E01D21/06

METHOD FOR THE PRODUCTION OF A DECK SLAB FOR A BRIDGE

“A method for producing a construction section of a deck slab for a bridge includes the following operations: producing a bottom layer composed of a segment and having cross beams, which are arranged in the transverse direction in regard to the longitudinal axis of the longitudinal bridge girder, from reinforced concrete; transporting the bottom layer having the cross beams for a construction section of the deck slab using a conveyor device from an assembly site to an installation site and lowering it into the installation position; producing a top concrete layer for a construction section of the deck slab on the bottom layer; removing the bottom layer having the cross beams for a construction section of the deck slab from the conveyor device and moving the conveyor device away from the installation site.”

Modular Longitudinal System for Bridge Decks for Double-Track Railways

A longitudinal modular system with boards (3) for underpass bridges for installation of two tracks for railway circulation in which the board (3) is placed between two consecutive piers (4) and comprises a pair of longitudinal beams (1), which themselves comprise a lower wing (2c), for supporting on the piers (4), a core (1b) and an upper wing (1a); and a plurality of transversal slabs (2) that are attached to the lower wings (2c) of the longitudinal beams (1), thus forming a

U-shaped configuration, where the length of the longitudinal beams (1) is essentially similar to the span between two piers (4), and the configuration of the board (3) has a transversal, U-shaped section such that the railway circulates inside said U shape. The invention also describes the method for constructing same.

Modular Longitudinal System for Bridge Decks for Double-Track Railways

A longitudinal modular system with boards (3) for underpass bridges for installation of two tracks for railway circulation in which the board (3) is placed between two consecutive piers (4) and comprises a pair of longitudinal beams (1), which themselves comprise a lower wing (2c), for supporting on the piers (4), a core (1b) and an upper wing (1a); and a plurality of transversal slabs (2) that are attached to the lower wings (2c) of the longitudinal beams (1), thus forming a

U-shaped configuration, where the length of the longitudinal beams (1) is essentially similar to the span between two piers (4), and the configuration of the board (3) has a transversal, U-shaped section such that the railway circulates inside said U shape. The invention also describes the method for constructing same.

Method for displacing a ceiling formwork, collision protection element, and ceiling formwork, supporting device and incremental launching device comprising such a collision protection element
11788307 · 2023-10-17 · ·

A method for displacing a ceiling formwork for a nearest concreting section, wherein first and second supporting devices for supporting the ceiling formwork are arranged below the nearest concreting section. Said supporting devices each have a shuttering position and a stripping position, wherein the ceiling formwork is raised to a concreting level in the shuttering position and lowered relative to the concreting level in the stripping position. The first supporting device is moved into the stripping position and the second supporting device is moved into the shuttering position, and a collision protection element is arranged between the second supporting device and an end face of the ceiling formwork when the end face of the ceiling formwork strikes the second supporting device after passing over the first supporting device, so the collision protection element forms a flank rising in the displacement direction for guiding the ceiling formwork in the displacement direction.

Construction method for upright lifting of large-tonnage box girder to bridge, and erection method for large-tonnage box girder

A construction method for the upright lifting of a large-tonnage box girder to a bridge, and an erection method for the large-tonnage box girder. The construction method comprises: constructing a lifting station (2) at reserved bridge piers (1); disposing a girder lifting base (3), lifter traveling rails (4), and a mounting lifter (6) in the lifting station (2); directly erecting a box girder (7) by the lifter (6) in a way that the lifter (6) travels to a position above the base (3) and erects the box girder (7). The erection method further comprises: lifting by the lifter (6) a single set of transport and erection apparatuses or two sets of transport and erection apparatuses to a bridge, a girder transport vehicle (9) cooperating with a bridge erecting machine (10) to repeatedly complete the erection of the box girder (7); hoisting by the lifter (6) the transport and erection apparatus off the bridge; lifting by the lifter (6) the box girder (7) within the scope of the reserved bridge pier (1) to the erected box girder (7); and constructing the reserved bridge piers (1); completing by the lifter (6) the erection of the box girder (7) within the scope of the reserved bridge piers (1). The construction and erection methods for the box girder occupy a small space and have high efficiency.

