Apparatus and Method for In-Situ Fabrication of Bi-Layer Composite Pipe By Deformation Manufacture of Compression-Fit, Shape Memory Polymer Pipe (SMPP) Mechanically United With Host Pipe
20210048134 ยท 2021-02-18
Inventors
Cpc classification
B32B2307/50
PERFORMING OPERATIONS; TRANSPORTING
F16L55/1653
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
B32B2597/00
PERFORMING OPERATIONS; TRANSPORTING
F16L55/1656
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
B32B27/304
PERFORMING OPERATIONS; TRANSPORTING
B32B27/06
PERFORMING OPERATIONS; TRANSPORTING
B29C63/42
PERFORMING OPERATIONS; TRANSPORTING
B32B2307/10
PERFORMING OPERATIONS; TRANSPORTING
F16L55/1652
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
International classification
F16L55/165
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
Abstract
A method and apparatus for lining a host pipe with a shape memory polymer liner in which the liner is fed through a manufacturing assembly including a pipe tensioner, followed by a deformation tool, prior to entering the host pipe, the liner being pulled through the host pipe from a leading end, the component parts of the manufacturing assembly acting to temporarily reduce the liner outside diameter during the pulling operation, while allowing the liner to revert to at least the internal diameter of the host pipe upon removal of the pulling load. The liner being used is a shape memory polymer which exhibits the ability to return from a deformed shape to an original shape induced by an external stimulus.
Claims
1. A method for in-situ fabrication of a bi-layer composite pipe by uniting a compression-fit, shape memory polymer pipe with and into a host pipe, the method comprising the steps of: providing an inner pipe comprised of a shape memory polymer which exhibits the ability to return from a deformed shape to an original shape induced by an external stimulus; feeding the shape memory polymer pipe to a pipe tensioner mechanism which pulls a tail end of the SMP pipe rearward while simultaneously pushing the pipe forward to or through a deformation tool mechanism and then into the host pipe; pulling the SMP pipe forward end with a winch mechanism while holding the pipe in axial tension sufficient to inhibit diameter memory recovery of the shape memory polymer and to overcome drag friction of the pipe at axial tension loads low enough to minimize axial creep elongation of the pipe undergoing insertion; discontinuing pulling of the inner pipe once the pipe is fully inserted within the host pipe and allowing the shape memory polymer to recover memory and be mechanically seated and locked by compressive friction within the host pipe.
2. The method of claim 1, wherein the pipe tensioning mechanism provides a predictable and constant processing speed for consistency of pipe processing to thereby give uniform deformation, uniform memory in radial recovery and minimum axial elongation of the shape memory polymer liner during the pipe insertion process.
3. The method of claim 1, wherein the deformation tool mechanism is used to reshape the shape memory polymer from an original pre-form shape to a temporarily smaller outer diameter, the deformation tool mechanism comprising an assembly of at least one orifice forging ring positioned for receiving the memory polymer, the orifice forging ring having a parabolic working surface, the shape memory polymer pre-form being acted upon by the orifice forging ring parabolic surface as it is being pushed through, pulled through or push and pulled through the at least one forging ring.
4. The method of claim 3, wherein there are a plurality of forging rings selectively positioned in sequential fashion to sequentially deform the shape memory polymer pre-form by small percentage reductions, the forging rings being sufficiently separated within the deformation tool assembly to enable viscoelastic creep strain during a time delay between entry into each successive forging ring, resulting in larger wall thickening and slight elongation at reduced loads.
5. The method of claim 4, wherein the selective spacing of the forging rings within the deformation tool enable partial shape memory polymer outer diameter recovery when passing through successive forging rings, so that the partially recovered shape memory polymer enters each successive forging ring at a slightly larger diameter than the diameter it possessed when exiting the prior forging ring.
6. The method of claim 5, wherein the forging rings are located a selected distance apart which is sufficient to develop axial compression between successive forging rings, resulting in radial wall thickening of the shape memory polymer.
7. The method of claim 6, wherein the shape memory polymer is subjected to external stimuli while in the deformation tool mechanism, said stimuli being selected from among the group consisting of temperature control, ultrasonics and the use of lubricants.
8. The method of claim 7, wherein one or more infrared radiation devices are incorporated into the manufacturing process to alter the shape memory polymer's physical properties raising the temperature of the polymer pre-form to a desired temperature to increase the malleability of the polymer using an infrared radiation energy at a selected infrared wave-frequency band, which is absorbed by a specific shape memory polymer.
9. The method of claim 8, wherein the shape memory polymer chosen for use in the process has a characteristic ability to absorb infrared energy up to a maximum watts per square inch density flux and wherein the produced watt density flux of the specifically absorbed infrared radiation frequency bands is kept at or below the shape memory polymer's maximum absorbable watt density flux limit.
10. The method of claim 1, wherein the shape memory polymer being acted upon by the deformation tool mechanism is also subjected to harmonic vibrational enhancement by subjecting the polymer to high speed vibration.
11. The method of claim 4, wherein the harmonic vibrational enhancement is accomplished by applying a fluid in direct contact with an external surface of the shape memory polymer as it passes through the one or more of the forging rings.
12. The method of claim 1, wherein the shape memory polymer liner is pulled into the host pipe by a pull head assembly which applies a tension load to the liner which is sufficient to oppose the inherent recovery of the shape memory polymer towards its original diameter, the tension load acting to neck-down the length of the liner while the liner is attempting to recover its original outer diameter, the force of the axially pull tension being sufficient to off-set, balance or slow down the outer diameter recovery process.
13. The method of 1, wherein the shape memory polymer is selected from the group consisting of amorphous and semi-crystalline macro-molecular structural polymeric materials having the characteristic ability to return from a deformed state to an original shape induced by an external stimulus such as a temperature change or a release of deformation stress.
