Methods for transmitting and receiving hybrid automatic retransmit request-acknowledgment (HARQ-ACK) index mapping and uplink resource allocation for channel selection transmission in inter-band time division duplex mode, user equipment to transmit HARQ-ACK, and eNODE-B to receive HARQ-ACK
09794029 · 2017-10-17
Inventors
Cpc classification
H04W72/20
ELECTRICITY
H04W76/28
ELECTRICITY
H04L1/1812
ELECTRICITY
International classification
H04L5/14
ELECTRICITY
Abstract
Hybrid Automatic Retransmit ReQuest-Acknowledgment (HARQ-ACK) index mapping and uplink resource allocation is performed and controlled for channel selection transmission. A method for transmitting HARQ-ACK information to an eNode-B (eNB) by a User Equipment (UE) includes identifying KPCell as a number of downlink subframe(s) of a PCell associated with an uplink subframe and identifying KSCell as a number of downlink subframe(s) of an SCell associated with the uplink subframe; generating Discontinuous Transmission (DTX) response information for a cell having a smaller number of downlink subframes between the PCell and the SCell; generating HARQ-ACK information including the generated DTX response information and response information on data received by the UE from the eNB; and transmitting the generated HARQ-ACK information to the eNB through the uplink subframe.
Claims
1. A method for transmitting Hybrid Automatic Repeat Request-Acknowledgment (HARQ-ACK), the method comprising: setting N pieces of HARQ-ACK to Discontinuous Transmission (DTX) for a cell, based on a difference between KPCell and KSCell, the difference being associated with the number N, the number N being an integer greater than one; generating the HARQ-ACK comprising the N pieces of HARQ-ACK set to DTX, the HARQ-ACK being responsive to data received from a base station (BS); and transmitting, to the BS, the HARQ-ACK, wherein the KPCell is a number of downlink subframe(s) of a Primary Cell (PCell) associated with an uplink subframe and the KSCell is a number of downlink subframe(s) of a Secondary Cell (SCell) associated with the uplink subframe.
2. The method of claim 1, wherein when the KPCell is smaller than the KSCell, the cell is the PCell, and when the KSCell is smaller than the KPCell, the cell is the SCell.
3. The method of claim 1, wherein two pieces of the HARQ-ACK are set to DTX when one of the KPCell and the KSCell is 1 and the other one of the KPCell and the KSCell is 3.
4. The method of claim 1, wherein the setting HARQ-ACK comprises: setting KSCell pieces of the HARQ-ACK to DTX when the KPCell is 0, or setting KPCell pieces of the HARQ-ACK to DTX when the KSCell is 0.
5. The method of claim 1, wherein in setting HARQ-ACK, piece(s) of the HARQ-ACK to DTX is mapped for each virtual downlink subframe generated in the cell having a smaller number of downlink subframe(s) between the PCell and the SCell, the difference corresponding to a number of the virtual downlink subframe(s).
6. A method of receiving Hybrid Automatic Repeat Request-Acknowledgment (HARQ-ACK) the method comprising: receiving, from a User Equipment (UE), an HARQ-ACK comprising N pieces of HARQ-ACK set to Discontinuous Transmission (DTX); identifying the N pieces of HARQ-ACK for a cell, based on a difference between KPCell and KSCell, the difference being associated with the number N, the number N being an integer greater than one; wherein the KPCell is a number of downlink subframe(s) of a Primary Cell (PCell) associated with an uplink subframe and the KSCell is a number of downlink subframe(s) of a Secondary Cell (SCell) associated with the uplink subframe.
7. The method of claim 6, wherein when the KPCell is smaller than the KSCell, the cell is the PCell, and when the KSCell is smaller than the KPCell, the cell is the SCell.
8. The method of claim 6, wherein two pieces of the HARQ-ACK are set to DTX when one of the KPCell and the KSCell is 1 and the other one of the KPCell and the KSCell is 3.
9. The method of claim 1, wherein the HARQ-ACK comprises: KSCell pieces of the HARQ-ACK set to DTX when KPCell is 0, or KPCell pieces of the HARQ-ACK set to DTX when the KSCell is 0.
10. The method of claim 6, wherein the HARQ-ACK is associated with virtual downlink subframe(s), and piece(s) of the HARQ-ACK set to DTX is mapped for each virtual downlink subframe generated in the cell having a smaller number of downlink subframe(s) between the PCell and the SCell, the difference corresponding to a number of the virtual downlink subframe(s).
11. A User Equipment (UE) to transmit Hybrid Automatic Repeat Request-Acknowledgment (HARQ-ACK), the UE comprising: a controller to set N pieces of HARQ-ACK to Discontinuous Transmission (DTX) for a cell, based on a difference between KPCell and KSCell, the difference being associated with the number N, and to generate the HARQ-ACK comprising the N pieces of HARQ-ACK set to DTX, the HARQ-ACK being responsive to data received from a base station (BS), the number N being an integer greater than one; and a transmitter to transmit, to the BS, the response, wherein the KPCell is a number of downlink subframe(s) of a Primary Cell (PCell) associated with an uplink subframe and the KSCell is a number of downlink subframe(s) of a Secondary Cell (SCell) associated with the uplink subframe.
12. The UE of claim 11, wherein when the KPCell is smaller than the KSCell, the cell is the PCell, and when the KSCell is smaller than the KPCell, the cell is the SCell.
13. The UE of claim 11, wherein the controller sets two pieces of the HARQ-ACK to DTX when one of the KPCell and the KSCell is 1 and the other one of the KPCell and the KSCell is 3.
14. The UE of claim 11, wherein the controller sets KSCell pieces of the HARQ-ACK to DTX when the KPCell is 0 or sets KPCell pieces of the HARQ-ACK to DTX when the KSCell is 0.
15. The UE of claim 11, wherein piece(s) of the HARQ-ACK set to DTX is mapped for each virtual downlink subframe generated in the cell having a smaller number of downlink subframe(s) between the PCell and the SCell, the difference corresponding to a number of the virtual downlink subframe(s).
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1) The accompanying drawings, which are included to provide a further understanding of the invention and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the principles of the invention.
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
(17)
(18)
(19)
(20)
(21)
(22) Throughout the drawings and the detailed description, unless otherwise described, the same drawing reference numerals will be understood to refer to the same elements, features, and structures. The relative size and depiction of these elements may be exaggerated for clarity, illustration, and convenience.
DETAILED DESCRIPTION
(23) Exemplary embodiments now will be described more fully hereinafter with reference to the accompanying drawings, in which exemplary embodiments are shown. This disclosure may, however, be embodied in many different forms and should not be construed as limited to the exemplary embodiments set forth therein. Rather, these exemplary embodiments are provided so that this disclosure will be thorough and complete, and will fully convey the scope of this disclosure to those skilled in the art. Various changes, modifications, and equivalents of the systems, apparatuses, and/or methods described herein will likely suggest themselves to those of ordinary skill in the art. Elements, features, and structures are denoted by the same reference numerals throughout the drawings and the detailed description, and the size and proportions of some elements may be exaggerated in the drawings for clarity and convenience.
(24) Additional features of the invention will be set forth in the description which follows, and in part will be apparent from the description, or may be learned by practice of the invention.
