge part, wherein the hinge construction comprises an upright main axis of rotation and an auxiliary axis of rotation aligned transversely to this upright main axis of rotation as well as transversely to the main bridge part, wherein the method for operating comprises rotating the base bridge part around only the upright base axis of rotation, and wherein the walkway installation further comprises a main drive provided between the hinge construction and the base bridge part for adjusting the main bridge part around the main axis of rotation.
21. The method according to claim 20, wherein the support construction comprises a deck of a ship.
Description
(1) The invention shall be described further using the embodiment represented in the figures.
(2)
(3)
(4)
(5)
(6)
(7) The walkway installation represented in
(8) The main bridge part 4 is a staircase with rotating steps 26 in the represented illustrative example. Furthermore, the main bridge part 4 is implemented telescopically with the two parts 15, 16. By extending part 16, together with the aforementioned rotational movements, the extremity of the walkway installation may be held next to an object, such as the leg 17 of a platform, for example. As represented in
(9) Onto the base bridge part 2 and the main bridge part 4, barriers 10 are attached. The intermediate platform 3 supports a barrier 14 that is concentric in relation to the main axis of rotation 12. As represented in
(10) As represented in
(11) The base 1 consists of a frame 19 with ISO connectors 20 on the four corners, by means of which the walkway installation can be connected to the corresponding connectors on the deck 5 of the vessel 6. However, a different, permanent arrangement is also possible. The entire walkway installation may be provided with a closed container shell 21 as reproduced in
LIST OF REFERENCE NUMBERS
(12) 1. Base 2. Base bridge part 3. Intermediate platform 4. Main bridge part 5. Deck 6. Vessel 7. Base drive 8. Main drive 9. Auxiliary drive 10. Barrier 11. Base axis of rotation 12. Main axis of rotation 13. Auxiliary axis of rotation 14. Barrier 15. Part of main bridge part 16. Part of main bridge part 17. Object 18. Web plate 19. Frame 20. ISO connector 21. Container shell 22. Platform 23. Axis of rotation of platform 22 24. Walking surface of base bridge part 25. Walking surface of platform 22 26. Steps of main bridge part 27. Floating body