14. The method of claim 13, wherein the shape memory polymer is selected from the group consisting of polyethylene, nylon, polycarbonate, PBT, and polyvinylchloride (PVC).
15. The method of claim 14, wherein the shape memory polymer is a pipe-grade polyethylene, as defined by ASTM D2837 and ISO 9080.
16. The method of claim 15, wherein the shape memory polymer is a pipe grade polyethylene selected from the group consisting of PE4710 (ASTM D3350) and PE100 (ISO).
17. The method of claim 16, wherein the shape memory polymer is selected from the group consisting of bi-modal, tri-modal, and/or multi-nodal molecular weight distribution PE4710's and PE100's.
18. The method of claim 1, wherein the specific shape memory polymer chosen for use in the process has a known degree of visco-elasticity influenced by the temperature of the polymer as it passes through the process, the speed at which the polymer is deformed, the percentage to which the polymer is deformed, as well as known polymer structural variables including percent crystallinity, molecular entanglement, and molecular mass, and by appropriately selecting the material temperature, the percentages of progressive deformation, and the speed of deformation, for a specific polymer with its own crystallinity, internal entanglement, and molecular mass, the process of diameter recovery in the shape memory polymer is optimized to thereby develop a desired compression-fit between the outer diameter of the polymer and the internal diameter of the host pipe to produce a dual layer pipeline with enhanced structural and or pressure performance.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0017]
[0018]
[0019]
[0020]
[0021]
[0022]
[0023]
[0024]
[0025]
[0026]
[0027]
[0028]
[0029]
DETAILED DESCRIPTION OF THE INVENTION
[0030] The invention described herein and the various features and advantageous details thereof are explained more fully with reference to the non-limiting examples which are illustrated in the accompanying drawings and detailed in the following description. Descriptions of well-known components and processes and manufacturing techniques are omitted so as to not unnecessarily obscure the workings of the invention. The examples used herein are intended merely to facilitate an understanding of ways in which the invention herein may be practiced and to further enable those of skill in the art to practice the invention. Accordingly, the examples should not be construed as limiting the scope of the claimed invention.
[0031] The process of the present invention provides for the deformation manufacture and installation of large diameter shape memory polymer (SMP) thermoplastic pipe which is compress-fit into and within a host pipe, achieving characteristics of a multi-layer and multi-material pressure capable conduit. The result is the improvement and/or restoration of the host pipe's leak integrity, and/or pressure capacity, and/or flow rate. In one preferred form, the invention allows for the deformation manufacture and installation of large diameter (e.g., greater than 14-inch diameter pipe) into short host pipes, and/or, very-long in-situ subterranean host pipelines.
[0032] The process of the invention uses thermoplastic tubulars (thermoplastic pipe liners) which are made from materials exhibiting shape-memory polymer (SMP) characteristics. The term Shape Memory Polymers (SMP's) as used herein will be taken to mean thermoplastic materials which exhibit the ability to return from a deformed state (temporary shape) to their original (permanent) shape induced by an external stimulus (trigger) such as temperature change or release of deformation stress.
[0033] The selection of the particular polymer for the tubular liner is an important factor in the overall success of the liner installation. The preferred polymeric materials for purposes of the present invention are shape memory polymers (SMP's) in tubular form, which exhibit the characteristic of being radially deformable to a smaller diameter, and the subsequently releasing said stored deformation energy, and recovering towards the original OD.
[0034] The preferred class of polymeric materials are Shape Memory Polymers (SMP) of the classes: typically semi-crystalline macro-molecular structure material. Examples of such SMP's are polyethylene, nylon, acetal, polybutyleneterathalate (PBT), polycarbonate (PC), etc. Generally, the most economically attractive SMP is pipe-grade polyethylene, as characterized by ASTM D2837 and ISO 9080. The preferred, most favored SMP pipe grade polyethylene resins are PE4710 (ASTM D3350) and PE100 (ISO). The most preferred SMP is bi-modal, tri-modal, and/or multi-nodal molecular weight distribution PE4710's and PE100's. These SMP's exhibit the property of enhanced viscoelasticity, which significantly contributes to the polymeric memory demonstrated by cylindrical recovery from radial compressive strain deformation.
[0035] The enhanced short-term radial recovery characteristic of PE4710 and PE100 materials is due to its enhanced molecular architecture which involves greater molecular entanglements within and throughout the amorphous portion of the semi-crystalline polymer. Viscoelasticity is a property of SMP's which provide for a simultaneous elastic and viscous response to deformation. Mechanistically, viscoelasticity is a physical displacement and slight rearrangement of chain molecules. As stress (load) is applied to the SMP viscoelastic polymer, some parts of the long chain molecules change position and re-arrange in proportion to the applied strain. The polymer remains a solid material even when those parts of the long chain molecules are rearranging, pushed about by the applied stress. As this movement occurs, it creates a spring-like back-stress in the material as the molecules are distorted. When the molecular back-stress resistance to deformation re-arrangement equals the magnitude of applied stress, the material no longer creeps. When the original distortional load is removed, the accumulated molecular straightening or bending wants to revert and recover back to its original un-distorted configuration. The stretched or compressed long chain molecule can deform in the direction of the applied stress, and upon removal of stress, the molecule is driven by its atoms to re-configure to their original conformation.
[0036] On a macro-scale, the polymeric structure can be observed to return to its original form. The slow return to original shape is a creep process (prefix: visco-), and its recovery to full original shape is elastic (suffix: elastic). The visco-elastic memory is a viscoelastic molecular process within the SMP. Where-as elasticity is usually the result of molecular bond stretching along crystallographic planes in an ordered solid, viscoelasticity is the result of diffusion movement of atoms and molecules or segments of molecules inside an amorphous material or the amorphous region of a semi-crystalline material. In this way, pre-form SMP tubulars are in-situ manufactured by the described proprietary process into smaller diameter cylinders, which later return towards their original dimeter, primarily by radial strain recovery.