(25) For the purposes of the present document, the following frequently used abbreviations apply. ACK Acknowledgement CCE Control Channel Element CIF Carrier Indicator Field DAI Downlink Assignment Index DCI Downlink Control Information DL Downlink DTX Discontinuous Transmission eNB evolved Node B/eNode-B HARQ Hybrid Automatic Retransmit reQuest HSPA High Speed Packet Access LTE Long Term Evolution NACK Negative Acknowledgement PCell Primary Cell PCFICH Physical Control Format Indicator Channel PDCCH Physical Downlink Control Channel PDSCH Physical Downlink Shared Channel PHICH Physical Hybrid ARQ Indicator Channel PUCCH Physical Uplink Control Channel PUSCH Physical Uplink Shared Channel RI Rank Indication SCell Secondary Cell SPS Semi-Persistent Scheduling TDD Time Division Duplex UE User Equipment UL Uplink UL-SCH Uplink Shared Channel WCDMA Wideband Code Division Multiple Access
(26) A method for handling PUCCH transmission based on different PDSCH HARQ timings between serving cells when cross carrier scheduling is configured under inter-band CA is provided.
(27) The PUCCH transmission efficiency may be improved by applying spatial bundling or time domain bundling appropriate for differently configured HARQ timings.
(28) A wireless communication system may be installed to provide various communication services, such as, a voice service, packet data and the like. The wireless communication system includes a User Equipment (UE) and a Base Station (BS or eNB). Throughout the specification, the user equipment may be an inclusive concept indicating a user terminal utilized in wireless communication, and should be construed as a concept including all of a User Equipment (UE) in WCDMA, LTE, HSPA and the like, and a Mobile Station (MS), a User Terminal (UT), a Subscriber Station (SS), a wireless device and the like in GSM.
(29) In general, the base station or a cell may refer to a fixed station communicating with the user equipment, and may also be referred to as another term, such as, a Node-B, an evolved Node-B (eNB), a sector, a site, a Base Transceiver System (BTS), an access point, a relay node or the like.
(30) That is, throughout the specification, the BS or the cell may be construed as an inclusive concept indicating a partial area covered by a Base Station Controller (BSC) in CDMA, a Node B in WCDMA, an eNB or sector (site) in LTE and the like, and the concept may include various coverage areas, such as, a megacell, a macrocell, a microcell, a picocell, a femtocell, a communication range of a relay node and the like.
(31) The UE and the BS are used as two inclusive transceiving subjects used to embody the teachings described in the specification, and may not be limited to a predetermined term or word. The UE and the BS are used as two (uplink and downlink) inclusive transceiving subjects used to embody the teachings described in the specification, and may not be limited to a predetermined term or word. Here, uplink (UL) refers to a connection used for sending or uploading data from the UE to the BS, and downlink (DL) refers to a connection for receiving data from the BS by the UE.
(32) A multiple access scheme applied to the wireless communication system is not limited. The wireless communication system may utilize various multiple access schemes, such as, Code Division Multiple Access (CDMA), Time Division Multiple Access (TDMA), Frequency Division Multiple Access (FDMA), Orthogonal Frequency Division Multiple Access (OFDMA), OFDM-FDMA, OFDM-TDMA, OFDM-CDMA, and the like. Exemplary embodiments of the present invention may be applicable to resource allocation in an asynchronous wireless communication scheme that is advanced through GSM, WCDMA, HSPA, to be LTE and LTE-advanced, and may be applicable to resource allocation in a synchronous wireless communication scheme that is advanced through CDMA and CDMA-2000, to be UMB. Exemplary embodiments of the present invention may not be limited to a specific wireless communication, and may be applicable to all technical fields to which the technical idea of the present invention is applicable.
(33) Uplink transmission and downlink transmission may be performed based on a Time Division Duplex (TDD) scheme that performs transmission based on different times, or based on a Frequency Division Duplex (FDD) scheme that performs transmission based on different frequencies.
(34) Further, a system, such as, LTE or LTE-A, configures uplink and downlink based on one carrier or a pair of carriers to establish the standard. The uplink and the downlink transmit control information through control channels, such as, a Physical Downlink Control Channel (PDCCH), a Physical Control Format Indicator Channel (PCFICH), a Physical Hybrid ARQ Indicator Channel (PHICH), a Physical Uplink Control Channel (PUCCH) and the like, and configures data channels, such as, a Physical Downlink Shared Channel (PDSCH) and a Physical Uplink Shared Channel (PUSCH) and the like to transmit the data.
(35) Meanwhile, time points are different between the downlink and the uplink in TDD. When there are various TDD configurations, the time points may vary.
(36) Table 1 below shows TDD configurations. It can be identified through Table 1 that the respective TDD configurations have different UL-DL subframe transmission timings.
(37) TABLE-US-00001 TABLE 1 Uplink-downlink configurations Uplink- Downlink- downlink to-Uplink Configura- Switch-point Subframe number tion periodicity 0 1 2 3 4 5 6 7 8 9 0 5 ms D S U U U D S U U U 1 5 ms D S U U D D S U U D 2 5 ms D S U D D D S U D D 3 10 ms D S U U U D D D D D 4 10 ms D S U U D D D D D D 5 10 ms D S U D D D D D D D 6 5 ms D S U U U D S U U D
(38) In Table 1, an area indicated by D is the downlink and an area indicated by U is the uplink in a radio frame corresponding to ten subframes. S is a special subframe, which has a downlink-to-uplink switch-point periodicity.
(39) Further, in TDD, downlink subframes associated with each uplink subframe according to the uplink-downlink configurations in Table 1 are as follows.
(40) TABLE-US-00002 TABLE 2 Downlink association set index {k0, k1, . . . , kM − 1} UL-DL Subframe n Config 0 1 2 3 4 5 6 7 8 9 0 — — 6 — 4 — — 6 — 4 1 — — 7, 6 4 — — — 7, 6 4 — 2 — — 8, 7, — — — — 8, 7, — — 4, 6 4, 6 3 — — 7, 6, 6, 5 5, 4 — — — — — 11 4 — — 12, 8, 6, 5, — — — — — — 7, 11 4, 7 5 — — 13, 12, — — — — — — — 9, 8, 7, 5, 4, 11, 6 6 — — 7 7 5 — — 7 7 —
(41) The uplink subframe associated with the downlink subframe varies depending on the UL-DL Config. For example, for the TDD UL-DL Config 3, subframe 2 is the uplink subframe and is associated with the downlink subframe received before subframes 7, 6, and 11. ACK/NACK information on the downlink subframe received before the subframes 7, 6, and 11 can be transmitted in the uplink subframe 2.
(42) Meanwhile, when one configuration of the TDD configurations is used, the UE can know in advance the subframe direction of the downlink and the uplink. This information allows the UE to pre-predict and then perform the operation.
(43) Meanwhile, the TDD configurations may be different for each band. However, carriers included in bands having the differently configured TDD UL-DL configuration may be used by one UE.
(44)
(45) Reference numeral 110 indicates a configuration of two component carriers, wherein CC#1 111 is a carrier having a coverage of a signal transmitted from an eNB with high power, and CC#2 112 is a carrier having a coverage of a signal transmitted from the eNB with low power. CC#1 111 and CC#2 112 are included in different bands. A TDD configuration of CC#1 111 corresponds to 1, which is indicated by reference numeral 181, and a TDD configuration of CC#2 112 corresponds to 2, which is indicated by reference numeral 182. Meanwhile, a hot-spot areal 15 consists of the CA environment including CC#1 111 and CC#2 112. Further, reference numeral 110 can configure the CA for UEs in the CC#2 coverage.
(46) Here, the UE performing communication with the hot-spot 115 has different TDD configurations, such as, CC#1111 and CC#2 112, and the uplink subframe and the downlink subframe may be differently configured for each component carrier in some subframes.
(47) In this case, operation schemes are different for each subframe according to whether a transmission mode supportable by the UE is a half-duplex mode or a full duplex mode.
