Method for Operating a Textile Machine and a Textile Machine
20170283993 · 2017-10-05
Inventors
Cpc classification
B65H67/00
PERFORMING OPERATIONS; TRANSPORTING
D01H9/00
TEXTILES; PAPER
D01H15/00
TEXTILES; PAPER
B65H63/00
PERFORMING OPERATIONS; TRANSPORTING
B65H54/22
PERFORMING OPERATIONS; TRANSPORTING
International classification
Abstract
The invention relates to a method for operating a textile machine (1) with a multiple number of similar work stations (2), whereas, with the assistance of work stations (2) during the normal operation of the same, yarn is produced or is rewound by a delivery coil onto a receiver coil, and whereas normal operation is initiated at the individual work stations (2) after a stop of the textile machine (1), or is interrupted at certain time intervals by a service operation in the form of a spinning-in process, a sleeve changing process or a yarn joining process. In accordance with the invention, it is proposed that
at least one of the specified service operations is divided into several partial sequences, and that a pending partial sequence is carried out independently of the other partial sequences of the corresponding service operation, if the required energy resources for carrying out the pending partial sequence are available. In addition, the invention relates to a textile machine.
Claims
1. Method for operating a textile machine (1) with a multiple number of similar work stations (2), whereas, with the assistance of work stations (2) during the normal operation of the same, yarn is produced or is rewound by a delivery coil onto a receiver coil, and whereas normal operation is initiated at the individual work stations (2) after a stop of the textile machine (1), or is interrupted at certain time intervals by a service operation in the form of a spinning-in process, a sleeve changing process or a yarn joining process, characterized in that at least one of the specified service operations is divided into several partial sequences, and that a pending partial sequence is carried out independently of the other partial sequences of the corresponding service operation, if the required energy resources for carrying out the pending partial sequence are available.
2-11. (canceled)
Description
[0023] The method in accordance with the invention is described in detail in the following example. The following is shown:
[0024]
[0025]
[0026]
[0027]
[0028]
[0029]
[0030]
[0031]
[0032] A main current line 6 and two main vacuum lines 7 also extend from the machine end 4. The main current line 6 is designed centrally for the entire textile machine 1 and branches into a multiple number of current lines 8, which supply the devices 3 with electrical current. Each of the main vacuum lines 7 is assigned to one machine half. They branch into several vacuum lines 9, which supply the devices 3 with negative pressure.
[0033] If a work station 2 now requires a service operation, it issues a request to the control unit 5. The control unit 5 checks whether the energy resources permit the carrying out of a pending partial sequence of such service operation. In this case, the control unit 5 for the electrical current considers the accumulated consumption at all work stations 2 of the textile machine 1. On the other hand, for the consumption of negative pressure—by reason of the separate distribution of the negative pressure over two main vacuum lines 7—only the machine half of the textile machine 1 that is allocated to the work station 2 that has requested the service operation is considered.
[0034] If the energy resources required by the pending partial sequence are available, the control unit 5 instructs the device 3 to carry out such partial sequence of the service operation.
[0035] In the following figures, the consumption of energy resources of spinning-in processes on a spinning machine is shown. This is intended to illustrate the method in accordance with the invention; the values shown are freely selected.
[0036]
[0037] As can be seen in
[0038]
[0039]
[0040] In this example, with the conventional method, the number of spinning-in processes that can take place simultaneously is limited by the available electrical current. Since a spinning-in process requires 40% of the available electrical current upon start-up, a maximum of two spinning-in processes can take place simultaneously.
[0041] Initially, the spinning-in process is carried out for two work stations. The thread search (FS1 and FS2) is followed by the start-up (HF1 and HF2) of such work stations. During this time, the three other work stations must wait. If the spinning-in process for the first two work stations has been completed after eight time units, the spinning-in process for the next two work stations begins. The spinning-in process once again comprises the thread search (FS3 and FS4) and the start-up (HF3 and HF4) of the work stations. During this time, the first two work stations already work in normal operation and the fifth is still waiting. At time 16, the third and fourth work stations are then also finished with the spinning-in process and resume normal operation. At that point, the spinning-in process can begin with thread search (FS5) and start-up (HF5) for the fifth work station. This is completed after a total of 24 time units.
[0042] As can be seen in
[0043] With the method in accordance with the invention, which is shown in
[0044] In contrast to the conventional method, in the method in accordance with the invention, interruptions can occur between the individual partial sequences.
[0045] The thread search is limited by the available negative pressure, and in this example, three work stations can start with the thread search (FS1, FS2 and FS3). As soon as the thread search for such three work stations has been completed, the first two work stations can begin with the start-up (HF1 and HF2). There is not enough electric power available for the start-up of the third work station. However, sufficient energy resources are still available, such that work stations four and five can already start with the thread search (FS4 and FS5).
[0046] At time eight, the first two work stations have completed the start-up and can resume normal operation. At that point, enough energy resources are free once again, such that work station three can begin with the start-up (HF3).
[0047] Work station four can only start with the start-up (HF4) at time ten, since the thread search was completed only then. At this point in time, work station five has also completed the thread search. However, work station five has to wait for its start-up (HF5) until work station three has completed its start-up at time eleven, and enough electrical current is once again available. At the time 13 and 14, work stations four and five have completed the start-up.
[0048] With the method in accordance with the invention, the energy resources are significantly better utilized than with the conventional method. In this example, the cumulative waiting time of the five work stations until the respective normal operation amounts to only 54 (=8+8+11+13+14) time units, thus 25% less than with the conventional method. With an even higher number of work stations requiring a spinning-in process, the savings would be even greater.
[0049] By means of shorter waiting times, the work stations can more quickly once again proceed with the normal operation of yarn production, and the productivity of the spinning machine is increased.
[0050] The present invention is not limited to the illustrated and described examples, and can be modified within the scope of the claims.