[0037] The degree of visco-elasticity is influenced by the temperature of the SMP (velocity of molecular motion), the speed at which the polymer is deformed, the percentage to which the polymer is deformed, as well as polymer structural variables such as percent crystallinity, molecular entanglement, and molecular mass (weight average molecular weight at a molecular distribution curve). By influencing the material temperature, the percentages of progressive deformation, and the speed of deformation, for a specific polymer with its own crystallinity, internal entanglement, and molecular mass, it is possible to optimize the process for diameter recovery to develop the desired compression-fit between the SMP pipe OD, and the host pipe ID. The result is a final dual layer pipeline with enhanced, united, structural and/or pressure performance.
[0038] The thermoplastic tubulars used in the practice of the invention can include SMP's in solid-wall tubular form in large diameters (e.g., greater than about 14-inch to 108-inch diameters) with thick walls (greater than about 0.625 thick, to 6-inch thick). The size, massive weights, and forces involved in manipulating large diameter pipes at deeper burial depths is vastly different from small diameter pipes at shallow depths, necessitating significantly different equipment and processes.
[0039] In order to appreciate the advantages of the present invention, it is necessary to briefly refer to the prior art swage-lining process.
[0040]
[0041] Note also that some slight memory recovery may occur at the region indicated as 39 in
[0042]
[0043] In the simplified view of
[0044] In the practice of the method of the invention, a deformed SMP cylinder is installed in the host pipe after the deformation tool apparatus by pulling. When pulling, the SMP tubular is typically dragged forward under tension. The pull-head assembly chosen must be sufficient for the project installation length. In certain high-risk situations, the pull-head assembly head preferably exhibits a tensile load capacity equal to or greater than the tensile strength of the SMP tubular itself. The applied tension load is a predictable variable load, because the pull load must hold a constant base tension to prevent or slow diameter recovery until the SMP pipe is completely through the host pipe. The pull-load must also increase as the frictional drag increases with the increasing length of the SMP pipe within the host pipe, and with the multiplier load of host pipe bends. The technology for predicting the insertion loads has been in existence for many years, following the pulling and pushing installation equations of one long smaller cylinder inside another long larger cylinder. Example engineering information, available since the 1980's was first published in the AEIC Publication G5-90 Underground Extruded Power Cable Pulling, AEIC Task Group 28; see, also, IEEE Standard 1185-1994, Guide for Installation Methods for Generation Station Cables; and, Installation of Optical Cables in Ducts, by Griffioen (1993), which discusses the theory of pushing and pulling of long cylinders of one inside the other (Chapters 2 & 3).
[0045] It is important during the practice of the method of the invention that, when installing the temporarily deformed SMP tubular by axial pulling it into and through the host pipeline, the applied tension is sufficient to oppose the inherent recovery of the SMP cylinder towards its original diameter. The tension attempts to neck-down the long length tubular, while the SMP tubular is dynamically trying to recover OD. The force of the axial pull-tension should be sufficient to off-set, balance, equal, or slow down the OD recovery process, thus enabling very long lengths to be installed in the host pipeline, prior to OD recovery, which locks the SMP cylinder in place, uniting it with the host pipe and forming the composite pipe structure. OD recovery of the cylindrically deformed SMP cylinder is triggered by the release of axial tension, and the un-constrained memory recovery of the deformed polymer pipe.
[0046] The first mechanical component used in the preferred method of practicing the invention thus involves the use of the SMP pipe tensioner mechanism. The tensioner mechanism pulls the tail-end pipe segments forward, and simultaneously pushes that heavy, large-diameter pipe through the deformation tool apparatus and then into the host pipe, where thereafter, the inserted pipe is simply held in axial tension sufficient to prevent diameter memory recovery and to overcome drag friction, at a axial tension low enough to minimize axial creep elongation of the SMP cylinder length undergoing insertion. This provides uniform speed for consistency in the lining process and allows for longer and longer installation lengths through, for example, a subterranean pipeline. Pipe Tensioners, of the general type under consideration, are used at the present time on very large pipe, typically for ship-borne pipe-lay vessels, and have never previously been used to manage SMP pipe manufacture and installation for the purpose of maintaining a desired ratio of wall thickening and minimum axial elongation in the type of applications presently envisioned. Examples of large diameter Pipe Tensioners can be found in the published literature, including: www.controlflow.com/products/westech/linear-pipe-tensioners.
[0047] It is important in the practice of the invention that the use of such a large diameter pipe tensioner provide a predictable speed for consistency on SMP pipe processing to give uniform deformation, uniform memory in radial recovery, with minimum axial elongation. The host pipeline geometry can have elbows, sag bends, side bends, and over-bends. These pipeline components multiply the drag-load required to keep the forged SMP pipe moving forward. On some occasions, as the loads rapidly multiply, the pull-nose used to pull the SMP can be temporarily stopped and the axial nose tension becomes isolated from the tail end of the SMP pipe. Under such conditions, the length of pipe intermediate between the tail end and nose end SMP pipe can begin diameter recovery, potentially locking the SMP pipe in place while being only partially installed along the project length.
[0048] Alternatively, the frictional drag load on the pull-nose can build and build, and then suddenly release, causing the SMP pipe to suddenly accelerate and jump forward through the deformation mechanism at high speed for a short section until the dynamic forces come to equilibrium. Such surges in axial speeds through the deformation mechanism impose less diameter reduction and wall thickening (consequently a smaller radial clearance between SMP pipe and the host pipe ID) than optimal and balanced compression strain at slower constant speed. The important aspects to the SMP pipe tensioner, is that it provides constant processing speed without surging, uniform radial deformation and wall thickening and memory recovery due to that constant speed, and provides control within and over the process, not previously disclosed in Prior art.