(48) In order to avoid an interference issue with TDD systems, for example, TD-SCDMA, Mobile WiMAX and the like, coexisting in the same band, different TDD UL-DL configurations are required on the inter-band CA.
(49) A TDD UL-DL configuration including many UL subframes can be induced on a low frequency band and the TDD UL-DL configuration including many DL subframes can be induced on a high frequency band. Such a configuration helps a coverage enhancement, and also influences peak throughput.
(50)
(51)
(52) Referring to
(53) In a case of the UE having the CA of component carriers B and C, the TDD configurations are different (that is, the UE has the inter-band CA with different UL-DL configurations). According to whether the UE is in the half-duplex transmission mode or the full-duplex transmission mode, some subframes are muted or simultaneous transmission/reception (Tx/Rx) is performed as illustrated in
(54)
(55) In reference numeral 310 of
(56) On the other hand, in reference numeral 320, when the UE supports only the full-duplex transmission mode, both the uplink subframes of the PCell and the downlink subframes of the SCell are operated in subframes 3 and 8 of the radio frame. That is, the full-duplex transmission mode can implement the uplink/downlink in each of the PCell and the SCell since transmission and reception can be simultaneously performed. In reference numeral 320, since the full-duplex transmission mode can be executed even in subframes 3 and 8 in which the downlink and the uplink conflict, both the downlink subframes and the uplink subframes can be operated.
(57) In the configuration of
(58)
(59) In
(60) Reference numeral 410 shows a process of PUCCH transmission through an uplink subframe which is associated with each one downlink subframe in the PCell/SCell. The PCell/SCell means two configured CCs, but the present invention is not limited thereto.
(61) A relation table employed in FDD is used. The following equation is applied.
A={2,3,4}, 0≦j≦A−1, HARQ-ACK(j) (1)
(62) In Equation (1), the A denotes the number of resources to be allocated for PUCCH transmission for a channel selection transmission method. According to A, respective transport block and serving cell to HARQ-ACK mapping can be applied as shown in Table 3.
(63) TABLE-US-00003 TABLE 3 Table 10.1.2.2.1-1: Mapping of Transport Block and Serving Cell to HARQ-ACK(j) for PUCCH format 1b HARQ-ACK channel selection HARQ-ACK(j) HARQ- HARQ- HARQ- A HARQ-ACK(0) ACK(1) ACK(2) ACK(3) 2 TB1 Primary cell TB1 Secondary NA NA cell 3 TB1 Serving TB2 Serving TB1 Serving NA cell1 cell1 cell2 4 TB1 Primary cell TB2 Primary TB1 Secondary TB2 Secondary cell cell cell
(64) When A is 2, that is, when one CodeWord (CW) is transmitted in each of the PCell and the SCell, the number of required resources (A) is 2. As a result, the one CW delivered by the PCell is allocated to the HARQ-ACK(0), and the one CW delivered by the SCell is allocated to the HARQ-ACK(1) based on Table 3. Hereafter, each CW can be interpreted as a Transport Block.
(65) Meanwhile, when A is 3, one CW is transmitted in either the PCell or the SCell, and two CWs are transmitted in the other cell. In this case, HARQ ACK information on the two CWs transmitted from the cell (cell 1) is indexed by HARQ-ACK(0) and HARQ-ACK(1), respectively, and HARQ ACK of the cell (cell 2) in which the one CW is transmitted is indexed by HARQ-ACK(2). For example, when the two CWs are transmitted in the PCell, the PCell becomes the cell 1 and the SCell becomes the cell 2.
(66) When A is 4, that is, when two CWs are transmitted in each of the PCell and the SCell, the total number of desired resources (A) is 4. As a result, information on the two CWs transmitted in the PCell is indexed by HARQ-ACK(0) and HARQ-ACK(1) and information on the two CWs transmitted in the SCell is indexed by HARQ-ACK(2) and HARQ-ACK(3).
(67) Reference numeral 420 shows a process of PUCCH transmission through the uplink subframe associated with two downlink subframes in the PCelI/SCell (2 configured CCs).
(68) In this case, a channel selection transmission method is performed by using A=4 resources through a mapping rule as shown in Table 4 below.
(69) TABLE-US-00004 TABLE 4 Mapping of subframes on each serving cell to HARQ-ACK(j) for PUCCH format 1b HARQ-ACK channel selection for TDD with M = 2 HARQ-ACK(j) HARQ- HARQ- A ACK(0) ACK(1) HARQ-ACK(2) HARQ-ACK(3) 4 The first The second The first The second subframe of subframe of subframe of subframe of Primary cell Primary cell Secondary cell Secondary cell
(70) Reference numerals 430 and 440 show a case of M>2 in the PCell/SCell.
(71) When M=3 or 4, the channel selection transmission is performed in the following way without using Tables 3 and 4 applied when M=1 or M=2.
(72) When PDSCH transmission indicated by a PDCCH transmitted in the PCell or PDCCH indicating DL Semi-Persistent Scheduling (SPS) release is received in the PCell, PUCCH resources are induced by applying either process a-i) or a-ii) described below.
(73) a-i) When there is SPS PDSCH transmission in the PCell, n.sub.PUCCH,0.sup.(1) is indicated by using high layer signaling and a Transmit Power Control (TPC) field. In addition to the SPS PDSCH transmission in the PCell, when the PDCCH having Downlink Assignment Index (DAI)=1 is transmitted to indicate PDSCH transmission or DL SPS release, the PUCCH resource is derived through: n.sub.PUCCH,1.sup.(1)=(M−m−1).Math.N.sub.c+m.Math.N.sub.c+1+n.sub.CCE,m+N.sub.PUCCH.sup.(1).
(74) In this case, A/N for the SPS PDSCH is allocated to HARQ-ACK(0).
(75) According to j(1≦j≦M−1), a HARQ-ACK(j) indexing rule is based on a DAI value. For example, A/N for the PDCCH having DAI=1 is allocated to HARQ-ACK(1).
(76) In cases of the a-ii) which is not the case as a-i), n.sub.PUCCH,0.sup.(1) is implicitly derived from the PDCCH having DAI=1.
(77) n.sub.PUCCH,1.sup.(1) is implicitly derived from the PDCCH having DAI=2. That is, in the HARQ-ACK(j) indexing, the DAI value of the PDCCH is equal to j+1 according to j(0≦j≦M−1).
(78) When PDSCH transmission indicated by the PDCCH transmitted to the SCell is received in the SCell, a method selected from either b-i) or b-ii) is applied.
(79) b-i) Cross-carrier scheduling on PCell
(80) n.sub.PUCCH,2.sup.(1) is implicitly derived from the PDCCH having DAI=1.
(81) n.sub.PUCCH,3.sup.(1) is implicitly derived from the PDCCH having DAI=2.
(82) b-ii) Self scheduling
(83) n.sub.PUCCH,2.sup.(1) and n.sub.PUCCH,3.sup.(1) are indicated by a combination of higher layer signaling and a TPC field.
(84) In the methods b-i) and b-ii), HARQ-ACK(j) allocation is j(0≦j≦M−1) and the DAI value is j+1.
(85) In
(86) In the conventional (Rel-10) CA TDD, it is assumed that numbers of DL subframes associated with one PCell UL subframe are the same in a channel selection and PUCCH format 3 transmission method, because the Rel-10 CA TDD defines that all serving cells have the same TDD UL-DL configuration. However, Rel-11 supports different TDD configurations in different carriers, and additional handling is used to support the PUCCH transmission method. Accordingly, the present disclosure provides an additional handling method, which may solve errors in the PUCCH transmission method which can be generated in such an environment.
