NICKEL-CHROMIUM-IRON ALLOYS WITH IMPROVED RESISTANCE TO STRESS CORROSION CRACKING IN NUCLEAR ENVIRONMENTS
A Ni—Cr—Fe alloy with improved resistance to stress corrosion cracking in nuclear environments, the alloy comprising 23-28 wt % Cr, 25-35 wt % Ni, <0.03 wt % C, <0.70 wt % Si, <1.0 wt % Mn, <0.015 wt % S, >0.35 wt % Ti, 0.15-0.45 wt % Al, <0.75 wt % Cu, and balance Fe and incidental impurities. The alloy may be used in steam generator tubing of a nuclear reactor. A method of producing an article includes: providing the alloy as disclosed herein; forming the alloy into the article by cold working the alloy to 20%; and heat treating the article.
Tube leak detection device and tube leak detection method
A tube leak detection device for detecting leak of at least one tube of a heat exchanger which increases a temperature of a liquid by heat exchange between the liquid flowing inside the at least one tube and a fluid flowing outside the at least one tube includes: an inlet opening-and-closing valve and an outlet opening-and-closing valve disposed at an inlet end and an outlet end of the at least one tube, respectively; and a pressure detection member for detecting a pressure inside the at least one tube between the inlet opening-and-closing valve and the outlet opening-and-closing valve.
Steam generator pipe having a turbulence installation body
A steam generator pipe for producing a steam generator pipe with a spiral-shaped installation body, wherein an elevation extends on the inner side of the steam generation pipe in the axial direction of the steam generator pipe. A method for producing a steam generator pipe having an installation body.
Coating and method for forming the same
A coating is formed on a surface of a base material of a furnace, and includes a base layer and a sliding material layer that is formed on a surface of the base layer and contains an oxide ceramic and a compound having a layered crystal structure. The sliding material layer causes the collided ashes to be slipped and facilitates the drop off of the adhered ashes. The base material forms a heat transfer tube or a wall surface of the furnace. The coating is also applied to a coal gasification furnace, a pulverized coal fired boiler, a combustion apparatus, or a reaction apparatus containing a furnace.
Method of installing liner assembly for pipeline repair or reinforcement, and liner assembly and steam generator for same
A method of installing a liner assembly for pipeline repair or reinforcement includes: pulling a prepared liner assembly into position in the pipeline, the liner assembly including a tubular liner wetted with a curable compound; introducing fluid into the inflatable bladder to bring the tubular liner into firm contact with an interior surface of the pipeline; flowing the fluid continuously through the bladder and discharging the fluid into the pipeline, while maintaining the liner assembly in an inflated condition; measuring a flow rate and a temperature of the fluid entering the bladder; calculating a time period sufficient for the tubular liner to cure based on: an amount of heat required for curing, based on dimensional information of the liner, and the measured flow rate and temperature of the fluid; and maintaining the liner assembly in an inflated condition for the time period sufficient for the tubular liner to cure.
METHOD OF INSTALLING LINER ASSEMBLY FOR PIPELINE REPAIR OR REINFORCEMENT, AND LINER ASSEMBLY AND STEAM GENERATOR FOR SAME
A steam generator for use with a liner assembly for pipeline repair or reinforcement, includes: a water heater configured to heat water to generate steam; a water feed conduit configured to convey water to the water heater; an air heater configured to generate heated air; an air supply conduit configured to convey pressurized air to the air heater; a heated air supply conduit configured to convey heated air from the air heater to the water heater to yield a steam-air mixture; and an output conduit configured to convey the steam-air mixture from the water heater. An automated steam generator system including the steam generator is also described.
TRANSITION CASTING FOR BOILER WITH STEAM COOLED UPPER FURNACE
Transition castings are disclosed which comprise a steam tube and a water tube, which are joined together by membranes. A heat transfer fin extends from the membrane and abuts the water tube. The steam tube bends such that an upper end is on one side of the water tube, and a lower end is on an opposite side of the water tube. The transition castings are used in a transition section of a boiler in which the furnace is divided into a lower furnace and an upper furnace. The lower furnace uses water-cooled membrane walls, while the upper furnace uses steam-cooled membrane walls that act as superheating surfaces. The transition casting joins the lower furnace and the upper furnace together.
Method for welding thin-walled tubes by means of peak temperature temper welding
A method is disclosed for connecting two components by TIG welding, the components consisting of an air-hardening steel alloy and, for example, of the material T23 or T24. A joint is produced between the components that are to be connected, said joint widening, in particular, from an inside toward an outside. First, a root layer is welded in the region of the inside. Subsequently, a fill layer adjoining the root layer is welded, so that the joint is at least 90% filled. Finally, a cover layer is welded onto the fill layer, whereby the welding parameters are prespecified in such a manner that a temperature in an optimizing temperature range is adjusted on the inside in the region of the root layer.
Collar supported pressure parts for heat recovery steam generators
Disclosed herein is a heat recovery steam generator system comprising a vestibule comprising a base plate, a roof and side walls; where the base plate is opposedly disposed to the roof; a heat exchanger space through which an exhaust gas stream is charged; where the vestibule is disposed atop a heat exchanger space; and where the vestibule comprises at least one header in fluid communication with a tube bundle; where a portion of the tube bundle is disposed in the heat exchanger space; and a support system for the tube bundle; where the support system comprises a strap that is reversibly attached to the base plate as well as to the roof of the vestibule or to a structural member in the vestibule; and where each tube of the tube bundle contacts a collar that rests on the base plate.
Method of forming flat bar
A method of forming a flat bar is provided. A tube is provided having an inside surface and an outside surface. The outside surface of the tube can be clad with a nickel or stainless alloy material. A helix shaped strip can be cut from the tube. The helix shaped strip can be uncoiled to form an uncoiled strip, and the uncoiled strip can be straightened and flattened to meet mill standards.