[0049]
[0050] The use of parabolic work surfaces, as well as the optional temperature control, ultrasonics and lubricants introduced through the port 45 (
[0051]
[0052]
[0053] It is found that material internal shearing strength is decreased by ultrasonic vibration, which can be attributed to acoustic softening effect, considering the absorbed acoustic energy. The sonic velocity of polyethylene is about 3000-ft/sec, and sound waves are transmitted through the mass of the pipe wall. Application of ultrasonic energy reduces the static stress necessary for plastic deformation of materials, to reduce both deformation load and energy; the effect being known as the acoustic softening effect (ASE). Ultrasonic vibration promotes material flow under load, decreased resistance to flow, and increases overall plasticity. Additionally, the heat generated internal to the SMP pipe wall coming from both frictional work and plastic deformation, and IR adsorption, is slightly added to and influenced by ASE. The ultrasonic vibration helps enable slippage in the polymer's inter-molecular region between macro-molecular structures, somewhat analogous to harmonic vibrations fluidizing or consolidating poured concrete or particulate suspensions. Powerful single frequency or multi-frequency ultrasonic generators are available from manufacturers such as Ransohoff, Inc or Blackstone-NEY Ultrasonics.
[0054]
[0055]
[0056]
[0057] Another important principle incorporated into the practice of the invention is the discovery that SMP's can change physical properties (such as the Young's Modulus of Elasticity, Compressive Strain Limit, and the Elastic or Viscoelastic Strain Response) by the alteration of the SMP temperature before, during, and/or after SPM pipe manufacture. Taking advantage of the change in properties of the SMP material can promote the ease of manufacture and installation of SMP Tubulars.
[0058] In the past, the SMP tubular has been treated by various heat sources such as hot gases in convection and induction environments. However, in the process of the invention, Infrared Radiation (IR) is the preferred method used to alter the SMP tubular's physical properties, prior to the SMP pipe manufacture. The SMP pipe surface and thru-wall mass is not easily temperature treated by the process of conduction. Additionally, the pipe surface and thru-wall mass is very in-efficiently temperature treated by convection using thermally controlled air, because the mass of the air molecules is low, and cannot efficiently convey heat onto the pipe at the laminar pipe-surface air boundary. Raising the temperature of a thick wall SMP pipe to a desired malleability temperature, can take hours, because the large SMP mass per foot and its high specific heat. Convection processes consequently limit the speed of SMP pipe installation to un-economical production and installation speeds.
[0059] IR energy is characterized by its wave frequency. SPM's are transparent to many bands of IR wave-energy frequencies, and, are highly absorptive of one or more narrow bands of IR wave-energy frequencies. The process of the invention uses IR energy generated at selected IR wave-frequency bands, which are absorbed by a specific SMP. The SMP's absorb the specific frequency band of IR energy wave through the tubular OD and into the thru wall thickness, where-in it converted into thermal heat conducted throughout the SMP tubular's thru-wall thickness in a quick and efficient manner. Polymers can absorb energy up to a certain watts per square inch density flux. In the practice of the invention, the produced watt density flux of the specifically absorbed IR frequency band(s) is kept at or below the SMP's maximum absorbable watt density flux limit.
[0060]
[0061] The improved process of the invention, which uses the IR heaters 97, 99, 101 produce deep penetration at a tuned IR frequency, high conduction, a high watts per square inch, high thermal efficiency/absorption. The IR power can be matched to the velocity of the moving tubular with a resulting thermal gradient across the wall thickness. The IR energy penetration heats the SMP pipe wall, reducing its elastic modulus, reducing its resistance to diameter deformation, such that the reduced loads from downsizing can be otherwise be mobilized to enable the manufacture of longer length composite bi-layer pipes. The IR heating can be optionally applied for longer length pipeline installations, and in colder weather climates. The IR heating is not intended to create a uniform wall temperature, but rather to generate a thermal gradient across the SMP pipe-wall, which net effect is to reduce the overall radial strength of the tube, to reduce resistance to temporary diameter reduction, enabling easier and longer composite pipe construction. Prior art use of warmed gas is very in-efficient and in-effective, being only a slow surface warming. This advancement heats immediately by penetrating wave energy tuned absorption, versus surface gas-film thermal conduction, allowing faster speed of construction.
[0062] The preferred deformation mechanism used in the practice of the invention will now be further described. The preferred process uses a special type of deformation mechanism to re-shape the frigid, ambient or warmed temperature SMP tubular pre-form to its temporarily smaller diameter. The deformation tool apparatus preferably consists of the assembly of one or more orifice forging rings positionally locked in a static frame, so as to work the SMP tubular as it is pushed through, pulled through, or pushed and pulled through the forging rings. Pushing the SMP tubular through one or multiple forge-rings builds axial compression resistance stress, which results primarily in compressive strain radial wall thickening of the tubular, with minimal axial elongation, as the SMP cylinder is forged into a smaller diameter. Pulling the SW tubular through one or multiple forge-rings results in modest wall thickening, but primarily axial elongation and stretching.
[0063] To control the applied pulling loads so that the SMP pipe does not elongate excessively under load, especially for larger diameter SMP pipes at much longer lengths, an optional load controller may be used. Initially the tensioner pull load is high. The pull-push tensioner absorbs the initial drag-load of the assembled, long SMP pipe string entering the tool-box. As the pipe length entering the tensioner shortens, its drag load decreases. The SMP pipe is not drug through the tool box, it is fed into it, such that there is no pull-nose tension required to drag the initial pipe string up to the tool-box. The frictional drag resistance through the downsizing tool box is relatively constant. The SMP pipe length pull-nose exerts sufficient tension to pull it through the tool-box and hold additional tension sufficient to keep the SMP pipe from diameter recovery. As the downsized SMP pipe passes into the host pipe, the pull-head tension increases slowly with every foot of additional drag-load moving into the host pipe. At some installed length, the pull-head tension can become excessive and start necking-down the SMP pipe. The SMP pipe pull-head load (force) is monitored. To prevent pull-head loads form becoming excessive, the controller's load set point speeds up the tensioner velocity feeding the tool-box, so as to partially off-set the sum of the tool box drag resistance force, and the installed SMP pipe's frictional drag-load inside of the host pipe. In this way, by balancing the difference between the push-feed load and the pull-installation load, the pull-head tension force is controlled within an upper and lower load boundary, so that the SMP pipe neither prematurely OD recovers, nor necks down and elongates excessively during the time duration of liner installation. The SMP pipe wall tension stress is maintained in an acceptable range of viscoelastic creep stress intensity, by means of load control between the tensioner and pull-head.