(87) The present teachings provide a method that may solve the problems of the conventional Rel-10 channel selection transmission method generated due to different PDSCH HARQ timings between the PCell and the SCell.
(88) In the prior art (Rel-10), the channel selection transmission method is defined as an HARQ-ACK transmission method only for the CA UE having two configured CCs. Particularly, unlike FDD (frame structure type 1), HARQ-ACK feedbacks to be transmitted on one UL subframe may become greater due to an increase in the number of DL subframes in TDD (frame structure type 2). Accordingly, in Rel-10, for the channel selection transmission in the TDD CA environment, several mapping rules and resource allocation rules are differently defined according to the number of DL subframes (that is, M values in Tables 3 and 4 above). However, as described above, when different TDD UL-DL configurations are applied to the TDD CA environment (more accurately, due to different PDSCH HARQ timings between the PCell and the SCell), additional handling is provided for channel selection transmission. Table 5 illustrates case-A, case-B, and case-C; cases that are not covered by the prior art (Rel-10), and the exemplary embodiments include an additional handling method for each of the case-A, the case-B, the case-C, and the case-D.
(89) TABLE-US-00005 TABLE 5 Detailed embodiments to implement different PDSCH HARQ timings between the PCell and the SCell M = 1 M = 2 M = 3 M = 4 for PCell for PCell for PCell for PCell M = 1 for SCell Rel-10 case Case-A Case-B Case-C M = 2 for SCell Case-A Rel-10 case Case-C Case-C M = 3 for SCell Case-B Case-C Rel-10 case Case-C M = 4 for SCell Case-C Case-C Case-C Rel-10 case M = 0 for PCell or M = 0 for SCell: Case-D
(90) The PCell and the SCell need additional parameters for indicating different M values. The additional parameters are defined as follows.
K.sub.PCell:{k.sub.0,Pcell,k.sub.1,Pcell, . . . , k.sub.M-1,Pcell}
K.sub.SCell:{k.sub.0,Scell,k.sub.1,Scell, . . . , k.sub.M-1,Scell}
(91) The additional parameters can be parameters when the PCell and the SCell have different M values.
(92) In the case-A/B/C/D described below, #1 and #2 indicating serving cells are not limited to the PCell or the SCell, but can be defined according to each case or by an appointment between the base station and the UE. Also, when the mapping is made with HARQ-ACK(j) according to each case, orders thereof may be inversed or changed, and the order can be variously applied according to implementations.
(93) Exemplary Case-A
(94) First, a case where a ratio of the numbers of DL subframes on two serving cells (PCell and SCell) associated with one UL subframe is 2:1 is considered. HARQ-ACK(j) mapping according to a value of “A” which is the number of PUCCH resources required for the channel selection transmission method in the case-A is as shown in Table 6 (Mapping of Transport Block and Serving Cell to HARQ-ACK(j) for PUCCH format 1b HARQ-ACK channel selection in CA with different TDD configurations).
(95) TABLE-US-00006 TABLE 6 A channel selection mapping table in the case-A HARQ-ACK(j) HARQ- HARQ- A HARQ-ACK(0) HARQ-ACK(1) ACK(2) ACK(3) 3 First subframe of Second subframe First subframe NA serving cell #1 of serving cell #1 of serving cell #2 4 First subframe of Second subframe TB1 of serving TB2 of serving cell #1 of serving cell #1 cell#2 serving cell#2
(96) In Table 6 HARQ-ACK index for two subframes of serving cell #1 are mapped to HARQ-ACK(0) and HARQ-ACK(1), respectively. Depending on configuring one or two TBs for the cell (serving cell #2), HARQ-ACK index on the downlink transmission in one subframe of the cell are mapped into HARQ-ACK(2) or HARQ-ACK(3), respectively.
(97) In the case of M=2:1, a mapping relation between the number of PUCCH resources and a corresponding serving cell will be described.
(98)
(99)
(100) In the case of A=3, different correlations are made according to a Transmission (TM) mode (i.e., 1 TB or 2 TB transmission) configured in each serving cell, the number of configured serving cells, and an M value (see Tables 6,
(101) That is, in the case of A=3, when Table 6 is applied to the case-A, the serving cell (M=2) in which two downlink subframes are associated with the uplink subframe is allocated to HARQ-ACK(0) and HARQ-ACK(1), and the serving cell (M=1) is allocated to HARQ-ACK(2). Of course, such an order may be inversely performed according to prearrangement. For example, in an inverse way, the serving cell (M=1) in which one downlink subframe is associated with the uplink subframe is allocated to HARQ-ACK(0), and the serving cell (M=2) in which two downlink subframes are associated with the uplink subframe is allocated to HARQ-ACK(1) and HARQ-ACK(2)
(102) Accordingly, reference numerals 510, 520, 530, and 540 are expressed by Table 7 according to mapping of Table 6 corresponding to A=3.
(103) TABLE-US-00007 TABLE 7 HARQ-ACK(j) resource mapping in FIG. 5 HARQ-ACK(0) HARQ-ACK(1) HARQ-ACK(2) 510 The first subframe of The second subframe The subframe SCell of SCell of PCell 520 Perform spatial Perform spatial The subframe of bundling for the first bundling for the PCell subframe of SCell second subframe of SCell 530 Perform spatial Perform spatial Perform spatial bundling for the first bundling for the bundling for the subframe of SCell second subframe subframe of SCell of SCell 540 The first subframe of The second subframe Perform spatial SCell of SCell bundling for the subframe of PCell
(104) Further, c-i), c-ii), c-iii), and c-iv) are methods of inducing A(=3) PUCCH resources.
(105) c-i) When the PDSCH indicated by reception of a PDCCH in subframe n−k.sub.Pcell,m (k.sub.PCell,mεK.sub.PCell) or “PDCCH indicating downlink SPS release” is received on the PCell, PUCCH resources can be induced through an implicit resource allocation method, such as, n.sub.PUCCH,j.sup.(1)=(M−m−1).Math.N.sub.c+m.Math.N.sub.c+1+n.sub.CCE,m+N.sub.PUCCH.sup.(1).
(106) When Table 6 (A=3) and the implicit resource allocation are used and the PCell has M=1, HARQ-ACK(2)=>n.sub.PUCCH,j=2.sup.(1) can be induced as an example. When the PCell has M=2, two PUCCH resources can be induced from each of the DL subframes as following. Accordingly, HARQ-ACK(O)=>n.sub.PUCCH,j=0.sup.(1), HARQ-ACK(1)=>n.sub.PUCCH,j=1.sup.(1) can be induced by using table 6 (A=3) and the implicit resource allocation.
(107) c-ii) In case there is a SPS transmission on the PCell, HARQ-ACK(j) for SPS transmission on the PCell uses resources for the SPS n.sub.PUCCH,j.sup.(1).
(108) c-iii) When the PDSCH by PDCCH reception in subframe n−k.sub.Scell (k.sub.SCellεK.sub.SCell) on the PCell is received on the SCell, the PUCCH resource is indicated by using the implicit resource allocation method by the PDCCH received on the PCell.