Construction method for upright lifting of large-tonnage box girder to bridge, and erection method for large-tonnage box girder

A construction method for the upright lifting of a large-tonnage box girder to a bridge, and an erection method for the large-tonnage box girder. The construction method comprises: constructing a lifting station (2) at reserved bridge piers (1); disposing a girder lifting base (3), lifter traveling rails (4), and a mounting lifter (6) in the lifting station (2); directly erecting a box girder (7) by the lifter (6) in a way that the lifter (6) travels to a position above the base (3) and erects the box girder (7). The erection method further comprises: lifting by the lifter (6) a single set of transport and erection apparatuses or two sets of transport and erection apparatuses to a bridge, a girder transport vehicle (9) cooperating with a bridge erecting machine (10) to repeatedly complete the erection of the box girder (7); hoisting by the lifter (6) the transport and erection apparatus off the bridge; lifting by the lifter (6) the box girder (7) within the scope of the reserved bridge pier (1) to the erected box girder (7); and constructing the reserved bridge piers (1); completing by the lifter (6) the erection of the box girder (7) within the scope of the reserved bridge piers (1). The construction and erection methods for the box girder occupy a small space and have high efficiency.

Construction method for upright lifting of large-tonnage box girder to bridge, and erection method for large-tonnage box girder

A construction method for the upright lifting of a large-tonnage box girder to a bridge, and an erection method for the large-tonnage box girder. The construction method comprises: constructing a lifting station (2) at reserved bridge piers (1); disposing a girder lifting base (3), lifter traveling rails (4), and a mounting lifter (6) in the lifting station (2); directly erecting a box girder (7) by the lifter (6) in a way that the lifter (6) travels to a position above the base (3) and erects the box girder (7). The erection method further comprises: lifting by the lifter (6) a single set of transport and erection apparatuses or two sets of transport and erection apparatuses to a bridge, a girder transport vehicle (9) cooperating with a bridge erecting machine (10) to repeatedly complete the erection of the box girder (7); hoisting by the lifter (6) the transport and erection apparatus off the bridge; lifting by the lifter (6) the box girder (7) within the scope of the reserved bridge pier (1) to the erected box girder (7); and constructing the reserved bridge piers (1); completing by the lifter (6) the erection of the box girder (7) within the scope of the reserved bridge piers (1). The construction and erection methods for the box girder occupy a small space and have high efficiency.

Construction method for upright lifting of large-tonnage box girder to bridge, and erection method for large-tonnage box girder

A construction method for the upright lifting of a large-tonnage box girder to a bridge, and an erection method for the large-tonnage box girder. The construction method comprises: constructing a lifting station (2) at reserved bridge piers (1); disposing a girder lifting base (3), lifter traveling rails (4), and a mounting lifter (6) in the lifting station (2); directly erecting a box girder (7) by the lifter (6) in a way that the lifter (6) travels to a position above the base (3) and erects the box girder (7). The erection method further comprises: lifting by the lifter (6) a single set of transport and erection apparatuses or two sets of transport and erection apparatuses to a bridge, a girder transport vehicle (9) cooperating with a bridge erecting machine (10) to repeatedly complete the erection of the box girder (7); hoisting by the lifter (6) the transport and erection apparatus off the bridge; lifting by the lifter (6) the box girder (7) within the scope of the reserved bridge pier (1) to the erected box girder (7); and constructing the reserved bridge piers (1); completing by the lifter (6) the erection of the box girder (7) within the scope of the reserved bridge piers (1). The construction and erection methods for the box girder occupy a small space and have high efficiency.

SLIP FORMING STRUCTURES USING MULTIPLE MOLDS
20220098803 · 2022-03-31 ·

A method of slip forming a concrete structure can include using a first slip form mold that travels along a path to form a portion of a concrete structure by delivering a first flow of concrete into the first mold through a first hopper. The first hopper can be configured to receive the first flow of concrete. The portion of the concrete structure can be modified using a second slip form mold different from the first mold by advancing the second mold along the concrete structure and, while advancing the second mold, delivering a second flow of concrete into the second mold through a second hopper that is configured to receive the second flow of concrete.

Bridge span replacement system

A vertically-adjustable gantry assembly installation adapted for removal or placement of a train bridge-span of the type which spans and is supported by two piers, comprises a gantry assembly positioned on load-bearing first ground-support locations, the gantry assembly comprising a gantry and a ground-engaging vertical support and lift system, the vertical support and lift system adapted for supporting a combined weight of the gantry and a bridge span in at least one operational vertical position above respective bridge span support-surfaces of the piers including a position corresponding to a disembarking plane in which the leg portions are extended from a stowed position to an extent at least sufficient for the gantry assembly to self-liftoff the pre-installation conveyance system onto the first ground-support locations to effect the gantry assembly installation.