[0064] According to the teachings of the invention, the previously described Pipe Tensioner uses pushing, pulling, and combined pushing and pulling, to achieve the desired balance between radial wall thinning and axial elongation. The compressed radial wall ring-strain wants to recover towards its original larger diameter, by giving up its thickened wall as it recovers and enlarges, resulting in radial wall thinning recovery and reduction of compressive stress and strain. The axial elongation also stores recoverable SMP tensile strain, like the Chinese Finger effect, such that when elongated, the cylinder gets longer and smaller in diameter, and when contracted, gets shorter and larger in diameter. The use of the Deformation Tool of the invention, with correct forge-ring geometry, when used with pushing or pulling, or pushing and pulling, generates the desired ratio between cylindrical SMP's recoverable radial wall thickening and recoverable axial elongation.
[0065] The process of the invention also preferably uses SMP materials in tension or compression, within short-term strain limits. Above a compressive strain limit determined at a specific temperature, many polymeric materials will crush, suffering permanent non-recoverable compressive deformation. Above a tensile strain limit determined at a specific temperature, many polymeric materials will molecularly dis-entangle, suffering permanent non-recoverable tensile deformation. The present process, in its preferred form, uses SMP's with elastic deformation limits of less than or equal to 16% in compression, and/or less than or equal to 13% in tension.
[0066] The preferred deformation tool apparatus used in the practice of the invention consists of a rugged, high-load tolerant frame, within which are one or multiple orifice forging-rings (illustrated schematically in
[0067] Reduced loads result in longer installation lengths. The deformation tool apparatus is arranged to provide a separation distance between the successive forge-rings to enable partial SMP cylinder diameter recovery enlargement, so that when passing through the next forge ring and the next subsequent forge rings, the partially recovered SMP cylinder enters at a diameter slightly larger than the diameter it possessed when exiting the prior forge-ring. The repeated down-size working of the SMP pipe diameter results in a higher percentage of radial wall thickening, versus axial elongation.
[0068] As has been emphasized, an important aspect of the practice of the invention is the use of orifice forge-rings with a parabolic curvature through the ring entry and exit. Prior art has used angular tapers, primarily as applied to metals. The problem with angular tapers is that they can be long resulting in high frictional loads and those forces can be inclined at non-perpendicular angles to the SMP cylinder surface, both resulting in undesirably large axial SMP stretch. With SMP cylinders, the short parabolic curvature applies deformation strain perpendicular to the SMP cylinder surface as it changes shape as it passes through the forge-ring, resulting primarily in ring compression, with minimal axial elongation. SMP cylindrical ring compression resulting in wall thickening is preferable over axial elongation. It is desirable to maximize radial compression versus axial elongation, as the installation objective is to allow the SMP cylinder to recover radially so as to be in ring-compression, tight to the ID of the host pipe. The parabolic curvature aids in maximizing the balance (ratio) between percent radial wall thickening and percent axial stretch.
[0069] Preferably, the series of multiple orifice forge-rings are separated sufficiently apart to develop axial compression between orifice forge-rings. As the SMP cylinder exits one ring and moves along to the next, the wall exits the first forge ring as somewhat thickened, and slightly elongated. The distance between forge rings is such that when compared to the macro-pulling speed, as the SMP cylinder is progressively reduced, it gets progressively longer, such that its axial velocity increases between forge rings, thus pushing the progressively deformed ring into the next forge ring at a faster speed, driving it forward, and loading the cylinder more in axial compression, which results in better radial wall thickening with reduced elongation. Hence, multiple forge rings, or sets of forge rings, can be advantageously positioned apart to maximize radial wall thickening, as compared to a single forge-ring.
[0070] Another feature which can be advantageous used with respect to the forge-rings is the feature of harmonic vibrational enhancement. Real polymers do not creep under deformation load with a single creep-mode. Molecular segments of varying lengths contribute to the overall creep-rate, with the simpler and shorter segments relaxing much more quickly than the longer ones. This leads to a distribution of molecular creep-rates. This distribution is most effectively modeled by the Wiechert Polymeric Creep-Rate Model, with its many springs and dash-points. It has been discovered that when certain polymeric materials are subjected to high speed vibration, they are more easily worked, as the vibration force from waves mobilize the shorter molecular structures, promoting a higher creep-rate (reduced deformation loads and increased rates of permissible deformation, i.e., line-speed). Harmonic vibration provides for faster deformation and installation line-speed.
[0071] The vibrational harmonic is most easily applied by a fluid in direct contact with the surface of the SMP cylinder as it passes through one or more forge rings, within the Deformation Tool Apparatus. The vibration can be induced by ultrasound, or high frequency pulses of pressure. The vibration harmonic fluid can be, for example, water, synthetic chemicals, vegetable oil, or other organoleptic fluids. The vibration fluid usually is thermally tempered to be at the same temperature as the SMP tubular passing through the forge-ring, so as to not alter the SMP thermo-mechanical properties, as the tubular is being processed. Such fluids have also been found to have beneficial effects when containing solid lubricants such as graphite, or, molybdenum di-sulfide, which attach to the surface of the SMP cylinder. Solid lubricants of this type aid in reducing forging die frictional drag, resulting in more radial wall thickening and less axial elongation. As a result, such solid lubricants aid in the installation of longer lengths of SMP tubulars inside of host pipes, by reducing frictional installation drag-loads between the SMP pipe and the host pipe.