(109) c-iv) In the case where the PDSCH transmission by PDCCH reception in subframe n−k.sub.Scell (k.sub.SCellεK.sub.SCell) on the SCell is received on the SCell, when the SCell has M=2, two explicit PUCCH resources are indicated by using a higher layer configuration and a TPC field within Downlink (DL) Downlink control Information (DCI) regardless of the TM mode supporting one TB or two TBs. Accordingly, HARQ-ACK(0)=>n.sub.PUCCH,j=0.sup.(1) and HARQ-ACK(1)=>n.sub.PUCCH,j=1.sup.(1) can be induced through the proposed table (A=3) and the method. Further, when the SCell has M=1, only one explicit PUCCH resource is indicated by using a higher layer configuration and a TPC field within the DL DCI regardless of the mode supporting one TB or two TBs.
(110)
(111) In
(112)
(113) Accordingly, reference numerals 610 and 620 may be defined as in Table 8 based on the mapping of Table 6.
(114) TABLE-US-00008 TABLE 8 HARQ-ACK(j) resource mapping in FIG. 6 HARQ- HARQ- HARQ- HARQ- ACK(0) ACK(1) ACK(2) ACK(3) 610 Perform spatial Perform spatial The first TB of The second TB bundling for bundling for the subframe of of the subframe the first the second the PCell of the PCell subframe of subframe of the the SCell SCell 620 The first The second The first TB of The second TB subframe of the subframe of the the subframe of of the subframe SCell SCell the PCell of the PCell
(115) In this case, since A=4, four PUCCH resources should be induced and an induction process corresponds to d-i), d-ii), d-iii), and d-iv).
(116) d-i) When the PCell has M=1, all HARQ-ACK bits are directly transmitted without applying spatial bundling as shown in
(117) following mapping relation.
(118) d-ii) In the case where the PCell has M=1, when SPS transmission is received, HARQ-ACK(2) is indicated through the TPC field within the DL DCI and an SPS-dedicated PUCCH resource set, and HARQ-ACK(3) is indicated through n.sub.PUCCH,j=3.sup.(1)=n.sub.PUCCH,j=2.sup.(1)+1 for HARQ-ACK(2).
(119) d-iii) When the PCell has M=2, resources for HARQ-ACK (j=0) and HARQ-ACK(j=1) are indicated through the implicit method of n.sub.PUCCH,j.sup.(1)=(M−m−1).Math.N.sub.c+m.Math.N.sub.c+1+n.sub.CCE,m+N.sub.PUCCH.sup.(1) on each downlink subframe.
(120) d-iv) The SCell indicates two explicit PUCCH resources by using the higher layer configuration and the TPC field within the DL DCI regardless of M=1 or M=2.
(121) Exemplary Case-B
(122) Next, a case where a ratio of the numbers of DL subframes associated with one to UL subframe is 3:1 on the DL subframe of two serving cells (PCell and SCell) will be first described (see Table 5). In the case-B, “A” which is the number of PUCCH resources for channel selection transmission is 4.
(123) Hereinafter, mapping between HARQ-ACK(j) and a corresponding serving cell in the case of M=3:1 (1:3) will be described (A is the number of PUCCH resources for channel selection transmission).
(124)
(125)
(126) Table 9 shows an HARQ-ACK resource allocation method when M between two serving cell is 3:1 (or 1:3).
(127) TABLE-US-00009 TABLE 9 Mapping in the Case-B (Mapping of each Serving Cell to HARQ-ACK(j) for PUCCH format 1b HARQ-ACK channel selection in different TDD configurations) HARQ-ACK(j) HARQ- HARQ- HARQ- A ACK(0) HARQ-ACK(1) ACK(2) ACK(3) 4 First subframe Second subframe Third subframe First subframe of serving of serving cell #1 of serving of serving cell #1 cell #1 cell #2
(128) In Table 9, three downlink subframes of the serving cell (serving cell #1) in which the three downlink subframes are associated with the uplink subframe are mapped into HARQ-ACK(0), HARQ-ACK(1), and HARQ-ACK(2), respectively, and one downlink subframe of the serving cell (serving cell #2) in which the one downlink subframe is associated with the uplink subframe is mapped into HARQ-ACK(3). Of course, various modifications, such as, mapping the three downlink subframes into HARQ-ACK(1), HARQ-ACK(2), and HARQ-ACK(3), mapping other serving cells into HARQ-ACK(0), and inversely arranging the orders of Table 9 can be implemented.
(129) Table 10 is achieved by applying Table 9 to reference numerals 710, 720, 730, and 740 of
(130) TABLE-US-00010 TABLE 10 HARQ-ACK(j) resource mapping in FIG. 7 HARQ-ACK(0) HARQ-ACK(1) HARQ-ACK(2) HARQ-ACK(3) 710 The first The second The third The subframe of subframe of the subframe of the subframe of the the SCell PCell PCell PCell 720 Perform spatial Perform spatial Perform spatial The subframe of bundling for the bundling for the bundling for the the SCell first subframe of second subframe third subframe of the PCell of the PCell the PCell 730 The first The second The third Perform spatial subframe of the subframe of the subframe of the bundling for the PCell PCell PCell subframe of the SCell 740 Perform spatial Perform spatial Perform spatial Perform spatial bundling for the bundling for the bundling for the bundling for the first subframe of second subframe third subframe of subframe of the the PCell of the PCell the PCell SCell
(131) Meanwhile, in order to indicate PUCCH resources for the HARQ-ACK(j) in Table 10, methods e-i), e-ii), and e-iii) are applied.
(132) e-i) When the PDSCH transmission indicated by the PDCCH transmitted on the PCell or the PDCCH indicating downlink SPS release is received on the PCell, PUCCH resources can be induced on each DL subframe through the implicit resource allocation method, such as, n.sub.PUCCH,j.sup.(1)=(M−m−1).Math.N.sub.c+m.Math.N.sub.c+1+n.sub.CCE,m+N.sub.PUCCH.sup.(1) and the mapping relation shown in Table 9.
(133) e-ii) When the PDSCH transmission indicated by the PDCCH transmitted on the PCell is received on the SCell, PUCCH resources can be induced on each DL subframe through the implicit resource allocation method, such as, n.sub.PUCCH,j.sup.(1)=(M−m−1).Math.N.sub.c+m.Math.N.sub.c+1+n.sub.CCE,m+N.sub.PUCCH.sup.(1) and the mapping relation in Table 8.
(134) e-iii) In the case of M=1, the SCell indicates one explicit PUCCH resource by using the higher layer configuration and the TPC field within the DL DCI. In the case of M=3, the SCell indicates three explicit PUCCH resources by using the higher layer configuration and the TPC field within the DL DCI.
(135)
(136) In reference numeral 810, the PCell performs the time domain bundling for three downlink subframes and thus requires two HARQ-ACK resources. Since the SCell is one CW, the SCell requires one HARQ-ACK resource. The case where the SCell is two CWs in this process corresponds to the case-C, and the SCell requires a total of four HARQ-ACK resources.
(137) Since A is 2, the case of reference numeral 810 can be implemented in a similar way to that of Table 6. The implementation is made as shown in Table 11. When Table 11 is applied to reference numeral 810, serving cell #1 is the PCell and serving cell #2 is the SCell. The case where one CW is transmitted in the SCell corresponds to A=3 of Table 11, and the case where two CWs are transmitted in the SCell corresponds to A=4 of Table 11.
(138) TABLE-US-00011 TABLE 11 A channel selection mapping table in the Cases-B and C (time domain bundling is applied only to the case of M = 3) HARQ-ACK(j) HARQ- HARQ- A HARQ-ACK(0) HARQ-ACK(1) ACK(2) ACK(3) 3 Result of Time Domain Bundling in First subframe NA Serving cell #1 of serving cell #2 4 Result of Time Domain Bundling in TB1 of serving TB2 of Serving cell #1 cell#2 serving cell#2
(139) A more detailed description will be made below.