[0072] One principle of the improved process of the invention is thus to provide a deformation tool apparatus which features multiple forge rings of mechanically variable diameter, and, with means to axially position the multiple forge rings at variable distances from one another, to enhance radial wall thickening and to minimize axial stretch.
[0073] The preferred forge-rings, with parabolic curvature on its ID entrance and exit, may be bolted to a master mounting plate in multiple segments. In most applications, there will be multiple segments, i.e., more than two and less than 10 circumferential segments. The individual segments can be loosened at the master mounting plate and, can then be safely, controllably, radially moved outwardly to release the ring compression from the SMP cylinder, once the SMP pipe is in place in the host pipe. Prior art provides no safe way to release the deformed SMP pipe from the deformation tools one the axial pipe installation process has stopped.
[0074] The parabolic entry and exit profile of the Deformation Tool assists with radial compression and wall thickening, while minimizing axial elongation, because as the SMP pipe enters the parabolic curvature, the forces are perpendicular to the tangent surface of the SMP at any point of mutual contact, promoting radial compression without axial tensor vectors. Alternately, upon exit from the forge-ring orifice, with the multiple forge rings spaced sufficiently apart, the curvature of the slightly diameter recovering SMP pipe pushes against the exiting parabolic curvature developing an axially forward exit force, while incrementally lengthening due to diameter reduction, such that the net force to process thru the parabolic curvature die is much less than that of a straight angular taper forge-ring. Additionally, when reduced slightly in diameter, the SMP tubular elongates slightly in length, increasing the forward axial velocity, so as to naturally push the segment length between forge-rings forward into the next forge-ring orifice. In essence, the parabolic shapes work to minimize axial loads, and maximize radial wall thickening, working with the SMP pipe characteristics, instead of working against the pipe characteristics.
[0075] The mechanical aspects of the present inventive method will include large massive handling, fusion, tensioning, deformation, and installation equipment capable of managing loads up to 3 million lbs capacity for the largest of SMP Pipes (108-inch diameter, 5.15-inch thick wall). For example: 108-inch DR 21 polyethylene PE4710 bi-modal SMP pipe weighs 673 lbs per foot. The weight 5000-feet of the pipe is just over 3 million pounds. The maximum recommended push or pull stress of 1600-psi applied at 73 F on the SMP pipe cross-sectional area develops just under 3 million pounds force.
[0076] The mechanical equipment system used in the practice of the invention will be operated under the following approximate procedures:
[0077] 1.0 LARGE DIAMETER SMP PIPE FUSION:
[0078] 1.1 Safely unload the SMP pipe and stack no more than recommended heights, so as to maintain tubular roundness. Inspect the received pipe to assure it meets specifications.
[0079] 1.2 Establish the SMP pipe fusion area, and erect a welding-fusion tent, if weather is adverse.
[0080] 1.3 Using large cranes or safe handling equipment to maneuver the big diameter and long length SMP Pipe segments, and, following standard industry practice per ASTM F2620, prefuse the entire pipeline lengths together; or to preferably minimize entry-end weight and frictional drag, fuse several tubular segments into manageable shorter length sections (ie: 500-ft) which can be subsequently fused together using a fusion machine with wheels or tracks, as the SMP pipe is in motion, being processed through the Deformation Tool Apparatus.
[0081] 1.4 Use only Trained and CURRENTLY certified fusion machine operators. Data-Log a sufficient number of joints to verify repeatable processing. Monitor the fusion machine for continuous proper operation.
[0082] 1.5 Pay close attention to the heater plate to ensure the Teflon coating is intact. Use a pyrometer to take temperature readings at the 3, 6, 9, and 12 o'clock positions on the heater plate to make sure the heater temperature is within tolerance. Repeat this in-process inspection every hour the machine is in operation. Report any defects on the heater plate immediately. No joints should be made prior to a thorough evaluation.
[0083] 1.6 Perform a complete visual inspection of the pipe before loading the first joint of the session. Locate any damage to the exterior of the pipe and remove any foreign material that may have migrated to the interior of the pipe.
[0084] 1.7 Set the data logger to record the jointing procedure with the first joint recorded as a sacrificial joint. The first joint of each daily start-up session is considered a sacrificial joint. This joint goes through all the fusion steps, Including Guided Reverse Bend testing IAW ASTM F3183.
[0085] 1.8 Two-way radio communication is needed when loading and moving the pipe string for fusing.
[0086] 1.9 Take diligent care when moving the SMP pipe to avoid mechanical damage. If there is pipe damage, onsite evaluation will be necessary. Under no circumstances should damage leaving less than 90% of the minimum specified wall thickness be left and not re-fused. Cut out any excessively damaged sections and re-fuse.
[0087] 1.10 Use a suitable paint pen to mark each joint with the pipe string number, joint number, time, date, and fusion tech's name. Maintain a separate hand written log book throughout the day's fusion production.
[0088] 1.11 External de-beading is required after each joint and internal de-beading is required when specified. Use commercially available bead removal tools.
[0089] 1.12 Save and mark all external beads for evaluation purposes.
[0090] 1.13 Measure each host pipe string from insertion bulkhead to exit bulkhead; then fuse-on an additional 20-ft to the SMP pipe string, to make it longer than the host pipe length. More length may be added if necessary, but rule-of-thumb is 20 ft (6.3 meters).
[0091] 1.14 After each fusion session, download and save all information from the data logger.
[0092] 1.15 Temporarily plug or cap all pipe ends, prior to the completion of the day's work.
[0093] 2.0 Site Pre-Construction:
[0094] 2.1 After identification of the launch and receive pits for the insertion of the SMP into the 1st Host Pipe Section, construct the system bulkhead forms and prepare for pouring. This typical bulkhead is sufficient for pull forces up to 100 tons. (Further evaluation is required when using higher tonnage for very large diameters, exerting axial forces in the range of 1500-tons.) Two concrete bulkheads are required; one for the exit-end pull rig to brace against and another for the Deformation Tool Apparatus to brace against. The minimum dimensions for each bulkhead is: 2-ft above the pipe, at least to 2-ft each side of the host pipe, 12 underneath the host pipe, and 2 thick in the axial direction. 3500 psi strength concrete is the minimum concrete strength requirement and rebar may be necessary. The bulkheads need a minimum of 0.5 pipe diameters to 1.5 pipe diameters of host-pipe length protruding through beyond the entrance and exit bulkheads when connecting to adjacent SMP pipe sections, or valves, or other pipeline components.
[0095] 2.2 Determine the location of any potential hazards prior to pit excavation.
[0096] 2.3 Entry Pit Length and Slope: L=2.5D+12d where: L is length of lead in trench from the Deformation Tool Apparatus die to the ground level. Some of this length can be at a slope. Add the length of the Deformation Tool Apparatus to the calculated length L. D is depth of cover of the host pipe. d is OD of PE pipe
[0097] 2.4 Example: Depth 6 ft=62.5=15 ft OD of HDPE=4012=3.3312=39.99 ft+15 ft=54.99 ft. This is the minimum needed for the flat bottom of the trench. A slope of 4:1 can then be used for the remainder of the trench. Therefore, the overall length of the trench will be 46=24 ft+54.99 ft=78.99 ft.
[0098] 3.0 HOST PIPE CLEANING and GAGING: When working with various host pipe materials, different cleaning applications are needed for each host pipe. Numerous factors affect the tuberculation of the host pipe (i.e., calcium contents of the water being supplied). Determining the condition of the interior of the pipe may be impossible until the main line is decommissioned. However, experienced personnel can make a calculated evaluation of required cleaning equipment. A video camera may be fed through 16 to 30 host pipe. If the pipe size is over 30, a person may enter the pipe with correct safety measures in place. The cleaner the pipe the more room for the insertion process, therefore it is essential to obtain the cleanest pipeline possible.
[0099] 3.1 Of all host pipes, some may have a higher concentration of tuberculation and require extra cleaning.
[0100] 3.2 After decommissioning the host pipeline, remove sections of pipe to allow for entrance and exit access.
[0101] 3.3 Immediately verify and record the ID at both ends.
[0102] 3.4 After all the water or fluid has been drained from the system, evaluate the internal condition by either camera or man in the line. Install a tag line in the main during this process.
[0103] 3.5 Pull a heavy-duty cable, chain, or links through the host pipeline using the tag line. After review of the internal condition and evaluation of the tuberculation, select the appropriate scraper.
[0104] 3.6 Connect a heavy-duty wire-rope or safety-cable to the backside of the scraper in case the scraper stops moving forward and needs to be pulled back out. After scraping, perform a second internal review to identify any potential hazards such as offset joint, protruding service feral, etc. If a hazard is identified it first must be removed or smoothed out. After scraping is complete, pull a pull-through swab plunger through the host pipeline. This may take more than one pass and must continue until all scraped debris is removed.
[0105] 3.7 Pull a soft foam pig through the line. When exiting, examine the foam pig for any visible rips or tears.
[0106] 3.8 After the cleaning operation is complete and the line looks clean, pass the gauging pig through the pipe at a constant, steady speed to locate any potential blockages still present. Inspect the gauging pig for existing marks before it enters the line.
[0107] 3.9 After the gauging pig is pulled through without issue, plug the host pipeline at each open end. With most other non-metallic type pipes such as PCCP, AC and concrete pipe, only steps 3.6 through 3.9 are required.
[0108] 4.0 Setting Entry SMP Pipe Tensioner, The Deformation Tool Apparatus, & Exit Pull Tensioner:
[0109] 4.1 Set a foundation for the heavy TENSIONER, which picks up the entry portion of the SMP pipe in axial tension, and, delivers it to the Deformation Tool Apparatus in axial compression.
[0110] 4.2 The pulling device at the exit end of the host pipeline exerts axial tension on the SMP pipe. The TENSIONER at the entry end, picks up the pre-fused SMP pipe, and also balances the axial compression into and the tension out of the Deformation Toll Apparatus. It is PLC managed. This device is large, heavy, and exerts high force. The Tensioner must be securely anchored to the ground by foundation and other removable anchoring devices between the TENSIONER and the ground, to deliver the required, balanced forces on the SMP pipe, at a consistent controlled speed.
[0111] 4.3 Place the exit end pull rig and entry end Deformation Tool Apparatus unit on a smooth, even ground-floor in the trench excavation pits, preferably using crushed concrete bedding.
[0112] 4.4 Once the rock bottom is placed to the correct height, position the trench-shoring box catch cages in the receiving exit pit. Bolt the shoring box catch cages together and place flush with the exit concrete bulk head. Larger pipes are buried deeper, requiring safety trench shoring devices.
[0113] 4.5 Lower the exit pit pull-rig behind the trench box catch cages and slide forward flush to the concrete bulkhead. Centralize the height of the pull-rig to the center of the host-pipe, by adding/subtracting rock to elevate (lower) the trench floor.
[0114] 4.6 Insert the pulling link rods or thick wire rope through the host pipeline. Take special care to ensure no foreign debris enters the host pipeline. Once pull link rods or heavy-duty wire rope is installed through the host pipeline to the entry-end launch pit, position it about 6 short of the end of the host pipe. Do not let it exit the host pipe into the entry pit area.
[0115] 4.7 After the rock bottom is placed to the correct supportive depth, position the Deformation Tool Apparatus into the launch pit, and move It forward and mount it flush with the entry pipe concrete bulkhead. Insure the Deformation Tool Apparatus is secured and centralized to the center of the host pipe.