(140) In reference numeral 810, the channel selection mapping table corresponding to A=3 of Table 3 may be used. In some embodiments, when the TB of the serving cell, which does not apply the time domain bundling, is in a 2-TB transmission mode, the channel selection transmission can be performed by using the channel selection mapping table corresponding to A=4 of Table 3.
(141) Two PUCCH resources are induced through the serving cell having M=3 and one or two resources are induced through another serving cell (M=1). n.sub.PUCCH,j=0.sup.(1) and n.sub.PUCCH,j=1.sup.(1) are derived from the PCell, n.sub.PUCCH,j=2.sup.(1) and n.sub.PUCCH,j=3.sup.(1) are derived from the SCell, as described above. In this case, the serving cell and HARQ-ACK mapping relation as shown in Table 9 is not used.
(142) Reference numeral 820 shows the case of applying the time domain bundling to the serving cell having M=1 as well as the serving cell having M=3. In order to apply the time domain bundling to the serving cell having M=1, it is assumed that there is a virtual DL subframe. An A/N value for the virtual DL subframe corresponds to one state among those including Discontinuous Transmission (DTX), Acknowledge or Acknowledgement (ACK), or Negative Acknowledgement (NACK) according to prearrangement with the base station.
(143) In reference numeral 820, since the PCell has the M=3 number of DL subframes and the SCell has the M=1 number of DL subframe, a time domain bundling method is applied based on a larger M value for both two serving cells, that is, M=3. Accordingly, by virtually assuming that the serving cell (SCell in reference numeral 820) having M=1 has an M=3, there seems to be an environment where both the conventional PCell and SCell have the same M=3. Therefore, HARQ-ACK is transmitted by using the same M=3 time domain bundling.
(144) An associated PUCCH resource allocation method can be implemented through the aforementioned method.
(145) In this case, the serving cell and HARQ-ACK mapping relation as shown in Table 9 is not used.
(146) In reference numeral 820, it is assumed that the serving cell having a smaller M value has the M value of the serving cell having a larger M value (in this case M>2). In reference numeral 820, it is assumed that an M value of the SCell is 3.
(147) Under this assumption, the UE may appoint or configure in advance ACK/NACK information (A/N state) of a blank subframe (or virtual subframe), such as, reference numeral 821 or 822 as DTX or NACK/DTX.
(148) Exemplary Case-C
(149) In the cases which are not the case-A/B, the time domain bundling can be applied as shown in
(150)
(151) That is, the time domain bundling is applied to the cell having the larger M value between two cells. When the M value of the other cell is 3, the time domain bundling can be also applied. In some embodiments, as described above, based on the method using larger M value, the current Rel-10 PUCCH A/N transmission method can be applied to two serving cells by using the virtual DL subframe in order to make the same M values between PCell and SCell.
(152) Exemplary Case-D
(153) In the case-A to case-C, the M values of the PCell and the SCell are not 0 and are different from each other.
(154) Meanwhile, when a currently considered combination of HARQ timings which can be applied for the PCell and the SCell is considered, a case where there is no downlink subframe related to a particular uplink subframe on one serving cell of the PCell and the SCell, that is, a case where there is no A/N transmission due to no PDSCH can occur. In other words, only the A/N for the PDCCH indicating the PDSCH transmission and the DL SPS release on the PCell in the particular uplink subframe is transmitted without those of SCell or only the A/N for the PDCCH indicating the PDSCH transmission or the DL SPS release on the SCell is transmitted without those of PCell.
(155) For example, with respect to the PCell and the SCell, M=1:0, 0:1, 2:0, 0:2, or 0:4. However, this case is not limited thereto.
(156) In this case, in one example, by virtually assuming that the M value of the cell in which there is no downlink subframe (i.e. M=0) is the same M value of the other cell in which there is the downlink subframe in a similar way to that of reference numeral 820 of
(157) However, the UE and the base station can fix A/N information as DTX in the case of M=0, and the UE is not required to report corresponding DTX information to the base station. In this case, a channel selection transmission method described below can be used.
(158) The following technology assumes an environment where two serving cells are configured. When cross-carrier scheduling with carrier indicator field (CIF) is configured on PCell, it is assumed that the PCell is a scheduling cell which performs scheduling for the cells, and the SCell is a scheduled cell which is scheduled by the scheduling cell (i.e. PCell).
(159) Exemplary Case D-1: M=1:0
(160)
(161) Exemplary Case D-2: M=2:0
(162)
(163) In one example, channel selection transmission can be performed by using a relation table between an HARQ-ACK index and a transport block transmitted on the serving cell of Table 12 and a channel selection mapping table. The TB and the serving cell can be associated with the HARQ-ACK(j) index by using Table 12.
(164) TABLE-US-00012 TABLE 12 A relation mapping table between HARQ-ACK index and a transport block of the serving cell in M = 2:0 HARQ-ACK(j) HARQ- HARQ- HARQ- A ACK(0) HARQ-ACK(1) ACK(2) ACK(3) 2 First subframe Second subframe NA NA of serving cell of serving cell #1 #1 4 TB1 of first TB2 of first TB1 of second TB2 of second subframe in subframe in subframe in subframe in serving cell#1 serving cell#1 serving cell#1 serving cell#1
(165) As noted from reference numeral 1110 of
(166) As noted from reference numeral 1120 of
(167) In some embodiments, as noted from reference numeral 1130 of
(168) Exemplary Case D-2: M=0:1
(169)
(170) In a case of self-scheduling (PDSCH scheduling information of the SCell is transmitted through the PDCCH of the SCell), the PUCCH resource can be derived from the Acknowledgement Resource Indication (ARI) reusing the TPC field (2 bits) within the PDCCH (that is, DL DCI format) of the SCell.
(171) In a case of cross carrier scheduling, the PUCCH resource can be derived from a first CCE (nCCE) to which the PDCCH of the PCell is allocated. Meanwhile, when the PCell cannot control the PDSCH transmission to the downlink subframe on the corresponding SCell, that is, when the subframe configured as the downlink by the SCell is not configured as the downlink by the PCell, HARQ-ACK may not be transmitted.
(172) Exemplary Case D-4: M=0:2
(173)
(174) In one example, channel selection transmission can be performed by using the relation between the HARQ-ACK index and the transport block of the serving cell and the channel selection mapping table. The TB and the serving cell can be associated with the HARQ-ACK(j) index by using Table 12.
(175) As noted from reference numeral 1310 of
(176) As noted from reference numeral 1320 of
(177) In some embodiments, as noted from reference numeral 1330 of
(178) In the case of the self-scheduling, the PUCCH resource can be induced as follows.
(179) 1) When two CWs are transmitted in the SCell (A=4, the SCell receives four resources through the ARI reusing the TPC field (two bits) within the PDCCH and induces a relation between the corresponding PUCCH resource and the HARQ-ACK index by using a mapping relation between the case of A=4 of Table 12 and the HARQ-ACK index. At this time, the ARI can indicate four PUCCH resources.
(180) 2) When one CW is transmitted in the SCell, or when two CWs are transmitted in the SCell and spatial bundling is applied to each downlink subframe, the SCell receives two resources through the ARI reusing the TPC field (two bits) within the PDCCH and induces a relation between the corresponding PUCCH resource and the HARQ-ACK index by using a mapping relation between the case of A=2 of Table 12 and the HARQ-ACK index. At this time, the ARI can indicate two PUCCH resources.
(181) In a case of cross carrier scheduling, the PUCCH resource can be induced as follows.