[0116] 4.8 Pull additional pull-link rods or massive wire rope through the Deformation Tool Apparatus in preparation of the SMP pipe string hook up to the SMP pipe pull-head. Use care in going through the Deformation Tool Apparatus. Use wood or half-moons of plastic pipe to cup and support the metallic rods or wire, so as to eliminate any potential mechanical scraping or impact damage to the Deformation Tool Apparatus. Bring the fused SMP pipe string to the Deformation Tool Apparatus and connect the SMP pipe pull-head to the pull-link rods or thick wire rope with an approved connection assembly, such as a large shackle and clevis of approved load capacity.
[0117] 4.9 The entry-end, fused, SMP pipe string should be supported and assisted by roller-frame assemblies along its length, at all times, before and during installation.
[0118] 5.0 SMP Pipe Installation and Shape Memory Recovery.
[0119] 5.1 A final check of all equipment is required before the insertion operation is started. This includes, but is not limited to, oil and fuel in the pull rig power pack, Tensioner power, two-way radios with sufficient charge, all pumps topped off with reserve fuel available, sufficient harmonic resonant fluid, etc.
[0120] 5.2 Carefully inspect the Deformation Tool Apparatus to ensure it is clean and free of deficiencies, prior to SMP Pipe insertion from the Tensioner to the puller apparatus.
[0121] 5.3 Carefully inspect the fused SMP pipe string for any debris that may be attached to the pipe (i.e., small stones or dried mud) prior to the deformation and insertion operation. If present, remove the debris.
[0122] 5.4 After the pipe is deemed clean, apply a light coating of vegetable oil to the top of the SMP pipe string at start-up, until the pipe reaches the Harmonic Resonance portion of the Deformation Tool Apparatus.
[0123] 5.5 During the insertion operation, a person with a radio must be at the insertion end at all times. A person at the pull rig pit must maintain contact with the insertion pit by radio at all times. Under no circumstances will the insertion operation begin without two-way communication at each end.
[0124] 5.6 Under no circumstances are personnel allowed in the entry end insertion pit when the pipe is moving through the Deformation Tool Apparatus.
[0125] 5.7 Perform the initial entry and passage pull through the Deformation Tool Apparatus at a very slow controllable speed. Maintain constant observation to ensure the SMP pipe string is centered within the host pipe. Once the SMP pipe enters the host pipe sufficiently past the pull-head, the Tensioner and pull rig can operate at their optimum deformation and insertion speed.
[0126] 5.8 Continuously monitor the Tensioner and pull rig's forces during the SMP pipe insertion operation to assure proper balance so as to maximize SMP pipe radial wall thickening and to minimize its axial elongation. Maintain constant communication between both entry and exit ends during the SMP pipe string insertion.
[0127] 5.9 Once the SMP pipe pull-head has entered the exit pull pit and been pulled as far forward as possible, shut-off and lock the entry-end Tensioner and the exit-end pull rig so the pull-head cannot withdraw back into the host pipe. Shut off the equipment and keep it locked for at least 12 hours to facilitate strain equilibrium along the full length of the SMP pipe inside the Host Pipe.
[0128] 5.10 The insertion pit it is now safe to enter. Mark the pipe 30-ft from the Deformation Tool Apparatus in one foot intervals, so as to be able to witness the length of retraction as the SMP pipe recovers towards its original diameter.
[0129] 5.11 Gather all of the entry side rollers and place back in their storage area.
[0130] 5.12 Safely Disconnect the Deformation Tool Apparatus. A maximum of two skilled personnel are allowed in the insertion pit at any time. Maintain vigilance at all times.
[0131] 5.13 Safely Release the TENSIONER load and allow the SMP pipe to naturally recover its molecular memory as macro-demonstrated by its enlarging in diameter, thinning from the thickened wall, and foreshortening from minor axial stretching. Monitor the speed and distance the entry end of the SMP moves into the host pipe until it stops in full contact with the ID of the host pipe.
[0132] 5.14 Leave the SMP pipe to relax molecularly recover memory overnight for a minimum of twelve hours. After twelve hours, the SMP pipe string can be released at the pull-rig end and the pull-rig and trench catch cages removed from the pit.
[0133] 5.15 Cut away the pulling head, leaving a square cut SMP pipe end.
[0134] 5.16 From the host pipe exit end to the end of the SMP pipe string, mark the SMP pipe at one foot intervals to monitor and observe axial memory recovery.
[0135] 5.17 Some frictional resistance is encountered as the SMP ID and host Pipe ID encroach each other. Mechanically bump the ends of the pipe string in the insertion and exit trench pits to push the SMP into the host pipe, and to compressively reduce axial tension and to speed the memory reversion process, which leaves the SMP pipe in radial compression with the host pipe ID.
[0136] 5.18 Allow a minimum of an additional 24 hours or until the memory recover has reached its limit, before installing any connections to the new pipe.
[0137] 5.19 Where the newly installed pipeline enters the host pipe, at minimum locations of the 3, 6, 9 and 12 o'clock positions, electro-fuse a standard plastic anchor-block to the OD surface of the SMP pipe, to minimize additional axial memory retraction, and to guard against thermal contraction or expansion. Cover this local assembly with flowable-fill or Cellular Lightweight Concrete (CLC) to stabilize.
[0138] 5.20 Terminations of the new SMP Pipe can be made by using butt-fusion Flange adapters, butt-fusion Mechanical-Joint adapters, electrofusion couplings, and mechanical couplings. The preferred method of SMP pipe connection should be addressed with the client/owner. There are different methods using many different products and materials. A minimum of 6-feet, or 1 to 2 pipe diameters of length, which-ever is larger, is recommended to protrude from the end of the host pipe to aid in termination connections.
[0139] While the invention has been shown in several of its forms, it is not thus limited but is susceptible to various changes and modifications therein without departing from the spirit thereof.