(182) 1) When two CWs are transmitted in the SCell (A=4), a total of four PUCCH resources can be induced through nCCE and nCCE+1 of the PDCCH (DAI=1, 2) of the PCell in each downlink subframe.
(183) 2) When one CW is transmitted in the SCell, or when two CWs are transmitted in the SCell and spatial bundling is applied to each downlink subframe, a total of two PUCCH resources can be induced through nCCE of the PDCCH (DAI=1, 2) of the PCell in each downlink subframe.
(184) Meanwhile, when the PCell cannot control the PDSCH transmission to the downlink subframe on the corresponding SCell, that is, when the subframe configured as the downlink by the SCell is not configured as the downlink by the PCell, HARQ-ACK may not be transmitted.
(185) Exemplary Case D-4: M=0:4
(186)
(187) In the case of the self-scheduling, the PUCCH resource can be induced as follows.
(188) 1) As noted from reference numeral 1410 of
(189) TABLE-US-00013 TABLE 13 Time domain bundling table with M = 4 HARQ-ACK(0), HARQ-ACK(1), HARQ-ACK(2), HARQ-ACK(3) Mapped state ‘D, any, any, any’ or no DL assignment is received. D, D ‘A, D, D, D’ A, N ‘A, A, N/D, any’ N, A ‘A, A, A, N/D’ A, A ‘A, A, A, A’ A, N ‘N, any, any, any’ or ‘A, D/N, any, any except for A, N, N D, D, D’
(190) 2) As described in 1), bundled two HARQ-ACK bits can be transmitted to PUCCH format 1b.
(191) 3) As noted from reference numeral 1420 of
(192) TABLE-US-00014 TABLE 14 A relation mapping table between the HARQ-ACK index and the TB of the serving cell in the case of M = 0:4 HARQ-ACK(j) HARQ- HARQ- A HARQ-ACK(0) HARQ-ACK(1) ACK(2) ACK(3) 4 first subframe second subframe third subframe fourth in serving in serving cell#1 in serving subframe in cell#1 cell#1 serving cell#1
(193) In the case of the cross carrier scheduling, the PUCCH resource can be induced as follows.
(194) 1) As noted from reference numeral 1410 of
(195) 2) As described in 1), bundled two HARQ-ACK bits can be transmitted to PUCCH format 1b.
(196) 3) As noted from reference numeral 1420 of
(197) The above-described example discloses, in detail, a case where M=0 of the PCell and M=4 of the SCell, but the M value of the SCell may be a value larger than 2. For example, when M=3, two HARQ-ACK bits can be generated by using the time domain bundling using Table 15 or three HARQ-ACK bits can be generated without time domain bundling.
(198) TABLE-US-00015 TABLE 15 Time domain bundling table with M = 3 HARQ- ACK(0), HARQ-ACK(1), HARQ-ACK(2) Mapped state ACK, ACK, ACK ACK, ACK ACK, ACK, NACK/DTX NACK/DTX, ACK ACK, NACK/DTX, any ACK, NACK/DTX NACK/DTX, any, any NACK/DTX, NACK/DTX
(199) Further, the above-described example discloses M=0 of the PCell, but a case of M=0 in the SCell can be applied.
(200) So far, the detailed embodiments have been described to control the case where TDD configurations of two cells are different in an implementation of the channel selection transmission in the two cells.
(201)
(202) When the PUCCH resource is induced, a corresponding HARQ-ACK is inserted into the induced PUCCH resource and PUCCH transmission according to channel selection is performed in step S1590. The eNB 1510 decodes HARQ-ACK for the TB/subframe in step S1595.
(203)
(204) The UE performs an RRC configuration step from the eNB, and different TDD configurations and channel selection are made on two CCs in step S1610. Further, it is identified whether M values for the PCell and the SCell are different on the UL subframe of the PCell in step S1620. As shown in Table 5, the different M values correspond to the case-A, the case-B, the case-C, and the case-D. When the M values are the same, the conventional Rel-10 scheme can be applied in step S1690.
(205) Meanwhile, when the M values are different from each other, an M value associated with the UL subframe of the PCell is determined in step S1630. The determination is for performing different channel selection according to the case-A, the case-B, the case-C, and the case-D. Further, a new TB/subframe and HARQ-ACK(j) mapping relation and a new bundling rule according to the number of M values are applied in step S1640. The embodiments described through
(206)
(207) The operation process of the eNB described through
(208) The eNB controls two or more bands having different TDD configurations. Also, the eNB controls HARQ-ACK index mapping and uplink resource allocation for channel selection transmission in the inter-band TDD transmission scheme.
(209) The eNB transmits TDD configuration information of a first serving cell and a second serving cell to the UE in step S1710. Further, the eNB transmits data to the UE in downlink subframes of the first serving cell and the second serving cell in step S1720.
(210) Thereafter, the eNB receives data including the response information on the data transmitted from the first serving cell and the second serving cell through the PUCCH by the channel selection transmission in the uplink subframe from the UE in step S1730. The eNB decodes the response information from the HARQ-ACK index into which the response information (ACK/NACK state) on the data transmitted in the downlink subframe of the first serving cell and the response information on the data transmitted in the downlink subframe of the second serving cell are mapped in step S1740 by applying the received PUCCH mapping rule and resource allocation rule.
(211) Here, when the number of downlink subframes associated with the uplink subframe in which the PUCCH is transmitted is different between the first serving cell and the second serving cell, the mapping rule is determined according to the number of associated downlink subframes of the first serving cell and the second serving cell, and includes the mapping rule described in the embodiments of
(212) More specifically, as illustrated in
(213) Further, in connection with the spatial bundling, when the downlinked data of the first cell or the second cell is two CWs, the response information of the first cell or the second cell is generated through the spatial bundling.
(214) As illustrated in
(215) The time domain bundling described with reference to
(216) Further, the virtual time domain bundling described with reference to
(217) As illustrated in
(218) As illustrated in
(219) As illustrated in
(220) Meanwhile, the resource allocation rule for allocating PUCCH resources to include three or four HARQ-ACKs can use the implicit resource allocation method and the explicit resource allocation method. Two or more PUCCH resources are calculated through the implicit resource allocation method using information extracted when the PDCCH reception is performed in the downlink subframe of the PCell between the first cell or the second cell, and one or more PUCCH resources are calculated through the explicit resource allocation method by providing a TPC value within the DL DCI of the SCell between the first cell and the second cell.
(221) The first cell and the second cell can be the PCell and the SCell, respectively, or inversely the first cell and the second cell can be the SCell and the PCell, respectively. The HARQ-ACK(j) index mapping in the embodiments of
(222)
(223) The UE is connected to the eNB controlling two or more bands having different TDD configurations. The UE performs the HARQ-ACK index mapping and the uplink resource allocation for channel selection transmission in the inter-band TDD transmission scheme.
(224) The UE receives TDD configuration information of the first serving cell and the second serving cell from the eNB in step S1810. Also, the UE receives data downlinked in the downlink subframes of the first serving cell and the second serving cells from the eNB in step S1820.
(225) The UE maps response information (ACK/NACK state) on data received in the downlink subframe of the first serving cell and response information on data received in the downlink subframe of the second serving cell into three or four HARQ-ACK indexes in step S1830. This process has been described with reference to
(226) Further, the UE calculates a resource of the Physical Uplink control CHannel (PUCCH) to include the mapped HARQ-ACK in step S1840, and inserts the three or four HARQ-ACKs into the calculated PUCCH resource and transmits the PUCCH to the eNB through the channel selection transmission in step S1850.
(227) Here, the number of downlink subframes associated with the uplink subframe in which the PUCCH is transmitted is different between the first serving cell and the second serving cell, and the response information on the downlinked data and the HARQ-ACK index mapping are determined based on the number of associated downlink subframes of the first serving cell and the second serving cell.
(228) More specifically, as illustrated in
(229) Further, in connection with the spatial bundling, when the downlinked data of the first cell or the second cell is two CWs, the response information of the first cell or the second cell is generated through the spatial bundling.
(230) As illustrated in
(231) The time domain bundling described with reference to
(232) Further, the virtual time domain bundling described with reference to through
(233) As illustrated in
(234) As illustrated in
(235) As illustrated in
(236) Meanwhile, the resource allocation rule for allocating PUCCH resources to include three or four HARQ-ACKs can use the implicit resource allocation method and the explicit resource allocation method. In calculating the PUCCH resources to include the mapped HARQ-ACK, two or more PUCCH resources are calculated through the implicit resource allocation method using information extracted when the PDCCH reception is performed in the downlink subframe of the PCell between the first cell or the second cell, and one or more PUCCH resources are calculated through the explicit resource allocation method by using a higher layer configuration from the eNB or a TPC value within the DL DCI of the SCell between the first cell and the second cell.
(237) The first cell and the second cell can be the PCell and the SCell, respectively, or inversely the first cell and the second cell can be the SCell and the PCell, respectively. The HARQ-ACK(j) index mapping in the embodiments of
(238)
(239) An eNB 1900 controls two or more bands having different TDD configurations. Also, the eNB controls the HARQ-ACK index mapping and the uplink resource allocation for channel selection transmission in the inter-band TDD transmission scheme.
(240) The eNB 1900 includes a transmitter 1910, a controller 1920, and a receiver 1930.
(241) The transmitter 1910 transmits TDD configuration information of the first serving cell and the second serving cell to the UE, and transmits data to the UE in downlink subframes of the first serving cell and the second serving cell. The receiver 1430 receives data including the response information on the data transmitted from the first serving cell and the second serving cell through the PUCCH by the channel selection transmission in the uplink subframe from the UE.
(242) The controller 1920 decodes the response information from three or four HARQ-ACK indexes into which the response information (ACK/NACK state) on the data transmitted in the downlink subframe of the first serving cell and the response information on the data transmitted in the downlink subframe of the second serving cell are mapped in step S1740 by applying the received PUCCH mapping rule and resource allocation rule.
(243) Here, when the number of downlink subframes associated with the uplink subframe in which the PUCCH is transmitted is different between the first serving cell and the second serving cell, the mapping rule is determined according to the number of associated downlink subframes of the first serving cell and the second serving cell, and includes the mapping rule described in the embodiments of
(244) More specifically, as illustrated in
(245) Further, in connection with the spatial bundling, when the downlinked data of the first cell or the second cell is two CWs, the response information of the first cell or the second cell is generated through the spatial bundling.
(246) As illustrated in
(247) The time domain bundling described through
(248) Further, the virtual time domain bundling described through
(249) As illustrated in
(250) As illustrated in
(251) As illustrated in
(252) Meanwhile, the resource allocation rule for allocating PUCCH resources to include three or four HARQ-ACKs can use the implicit resource allocation method and the explicit resource allocation method. Two or more PUCCH resources are calculated through the implicit resource allocation method using information extracted when the PDCCH reception is performed in the downlink subframe of the PCell between the first cell or the second cell, and one or more PUCCH resources are calculated through the explicit resource allocation method by providing a TPC value within the DL DCI of the SCell between the first cell and the second cell.
(253) The first cell and the second cell can be the PCell and the SCell, respectively, or inversely the first cell and the second cell can be the SCell and the PCell, respectively.
(254) The HARQ-ACK(j) index mapping in the exemplary embodiments of
(255)
(256) A UE 2000 is connected to the eNB controlling two or more bands having different TDD configurations. The UE performs the HARQ-ACK index mapping and the uplink resource allocation for channel selection transmission in the inter-band TDD transmission scheme.
(257) The UE 2000 includes a transmitter 2010, a controller 2020, and a receiver 2030.
(258) The receiver 2030 receives TDD configuration information of the first serving cell and the second serving cell from the eNB, and receives data downlinked in the downlink subframes of the first serving cell and the second serving cells from the eNB.
(259) The controller 2020 maps response information (ACK/NACK state) on data received in the downlink subframe of the first serving cell and response information on data received in the downlink subframe of the second serving cell into three or four HARQ-ACK indexes. Further, controller 2020 calculates a resource of the PUCCH to include the mapped HARQ-ACK and inserts three or four HARQ-ACKs into the calculated PUCCH resource.
(260) Further, the transmitter 2010 transmits the PUCCH to the eNB through the channel selection transmission.
(261) Here, the number of downlink subframes associated with the uplink subframe in which the PUCCH is transmitted is different between the first serving cell and the second serving cell, and the response information on the downlinked data and the HARQ-ACK index mapping are determined based on the number of associated downlink subframes of the first serving cell and the second serving cell.
(262) More specifically, as illustrated in
(263) Further, in connection with the spatial bundling, when the downlinked data of the first cell or the second cell is two CWs, the response information of the first cell or the second cell is generated through the spatial bundling.
(264) As illustrated in
(265) The time domain bundling described through
(266) Further, the virtual time domain bundling described through
(267) As illustrated in
(268) As illustrated in
(269) As illustrated in
(270) Meanwhile, the resource allocation rule for allocating PUCCH resources to include three or four HARQ-ACKs can use the implicit resource allocation method and the explicit resource allocation method. In calculating the PUCCH resources to include the mapped HARQ-ACK, two or more PUCCH resources are calculated through the implicit resource allocation method using information extracted when the PDCCH reception is performed in the downlink subframe of the PCell between the first cell or the second cell, and one or more PUCCH resources are calculated through the explicit resource allocation method by using a higher layer configuration from the eNB or a TPC value within the DL DCI of the SCell between the first cell and the second cell.
(271) The first cell and the second cell can be the PCell and the SCell, respectively, or inversely the first cell and the second cell can be the SCell and the PCell, respectively.
(272) The HARQ-ACK(j) index mapping in the exemplary embodiments of
(273) When the methods provided by the exemplary embodiments is applied, it is possible to improve the transmission efficiency by solving the PUCCH transmission method problem generated due to different PDSCH HARQ timings in the LTE Rel-11 inter-band A TDD system.
(274) Unlink the conventional same TDD UL-DL configuration among all UEs allowing CA, these embodiments may allow PUCCH A/N transmission when the PCell and the SCell have different PDSCH HARQ timings in a state where different TDD UL-DL configurations are possible when CCs are aggregated on different bands.
(275) As disclosed, it may be possible to support a more stable and improved channel selection transmission method in an inter-band condition where different TDD configurations are made.
(276) The embodiments of the present invention are merely for describing the technical idea of the present invention, but various modifications and changes can be made by those skilled in the art without departing from essential characteristics of the present invention. Accordingly, the embodiments disclosed in the present invention do not limit but describe the technical idea of the present invention, and the scope of the technical idea of the present invention is not limited by the embodiments. The protection range of the present invention should be construed by the appended claims and all technical ideas within an equivalent range thereof should be construed as being included in the scope of the present invention.
(277) While the exemplary embodiments have been shown and described, it will be understood by those skilled in the art that various changes in form and details may be made thereto without departing from the spirit and scope of this disclosure as defined by the appended claims and their equivalents. Thus, as long as modifications fall within the scope of the appended claims and their equivalents, they should not be misconstrued as a departure from the scope of the invention itself.